Sie sind auf Seite 1von 37

RATE ANALYSIS

Name of Project : F./Y.:-


Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
1 Site clearance for1Sqm Unskill 0.23 700 161.00 Tools & Plant 3 % of labour cost 4.83 4.83 16.58 1.54 U/D A.(3)
1 Site clearance for1Sqm Unskill 0.04 700 28.00 Tools & Plant 3 % of labour cost 0.84 0.84 28.84 2.68 DoLIDAR 1-1.6
dismentaling of old
bldg(mud mortar) Unskill 1.06 700 742.00 Tools & Plant 3 % of labour cost 22.26 22.26 m3 764.26
Skill 0.054 955 51.57 Tools & Plant 3 % of labour cost 1.55 1.55 53.12
roof dismentaling work Unskill 0.081 700 56.70 Tools & Plant 3 % of labour cost 1.70 1.70 m2 58.40
111.52

2
Earthwork in excavation in

a
ordinary soft soil- For 1 m3 Unskill 0.50 700 350.00 Tools & Plant 3 % of labour cost 10.50 10.50 360.50 10.22 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.60 700 420.00 Tools & Plant 3 % of labour cost 12.60 12.60 432.60 12.26 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 3.00 700 2100.00 Tools & Plant 3 % of labour cost 63.00 63.00 2163.00 61.30 5.2-1.2.2(d)

e Hard Rock- For 1 m3 (no


chino) Unskill 5.00 700 3500.00 Tools & Plant 3 % of labour cost 105.00 105.00 3605.00 102.16 5.2-1.2.2(e)
with chino Unskill 24.00 700 16800.00 Tools & Plant 4 % of labour cost 504.00 504.00 17304.00 490.37 5.2-1.2.2(e)
f. BMS- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 U/D B1)2-2
Stone Solling in foundation
4
& Leveling Unskill 1.50 700 1050.00 Tools & Plant 3 % of labour cost 31.50 31.50 1081.50
Blockstone 1.00 1752.00 1500.00 1752.00 1500.00 1752.00 DoLIDAR
Bondstone 0.20 1752.00 1500.00 350.40 300.00 350.40
Total 1050.00 1831.50 2881.50 81.66 49)17-6
Formworks of Local wood
5
for Beam/Slab Skill 0.150 955 143.25 Local Wood 0.0070 45000.00 45000.00 315.00 315.00 m3 U/D+DoLIDAR
For 1 Sq.m. Unskill 0.200 700 140.00 Nails 0.25 113.00 100.00 28.25 25.00 kg 39)9.a
Total 283.25 343.25 340.00 626.50 58.23
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.
10 Skill 0.80 955 764.00 Cement 0.32 22128.0 19840.0 7080.96 6348.80 MT
Unskill 7.00 700 4900.00 Agg.40mm 0.52 3002.0 3002.0 1561.04 1561.04 cu.m Nirman tatha Ya.
M15(1:2:4) mix plain cement
concrete works in Agg.20mm 0.22 3002.0 3002.0 660.44 660.44 cu.m 7-4b
superstructure including Agg.10mm 0.11 3002.0 3002.0 330.22 330.22 cu.m
material collection &30m
lead - For 1 m3 Sand 0.445 5984.0 5984.0 2662.88 2662.88 cu.m
Total 5664.00 12295.54 11563.38 17959.54 508.95

11 Skill 0.80 955 764.00 Cement 0.40 22128.0 19840.0 8851.20 7936.00 MT
M20(1:1.5:3) mix plain
cement concrete works in Unskill 7.00 700 4900.00 Agg.20mm 0.57 3002.00 3002.00 1711.14 1711.14 cu.m U/D
superstructure including
material collection &30m Agg.10mm 0.29 3002.00 3002.00 870.58 870.58 cu.m D2 7b
lead - For 1 m3
Sand 0.425 5984.00 5984.00 2543.20 2543.20 cu.m

Total 5664.00 13976.12 13060.92 19640.12 556.57 U/D


13 Skill 1.50 955 1432.50 Cement 0.106 22128.0 19840.0 2345.57 2103.04 MT U/D
Random Rubble Stone
masonry work in 1:6 cement Unskill 5.00 700 3500.00 Sand 0.47 5984.00 5984.00 2812.48 2812.48 cu.m C6 6(a)1-3
sand mortar - For 1 m3
Blockstone 1.00 1752.00 1752.00 1752.00 1752.00 cu.m
including material
collection,preparation of
mortar with 5m lift and 10m
lead
Bondsotne 0.10 1752.00 1752.00 175.20 175.20 cu.m
Total 4932.50 7085.25 6842.72 cu.m 12017.75 340.57
14 Skill 0.50 955 477.50 Blockstone 1.00 1752 1752 1752.00 1752.00 cu.m DoLIDAR
Dry stone masonry work
with rubble stone For 1 m3 Unskill 1.50 700 1050.00 Bondsotne 0.10 1752 1752 175.20 175.20 cu.m 38. 8
Total 1527.50 1927.20 1927.20 cu.m 3454.70

18 Urban Devemt
Chimney Bhatta Brick Skill 1.50 955 1432.50 Cement 0.070 22128.0 19840.0 1548.96 1388.80 MT
masonry work in 1:6 C/S
mortar in Superstructur- For 1 Unskill 2.20 700 1540.00 Sand 0.30 5984.00 5984.00 1795.20 1795.20 cu.m 5(1)B-3
m3 including material
collection,preparation of
mortar with 30m lead
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
Chimney Bhatta Brick per m.d. Including Excluding Including Excluding No.
UC)
masonry work in 1:6 C/S
mortar in Superstructur- For 1 Rs. Rs. VAT VAT VAT VAT in m in ft
m3 including material
collection,preparation of
mortar with 30m lead
Brick 560.00 20.29 18.60 11362.40 10416.00 cu.m
Total 2972.50 14706.56 13600.00 cu.m 17679.06 501.00
Total 5945.00 29413.12 27200.00 cu.m 35358.12 1002.00
20 Sal wood work in pannelled Skill 4.730 955 4517.15 wood 0.0397 45000.00 45000.0 1786.50 1786.50 m3 Urban Devemt
Door &Window Shutter For Unskill 0.473 700 331.10 Hinges 4" 2.8382 33.90 30.00 96.21 85.15 No G2 10-2
1 m2 (1.07*1.982=2.114)
Tower bolt 6" 0.4730 50.85 45.00 24.05 21.29 No
Tower bolt 10" 0.4730 67.80 60.00 32.07 28.38 No
Handle 6" 0.9461 28.25 25.00 26.73 23.65 No
L-drop 10"x12" 0.4730 226.00 200.00 106.90 94.60 no
Screw 14.1911 1.47 1.30 20.86 18.45 LS
Total 4848.25 2093.32 2058.02 6941.57 645.22
22 Localwood Beams work For Skill 17.65 955 16855.8 wood 1.050 45000.00 45000.00 47250.00 47250.00 m3 Urban Devemt
1 Cu. m Unskill 1.760 700 1232.00 Nails 1.000 113.00 100.00 113.00 100.00 kg F 19 10(17)
Total 18087.8 47363.00 47350.00 65450.80 1854.8
23 25 mm Locall wood Eaves Skill 0.143 955 136.57 wood 0.0275 45000.00 45000.00 1237.50 1237.50 m3 Urban Devemt
Boards for 1 sq.m Unskill 0.014 700 9.80 Nails 0.1000 113.00 100.00 11.30 10.00 kg F20 10(19)
Total 146.37 1248.80 1247.50 1395.17 129.68
24 25 mm Local wood Skill 0.143 955 136.57 wood 0.0275 45000.00 45000.00 1237.50 1237.50 m3 Urban Devemt
Plankings 1 sq.m Unskill 0.014 700 9.80 Nails 0.1000 113.00 100.00 11.30 10.00 kg F20 10(19)
Total 146.37 1248.80 1247.50 1395.17 129.68
25 3 mm plywood shutter on 2 Skill 3.118 955 2977.69 wood 0.01541 45000.00 45000.00 693.45 693.45 m3 Urban Devemt
sides with 38 mm salwood Unskill 0.312 700 218.40 Plywood 2.07127 218.86 193.68 453.32 401.16 Sq.m G4 10(7)
frame for 1 Sq. m
Hinges 4" 1.33630 33.90 30.00 45.30 40.09 No
Tower bolt 6" 0.89087 50.85 45.00 45.30 40.09 No
Mortise Lock 0.44543 904.00 800.00 402.67 356.34 No
Handle 4" 0.89087 33.90 30.00 30.20 26.73 No
Screw 13.36303 1.47 1.30 19.64 17.37 LS
Total 3196.09 1689.88 1575.23 4885.97 454.15
26 28#Plain Sheet shutter on 2 Skill 3.118 955 2977.69 wood 0.015412 45000.00 45000.00 693.54 693.54 m3 Urban Devemt
sides with 38 mm salwood Unskill 0.312 700 218.40 Plain Sheet 2.071269 384.20 340.00 795.78 704.23 Sq.m G4 10(9)
frame for 1 Sq. m
Hinges 4" 1.336303 33.90 30.00 45.30 40.09 No
Tower bolt 6" 0.890869 50.85 45.00 45.30 40.09 No
L-drop 10"x12" 0.445434 226.00 200.00 100.67 89.09 No
Handle 4" 0.445434 33.90 30.00 15.10 13.36 No
Screw 13.363029 1.47 1.30 19.64 17.37 LS
Total 3196.09 1715.33 1597.77 4911.42 456.52
CGI sheet Roofing for 1 Sq. 0.38 mm th Colour
27 Skill 0.110 955 105.05 CGI Sheet 0.071000 10090.90 8930.00 716.45 634.03 Bundle Urban Devemt
m
Unskill 0.125 700 87.50 Nut Bolt 8 mm 28.25 25.00 0.00 0.00 No F3 9(1)
J-Hook 6" 29.38 26.00 0.00 0.00 No
Bitumin Washer 1.13 1.00 0.00 0.00 No
Total 192.55 716.45 634.03 909.00 84.49
33 Skill 0.1400 955 133.70 Cement 0.00810 22128.00 19840.00 179.24 160.70 MT Urban Devemt
20 mm Thick 1:4 Cement
sand Plaster work excluding
ceiling for 1Sq. M Unskill 0.1900 700 133.00 Sand 0.02200 5984.00 5984.00 131.65 131.65 cu.m I4) 12(4)b
Total 266.70 310.89 292.35 577.59 53.69
39 Reinfocement for RCC work Skill 0.012 955 11.46 M.S. Rod 0.001050 99420 88240 104 92.65 MT Urban Devemt
in position and binding of
M.S. rod for R.C.C. works -
for 1 kg D9 7-5
Unskill 0.012 700 8.40 Binding wire 0.01000 118.65 105.00 1.19 1.05 Kg
Total 19.86 105.19 93.70 125.05
1.56
187.2
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Gorkha
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
1 Skill Labour 955.00 955.00 955.00 md
2 Unskilled Labour 700.00 700.00 700.00 md
3 Painter 955.00 955.00 955.00 md
4 Sand 2400.00 5984.00 5,984.00 m3 1600.00 0.14 0.75 16.00 3584.00 0.00 0.00
5 Aggregate 40mm 2750.00 3002.00 3,002.00 m3 1800.00 0.14 0.59 1.00 252.00 0.00 0.00
6 Aggregate 20mm 2750.00 3002.00 3,002.00 m3 1800.00 0.14 0.59 1.00 252.00 0.00 0.00
7 Aggregate 10mm 2750.00 3002.00 3,002.00 m3 1800.00 0.14 0.59 1.00 252.00 0.00 0.00
8 Stone 1500.00 1752.00 1,752.00 m3 1800.00 0.14 0.59 1.00 252.00 0.00 0.00
9 Mud for masonry 280.00 280.00 280.00 m3 1400.00 0.14 0.59 0.00 0.00 0.00
10 Sal wood 45000.00 45000.00 45,000.00 m3 600.00 0.14 0.59 0.00 0.00 0.00
11 Local Wood 45000.00 45000.00 45,000.00 m3 600.00 0.14 0.59 0.00 0.00
12 Sisau 70560.00 70560.00 70,560.00 m3 600.00 0.14 0.59 0.00 0.00
13 Cement(NS Mark OPC) 17600.00 2288.00 22128.00 19,840.00 mt 1000.00 0.14 0.59 16.00 2240.00 0.00 0.00
14 Brick(Chimney ) 13.00 1.69 20.29 18.60 Nos 2.50 0.14 16.00 5.60 0.00 0.00
15 Nail 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
31 Reinforcement Bar(10-40mm) 86000.00 11180.00 99420.00 88,240.00 mt 1000.00 0.14 0.59 16.00 2240.00 0.00 0.00
32 GI Wire 12Swg (Heavy Coating) 105.00 13.65 118.65 105.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
33 GI Wire 10Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
34 GI Wire 8Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
35 3mm Glass 500.00 65.00 565.00 500.00 m2 8.40 0.14 0.59 0.00 0.00 0.00
36 4mm Glass 640.00 83.20 723.20 640.00 m2 11.20 0.14 0.59 0.00 0.00 0.00
37 5mm Glass 750.00 97.50 847.50 750.00 m2 14.00 0.14 0.59 0.00 0.00 0.00
38 Lime 18.00 2.34 21.74 19.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
39 Gum (Rathicol) 200.00 26.00 227.40 201.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
40 Primer (wood) 290.00 37.70 329.10 291.40 Ltr 1.00 0.14 0.59 10.00 1.40 0.00 0.00
41 Enamel (Tayari) 420.00 54.60 474.60 420.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
42 Alumunium Paint 500.00 65.00 565.00 500.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
43 Sand Paper 10.00 1.30 11.30 10.00 Sheet 0.14 0.59 0.00 0.00 0.00
44 Red Oxide No 1 350.00 45.50 395.50 350.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
45 Binding wire 105.00 13.65 118.65 105.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
46 CGI Sheet 0.38 mm th Colour 8930.00 1160.90 10090.90 8,930.00 bun. 65.00 0.14 0.59 0.00 0.00 0.00
47 CGI Sheet 0.4 mm th Colour 9300.00 1209.00 10509.00 9,300.00 bun. 60.00 0.14 0.59 0.00 0.00 0.00
48 Plain sheet 28 gauge 340.00 44.20 384.20 340.00 rm 1.00 0.14 0.59 0.00 0.00 0.00
49 3mm plywood 193.68 25.18 218.86 193.68 m2 2.00 0.14 0.59 0.00 0.00 0.00
50 Snowcem Paint 77.00 10.01 88.41 78.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
51 Chimney Brick 12.00 1.56 13.56 12.00 nos 2.80 0.14 0.59 0.00 0.00 0.00
52 Wall Tile (Indian) 8"x6" 645.83 83.96 729.79 645.83 m2 12.00 0.14 0.59 0.00 0.00 0.00
53 Tile floor (Indian) 8"x8" 839.59 109.15 948.74 839.59 m2 15.00 0.14 0.59 0.00 0.00 0.00
54 White Cement 26.00 3.38 29.38 26.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
55 2X 500 gauge polythene 83.00 10.79 93.79 83.00 m2 0.14 0.59 0.00 0.00 0.00
56 Railing with GI & Black Pipe 250.00 32.50 282.50 250.00 sqft 2.50 0.14 0.59 0.00 0.00 0.00
57 Nut Bolt 8 mm 25.00 3.25 28.25 25.00 No 0.14 0.59 0.00 0.00 0.00
58 Bitumin Washer 1.00 0.13 1.13 1.00 No 0.14 0.59 0.00 0.00 0.00
59 J-Hook 4" 22.00 2.86 24.86 22.00 No 0.14 0.59 0.00 0.00 0.00
60 J-Hook 6" 26.00 3.38 29.38 26.00 No 0.14 0.59 0.00 0.00 0.00
61 Iron Grill(Ready made) 120.00 15.60 135.60 120.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
38 mm dia 16Gauge thick
62 350.00 45.50 395.50 350.00 Rm 0.14 0.59
stainless steel pipe 2.50 0.00 0.00 0.00
25 mm dia 16Gauge
63 200.00 26.00 226.00 200.00 Rm 0.14 0.59
thickstainless steel pipe 1.50 0.00 0.00 0.00
Gas welding for stainless steel
64 150.00 19.50 169.50 150.00 sq m 0.14
pipe 0.00 0.00 0.00
65 Black Iron Pipe 1.8 mm Thick 95.00 12.35 107.35 95.00 kg 1.00 0.14 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
B..Hard Soil
Norms No: 5.2-1.2.2(b) DoLIDAR
Unit :cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 0.000 870.00 -
Unskill Md 0.60 650.00 390.00
Tools andSub-Total
plants 390.00
@3% 11.70
Total 401.70
Item: Dry Stone Pitching/Soling & Levelling Works
Norms No: 49.17-6 DoLIDAR
Unit :m3
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md - 870.00 -
Unskill Md 1.00 650.00 650.00
Material Stone m3 1.10 1,602.00 1,762.20
Sub-Total
Tools and plants 2,412.20
@3% 72.37
Total 2,484.57
15 % Overhead
Unit Rate 2,484.57

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:4:8
Norms No: 41(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.17 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Total 3,470.00 cft
Unit Rate 3,470.00 98.26

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:3:6
Norms No: 42(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.22 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Sub-Total 3,470.00
15 % Overhead 520.50
Unit Rate 3,990.50
Item: plain cement concrete works in foundation including material collection &30m lead
B.M 15 Grade (1:2:4 mix by volume)
Norms No: 41.11.b DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.06 650.00 2,639.00
Cement ( OPC NS
Material mark) MT 0.32 20,804.00 6,657.28
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.440 2,300.00 1,012.00
Sub-Total 11,585.28
15 % Overhead 1,737.79
Unit Rate 13,323.07
Item: plain cement concrete works in superstructure including material collection &30m lead
A. 1:2:4 mix
Norms No: 44(7-4)a,
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.32 20,804.00 6,657.28
mark)
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.445 2,300.00 1,023.50
Sub-Total 13,333.78
15 % Overhead 2,000.07
Unit Rate 15,333.85

Item: plain cement concrete works in superstructure including material collection &30m lead
B. 1:1.5:3 mix
Norms No: 7(4)b,45
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.40 20,804.00 8,321.60
mark)
Agg 20 mm cu.m 0.57 1,850.00 1,054.50
Agg 10 mm cu.m 0.29 - -
Coarse sand cu.m 0.425 2,300.00 977.50
Sub-Total 15,599.60
15 % Overhead 2,339.94
Unit Rate 17,939.54
Item: Reinforcement for RCC works including procuring steel, bending, placing, bindibg and fixing in
position all complite RCC works
Norms No: 40-10
Unit : Kg.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.0070 870.00 6.09
Unskill Md 0.0070 650.00 4.55
Material M.S. Rod MT 0.00105 93,790.00 98.48
Binding wire kg 0.01000 113.00 1.13
-
-
Sub-Total 110.25
15 % Overhead 16.54
Unit Rate 126.79

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:4
Norms No : 38.8-A. c DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.24 md 650.00 2,106.00

Material Cement ( OPC NS


mark) 0.116 MT 20,804.00 2,413.26
RubbleStone 1.10 M3 1,602.00 1,762.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 8,667.46
15 % Overhead 1,300.12
Unit Rate 9,967.58

B. Random rubble Masonary 1:6


Norms No : 6(1)a-3,32
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 5.00 md 650.00 3,250.00
Material Cement ( OPC NS 0.106 MT 20,804.00 2,205.22
mark)
Blockstone 1.00 M3 20,804.00 20,804.00
Bondstone 0.10 M3 1,602.00 160.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 28,805.42
15 % Overhead 4,320.81
Unit Rate 33,126.23

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:6
Norms No : 38.8-A. d DoLIDAR
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.29 md 650.00 2,138.50
Cement ( OPC NS
Material mark) 0.092 MT 20,804.00 1,913.97
Rubble Stone 1.10 M3 1,602.00 1,762.20
Sand 0.50 M3 2,300.00 1,150.00
Sub-Total 8,269.67
15 % Overhead 1,240.45
Unit Rate 9,510.12
B)12.5 mm thick plastering with cement sand mortar on brick wall or concrete surfaces including full
compensation for all labour, materials , scafolding and otter incidental required to complete tte works as per the
specifications
d). In 1:6 mix ratio
Norms No : 37.7-9.4 d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 15.00 md 870.00 13,050.00
Un-skill 13.70 md 650.00 8,905.00
Cement ( OPC NS
Material mark) 0.288 MT 20,804.00 5,991.55
Sand 1.58 M3 2,300.00 3,634.00
Sub-Total 31,580.55
15 % Overhead 4,737.08
Total 36,317.63
Unit Rate 363.18

C)pointing works with cement sand mortar on brick wall with all required operation including full compensation
for all labour, materials , scafolding and otter incidental required to complete tte works as per the specifications

c .In 1:3 mix ratio


Norms No : 37.7-9.3d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 8.00 md 870.00 6,960.00
Un-skill 8.88 md 650.00 5,772.00
Cement ( OPC NS
Material
mark) 0.096 MT 20,804.00 1,997.18
Sand 0.29 M3 2,300.00 667.00
Sub-Total 15,396.18
15 % Overhead 2,309.43
Total 17,705.61
Unit Rate 177.06
Preparation of bedding for pipe with granular materials . It includes all labour,materials.
Norms No : 46 .15-4 DoLIDAR
Unit :1 Cub.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill md 870.00 -
Un-skill 1.00 md 650.00 650.00
Well grage granular
materials passing
Material 4.75mm sieve and
down 1.100 M3 1,400.00 1,540.00
Sub-Total 2,190.00
15 % Overhead 328.50
Unit Rate 2,518.50
Laying,fitting and fixing of hume pipe having a length of 1 m or more. Its includes all operations required to
complete the works upto atrench depth of 2.2 m below the ground level and jointing of pipes with 1:2
cement sand ratio

b.) For every subsequent pipe having length of minimum 1m, Dia 30 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.02 md 870.00 17.40
Un-skill 0.10 md 650.00 65.00
Material Cement 0.001 MT 20,804.00 20.80
Sand 0.002 m3 2,300.00 4.60
Jute, Bitumin LS 30.00 30.00
Sub-Total 82.40
15 % Overhead 12.36
Unit Rate 94.76

b.) For every subsequent pipe having length of minimum 1m Dia 60 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.050 md 870.00 43.50
Un-skill 0.200 md 650.00 130.00
Material Cement 0.003 MT 20,804.00 62.41
Sand 0.004 m3 2,300.00 9.20
Jute, Bitumin LS 40.00 40.00
Sub-Total 285.11
15 % Overhead 42.77
Unit Rate 327.88

Hence,
Total cost of 30cmdia.1m H.P. 94.76
Total cost of 60cmdia.1m H.P. 327.88
Total 45mm dia. H.P.1m(Average cost) 422.64 211.32

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(2X1X 1) (11 m2)
Unit :Per m3 44.2.a DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.09 md 650.00 58.50

Binding wire
Materials 0.95 kg 121.170 115.11
12swg(Heavy Coated)
Sub-Total 173.61
15 % Overhead -
Rate per Box
Size(2X1X1) 173.61
Rate per m3 86.81

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)

Unit :Per m3 44.1.A.ii.b DoLIDAR


Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.13 md 650.00 84.50

Binding wire
Materials 1.3 121.17 157.52
12swg(Heavy Coated)
kg
Sub-Total 242.02
15 % Overhead -
Rate per Box
Size(3X1X1) 242.02
Rate per m3 80.67

Unit rate/m3 Gabion Box


Size(2x1x1) NRs. 86.81
Gabion Box
Size(3x1x1) NRs. 80.67

Average Unit Rate 167.48 86.81 m3


45) Packing and filling of Gabion crates with stone
Unit :1m3 45.17-6 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.3 md 870.00 261.00
Unskilled 0.75 md 650.00 487.50
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 2,510.70
15 % Overhead -
Unit Rate 2,510.70 m3
Providing Mechine Made Heavy coated gabion Box Hexagonal Mesh size 10X12 cm,Mesh wire 10swg
(Heavy Coated),Selvedge wire 8swg (Heavy Coated),Binding wire 12swg(Heavy Coated) at site.

Size Sq.m/box Rate/Sq.


m Rate/Box Rate/Cu.m
Gabion Box 8
Size(1.5x1x1) 297.457 2379.65935 1586.44
Gabion Box 11
Size(2x1x1) 297.457 3272.0316 1,636.02
Gabion Box 16
Size(3x1x1) 297.457 4759.31869 1,586.44
1602.96667

Mechine Made Heavy coated gabion Box 1,602.97 m3


Packing and filling of Gabion crates with stone 2,510.70 m3
Sub Total Cost 4113.67
Assembling 86.81
Total Cost 4200.48
38.8 Dry Uncoursed Rubble Stone Masonry

Norms No : 38-8 DoLIDAR


Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.5 md 870.00 435.00
Unskilled 1.5 md 650.00 975.00
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 3,172.20
15 % Overhead -
Unit Rate 3,172.20 m3

26.3-1 Riverbed Material


Unit :1m3 38-8 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 1 md 650.00 650.00
Materials River Bed Materials 1.00 m3 1400.00 1400.00
Sub-Total 2,050.00
15 % Overhead 307.50
Unit Rate 2,357.50 m3

1 .Transportation of BM Soil by truck or Tractor (15 KMpH)


DoLIDAR
Unit: 10 Cu. M. Norms S.N: 56.2
Spec.C No: G-13.2
Lead source Type Quantity Unit Rate Amount
First 1KM Labour Unskill 1.36 md 650.00 884.00
Material Disel 2.35 LTR 86.50 203.28
Truck/Tractor -
Equipment Working Hr. 0.39 Hr. 300 117.00
Idle HR. 2.21 Hr. 150 331.50
Actul Rate 1,535.78
Unit Rate 153.58

item : laying of locally available granular materials for gravelling in Roadway for gravelling including
j10m lead & 1.5m lift-per m3
particular unit Qantity Rate Amount Remarks
subgrade preparation 10 cm depth
labour unskill md 0.05 650.00 32.5

laying of sub base for gravelling 15cm 0


thick 0
labour unskill md 1.5 650.00 975 pouring &
Material kg km levelling
Transportation upto 4
km for 1m3=1800kg/m3

1800 3.5 0.047 296.1


Sub-total 1303.6
15%overhead 195.54
unit rate 1499.14
3.24
Kathekhola Rural Municipality
Office of the Rural Municipality Executive
Bihunkot, Baglung
Gandaki Province, Nepal

Measurement Book

Project Name:- Homestay paryatan purbadhar karyakaram sanchalan


Homestay Name:- Thuldhunga homestay kadesh
Location:- Kathekhola Rural Municipality-8, Lekhani
Allocated budget(Gandaki Province Office):-1000000
Allocated budget(kathekhola rural municipality):-min 10% of1000000
Salient Features of Project
Project Name :-Pala ward bhavan nirman
Location :-Pala

sfo{qmdsf] gfd
sfd ug]{ lgsfo pkef]Qmf ;ldlt
cfly{s aif{ 074/075
ljlgof]lht jh]6 #REF!
cg'dflgt nfut 1434547.97
sG6LGh]G;L 0.00
pkef]Qmf >dbfg #REF!
v'b e'QmfgL x'g;Sg] /sd #REF!
l;=g sfdsf] ljj/0f

gf]6
ufp+kflnsfsf] sfof{non] pkef]Qmf ;ldlt;+u ;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
dfq ;Demf}tf
!=pkef]Qmf u/fpgsf
;ldltn] gS;f tyfnflu
nfut cg'/f]w
Ol:6d]6 adf]lhd lgdf{0f ubf{ k'/fgf
vfg]kfgL, l;+rfO{, ljBfno ejg, lghL 3/, uf]7, cf+“ug cfbL k"jf{wf/ ;+/rgf Iflt
k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn] cfkm";+u ePsf] ;Demf}tf /sd leqsf]
ah]6af6 dd{t, lgdf{0f jf k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L
kg{ cfPdf pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf ;ldltsf]
vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf ldnfpg'x'g .
@= ;DjlGwt k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf] :jLs[t nfut cg'dfg
Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|ltj4tf lng' x'g .
#= :jLs[t nfut cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non] d"Nof+sg gu/]sf]
v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f P]g @)%# /
jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds k|efj gkg]{ul/ u/fpg] k|ltj4tf
lng'x'g .
Kathekhola Rural Municipality
Office of Rural Municipality Executive
Bihunkot, Baglung

Quantity Estimate

Project Name:- Homestay paryatan purbadhar karyakaram sanchalan


Homestay Name:- Thuldhunga homestay kadesh
Location:- Kathekhola Rural Municipality-8, Lekhani

work name:-view tower and stairs construction


S.N Description of items No Length Breadth Height Quantity Unit Rate Amount
1 Earthwork
land development 0.5 6.00 6.00 0.30 5.40
columns 4 1.50 1.50 1.50 13.50
footing tie beam 4 3.00 0.60 0.60 4.32
stairs 200 1.20 0.45 0.60 64.80
total 88.02 m3 432.6 38077.45
2 Stone soling work
column base 4 1.50 1.50 0.15 1.35
footing tie beam base 4 3.00 0.60 0.15 1.08
floor 1 4.50 4.50 0.15 3.04
total 5.47 m3 2881.5 15761.81
3 Dry wall construction
dry stairs 200 1.20 0.45 0.20 21.60 m3 3454.7 74621.52
4 M15 pcc work (c/s/a 1/2/4)
column base 4 1.50 1.50 0.10 0.60
footing tie beam base 4 3.00 0.60 0.11 0.26
floor 1 4.50 4.50 0.10 2.03
stair pcc
riser 200 1.20 0.08 0.20 3.84
tread 200 1.20 0.40 0.08 7.68
total 14.41 m3 17959.54 258796.97
5 M20 RCC work (c/s/a 1/1.5/3)
footing square part 4 1.50 1.50 0.30 2.70
footing trapezoidal part no volume
4 0.28 1.12
footing tie beam 4 4.35 0.30 0.30 1.57
plinth beam 4 4.35 0.30 0.30 1.57
columns 4 3.00 0.30 0.30 1.08
first floor tie beam 4 6.35 0.30 0.35 2.67
stair
waist slab 1 5.00 1.20 0.10 0.60
rise and treads 15 1.20 0.25 0.15 0.68
first floor slab 1 6.50 6.50 0.13 5.49
total 17.48 m3 19640.12 343309.30
6 Stone masonry work in 1:6 c/s mortar
wall footing 4 4.35 0.45 0.60 4.70 m3 12017.75 56483.43
7 Formworks
plinth beam 8 4.35 0.30 10.44
columns 16 3.50 0.30 16.80
first floor tie beam 12 6.35 0.30 22.86
total 50.10 m2 626.5 31387.65
8 Reinforcement bar
120 kg per cubic m 1 2097.60 kg 125.05 262304.88

9 Railing work using black unit wt


pipe(medium type)
2" pipe(horizontal-4 no) 4 26.00 5.02 522.08
2" pipe (vertical) 12 1.10 5.02 66.26
total 588.34 kg 107.35 63158.30
10 Fabrication cost @10% 1 1.00 job 69474.13 69474.13
11 Brick masonary wall in 1:6 c/s mortar
wall 4 4.00 0.23 3.00 11.04
deductions, door -1 1.00 0.23 2.40 -0.55
deductions, window -2 1.50 0.23 1.20 -0.83
total 9.66 m3 17679.06 170779.72

12 Woodwork ( framework)

door 1 5.60 0.10 0.08 0.04


windows 2 5.00 0.10 0.08 0.08
total 0.12 m3 65450.8 7854.10
13 Woodworks(shutterwork)
door 1 0.80 2.20 1.76
windows 2 1.30 1.20 3.12
total 4.88 m2 6941.57 33874.86
15 Plaster work in 1:4 c/s mortar
wall 1 5.00 3.00 15.00 m2 577.59 8663.85

Estimated amount(NRs) 1434547.97


458.1 18.288

22.86 914.4
Kathekhola Rural Municipality
Office of Rural Municipality Executive
Bihunkot, Baglung
Gandaki Province, Nepal

Measurement Book

Project Name:- Homestay paryatan purbadhar karyakaram sanchalan


Homestay Name:- Thuldhunga homestay kadesh
Location:- Kathekhola Rural Municipality-8, Lekhani

work name:-view tower and stairs construction


S.N Description of items No Length Breadth Height Quantity Unit Rate Amount
1 Earthwork
land development 0.5 6.00 6.00 0.30 5.40
columns 4 1.00 1.00 1.00 4.00
footing tie beam 4 3.00 0.60 0.60 4.32
stairs 101 1.20 0.45 0.60 32.72
Long Stair 45 1.20 1.00 0.60 32.40

total 78.84 m3 432.6 34106.18


2 Stone soling work
column base 4 1.00 1.00 0.20 0.80
footing tie beam base 2 3.00 0.60 0.15 0.54
floor 1 4.50 4.50 0.15 3.04
total 4.38 m3 2881.5 12620.97
3 Dry wall construction
dry stairs 101 1.20 0.45 0.20 10.91 m3 3454.7 75001.54
Dry Stairs for Long 45 1.20 1.00 0.20 10.80 21.71
4 M15 pcc work (c/s/a 1/2/4)
column base 4 1.00 1.00 0.10 0.40
footing tie beam base 2 3.00 0.60 0.11 0.13
floor 1 4.50 4.50 0.10 2.03
stair pcc
riser 101 1.20 0.08 0.20 1.94
tread 101 1.20 0.40 0.08 3.88
Riser Long 45 1.60 0.08 0.20 1.15
Tread Long 45 1.60 0.40 0.08 2.30
total 11.83 m3 17959.54 212461.36
5 M20 RCC work (c/s/a 1/1.5/3)
footing square part 4 1.00 1.00 0.30 1.20
footing trapezoidal part no volume
4 0.28 1.12
footing tie beam 2 4.35 0.30 0.30 0.78
plinth beam 4 4.35 0.30 0.30 1.57
columns 4 3.00 0.30 0.30 1.08
first floor tie beam 4 6.35 0.30 0.35 2.67
stair
waist slab 1 5.00 1.20 0.10 0.60
rise and treads 15 1.20 0.25 0.15 0.68
Ground floor slab & first floor slab 2 5.38 5.22 0.12 6.74
Deduct 1 1.80 0.93 0.12 0.20
total 19.85 m3 19640.12 389856.38
6 Stone masonry work in 1:6 c/s mortar
wall footing 3 4.35 0.45 0.60 3.52 m3 12017.75 42302.48
7 Formworks
plinth beam 8 4.35 0.30 10.44
columns 16 3.50 0.30 16.80
first floor tie beam 12 6.35 0.30 22.86
total 50.10 m2 626.5 31387.65
8 Reinforcement bar
120 kg per cubic m 1 2382.00 kg 125.05 297869.10

9 Railing work using black unit wt


pipe(medium type)
2" pipe(horizontal-4 no) 4 26.00 5.02 522.08
2" pipe (vertical) 12 1.10 5.02 66.26
total 588.34 kg 107.35 63158.30
10 Fabrication cost @10% 1 1.00 job 69474.13 69474.13
11 Brick masonary wall in 1:6 c/s mortar
wall 4 4.00 0.23 3.00 11.04
deductions, door -1 1.00 0.23 2.40 -0.55
deductions, window -2 1.50 0.23 1.20 -0.83
total 9.66 m3 17679.06 170779.72

12 Woodwork ( framework)

door 1 6.40 0.10 0.08 0.05


windows 2 5.30 0.10 0.08 0.08
total 0.13 m3 65450.8 8508.60
13 Woodworks(shutterwork)
door 1 0.80 2.20 1.76
windows 2 1.30 1.20 3.12
total 4.88 m2 6941.57 33874.86
15 Plaster work in 1:4 c/s mortar
wall 0.00 m2 577.59 0.00

Estimated amount(NRs) 1441401.27


458.1 18.288

22.86 914.4
6.4
5.3
sfo{;DkGg k|ltj]bg
sfof{nosf] gfd M– ufp+kflnsfsf] sfo{no d=n]=k=kmf=g+= M–
cfof]hgfsf] gfd Msfb]z ko{6g ka{2g sfo{qmd
7fpF M sf7]vf]nf uf=kf= *
nfut cfg"dfg /sdM– 1434547.97 sfd z'?ePsf] ldltM–
sfo{ ;DkGg ePsf] /sd M– 1441401.30 sfd ;DkGg ug'{+kg] ldltM–
Oi6d]6 eGbf 36L jf a9LM–6853.3 sfd ;DkGg ePsf] ldltM–
nfut sfof{ ;DkGg ePsf] km/s
qm= sfdsf] lhh/0f PsfO{ s}lkmot
kl/df0f :jLst b/ nfut ? kl/df0f :jLst b/ /sd kl/df0f :jLst b/ /sd
1 Earthwork m3 88.0200 432.60 38077.45 78.84000 432.60 34106.18 -9.180 0.00 -3971.27
2 Stone soling work m3 5.4700 2881.50 15761.81 4.38000 2881.50 12620.97 -1.090 0.00 -3140.84
3 Dry wall construction m3 21.6000 3454.70 74621.52 21.71000 3454.70 75001.54 0.110 0.00 380.02
4 M15 pcc work (c/s/a 1/2/4) m3 14.4100 17959.54 258796.97 11.83000 17959.54 212461.36 -2.580 0.00 -46335.61
5 M20 RCC work (c/s/a 1/1.5/3) m3 17.4800 19640.12 343309.30 19.85000 19640.12 389856.38 2.370 0.00 46547.08
6 Stone masonry work in 1:6 c/s mortar m3 4.7000 12017.75 56483.43 3.52000 12017.75 42302.48 -1.180 0.00 -14180.95
7 Formworks m2 50.1000 626.50 31387.65 50.10000 626.50 31387.65 0.000 0.00 0.00
8 Reinforcement bar kg 2097.6000 125.05 262304.88 2382.00000 125.05 297869.10 284.400 0.00 35564.22
9 Railing work using black pipe(medium tykg 588.3400 107.35 63158.30 588.34000 107.35 63158.30 0.000 0.00 0.00
10 Fabrication cost @10% job 1.0000 69474.13 69474.13 69474.13000 69474.13 69474.13 0.000 0.00 0.00
11 Brick masonary wall in 1:6 c/s mortar m3 9.6600 17679.06 170779.72 9.66000 17679.06 170779.72 0.000 0.00 0.00
12 Woodwork ( framework) m2 0.1200 65450.80 7854.10 0.13000 65450.80 8508.60 0.010 0.00 654.50
13 Woodworks(shutterwork) m2 4.8800 6941.57 33874.86 4.88000 6941.57 33874.86 0.000 0.00 0.00
14 Plaster work in 1:4 c/s mortar m2 15.0000 577.59 8663.85 0.00000 577.59 0.00 -15.000 0.00 -8663.85
s'n /sd 1,434,547.97 1,441,401.3 6,853.30

gf]6M–n=O= eGbf a9L eP-±_ jf sd eP-–_ lrGx n]Vg].


!= ljnsf] qmd ;+Vof M clGtd sf7]vf]nf ufp+kflnsf &= ;Demf}tf ldlt M
cfof]hgfsf] gfd Msfb]z ko{6g ka{ufp sfo{kflnsfsf] sfof{no lax'sf]6 *= sfd ;dfKt ug'{kg]{ ldlt M
#= pkef]Qmf ;ldltsf] cWoIfsf] g u08sL k|b]z g]kfn (= sfd gfkL ePsf] ldlt M
$= ;Demf}tf g+= M e'QmfgL ef}r/ g+= M
%= cl3Nnf] e'QmfgL ljnsf] qmd e'QmfgL ldlt M
^= cl3Nnf] e'QmfgL ljnsf] ef}r
cfO pkef]Qmf ;DaGwL lan gfkL lstfj g+= M
6d n=O{= cBfjlws sfd ePsf] cl3Nnf] ljnsf] r9]sf] xfn ePsf] sfd
sfdsf] ljj/0f PsfO{
g+ kl/df0f kl/df0f b/ hDdf d"No kl/df0fhDdf d"Nokl/df0f hDdf d"No s}lkmot
1= Earthwork m3 88.02 78.8400 432.60 34,106.18 78.84 34,106.18
2 Stone soling work m3 5.47 4.3800 2881.50 12,620.97 4.38 12,620.97
3 Dry wall construction m3 21.60 21.7100 3454.70 75,001.54 21.71 75,001.54
4 M15 pcc work (c/s/a 1/2/4) m3 14.41 11.8300 17959.54 212,461.36 11.83 212,461.36
5 M20 RCC work (c/s/a 1/1.5/3) m3 17.48 19.8500 19640.12 389,856.38 19.85 389,856.38
6 Stone masonry work in 1:6 c/s mortar m3 4.70 3.5200 12017.75 42,302.48 3.52 42,302.48
7 Formworks m2 50.10 50.1000 626.50 31,387.65 50.10 31,387.65
8 Reinforcement bar kg 2,097.60 2,382.0000 125.05 297,869.10 2,382.00 297,869.10
Railing work using black pipe(medium
9 type)
kg 588.34 588.3400 107.35 63,158.30 588.34 63,158.30
10 Fabrication cost @10% job 1.00 1.0000 69474.13 69,474.13 1.00 69,474.13
11 Brick masonary wall in 1:6 c/s mortar m3 9.66 9.6600 17679.06 170,779.72 9.66 170,779.72
12 Woodwork ( framework) m2 0.12 0.1300 65450.80 8,508.60 0.13 8,508.60
13 Woodworks(shutterwork) m2 4.88 4.8800 6941.57 33,874.86 4.88 33,874.86
14 Plaster work in 1:4 c/s mortar m2 15.00 - 577.59 - - -
hDdf /sd 1,441,401.3 - 1,441,401.3
! of] lan jdf]lhd e'QmfgL hDd 1,441,401.30 $ s§f ug'{ kg]{ ?=
@ hg;|dbfg 341,401.30 s= k]ZsL 400,000.00
# afFsL lbg' kg]{ ?= v= dfn;fdfgsf] df]n
ufpkflnsf af6 100,000.00 u= cGo
k|b]z ;/sf/af6 600,000.00 % v'b lbg'

k]z ug]{sf] ;xL M hfFr ug]{sf] ;xL M :jLs[t ug]{sf] ;xL M


bhf{ ;a–O{lGhlgo/ bhf{ M bhf{ M
hDdf cIf?kL r]s g+= =======================af6 k||fKt eof] egL ;xL ug]{ .

Das könnte Ihnen auch gefallen