Measuring the
Impact of BIM
on Complex
Buildings
Premier Partner:
Research Partners:
Supporting Partners:
■ Design and Construction Intelligence
SmartMarket Report
A
tool is only as good as High/very high impact ratings for BIM
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
ability of users to demonstrate tangible design earns top ratings from 74% of
and meaningful improvements repeatedly contractors, along with most owners
to a variety of project outcomes, positively (68%) and architects (64%).
impacting all key stakeholders. ■ Owners’ top praise goes to increased
Stephen A. Jones
Because those stakeholders’ fates ability to understand the design (73%), Senior Director
are intertwined, the positive impact of better construction documents (70%), Industry Insights Research
Dodge Data & Analytics
BIM is cumulative through successive and improved ability to plan construction
stages of a project, with design and phasing/logistics (70%). Stephen A. Jones leads
preconstruction benefits contributing ■ Engineers lead in citing improved quality/ DD&A’s Industry Insights
Research division. He
directly to improving downstream function of the final design (71%), which is is active in numerous
construction outcomes. When well also widely appreciated by owners (63%), industry organizations
deployed, BIM can benefit the entire and architects (62%). and frequently speaks at
project delivery process for everyone. industry events around
Examples of specific metrics for outcome the world. Before DD&A,
And, ultimately, owners can leverage key Jones was a vice president
improvements include:
data from model-based processes for with Primavera Systems
■ 40% of owners report that BIM
decades of enhanced operations. (now part of Oracle), a
accelerated project completion by a global leader in project
This study focuses specifically on how
minimum of 5%, and 15% credit it with management software.
much BIM is contributing to improved Prior to that, he was
more than 10% schedule compression.
outcomes in successive stages of principal and a Board of
■ 41% of contractors report that BIM
design and construction on complex Directors member with
reduced final construction cost by at Burt Hill,a major A/E firm
buildings (e.g., hospitals, laboratories,
least 5%, with 8% achieving more than (now merged with Stantec).
manufacturing), where execution is most
a 10% decrease.
challenging, risk is typically greatest and
■ 67% of contractors report a percentage
the need for improvements is critical.
of improved productivity, with 16%
It establishes baselines for:
seeing increases of 25% or more.
• The current level of positive impact
BIM is generating on 23 distinct project We want to acknowledge the support
outcomes in 10 categories. of the U.S. Department of Veterans
• Metrics for the current degree of positive Affairs as the Premier Partner for this
impact from BIM on six of the most research, and their commitment to
important of these outcomes, and a improving project delivery with BIM,
forecast for future impact. as well as numerous other organizations
Donna Laquidara-Carr
• The current state of model usage for who helped to get their members and Ph.D., LEED AP
facility management. customers to complete the survey for Industry Insights
• Factors for success and obstacles this research. Research Director
Dodge Data & Analytics
influencing BIM’s measurable impact. We will continue tracking the impact
of BIM on these and other outcomes in Donna Laquidara-Carr
subsequent studies, and encourage all currently provides editorial
direction, analysis
users to measure the impact BIM is having and content to DD&A’s
on your complex projects. SmartMarket Reports.
Prior to this position,
she worked for nearly
20 years with DD&A’s
Dodge Dodge editorial
team, where , where she
gained detailed insight into
the construction industry.
TABLE OF
CONTENTS
04 Executive Summary
06 Data
06 Introduction
This page:
Left: Edith Green Wendell Wyatt Federal
Building Modernization model, Portland,
Oregon; Below: Modeling for crane swing
review on the Nintendo of America
Headquarters in Redmond, Washington
CONTENTS
Case Studies
21 BIM and Collaboration Deliver Powerful Impacts for Major Hospital Project
The UCSF Medical Center at Mission Bay, San Francisco, California
24 Modeling, Coordination and Prefabrication Lead to Higher Productivity, Reduced Schedule and Improved Safety
Alfred I. duPont Hospital for Children Delaware Expansion, Wilmington, Delaware
52 Small But Complex: A Mechanical Contractor Uses BIM to Tackle Severe Site and Schedule Challenges
University of Massachusetts Boston, Boston, Massachusetts
56 Methodology
57 Resources
Architects, engineers and contractors were asked Metrics for the Impact of BIM on
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
about the impact of BIM on reducing the quantity of Cost, Schedule, RFIs and Safety
RFIs (Requests for Information), often an indicator of (Among Those Rating Medium or Higher
uncertainty, which can lead to changes, rework and BIM Impact on These Outcomes)
degraded performance. Three quarters (74%) see at least Dodge Data & Analytics, 2015
D
odge Data & Analytics (DD&A) has been
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
This part of the study establishes a baseline for the Impact of BIM on Complex Project
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
degree to which users are currently achieving 23 distinct Outcomes (Percentage of High and Very High
outcome improvements from BIM on their complex Ratings, Converted to a 1–10 Scale)
building projects, organized into 10 overall categories, Dodge Data & Analytics, 2015
4_1_1_AA_ImpactIntroOption2_#01.eps
It is widely acknowledged that complex projects are BIM Impact on Owner Engagement
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
usually far more successful when owners are actively and Understanding
engaged and truly understand and participate in the (According to Owners, Architects and Engineers)
proposed design solution. Not only does this help to Dodge Data & Analytics, 2015
optimize the functionality of the final design, it also aligns Very High High Medium
owner expectations more closely with the completed
project, improving the overall experience for everyone. Increased Owners' Understanding of
Owners, architects and engineers were asked to rate Proposed Design Solutions
the impact of BIM on increasing owners’ understanding Owners
of the design. 30% 43% 18% 91%
■ All parties are nearly unanimous in rating BIM as
Architects
having medium or higher impact (84% to 91%).
■ Among owners themselves, about three quarters 27% 37% 24% 88%
(73%) rate it as high or very high, again underscoring its Engineers
importance to that critical group. 21% 38% 25% 84%
The same group was also asked to rate BIM’s impact on
Increased Owners' Ability to Actively
driving higher engagement by owners. Participate in Design Process
■ Owners lead architects and engineers in citing the
Owners
effectiveness of BIM to increase their participation,
20% 30% 35% 85%
emphasizing its value to them.
■ 91% of the respondents who do more than half their Architects
work in BIM rate its effectiveness at medium or higher. 20% 24% 27% 71%
■ No respondents rate BIM as having no impact on
Engineers
increasing owner engagement in the design process.
22% 24% 29% 75%
projects where user needs are critical and modifications (According to Owners, Architects and Engineers)
or “scope creep” can have dramatic impact on budget Dodge Data & Analytics, 2015
and schedule. Owners and design teams are challenged Very High High Medium
to manage the scope of a project as it proceeds through
design, ensuring it provides the greatest value to Increased Ability to Manage Project Scope
end-users, while remaining achievable within time and Owners
cost constraints.
18% 25% 35% 78%
Owners, architects and engineers were asked to rate
the contribution of BIM to managing scope. Architects
■ Owners are most enthusiastic, with over three 12% 23% 39% 74%
quarters (78%) rating BIM impact as medium or higher,
Engineers
reflecting an important improvement in a traditionally
15% 22% 35% 72%
troublesome process.
■ 42% of respondents who do over half their work in BIM
Improved Quality/Function of Final Design
rate its impact as high or very high, compared with just
Owners
17% of respondents with less experience.
30% 33% 30% 93%
The same respondents rated the contribution of BIM to
improving the quality and function of the final design Architects
versus traditional methods of design. 21% 41% 24% 86%
■ Owners are overwhelming in their support of this
Engineers
assessment, with 93% citing this as having a medium 31% 40% 18% 89%
impact or higher.
■ The exceptionally strong response from engineers
The quality of construction documentation and the BIM Impact on Documentation and
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
constructability of the final design are critical to many Constructability (According to Owners,
downstream project activities on complex projects, from Architects, Engineers and Contractors)
estimating and bidding to the number of RFIs and amount Dodge Data & Analytics, 2015
of rework. Previous Dodge Data & Analytics BIM research Very High High Medium
studies around the world have consistently shown
that BIM has a positive effect on reducing rework, and Generated Better Construction Documents
reducing errors and omissions in documentation. Owners
Building on that previous research, respondents
30% 40% 20% 90%
in this study were asked to rate BIM’s contribution
specifically to generating better construction documents Architects
and to improving the constructability of the final design 27% 34% 26% 87%
versus traditional methods. Over half of all respondents
Engineers
were enthusiastic about the positive impact of BIM
28% 26% 27% 81%
on both counts.
■ Owners are particularly supportive, with 90% giving Contractors
medium or higher impact ratings to better construction 24% 35% 29% 88%
documents and 88% to improved constructability.
■ Reflecting their firsthand knowledge, contractors lead Improved Constructability of Final Design
the field for citing improved constructability, with Owners
almost all (98%) rating BIM as having at least a medium 40% 28% 20% 88%
level of positive impact.
■ It is notable that at least four out of five of every type of Architects
respondent rate both these factors very positively. 26% 38% 25% 89%
and Construction SmartMarket Report, published architects, contractors) identified design errors
by Dodge Data & Analytics in 2014. Design errors and design omissions as the second and third
and design omissions in the documentation were most contributing factors to uncertainty, behind
cited numerous times as significant contributors to unforeseen construction issues.
uncertainty on projects, leading to problems with cost, ■ Contractors identified the most frequent types of
of the design for complex projects should create a (According to Owners, Architects,
positive downstream impact on the process and Engineers and Contractors)
accuracy of estimating, and on the accuracy and Dodge Data & Analytics, 2015
The use of models to plan project phasing and optimize BIM Impact on Construction Phasing
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
visualizations are also effective for communicating Very High High Medium
plans to multiple stakeholders.
For this study, owners and contractors were Improved Ability to Plan Construction
asked to rate the impact of BIM on improving both Phasing and Logistics
the ability to develop construction phasing and logistics, Owners
and to convey these plans effectively to owners to 25% 45% 15% 85%
improve their understanding.
■ Both owners and contractors are nearly unanimous
Contractors
in their enthusiasm for the contribution of BIM 24% 39% 27% 90%
to improving phasing and logistics planning, with
Improved Owners' Understanding of
85% and 90%, respectively, rating its impact at Construction Phasing and Logistics
medium or higher.
Owners
■ Owners and contractors are almost equally
25% 38% 20% 83%
enthusiastic about owners’ improved ability
to understand model-based phasing and logistics, Contractors
with over three-quarters citing BIM’s impact as 21% 32% 24% 77%
medium or higher.
The increased certainty provided by modeling during BIM Impact on Cost Control and Reduction
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
design and preconstruction (due to factors like more (According to Owners, Architects,
highly engaged owners, better documented and more Engineers and Contractors)
constructable designs, and more accurate estimating Dodge Data & Analytics, 2015
and bidding) should enable project teams to exert Very High High Medium
closer control of costs during the dynamic process of
procurement, fabrication and installation of the work on Improved Process of Controlling Construction Costs
complex projects. Owners
Respondents were asked to rate the impact of BIM on
13% 28% 25% 66%
controlling costs during construction.
■ Contractors are tasked with controlling costs, and over Architects
three-quarters of them (77%) see at least a medium 9% 16% 36% 61%
level of positive impact from BIM on the process.
Engineers
■ The fact that the range for all the parties is weighted
18% 16% 31% 65%
toward medium versus high or very high indicates
that cost control is still an emerging capability Contractors
and expertise. 11% 27% 39% 77%
■ Importantly, none of the owners say BIM has no impact
Analytics in 2014 identifies interesting trends related to BIM’s contribution to lower project cost among their
both 5D BIM and construction cost reduction. top three factors that would improve ROI on BIM.
Owners, architects, engineers and contractors were BIM Impact on Schedule and Project Duration
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
asked to rate the contribution of BIM to the achievement (According to Owners, Architects,
of planned schedule milestones and to shortening project Engineers and Contractors)
duration by compressing the schedule. Dodge Data & Analytics, 2015
has shown an increasing focus on using BIM to improve key attraction that would encourage them to adopt BIM.
schedule performance.
In The Business Value of BIM for Construction in Global
Reduced project duration as a direct benefit of BIM Markets SmartMarket Report, published by Dodge Data
was studied in The Business Value of BIM in North & Analytics in 2014, results showed global recognition
America SmartMarket Report, published by Dodge Data of BIM’s impact on schedule.
& Analytics in 2012. ■ When measuring the ROI of BIM, schedule-related
■ Over half (53%) of contractors reported the benefit at cited by about a third (29%) of contractors as being among
that level, up from 32% three years previously. their top three BIM-related preconstruction activities.
Preconstruction benefits of BIM related to better and BIM Impact on Unplanned Changes,
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
increase certainty and predictability, thereby reducing a Very High High Medium
number of the problems that traditionally occur during
construction on complex projects. Increased Predictability/Fewer Unplanned Changes
Owners and contractors were asked to rate the degree Owners
that BIM increases predictability during construction,
23% 35% 25% 83%
resulting in fewer unplanned changes.
■ Response was extremely strong for this BIM benefit Contractors
from both parties, with an unusually large proportion 23% 40% 27% 90%
of each (23%) rating the impact as very high.
■ Across project types, manufacturing projects earned Reduced Rework
a very high rating from almost half (48%) of the Owners
respondents who work in that market sector. 20% 33% 23% 76%
The same respondents were asked to rate the Contractors
contribution of BIM to reducing rework during 21% 34% 34% 89%
construction, an all-too-frequent occurrence that almost
always negatively impacts both cost and schedule. Reduced Amount of Out-of-Sequence Work
■ With 89% finding at least a medium BIM impact, Due to Earlier Problems
contractors appear to be the most enthusiastic, which Owners
makes sense because they are on the frontline of 18% 30% 30% 78%
dealing with the multiple negative impacts of rework.
Contractors
■ Owners and contractors who do more than half their
9% 36% 38% 83%
work with BIM are far more supportive, with 28% rating
the impact as very high, versus only 10% of the less
experienced respondents. This reinforces the basic
tenet that greater BIM experience drives higher levels 2_9_Impact_Rework_#01.eps
of benefits.
■ BIM’s impact on reducing rework is most widely noted
In The Business Value of BIM in North America include reduced rework among the top three overall
SmartMarket Report, published by DD&A in 2012: BIM benefits for their organization. This is especially
■ 48% of all respondents (owners, architects, engineers true for contractors from the US (40%) and UK (35%).
and contractors) cited experiencing reduced rework ■ Model-driven layout in the field was top ranked as
on their BIM projects at a high or very high frequency. a frequent construction-phase BIM activity among
■ Contractors named reduced rework as their top
all contractors. This correlates directly to reduced
benefit of BIM, earning that ranking from nearly two rework,due to the ability to leverage the precision
thirds (65%) of contractor respondents. of laser-guided instrumentation and the granular
■ Owners ranked it second, after reduced errors and
accuracy of the model to prevent errors in physical
omissions in documents, which is often a root cause location of work-put-in-place, such as sleeves and
of rework. penetrations in slabs, or embeds for attachment of
In The Business Value of BIM for Construction in Major building envelope elements.
■ Augmented reality, laser scanning for validation of
Global Markets SmartMarket Report, published by
DD&A in 2014: work in place, GPS control of construction equipment
■ 40% of the most highly engaged contractors and model-driven robotics all scored lower for
(most BIM experience, BIM skills and level of BIM frequency, but each also has the potential to reduce
implementation) in the 10 global markets studied are rework. Thus,they can be expected to see increased
experiencing reduced rework at a high or very high popularity in future studies as they become more
level, compared with only 28% of those at the lowest widely available, understood and used.
Improved labor productivity, reduced site labor due to BIM Impact on Labor, Safety and
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
increased offsite fabrication, fewer reportable safety Material Waste (According to Owners,
incidents and less onsite material waste are increasingly Architects, Engineers and Contractors)
popular metrics tracked by project teams leveraging BIM. Dodge Data & Analytics, 2015
This growing popularity is no doubt due to their tangible Very High High Medium
value, potential for rapid scalability across projects and
quantifiable contribution to validating a multifaceted Improved Labor Productivity
business case for BIM. Owners
Owners and contractors were asked to rate the
8% 30% 28% 66%
contribution of BIM to improving labor productivity.
■ Though not garnering a large percentage of very high Contractors
impact ratings, this benefit performed solidly in high 9% 29% 35% 73%
and medium impact designations, especially with
contractors who have the firsthand responsibility for Reduced Site Labor Due to Increased Offsite Fabrication
measuring labor statistics. Owners
■ Experience with BIM has a major impact: 14% of the 8% 32% 30% 70%
respondents that do over half their work with BIM give
Contractors
this a very high rating, compared with only 2% of those
with less experience. 9% 21% 38% 68%
Owners and contractors also rated the impact Reduced Reportable Safety Incidents
of BIM on reducing site labor due to increased Owners
offsite prefabrication. 3% 15% 20% 38%
■ This labor-related factor also scored lightly at the very
high impact level, but it did similarly well in high and Contractors
medium impact ratings. 4% 9% 23% 36%
■ Experience also influences receipt of this benefit, with
over three quarters (78%) of respondents who do more Reduced Material Waste
than half of their work with BIM experiencing medium Owners
or higher impact, versus 56% of less experienced ones. 13% 18% 28% 59%
The finding that over half of owners and contractors systems-related items, such as unused duct runs that
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
give a medium or higher BIM impact rating indicates are often major elements of site waste.
awareness of this benefit and is encouraging.
More detail on the metrics of improved labor productivity,
■ The number of engineers giving a very high impact
reduced site labor due to increased offsite fabrication,
rating (12%) relative to architects (5%) may indicate the
and reduced reportable safety incidents can be found on
greater visibility at the site of the reduction in large
pages 31, 32 and 30, respectively.
In the 2012 Business Value of BIM in North America impact can be seen in the finding that safety metrics
SmartMarket Report, improved productivity ranked as applied to BIM ROI calculations scores as high or
the top metric overall that BIM users believe would have very high with 50% of all contractors, with small
a high or very high impact on improving their ROI for companies (56%) leading large (46%). Japanese firms
BIM (architects 79%, engineers 59%, contractors 85%). (86%) lead other regions in citing safety metrics.
■ Because it affects them more directly, a higher
• Model-driven prefabrication is cited by 43% of training as among the top three activities for which
contractors across 10 global markets as being among their organization leverages BIM during design/
the top three ways their organization leverages BIM preconstruction, ranking it last among 10 choices.
B
IM enables project teams “BIM generates discussion about risk
to incorporate safety more elimination or mitigation before the
effectively into planning.
challenge is staring you in the face.”
As Steve Smithgall, senior
vice president of safety at Balfour
Beatty Construction, puts it, “BIM safety; this is the best way to prevent 2D.” Also, modelers have to
generates discussion about risk incidents. You get an idea in 2D, but be “very knowledgeable,
elimination or mitigation before in 3D you have to think through all understand the modeling process,
the challenge is staring you in the the details and you can’t forget the Z and construction phases and
face. You can model for something [vertical] dimension.” process[es],” Downey says.
as simple as where to locate tie- Realizing the power of BIM, Turner Lack of engagement in BIM by
off points for work at height, or recently used BIM to preplan the pour environmental health and safety
something more complex like process and equipment sequencing managers on the jobsite is another
modeling an excavation to determine for the Wilshire Grand Hotel in Los challenge. Smith says,“Getting
where the top of a slope is located, Angeles, which was “pursuing a them in the room while planning
when shoring is necessary, or when Guinness World Record for the would help.”
you may have an engineered slope largest continuous mat slab pour,”
in play.” Downey says. “We modeled down Using Visualization and
to the level of rebar, then adjusted Gaming Technologies to
Conducting Safety the model from where it deviated Improve Safety Planning
Planning With BIM from the design to account for the With BIM
To illustrate project-wide minimum quantity difference,” she recalls. She To drive deeper engagement Skanska
safety requirements, Lend Lease notes that the potentially dangerous is incorporating augmented reality,
uses safety models during trade 18-hour pour was completed with no “which lets you see behind walls
buyouts. “It can be tough for subs, safety incidents. and identify potential hazards before
so we model and sequence safety At Skanska, project teams find taking action,” says Smith. Skanska
elements to show how to integrate BIM is an effective way to eliminate has also used virtual reality in
them into the workflow,” says risks to welders. Specifically, they hospitals to “understand patient flow,
Alexis McGuffin, Lend Lease BIM use it to detail concrete and steel so by having nurses look at a VR model
integration manager. accurately that the team can cast and help identify possible patient flow
Jennifer Downey, AIA, national the imbeds and the attached beams safety issues,” he continues.
BIM manager at Turner Construction, four levels up without the need Smith further notes that Skanska
New York, N.Y., finds BIM an for a worker to go up an elevator has developed “virtual reality
excellent tool for automated safety shaft to weld it, according to Greg games that set up scenarios for
logistics checking. “We can use BIM Smith, director of virtual design and superintendents and test them to see
to set up rules to evaluate geometric construction at Skanska in Seattle. if they can identify, for example, 10
relationships in models to be sure different hazards.” n
that [safety] requirements—including Challenges
OSHA and local requirements—are Despite these benefits, Smith points
covered,” Downey says. She makes out that “in logistics planning, there
the further point that “Any pre- is still a perception that the cost of
planning processes are important for using 3D BIM is more expensive than
y
Impacts for Major Hospital Project
The UCSF Medical Center at Mission Bay
SAN FRANCISCO, CALIFORNIA
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
New 878,000-square foot UCSF medical complex at Mission Bay in San Francisco
T
he University of California • Accurate MEP (mechanical, MEP Deck Inserts
San Francisco (UCSF) electrical, plumbing) openings Completed 300 inserts per day
■
Medical Center recently in the model minimized RFIs with 99.7% accuracy rate versus
completed a major and come-backs due to held-up typical rate of 125 per day with
new hospital complex in the city’s changes or other trades not conventional methods.
Mission Bay district. Under the completing correctly. • They used model-guided field
direction of J. Stuart Eckblad, ■ Saw a 4% increase in production for equipment to lay out inserts on
FAIA, Director of Design & sheetrock installation, and permitted model.
Construction for the Mission 11% increase of production for
Bay Hospitals Project, the team, taping and finishes. Precast Panels
which included Anshen + Allen • They were able to frame per Achieved installation rate of
■
(part of Stantec Architecture), modeled layout of drywall in 14 to 15 precast panels per day,
DPR Construction and almost
standup (vertical) versus railroading compared with typical rate of
20 subcontractors, collaborated
(horizontal), which minimized 10 to 12.
intensively in a specially created
butt joints and increased finished • Precast panel supports could be
Integrated Center for Design and
quality. detailed during preconstruction
Construction (ICDC) over the course
■ Saw a 6% decrease in waste in and prefabricated onto the
of the three-and-a-half-year project.
drywall and framing material, structural steel.
The team leveraged BIM
compared with 15% typical industry
extensively in this collaborative
environment, and credits numerous
performance. Structural and
positive impacts on project outcomes • These results were achieved by Miscellaneous Steel
to its use. Examples include: extracting material quantities Saved $2 million by prefabricating
■
■
the 300 pile caps were installed in Priority Walls • These are typically field fabricated
exactly the right location. ■ Used fabrication-level output (spool due to complicated detailing.
■ Material waste was less than 6% sheets) from the model to build • They did early coordination
versus typical rate of 15%. MEP penetrations before the MEP in the model with MEP systems
trades arrived, thus eliminating and detailed the supports
Drywall work (and frequent rework) during preconstruction, so they
Saw an 8% increase in production of
■ associated with typical hand layout could be prefabricated with the
full-height framing. and/or cutting the framing later. structural steel. n
Owner Insights
On BIM Impacts on Complex Projects
Eight expert owners agree that, currently, they see the greatest impact
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
from BIM on their complex projects from trade coordination and design.
E
ight owners with proven complex laboratory project that he However, full team engagement is
expertise in the use of attributes to using BIM for trade critical to optimizing this benefit.
BIM on their projects coordination. He notes that this Ryan Marzullo, Delta Airlines,
were asked in a series project in particular had “a very reports that the efforts they put
of in-depth interviews (IDIs) to mature BIM process ... and a lot of into trade coordination during the
evaluate several ways in which coordination upfront.” design phase on their recent project
BIM improves outcomes on their Stuart Eckblad, UCSF, notes that at JFK airport were discarded by
complex projects. The greatest they were “generally always right the construction management team
consensus on value is for trade on schedule or early with the subs’ because they did not communicate
coordination and design, which work” due to the value BIM added effectively with them about it. “We
supports the findings in this to the coordination process. He is an lost the value because of failure in
SmartMarket Report. However, a few advocate for having this take place communication bridging design
owners also reported other aspects as early as possible to support the and construction.” In the upcoming
of their work that BIM impacted opportunity for prefabrication: “The Phase III of that project, he will bring
positively, from planning model allows [mechanical, electrical in the trades early “and get them
to regulatory compliance. and plumbing trade contractors to] involved in the modeling effort,
really think through the sequence especially where we have more
Trade Coordination much better and coordinate that complex problems to solve.”
The top-cited BIM benefit among with all the other trades,” which
the owners participating in the IDIs facilitates prefabrication. Design
is improved trade coordination. ■ Meghan Ruffo, Carolinas There was also broad consensus
A couple of owners provide HealthCare System, sees across all the IDI participants that
specific metrics. trade coordination as connected BIM’s impact on design contributes
Andy Reinach, Alexandria Real to the other benefits she value to their complex projects in
Estate Equities, Inc., reports that experiences from BIM: several important ways.
he sees direct profit from BIM in this “To me, the trade coordination ■ Visualization: Several of the
area: “giving the trades the ability touches on a lot [of benefits], owners point to the benefits
to find issues in real time and work the schedule improvement, of BIM visualization for
them out so that you finish the the quality improvement, communicating with stakeholders
design virtually before you hit the construction activities and the and other team members.
field gives you the best bang for design quality too.”In fact, she • Ruffo states, “Having end
your buck.” credits BIM-supported trade users—nurses, doctors, other
In particular, he notes that on coordination with helping them clinical staff—be able to see the
one recent laboratory project, he achieve a 25% reduction in errors virtual mockups helped them
expected, based on general industry and omissions. better understand the design
expectations, to have around 900 ■ Digby Christian, Sutter FPS, process [and provide more
RFIs. The use of BIM for trade states the importance of BIM information earlier].”
coordination reduced the number for trade coordination quite • Porostosky finds he is able to
of RFIs actually produced on that directly: “Without the ability improve stakeholder satisfaction
project to 200. to push BIM heavily into design with the final building. “Most
Joe Porostosky, Ohio State and trade coordination, it would normal people do not understand
University, also reported a reduction be essentially impossible to build 2D drawing. They think they know
in RFIs and change orders on a projects that are this complex.” what it is, and then invariably, they
get into the space and say, “Without the ability to push BIM heavily into design
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
D
elivering a five- Prefabrication Strategy bathroom pods, 152 overhead MEP
story, 414,000-square Skanska was awarded the job racks and 144 patient headwalls.
foot expansion with after design documents from FKP Crews worked at an offsite
emergency department, Architects were complete. In order warehouse, approximately 10 miles
ICU, inpatient bed and surgical bed to preserve the design and maintain from the jobsite. By building offsite
capabilities to an existing hospital schedule, Skanska proposed in a controlled environment, the
comes with inherent complexities extensive use of prefabrication. team could better control schedule,
and challenges. Add in the fact that Although meeting the November eliminate waste, enhance quality and
the entire building was designed on 2014 completion date was a concern, improve safety.
a six-degree radius, and the team Hawthorne says Skanska trusted “Everyone works at waist height
needed to explore ways to ensure that if more time was committed like an assembly line,” says Matt
accuracy and preserve schedule. toward early prefabrication design Pentz, senior MEP project engineer.
“Everything was on a radius,” and coordination, construction time “We had zero accidents, and there
says Bill Hawthorne, project would be reduced. are never bad weather days when
executive at Skanska USA. “There “We gave them more time upfront you’re in the warehouse.”
wasn’t a straight wall in the place, to do the design,” he says. “Take a The MEP racks and bathroom
even the mechanical rooms in the few months upfront to do the mock- pods needed to be engineered
basement were on a radius. We ups and get the decisions made right. to a curved corridor, so materials
needed a high level of precision.” If we prefab it, we can make up that like copper pipe were ordered
The team’s plan included time difference in the construction. “pre-bent” from suppliers to
Photo courtesy of Skanska USA Building
uses of BIM for 4D scheduling, The end-date won’t move.” avoid the need to bend and stress
3D coordination, logistics, A BIM manager, IBSECAD, was them during assembly.
prefabrication, virtual and hired to maintain a single-source Prefabricated pieces were
physical mockups, digital layout model for all trades involved in delivered to the site as needed,
and barcode tagging for supply prefabrication. The prefabrication reducing the need for onsite storage.
chain management. strategy included building 144 On average, teams delivered 12
CONTINUED
TI
N
CO
st
at
racks per day. Around 40% of and Figures
s
the square footage of work was Construction Manager
completed at the prefabrication Skanska USA
warehouse, making the hospital Type of Project
jobsite significantly less congested. Hospital expansion with ground-
Barcode tagging was used to level parking garage
coordinate prefabricated modules Size
The entire building was designed on a
from warehouse fabrication to six-degree radius. 414,000 sq. ft. over 5 stories
onsite installation. The team Demolition
printed barcode stickers for each “[Crews] could install 14 to 18 March 2011
prefabricated component, and then panels per day because of how good
Completed
the barcodes were scanned with the coordination was,” he says. November 2014
an iPad camera and tracked in the “Typically, they might install six to
system with associated equipment, eight per day.”
documents and locations. The team Digital layout was another critical BIM-Related Results
created a status system to track component of the team’s strategy. A strategy that relied heavily
completion of components through Pentz says the team pushed for on prefabrication reaped a
schedule of delivery to the site. digital layout in part because variety of benefits:
Skanska recorded no rework the complex design had zero
associated with prefabrication. dimensions. “We saw it as really ■■ Two months schedule savings
For inspections, the jurisdiction the only way to do layout,” he says. ■■ 50% less time needed for layout
was brought into the prefabrication “Without dimensions, layout would by using digital process
warehouse once to sign off on all have been nearly impossible.”
■■ Zero injuries in warehouse
operations, rather than the typical For the bathroom pods, layout
■■ No rework needed on
process of conducting inspections on points were identified by the
prefabricated pieces
an ongoing basis. plumbing subcontractor, the
Based on the time savings concrete subcontractor and Skanska. ■■ Streamlined delivery and
accrued through construction In the field, the digital layout installation with barcoding
time, inspection time and reduced process was guided by a virtual
rework, Skanska estimates that model and allowed the team to
the prefabrication strategy saved layout approximately 500 points a
about two months on the overall day with one person.
project schedule. That translates The plumbing subcontractor Skanska estimates that digital
into a more than 10% savings on was responsible for the sleeve layout offered 50% time savings
the construction schedule. positions of the drain, sanitary and compared with a manual process.
vent lines.The drain was the most Without digital layout, Pentz says the
Other Modeling critical to align with the prefab team would have achieved 250 points
Advantages bathroom being set in the depression. a day with two people. “We never
Skanska credits modeling and The concrete subcontractor had would have achieved that without
Image courtesy of Skanska USA Building
coordination for speeding installation to maintain 1-inch oversize and digital layout” he says. “Quality
of other building components as make sure crews were spot on as was improved and the production
well. Hawthorne says installation the curtainwall was ½ inch from the achieved was unreal.” n
time for the building’s panelized prefab wall. When setting the prefab
curtainwall system was reduced pods, crews had to maintain the
by more than 50%. layout inside the depression.
This section of the study focuses on quantified impact For simplicity of reporting, the responses of architects
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
metrics for six specific outcomes on complex projects: and engineers are shown combined to reflect a unified,
■ Percentage Reduction of Final Construction Cost design team perspective.
■ Percentage of Accelerated Project Completion Due
The chart at bottom shows the percentage of each
to Schedule Compression
type of respondent who identifies the middle or higher
■ Percentage of RFI Reduction
range for degree of impact for these six outcomes. We
■ Percentage Reduction in Number of Reportable
expect that the proportion of users experiencing these
Safety Incidents
top level outcome improvements will grow significantly
■ Percentage of Improved Labor Productivity
in future studies.
■ Percentage Reduction of Site Labor Due to Increased
It is worth noting that each of these six outcomes
Offsite Fabrication
scores relatively low in the BIM impact ratings set
To capture these metrics, any respondent giving a forth earlier in this report, suggesting that they are still
medium, high or very high impact rating to one of these emerging. (See page 7 for a clear representation of how
six outcomes from the first part of the study was then each of the 23 measures performs on a one to 10 scale.)
asked to select a percentage range for the actual degree Their quantified scores in this part of the study will offer
of impact experienced. The ranges of impact were the opportunity to track the degree of progress over the
developed with input from experienced industry sources coming years as users advance in their effectiveness
and vary based on the expected degree of current and in using BIM, compared with the already highly ranked
potential impact on each outcome. outcomes where the impact of BIM is more established,
■ The ranges of the percentage impact choices for cost, and future increases are likely to be incremental. We
schedule, RFI’s and safety metrics are relatively low (in anticipate adding more outcomes to this quantified
increments of 5%, from less than 5% to more than 10%). metrics evaluation process in future studies.
■ The ranges for labor productivity and reduction of site
Higher-Scaled Metrics More Than 25% More Than 25% More Than 25%
Percentage of Improved Labor Productivity 10% 16% 13%
While over half (53%) of all respondents give a medium, Percentage Reduction of Final Construction Cost
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
high or very high rating to the impact of BIM on reducing (According to Owners, Design Teams and Contractors)
the final construction cost of complex projects, there is Dodge Data & Analytics, 2015
significant variety among the individual responses of BIM Has Medium or Higher Impact on Final Cost
contractors (64%), owners (45%) and design teams (37%) and Know the Percentage of Impact
who can provide a percentage of reduction experienced. BIM Has Medium or Higher Impact on Final Cost
The fact that contractors most commonly report a But Not Sure of Percentage of Impact
medium or higher impact on cost is important because Low/No/Don't Know Impact of BIM on Final Cost
they are most closely involved with managing the costs.
Therefore, they are in the most qualified position to Owners
make this judgement. In fact, the disparity in perceptions
across the groups may reflect their relative distance from Percentage of Impact
exposure to the direct cause-and-effect relationship More Than 10% 11%
42% 45%
between BIM and cost on a day-to-day basis throughout 5% to 10% 56%
the course of a long and complex project. So the lower
Less Than 5% 33%
ratings from owners and design teams may just reflect 13%
lack of familiarity rather than informed dissent.
Roughly 10% more respondents overall report that they Percentage of Accelerated Project
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
see at least a medium impact from BIM on accelerating Completion Due to Schedule Compression
project completion than they do on reducing final (According to Owners, Design Teams
construction cost. and Contractors)
■ Among all respondents, almost six in ten (59%) give Dodge Data & Analytics, 2015
it a medium, high or very high impact rating for BIM Has Medium or Higher Impact on Completion
accelerated completion, compared with 53% who give and Know the Percentage of Impact
that rating for cost reduction. BIM Has Medium or Higher Impact on Completion
But Not Sure of Percentage of Impact
■ Experienced users report more impact on accelerated
Low/No/Don't Know Impact of BIM on Completion
completion, with 11% of those who do more than half
their work with BIM rating its impact as very high,
versus just 4% of the less experienced respondents.
Owners
Owners and contractors are more closely aligned on the Percentage of Impact
meaningful impact of BIM on schedule than on cost. More Than 10% 27%
■ The percentages of contractors (61%) and owners 35% 55%
5% to 10% 46%
(55%) seeing at least medium impact are much more
similar than the percentage of those reporting medium Less Than 5% 27%
10%
or higher cost impacts (64% and 45%, respectively),
suggesting greater consensus on this outcome.
■ The impact of BIM on schedule acceleration is also Architects and Engineers
supported by the related findings on BIM’s ability to
improve the achievement of planned milestones (see Percentage of Impact
page 15), for which 77% of contractors and 78% of More Than 10% 29%
owners report medium or higher impact. 46% 46%
5% to 10% 53%
Since owners are typically not directly involved Percentage of RFI Reduction
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
with the RFI workflow, only contractors and design (According to Design Teams and Contractors)
team members were asked to identify the percentage Dodge Data & Analytics, 2015
that RFIs are reduced on their BIM projects. BIM Has Medium or Higher Impact on RFI Reduction
The impact of BIM on RFI reduction is the highest and Know the Percentage of Impact
among all six major metrics studied in this report. BIM Has Medium or Higher Impact on RFI Reduction
But Not Sure of Percentage of Impact
■ Almost three quarters (70%) of all respondents give
Low/No/Don't Know Impact of BIM on RFI Reduction
BIM a medium, high or very high rating for its impact
on reducing RFIs, compared with 53% and 59% at that
level for cost and schedule improvement. Architects and Engineers
■ Although the overall response is highly positive,
Percentage of Impact
significantly more contractors (81%) report a
medium or higher impact on RFI reduction than 34% More Than 10% 48%
56%
do engineers (71%) or architects (64%), indicating 5% to 10% 37%
an interesting divergence of perspectives between
Less Than 5% 15%
the parties that generate RFIs and those that receive 10%
them in this biaxial workflow.
■ Experienced users report more impact on
(57%) report more than 10% RFI reduction than 3_3_RFI metrics charts_#02.eps
architects (45%), perhaps showing the downstream
benefit of more collaborative and integrated design
activities with trade contractors and fabricators.
■ 65% of structural engineers report more than 10% RFI
Percentage Reduction
in Number of Reportable Safety Incidents
industry has established standard methods for tracking Reportable Safety Incidents
contractors’ safety performance that are now widely (According to Owners and Contractors)
accepted. The number of reportable incidents is one of Dodge Data & Analytics, 2015
those standard methods and provides a useful metric to BIM Has Medium or Higher Impact on Safety Incidents
determine the impact of BIM on safety. and Know the Percentage of Impact
Owners and contractors were asked for the percentage BIM Has Medium or Higher Impact on Safety Incidents
But Not Sure of Percentage of Impact
reduction in reportable incidents on their BIM projects.
Low/No/Don't Know Impact of BIM on Safety Incidents
■ Although the use of a reportable safety incidents
Forecasts for the construction industry agree that labor Percentage of Improved Labor Productivity
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
supplies will tighten over the coming years. Therefore, (According to Owners and Contractors)
the promise of improved labor productivity from model- Dodge Data & Analytics, 2015
based processes will become more critical as a metric BIM Has Medium or Higher Impact on Labor Productivity
for BIM, and its demonstrated effectiveness will greatly and Know the Percentage of Impact
raise its value. BIM Has Medium or Higher Impact on Labor Productivity
But Not Sure of Percentage of Impact
Importantly, two thirds (66%) of owners and three
Low/No/Don't Know Impact of BIM on Labor Productivity
quarters (73%) of contractors state that BIM has a
medium, high or very high impact on improving labor
productivity. This is a highly validating finding for this
Owners
important metric.
Percentage of Impact
■ Owing to their focus on and responsibility for
34% More Than 50% 0%
labor productivity, only a small percentage (6%) of
48% 21%
contractors were not able to assign a percentage to the 25% to 50%
improvement achieved on their BIM projects. 18% Less Than 25% 79%
■ Among project types, 90% of owners and contractors
The expanded opportunity for offsite and near-site Percentage Reduction of Site Labor Due to
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
around the world. This is fueling an accelerating industry BIM Has Medium or Higher Impact on Site Labor
shift toward prefabricated and modular assemblies, and Know the Percentage of Impact
instead of onsite construction from raw materials and BIM Has Medium or Higher Impact on Site Labor
But Not Sure of Percentage of Impact
components. The resulting reduction in the requirement
Low/No/Don't Know Impact of BIM on Site Labor
for relatively expensive and increasingly scarce site labor
is a measurable benefit of this trend and a tangible metric
to validate the use of BIM. Owners
Similar to the labor productivity metric, a very large
Percentage of Impact
portion of respondents (70% of owners and 68% of
contractors) believe that BIM-related prefabrication is 30% More Than 50% 0%
53% 14%
having a medium or higher impact on reducing site labor. 25% to 50%
■ Even more (78%) respondents who do at least
17% Less Than 25% 86%
half their work in BIM believe it has a medium or
higher impact, so the benefit increases with greater
BIM implementation.
■ Similar to the findings for productivity, a very small
Contractors
percentage (4%) of contractors in this group were not
Percentage of Impact
able to assign a percentage to the reduction in site
More Than 50% 3%
labor, underscoring their attention to labor utilization on
32% 64%
complex projects. 25% to 50% 30%
Less Than 25% 67%
Percentage of Impact
Owners and contractors were asked to identify the 4%
percentage range of reduced site labor due to increased
prefabrication on their complex BIM projects. Similar to
the scaling for improved labor productivity, these ranges 3_5_Red Labor from PreFab charts_#02.eps
(in increments of 25%, from less than 25% to more than
50%) are intentionally higher than the cost, schedule,
RFI and safety metrics in this study (see pages 27–30), in
order to establish an aggressive baseline against which to
track what is anticipated to be strong future growth.
Among respondents who can assign a percentage to
their labor productivity improvement: ■ Similar to productivity, BIM experience has a
■ More than twice as many contractors (30%) report the moderate influence, with 30% of all the respondents
reduction to be in the middle tier (25% to 50%) than who do more than half their work in BIM reporting
owners (14%), which likely relates to the level of detail middle-tier results, compared with 21% of those with
at which contractors track site labor compared with less experience.
owners, rather than an evidence-based difference of ■ A small (3%) but important portion of contractors are
opinion. The relatively large percentage of owners (17%) currently reporting greater than 50% reduction in site
who, though they believe model-driven prefabrication is labor due to increased prefabrication. We anticipate
reducing site labor, cannot assign an actual percentage that studies will reveal a much higher percentage in this
to it supports that inference. tier as this trend continues to grow.
Among the six outcomes where metrics for the impact of “Reduction of final construction cost” and “RFI
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
BIM are included in this study, all respondents who were reduction” tie for second in terms of the average across
asked about those metrics were also asked to designate all types of respondents. Importantly, though, the cost
the one they believe will have the greatest impact over the reduction metric scores more strongly with owners,
next five years. indicating that they increasingly expect to see cost
“Accelerated project completion due to schedule improvement from teams deploying BIM.
compression” is the outcome that scored highest. “Improved labor productivity” ranks fourth out
■ This is also currently one of the leading impacts overall; of six. Interestingly, engineers lead in the percentage
so many users clearly believe that this will continue to selecting this impact. Engineers may see more potential
be highly impactful. gains in mechanical, electrical, plumbing and structural
■ Interestingly, contractors are the least likely to select productivity, achievable through increasing model-based
this outcome, indicating either that they believe future integration of design with fabrication/installation.
improvements will be limited or, more likely, that they Although ranking fifth overall, the fact that owners
simply expect more growth elsewhere (e.g., cost, RFIs). cite “Reduction of site labor due to increased offsite
■ The No. 2 ranking among owners clearly indicates fabrication” top among these six outcomes should be
that owners will be expecting improved schedule noted by project teams as indicating that owners will
performance from their BIM project teams. expect to see this impact on future projects.
“Reduction in number of reportable safety incidents”
ranks last. This certainly does not mean it is considered
unimportant as a desired outcome, but more likely
provides further evidence that the direct connection
between BIM and improved safety is still emerging
compared with the other five outcomes studied.
Project Outcome Expected to Have the Greatest Positive Impact From BIM in the
Next Five Years (Respondents Could Only Select One Outcome)
Dodge Data & Analytics, 2015
Selected by Over 25% Selected by 15% to 25% Selected by Less Than 15%
Owners Architects Engineers Contractors Average
Accelerated Project Completion Due to Schedule Compression 31% 42% 31% 12% 29%
Reduction of Site Labor Due to Increased Offsite Fabrication 34% 0% 0% 21% 14%
F
aced with the complexities Early Engagement through the demolition area.
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
of building a new patient Early on, the team evaluated Mortenson was able to identify
tower that is bounded on massing and site design options and reroute utilities, scheduling
three sides by an operating to determine the best location for shutdowns and reconnects in
hospital, the team on this Central the tower. The selected configuration conjunction with hospital staff.
Washington Hospital project used for the 6 story 288,415-square foot Key trades, including mechanical
a comprehensive BIM strategy tower maximized adjacencies to and electrical, were brought in at the
that ultimately led to 10 weeks of existing hospital departments, end of the schematic design to help
schedule savings and created $7 took advantage of views of the with the effort.
million in budget savings that was nearby Cascade Mountains and “A huge part of that effort was
passed on to the owner. fit within the hospital’s 15-year refeeding the chilled water for the
The team of Mortenson campus master plan. building,” Hodge says. “The chilled
Construction and architecture The plan called for demolition water for the whole campus came
firm HDR worked closely with the of 30,000 square feet of existing through the demolition site. The
owner to execute a BIM plan that hospital space. The existing building old feeds were built in the 1970s,
carried through the project from had been constructed over many and they were degrading to near
early design visioning to post- phases and several years, resulting failure. We also needed to replace an
occupancy facilities management. in inconsistent foundation elevations existing chiller plant. We had a six-
Although HDR and Mortenson and roof heights. Mortenson month window during the winter,
held separate contracts with the modeled existing conditions and when we had to refeed the whole
owner, Mortenson was selected provided those to the architect to hospital. We originally had the chilled
three weeks after HDR, allowing inform ongoing design. water going up to the first floor then
the contractor to assist with the coming back down. When we looked
design. “It was very collaborative Systems Coordination at the schedule of the structure, we
from the get-go,” says Gene Hodge, The team also had to consider the weren’t able to support it. So we
director of project development at impact on hospital operations. were put in a position to bring in
Mortenson Construction. Eleven different utilities passed chillers temporarily. We used BIM
CONTINUED
TI
N
CO
water mains at the ground level.” During construction, the owner Project Facts
st
at
Early modeling helped the team decided to change the patient lifts and Figures
s
develop an approach that allowed used in the hospital. “We did have Construction Manager
many utilities to be permanently— to go back and re-coordinate some Mortenson Construction
rather than temporarily—rerouted, above ceiling space, but we were Type of Project
saving more than $200,000 in costs. able to work from the model, so it Hospital Patient Tower/
Modeling also enabled designers to was very straightforward—not a big Expansion
reduce the floor-to-floor heights from challenge,” Hodge says. Size
16 feet to 15 feet 6 inches on the upper 288,415 sq. ft. over 6 stories
floors, saving an additional $120,000 Critical Communication Completed
in enclosure and structure costs. Interaction with the model was February 2011
Through use of coordinated not limited to the project offices—
models, trade contractors were crews were also able to access
BIM-Related Results
able to prefabricate a total of 144 BIM in the field via wireless access
headwalls in the hospital. points. Field personnel could The BIM strategy led to 10
A mockup was provided to the reference the model at mobile weeks of schedule savings and
owner to approve final locations computer stations. Tablets were $7 million in budget savings:
for all utilities. Prefabrication was also used to help with tasks such as
executed to an accuracy within 1/8 inspections (including in-wall and ■■ 50% reduction in RFIs
inch. Coordination and prefabrication overhead) and punch lists. This saved ■■ $200,000 in savings during
of the headwalls saved an estimated hours of time that would otherwise utility relocation
18% in manhours, including four be spent traveling between the ■■ Prefabricated headwalls saved
weeks on interior rough-in and three jobsite and the project trailer. an estimated 18% in manhours:
weeks on casework. Throughout the entire project, four weeks on interior rough-in
The exterior framing subcontractor BIM was used extensively to and three weeks on casework
was able to collaborate with the team communicate with key stakeholders. ■■ Prefabricated exterior framing
to prefabricate the enclosure system. The architect and contractor worked saved six weeks on the exterior
Mortenson estimates that by using with the owner, hospital maintenance framing schedule
this coordinated system to eliminate staff and physicians to inform the
potential conflicts and speed design and construction plan.
installation onsite, the prefabricated Virtual mockups allowed users
exterior framing saved six weeks on to visualize and provide feedback
the exterior framing schedule. on potential designs for patient use for building operations in the
During interior rough-in, the team rooms, nurse stations, lobbies future. At occupancy, maintenance
relied on scheduling—planned one and the business center. Prior to staff was able to use touchscreen
year earlier—to start drywall on construction, key hospital staff computers to access the model,
time. Crews eventually met the final reviewed the operational access linked electronic documents, in-wall
acoustic ceiling tile date eight weeks required for future maintenance and photos, electronic O&M manuals and
ahead of schedule. repair. Mortenson estimates that this shop drawings.
Ultimately, the team’s coordination approach reduced the potential for “The facilities director was heavily
efforts with BIM resulted in a 50% costly design changes during later involved,” Hodge says. “He told us
reduction in RFIs, compared with a phases of the project, contributing to that when we came in and talked
similar project that did not utilize BIM. the project’s early completion. about BIM, he didn’t believe in it.
Although the team worked Upon completion, the team But when we were done, he said,
together to anticipate all needs as provided a model that the hospital’s ‘I don’t know how you’d build a
early as possible, they did have facilities management group could building without it.’” n
As the responses of the owners who participated in the Frequency With Which Owners Receive
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
in-depth interviews for this report reveal, many owners Models on Their Projects
familiar with BIM in the US regard the ability to use it for (According to Contractors and Owners)
the management and operation of their buildings after Dodge Data & Analytics, 2015
construction to be a significant part of the value of BIM for Contractors Providing Owners Receiving
their organization (see page 41 for more information). Models to Owners Models on Their
Projects
However, few owners in the US are currently 3%
capitalizing on this opportunity. According to the 2014 10%
15% Always
Business Value of BIM for Owners SmartMarket Report, 15% 22%
Frequently
over two thirds of owners in the US report that they
Occasionally 28%
had little or no capability to leverage BIM for building
30% 37% Rarely
operations after construction.
40%
Never
Delivery of Models to Owners
Interestingly, despite this low level of use, this study
finds that over half of contractors (52%) frequently/
always provide models to owners at the close of
2_1_E1E6_ProvideModels_#02.eps
construction. Not surprisingly, a higher percentage
of general contractors (58%) report doing so than do
trade contractors (33%).
The contractor findings are also roughly proportional
to the owner findings, where 62% report frequently or
always receiving models on their projects.
Both contractors who use BIM on 50% or more of their
projects and large contractors also report delivering
models more frequently to owners:
■ 68% of contractors using BIM on 50% or more of their
where nearly all respondents (87%) report that Frequency With Which Owners Receive Data
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
they have at least moderate ability to leverage BIM Derived From Models on Their Projects
for facility management. (According to Contractors and Owners)
While a similar mandate in the US is not likely Dodge Data & Analytics, 2015
because of the number of different, independent Contractors Providing Data Owners Receiving Data
government agencies handling public construction, Derived From Models to Owners Derived From Models
efforts to use COBie (Construction-Operations Building 5% 5%
Information Exchange) standards to help make data more 10% 9% Always
accessible to owners may eventually add to the value
Frequently 22% 19%
owners find in BIM. 21%
26% Occasionally
Delivery of Data Derived Rarely
49%
From Models to Owners 34% Never
Less than one third (30%) of contractors are currently
providing data derived from the models for owners
to use in facility management. Even though a smaller
percentage are delivering data versus models, the same
2_2_E1b-E6b_ProvideData_#02.eps
patterns evident in the delivery of models also hold for
the delivery of data, just on a smaller scale:
■ General contractors (35%) are more likely to deliver
Use of models for facility management presents one of Owner Engagement With Models for FM
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
the greatest opportunities for owners to gain value from (According to Owners Who Receive Models at
the use of BIM, not just during design and construction, Least Occasionally)
but across the lifecycle of their projects. While many Dodge Data & Analytics, 2015
owners are now receiving models on their projects (see Always/Frequently Occasionally
page 36), the study findings show that use of the models,
or the data within the models, during the building’s Require Models
operational phase is still quite limited. 86% 11% 97%
The first chart at the right represents the owners’
responses about their requirements for, standards for Have Specific Standards for Models
and use of models. The second chart represents 66% 17% 83%
contractor responses about owner requirements,
Actively Use Models for FM
standards and use of models.
17% 43% 60%
Models
USE OF MODELS FOR FM
While 86% of owners who receive models at least
occasionally state that they frequently or always require Owner Engagement With Models for FM
2_4_E7-OW_ModelRequirements_#02.eps
the use of models on their projects, only 17% report (According to Contractors Who Provide Models to
always or frequently using BIM models for facility Owners)
management (FM). Certainly, there are factors that could Dodge Data & Analytics, 2015
even well-informed owners are still struggling to use Owner Requirements for/Use of Data
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
Nearly three quarters (74%) of owners who use models Owner Organization Is Receiving Tangible
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
or the data derived from models for facility management Value From Models or Data Derived From
(FM) believe that this offers them tangible value. While Models for Facility Management
the number of owners in the survey who are using (According to Owners Using Models and/or
models or data for FM is relatively small, their evaluation Data for Facility Management)
of specific benefits reveals clear trends about where Dodge Data & Analytics, 2015
they find the greatest value and provides objectives for Strongly Agree
owners who want to join them. Agree
■ The benefit experienced most widely is the ease of
Neither Agree nor Disagree
accessing data when needed, reported by over 80% of
Disagree
owners using models/data for FM. Models can contain
not only as-built information that accurately indicates
the location of all building elements in a graphical 13%
image, but they also can include critical information like
29%
when to perform scheduled maintenance. Access to this 13%
information saves valuable time for building managers
and helps them operate the building more efficiently.
■ Over half of the owners also find that using models/
45%
data for FM helps with space management. Having an
accurate, as-built version allows facility managers to
more easily engage in space management, including the
ability to plan alteration projects with greater certainty.
■ Approximately one third of owners agree that they are
One ofte-cited study is Graham Ive’s 2006 report “Reexamining the Costs and Value Ratios of Owning and
Occupying Buildings.” One such citation is found in a U.S. Forest Service Document on calculating building
lifecycle costs at http://www.fs.fed.us/t-d/pubs/htmlpubs/htm08732839/page01.htm.
Even among the expert owners included in the owner IDIs, only a few are using
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
Use of BIM for Facility • They have all the as-builts. the level on the model that can
Management (FM) • They have preventative actually be of purpose to a director
Out of the eight expert owners maintenance information on iPads of engineering ... So what we would
interviewed, only two actually report that are embedded in the model. love to see is to be able to have all
using models or data derived from “If there’s an issue anywhere, they those barcodes on there for all your
them in their facility management can zoom in on the model.” PMs. That would be fantastic.”
program. However, all but one of • They can track how specific Joe Porostosky from Ohio State
those who are not using it right now equipment is running in their University is aggressively pursuing
consider it a strong opportunity for building management system. the use of BIM for FM by modelling
the future. • They can remotely troubleshoot 35 million square feet of his current
issues like temperature and building portfolio.
CURRENT VALUE REPORTED
contact someone onsite to make Porostosky is attempting to
FOR MODELS/DATA FOR FM
adjustments at a specific VAV box. address the challenge of accessing
Meghan Ruffo from Carolinas
needed data at the appropriate level
Healthcare System reports that However, he believes that this is just
from BIM for his FM team with clear
they are able to use models in their the start and that within two years,
direction about what the model
space management system and to they may be doing things differently
needs to contain in order to achieve
populate the data from the model in “because it [BIM] is going to evolve
their goal of using it more effectively
their enterprise asset management that rapidly.”
during facility management: “We’re
system. She reports that the time
telling [the project team] ‘Here’s
required to input data for space Expected Future Value what we want to see at the end of
management has been cut from of BIM for FM the project very specifically’ ... It’s
40 hours to one hour because now Among the remaining six owners
COBie-light, we want specific fields
a data transfer can automatically who are not currently using BIM
per different type of asset or piece of
populate the data into their system. for FM, only Digby Christian from
equipment.” (For more information
Creating requirements for the Sutter FPS does not necessarily
on COBie, see page 37.)
model is an important part of this believe that he will see great
Stuart Eckblad from UCSF raises
program. Ruffo states, “We have value from its use in the future,
the question of what the scale of the
pretty detailed requirements: We have because he believes that most
project needs to be for there to be
a template that everybody has to use, FM needs can be addressed in a
sufficient value in creating the model
we have tools or add-ins that we’ve “two-column spreadsheet with the
for use in FM, but he is unambiguous
developed that check the models at equipment number and the room
about its value for complex buildings:
each milestone phase and also help it is in.” However, the other five
“For complex buildings like hospitals
with the input of some of the data that owners express a strong desire
and labs, I think there is no question
we require from our consultants.” to find ways to utilize BIM in their
that [FM] is really the future of the
Andy Reinach from Alexandria building operations.
whole BIM ... if I get to FM, I’ll be
Real Estate Equities Inc. reports Denton Wilson from Methodist
pretty happy.” n
that his company manages the Health System explains the
laboratory spec buildings they build, opportunities and the challenges he
so being able to use BIM for FM is sees: “At this moment, the models
important to him. His engineers use are so big and cumbersome, we
the model as follows: haven’t found a tool that sucks out
Project Processes
That Contribute Most to the Success of Complex Projects
The construction industry has been grappling with Project Processes That Contribute
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
how to improve the processes involved in the design Most to the Success of Complex Projects
and construction of a project. The need to make these (According to Owners, Architects,
improvements is magnified on complex projects, where Engineers and Contractors)
the results of inefficient processes can be detrimental Dodge Data & Analytics, 2015
and suggests that the value placed on collaboration and full collaboration through integration. That conflict is
teamwork does not extend to full project integration for evident in the widespread, general recognition of the
many of these respondents. need for collaboration/teamwork and indications in
the findings of a persistent, traditional mind-set that
EARLY TRADE CONTRACTOR INVOLVEMENT
favors players’ individual contributions rather than an
Not surprisingly, nearly all (96%) trade contractors
emphasis on creating an integrated project team.
consider this an important contribution to the success
■ They suggest a leadership role for the owner in
of a project, and nearly two thirds (64%) of general
encouraging greater project integration. While
contractors agree.
individual players seem to place the greatest value on
Equally notable is the owner response. A higher
getting their own perspectives reflected throughout
percentage of owners (63%) see the contribution of early
the process, owners place strong weight on most of the
trade contractor involvement in the success of their
processes that directly encourage collaboration. They
projects than early involvement by general contractors in
are also best positioned to drive collaboration as a goal
the development of the model (53%).
on their projects.
GENERAL CONTRACTOR EARLY INVOLVEMENT
WITH DESIGN TEAM’S MODELS
It is also a natural expectation that more general
contractors (76%) highly value their own early
involvement in design than trade contractors
(46%) do. It is notable, though, that more than half
of owners (53%) recognize the importance of this
factor, and that owners are more likely to recognize it
than design team respondents (36%), some of whom
may be concerned about ceding control during the early
phases of the project.
Owners can have a major influence on the success Factors Related to Owner Engagement
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
of projects. For complex projects in particular, owner That Contribute Most to Project Success
leadership and engagement can be critical for team (According to Owners, Architects/Engineers
cohesion and clarity of scope. and Contractors)
Owners, design teams and contractors were asked Dodge Data & Analytics, 2015
Employ Delivery “The more you build your delivery model around the
Methods That Enhance BIM, it definitely improves any opportunity to get
Collaboration and
Early Trade Contractor value. You can’t get the productivity [improvements]
Involvement if you don’t work collaboratively with the model.”
Consistent with many of the findings
in this study, the in-depth interviews their contractual arrangements value. You can’t get the productivity
with expert owners demonstrate did not allow benefits like reduced [improvements] if you don’t work
that BIM is most effectively used project schedule to accrue to the collaboratively with the model.”
on complex projects when it is owner as well as the contractor.
combined with owner selection Therefore, he finds that owners Other Best Practices
of delivery methods that enhance in particular benefit most from Other practices were reported
collaboration and engage early trade using integrated project delivery, that help owners to improve the
contractor involvement. particularly when it includes trade positive impact of BIM on their
Joe Porostosky from Ohio State contractor involvement. “[The trade complex projects.
University explains that about two contractors] have the shared risk ■ Use of a third-party BIM manager
years ago, Ohio State switched and reward, and ... they feel like was reported by Christian to be
from requiring all projects to they are part of the team ... You see a valuable strategy for large,
have a design-bid-build delivery the trades help us come up with complicated projects because a
system to the use of other systems. innovative ideas, and they also share third party can “ drive the correct
This allowed them to see greater the benefits when we see cost and behaviors in terms of how a model
engagement from all project team duration reduction.” should be used to get design
members earlier on. “Because The value of early trade contractor finished and get all the trade
they were engaged from day involvement is echoed by other coordination done.”
one, there wasn’t as much of that owners. Meghan Ruffo from Carolinas ■ Consideration of impact of BIM
back and forth. It was ‘We are all in Healthcare System reports that they on process and risk management
this together, and we are going have developed an approach she as part of its implementation was
to collaborate.’” calls “collaborate-bid-build, where also considered by Christian to
For Digby Christian from Sutter we [engage] the key trade partners be fundamental to the successful
FPS, the strength of taking a early on, we look at incentivizing use of BIM. He states, “BIM will
collaborative approach is that it helps them, doing some collaboration and save nothing unless you think it
create a “single source of truth” then actually go out to bid with those through from a process and risk
before construction begins. trade partners, as well as similar management point of view [in
An IDI participant at a large competitors.”Their approach allows terms of] what you are trying to do.
technology firm who requested to them to ensure that they are getting If you think that through logically,
remain anonymous found initially low-cost bids while still benefiting you understand [that you] need BIM
that they, as the owner of the from early collaboration. to increase the certainty that [you]
project, “did not garner that much Stuart Eckblad from UCSF sums will manage [your] risk and achieve
benefit from BIM.” He attributes up the need to collaborate as follows: [your] operational goals. n
this to their contractor selection “... the more you build your delivery
and project delivery strategy, which model around the BIM, it definitely
wasn’t “conducive for BIM” since improves any opportunity to get
asked to select the top two project-team related obstacles Obstacles to Success for Complex Projects
out of a group of five possibilities. Notably, no single (Top Two Obstacles According to Owners,
obstacle was selected by more than 50% of any group. Design Teams and Contractors)
Dodge Data & Analytics, 2015
All Respondents
Owners
The one factor that ranks relatively high for most
Architects/Engineers
players is the perception that some AEC team members
only get involved in a project phase for which they are Contractors
contractually required to perform work. The strong Some AEC Team Members Only Get Involved in
showing for this obstacle among all players suggests Project Phase Where Contractually Required to
that a substantial portion of the industry values more Perform Work
integrated approaches, and regards the more traditional 48%
approaches as an active obstacle to success. On the 41%
other hand, over half still do not regard this as a serious 45%
obstacle, suggesting a still-developing perspective in the Some AEC Team Members Not Supportive of
industry about the impact of integrated teams. Using Advanced Tools/Methods
40%
Owners 57%
Owners differ from the industry practitioners in their 50%
ranking of other obstacles included in the survey. Only Perception by Some Project Team Members of
two percentage points separate their second, third and Additional Costs for Advanced Tools/Methods
fourth most important obstacles, suggesting an equal 38%
focus on team attitude, team concern about cost and lack 30%
of a formal plan for technology use, all of which can be 36%
addressed by savvy owners.
Lack of Formal Documentation for
It is notable, though, that only 15% of owners consider How Project Team Will Use
too few quantitative objectives for use of advanced tools/ Advanced Tools/Methods
methods to be an obstacle, although it also ranks last for 38%
the other players. 38%
27%
Design Team and Contractors Project Team Has No/Too Few Quantitative
The highest percentage of design teams and contractors Objectives for Use of Advanced Tools/Methods
are concerned about the lack of support for using 15%
advanced tools and methods by some AEC team 17%
members. This is especially strongly felt by companies 27%
using BIM on 50% or more of their projects (57%) versus
those using BIM on fewer projects (44%). It supports
the previous finding that an owners’ selection of teams
experienced with advanced tools is an important success 1_3_D1_Obstacles_Team_#02.eps
factor (see page 44).
Among the other findings, it is notable that design
team respondents who are focused on BIM deliverables,
are more concerned with formal documentation on the
use of advanced tools and methods on projects, while
contractors, who are used to measuring outcomes,
are more concerned about the need for quantitative
objectives for the use of advanced tools/methods.
The highest percentage of owners (58%), architects Most Significant Owner-Related Obstacles
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
(66%), engineers (50%) and contractors (59%) all to Success on Complex Projects
agree that a significant owner-related obstacle to (Top Two Obstacles According to Owners,
project success is when the owner organization does Architects, Engineers and Contractors)
not sufficiently understand the value of advanced Dodge Data & Analytics, 2015
tools/methods.
Owners
Second to that is lack of owner involvement in the
Architects
use of tools/methods, voiced most strongly by owners
Engineers
themselves (45%), who realize the importance of
Contractors
embracing the model and related processes as the center
of the project process. Owner Organization Does Not Sufficiently
Other key findings include: Understand Value of Advanced Tools/Methods
■ A higher percentage of owners (35%) and engineers 58%
(40%) consider the lack of owner-provided guidelines 66%
and standards for using advanced tools and methods 50%
an issue than architects (22%) and contractors 59%
(23%). The lower level of concern from architects and Owner Is Not Sufficiently Involved in
contractors is consistent with the findings that they Team's Use of Advanced Tools/Methods
are not seeking direct owner engagement in the use of 45%
tools/methods indicated in the owner-related project 31%
success factors (see page 44). 37%
■ A relatively low percentage of all players find active 33%
owner discouragement of the use of advanced tools
Owner Does Not Provide Guidelines/
and methods to be a significant obstacle. Given the Standards for Use of
importance of owner recognition of the value of these Advanced Tools/Methods
tools and methods, this suggests that few firms actually 35%
experience this issue. Apathy and lack of awareness 22%
toward these tools and methods is apparently a far 40%
greater issue than direct hostility, which perhaps offers 23%
AEC firms an opportunity to advance BIM use by further
Owner Actively Discourages Use of
educating their clients on its advantages. Advanced Tools/Methods
■ A much higher percentage of AEC firms consider the
25%
lack of owner support of the use of advanced tools and 21%
methods a significant obstacle than owners. Again, this 15%
is further support that owners can play an important 26%
role in promoting the effective use of these tools on
Owner Understands Value But
projects. The relatively low percentage of owners who Does Not Actively Support Use of
recognize this (23%) suggests that many owners may Advanced Tools/Methods
not understand the importance of their recognition and 23%
advocacy of the use of these tools. 38%
32%
38%
1_4_D2-Obstacles-Owner_#02.eps
selected as having a significant impact on the success Obstacles for Complex Projects
of complex projects by more than half of owners, (Top Two Obstacles According to Owners,
architects, engineers and contractors is lack of team Architects, Engineers and Contractors)
member skills at using advanced tools and methods. Dodge Data & Analytics, 2015
1_5_D3-Obstacles-Tech_#02.eps
Owners, architects, engineers and contractors This emphasis on more training needed is also reflected
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS DATA
were asked an open question about what prevents in the main survey findings (see page 48). However,
their organizations from moving to greater efficiency while other top obstacles for architects include owner
in complex building projects. Interestingly, while buy-in and change management, engineers are more
there is some overlap in the top selections, each player concerned about limitations with the software and its
has different obstacles that most frequently recur in interoperability and the development of standards for
their responses. the use of BIM. Since engineers typically have to work
■ Owners: Change management is the top obstacle for with many different architects and contractors and
owners. This may demonstrate growing recognition adapt to their BIM systems, it is not surprising that these
among owners that improving efficiency involves challenges would be higher top-of-mind concerns for
process change that is supported by the adoption of them than for other players.
tools like BIM. Other top obstacles for owners include: ■ Contractors: Owner buy-in is the top concern for
Increasingly, firms are using BIM and Lean processes in tandem to create
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
T
he Lean Construction for Turner Construction, “with BIM To implement their BIM and
Institute (LCI) defines Lean you’re trying to find the problem, Lean initiatives, Turner hired
design and construction and Lean is about a problem-solving dedicated BIM managers in all 11
as “a production mind-set… find the problems early of their regional offices, and will
management-based approach to and get them solved.” also soon have dedicated Regional
project delivery” that “maximizes Lean Managers. All of their upper
value,” “minimizes waste“ and is Better Builders management has received Lean
“particularly useful on complex, Turner Chief Innovation Officer Jim leadership training, hundreds
uncertain and quick projects”. Barrett is an advocate of BIM and of employees have been trained
Many firms are beginning to Lean processes. He says that “old through their BIM University and
leverage BIM as a Lean tool. They command and control doesn’t work. Advanced Lean programs, and
are using BIM to model owners’ Jobs are getting more complex, they hold biweekly companywide
process flows and to discover global supply chains, demanding Webinar Wednesdays alternating
conflicts in design and construction schedules…that old style of doing between BIM and Lean topics.
documents, model site logistics things—it’s a relic of another age” Turner National BIM Manager
issues and sequence construction that he believes they are addressing Jennifer Downey believes that BIM
to improve project workflow. BIM by using a Lean approach. and Lean go hand-in-hand. She says
is also being used to effectively Turner Construction, a company that “all of our complex projects are
support Lean processes, such as with 5,200 employees based out of almost always going to use both BIM
collaborative planning. Further, BIM New York, NY, conducted its first BIM and Lean because we need these
3D and 4D visualization can help project trial in 2002 and first used tools to figure out how to build these
identify and eliminate potential Lean processes on a project in 2005. buildings on time and on budget.”
planning problems. According to Both have subsequently become Turner has many projects that have
Kurt Gavalier, National Lean Manager Turner formalized standards—BIM
in 2008 and Lean in 2011. Since their
introduction, Turner has used BIM
Middle Tennessee Medical Nintendo of America
st
st
at
and Lean. For example, on the Pull Planning months versus a GSA average of
555,000-square foot, 286-bed Balfour Beatty Construction U.S., a 21–24 months and delivery duration
capacity Middle Tennessee Medical 2400-employee company based in of 48 months versus a GSA average
Center located in Murfreesboro, Dallas, is also an early adopter of BIM of 72–120 months.” The project had
Tennessee, they used BIM in tandem and Lean. BIM along with workflow an impeccable safety record with
with Lean practices, including pull practices such as 3D coordination, zero lost time incidents in 663,736
scheduling and extensive offsite virtual mockups, site logistics manhours. The LEED Platinum
prefabrication to deliver the GMP planning, model based estimating building won an AIA “Top Ten”
contract more than $3 million below and 4D visualization have now COTE award in 2014.
the owner’s target and more than become standard practices. Another notable Balfour Beatty
two months ahead of schedule. Vice president Bevan Mace notes project is the construction of the new
Turner also used a combination that over the last three to five years, Parkland Hospital in Dallas. Balfour
of BIM and Lean techniques to there has been a significant uptick Beatty used pull planning and offsite
construct the 380,000-square foot, in the use of pull planning methods fabrication extensively, and a BIM
four-story Nintendo of America and in other integrated practices, visualization room, which all resulted
Headquarters in Redmond, including target value design and the in a reduction in onsite manpower
Washington. Through the extensive use of big (co-location) rooms. and subsequent safety benefits.
use of BIM and Lean construction Last Planner® is the basis “Leveraging BIM and Lean
methods, they were able to deliver for their commitment-based practices in integrated project
the LEED Gold building over three planning approach. Last year they delivery is a team sport. A project’s
months ahead of schedule while implemented a national pull planning ultimate success requires servant
utilizing 37% less onsite labor than standard with the expectation that leadership and tight collaboration
originally forecast. Productivity on it would be used on 100% of their among all team members, and our
the project was 42% above average, major projects. Mace says,“Our experience on the new Parkland
and Turner was able to return 7% of primary focus right now is just Hospital project certainly reinforces
the total budget as savings. getting folks into a commitment- that,” Mace says. n
based planning approach versus
a critical path method scheduling
New Parkland Hospital,
st
approach.” They are implementing
at
Dallas, TX
s
this strategy across the company’s
Edith Green Wendell
st
At the University of Massachusetts Boston, J.C. Cannistraro crews had to fit their work within a maze of existing services.
A
t the University of 400-horsepower boiler during the “I was borderline nervous
Massachusetts Boston, upgrade. Crews had one weekend when I saw what we were dealing
operations on the 175- to install system isolation valves with,” he says. “I looked at it and
acre campus run 24 hours for the boiler and 30-inch chilled thought, ‘How do I get this done?’
a day, seven days a week. When the water valves. Several systems— It looked impossible.”
university moved ahead with plans including electrical, domestic water
to replace an existing 40-year-old and fire protection—had to remain Laser Scanning Of
central utility plant, the construction undisturbed while Cannistraro Existing Conditions
team needed solutions that would upgraded the HVAC systems. Detra’s solution was to laser scan the
allow crews to work within an Adding to the complexity, crews existing conditions, creating a point
extremely tight schedule and keep had to fit their work within a maze cloud to model new systems within
the campus operating. of existing services. Colin Detra, the existing ones. Cannistraro was
Elements of the major upgrade systems designer/coordinator at J.C. then able to use the model to help
included four 2,000-ton centrifugal Cannistraro, says that determining coordination and virtual layout. In
chillers, three 800-horsepower existing conditions—including what addition to the 50-plus connections
hot water boilers and one would remain and what needed to that need to be coordinated,
400-horsepower hot water boiler. be demolished—was a daunting Cannistraro was able to determine
Photo courtesy of J.C. Cannistraro
Trade contractor J.C. Cannistraro, task. In addition, Detra learned that locations for hanger rods.
which was responsible for hanger rods could not be attached to With an accurate model of
plumbing, HVAC, fire protection the underside of the vault’s concrete both new and existing systems,
and sheet metal, had to install deck, only to the sides of concrete the team was able to pursue
temporary chillers and re-pipe the support beams. BIM-enabled prefabrication.
CONTINUED
TI
N
CO
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
J.C. Cannistraro generated laser scans of the existing conditions to create a point cloud. It then leveraged that info to model
new systems and existing systems. The team used prefabrication to help reduce manhours in the field by 22% from estimate.
st
is performed in a controlled translating to almost 9,500 inches of
at
and Figures
s
environment, helping to improve X-ray-quality welding.
quality and safety. Work can also Trade Contractor
J.C. Cannistraro
be performed ahead of time with Saving Schedule
pieces delivered just in time for Although the schedule allowed Type of Project
installation, potentially saving for a whole weekend to complete Central Utility Plant
time in the schedule. This benefit the temporary installations, crews Major Components
was particularly important on were able to get the systems running Four 2,000-ton centrifugal
chillers, three 800-horsepower
the University of Massachusetts within a day.
hot water boilers and one
Boston project, where temporary Even more compelling, 400-horsepower hot water boiler
installations had to happen within a Cannistraro crews were able to
Completed
two-day window. reduce manhours in the field by 2014
Cannistraro employs 22% from its original estimate. Detra
prefabrication on its projects says the firm’s original estimate,
whenever possible, but Detra says created before the potential use BIM-Related Results
that can be difficult on jobs with of laser scanning was explored, J.C. Cannistraro crews were
complex existing systems. called for 700 hours of coordination able to reduce manhours
“It is very hard to catch everything and 22,706 hours in the field. In the in the field by 22% from its
in an existing environment and see end, Detra logged 792 coordination original estimate.
all of the interferences,” he says. hours—92 hours above estimate—
“[These tools] allowed us to do that.” but the field only needed 17,635 ■■ Coordination hours increased
Cannistraro generated hundreds hours to complete work. from 700 hours (original
Images courtesy of J.C. Cannistraro
of spool sheets on the project, but “I put in almost 100 extra hours estimate) to 792 hours (actual).
by fabricating from the model, Detra for coordination, but it saved ■■ Field hours decreased from
says it took half the time it would 5,000 hours in the field,” he says. 22,706 hours (original estimate)
with 2D drafting software. Data “All of that upfront effort was 100% to 17,635 hours (actual).
from the model was also used to worth it.” n
P
refabrication of building The most significant benefits to help flatten the peaks and valleys
components has emerged of prefabrication for SCL, achieved of workforce planning and mitigate
as a leading strategy on at a direct cost premium of only potential labor shortages.
complex projects. Driving 6%, included:
the shift is a convergence of enabling ■ Schedule compression of Best Practices
factors: BIM, integrated project 18 percent and labor savings for BIM-Enabled
delivery methods and project of 29,500 hours Prefabrication
management philosophies such as ■ 150,500 labor hours diverted offsite Whatever decisions the MUSC
Lean Construction. More than any for a productivity improvement of team makes around prefabrication,
other construction sector, healthcare $2.6 million from reduced onsite says Wiley, “we know we have to
projects are making the highest use labor density make them as a team.” Integration
of BIM-enabled prefabrication. That’s ■ Increased safety through reduced is the signature advantage of BIM-
because the modular elements congestion and improved based design, and a critical factor
typical of healthcare buildings make ergonomics and work settings in successful prefabrication. Early
a strong fit for the strategy. integration of specialty trades allows
“I would say that is the No. 1 Qualitative Goals the design to incorporate efficiencies
golden rule of prefabrication,” In addition to quantifiable benefits, that the trades identify and the model
says Brandon Bergholz, healthcare prefabrication can also support to provide the accuracy needed for
market leader with Mortenson qualitative goals. For example, successful prefabrication.
Construction. “You have to have one of the construction goals for A closely related best practice
multiple repeatable items to really the Medical University of South is what Bergholz calls the “right
be successful.” Carolina (MUSC)’s Children’s of reliance”: The model must at all
Hospital and Women’s Pavilion, times represent the current status
Quantifiable Benefits currently in design, is to maximize of the design, so that team members
SCL Health’s new St. Joseph local, and especially minority-group, can base their decisions on it
replacement hospital, which participation. Steve Wiley, senior with confidence.
opened in December 2014, made project manager at Robins & Morton,
extensive use of prefabrication: construction managers on the Challenges
250 exterior wall panels, over a project, has found that prefabrication On healthcare projects, clients
mile of multi-trade utility racks, can facilitate local participation by typically prefer to select equipment
446 bathroom pods complete portioning project components as late as possible, which affects
with fixtures and finishes, and out among local businesses. Wiley utilities and their placement. That
400 patient headwall assemblies. speaks from his experience on preference may represent a limit
An analysis conducted by MaineGeneral’s Alfond Center on the sector’s opportunities for
Mortenson as construction was for Health, where prefabrication prefabrication, which requires design
nearing completion expected every contributed to keeping 97% of decisions to be finalized even earlier
dollar spent on prefabrication to subcontractor costs in-state. than in conventional construction.
return about 13% to the project in Because prefabrication allows Apart from that, the applications
quantifiable benefits. Exterior wall building envelope panels and for prefabrication are “just a
panels’ benefit-to-cost ratio of 1.74 bathroom pods to be built while question of how far can we take
made it the most valuable of the foundation piles are still being it, how complete can we get it,”
prefabrication strategies. driven, MUSC is also considering it says Bergholz. n
Converging Technologies
Poised to Transform Construction
New technologies like robotics, drones and 3D printers are poised to increase the
MEASURING THE IMPACT OF BIM ON COMPLEX BUILDINGS
T
he increasing complexity of “[3D printing] enables a very sophisticated
construction projects may design, without the need to simplify [it]
be a critical factor helping to in a later stage to lower costs.”
drive the development and
integration of new technologies. Just comparisons of what the drones see print full-scale houses in concrete,
as BIM has proven to give new life to with what the project calls for. and the even bigger one it used to
older approaches like prefabrication, Drones are really just a special print a five-story apartment building,
the introduction of new technologies type of robot, one that flies. As seems a lot more like a robot than
are likely to increase the value of the Komatsu-Skycatch enterprise a printer.
BIM for construction projects. A few suggests, taking advantage of In May 2015, engineering
promising new technologies include their bird’s-eye view for aerial data consultant Arup announced the 3D
robotics, drones and 3D printing. collection is an emerging role for printing, or additive manufacturing,
drones on jobsites: scan-to-BIM of a structural steel connector
Builder Bots surveys of existing site and building weighing 75% less than its
In March 2015, Construction conditions to inform design, and conventional counterpart for the
Robotics, a New York State-based remote inspections of work in same loads. “On a construction
construction technology developer, progress. One scenario even project, that means we could be
won World of Concrete’s Most predicts drones conducting fly- looking at an overall weight reduction
Innovative Product award for a through verifications that trigger of the total structure of more than
brick-laying robot called SAM automatic weekly or bimonthly 40%,” says Arup team leader, Salomé
(semi-automated mason). Designed payouts to contractors. Galjaard. “But most important, this
to help with the repetitive and Heavy lifting may not be a strength approach potentially enables a very
strenuous task of lifting and placing associated with drones, but Flight sophisticated design, without the
each brick, SAM offers reduced Assembled Architecture, a project need to simplify the design in a later
strain on mason and crew, increased mounted in 2012 at an art center in stage to lower costs.”
consistency and estimated job France, showcased a team of drones One of the most profound
savings of over 30%. BIM and SAM laying up a complex architectural implications of these converging
may be a match in the making. form six meters high using some technologies, according to Mike
1,500 lightweight masonry units. Whaley of technology consultants
Flying Eyes The drones collaborated according Turis Systems, is waste reduction.
Meanwhile, Japanese construction to mathematical algorithms that Suppose, for example, resinous
machinery manufacturer Komatsu translated digital design data into hospital countertops could be
recently joined forces with San actions. This elegant project conveys 3D-printed onsite direct from the BIM
Francisco-based Skycatch to the poetic potential of channeling model; or a drywall installer could
integrate autonomous aerial data design intelligence through robotics. laser scan existing stud framing and
collection with automated heavy openings with a cell phone and send
machinery. Komatsu plans to Additive Manufacturing the data to print drywall pieces onsite
automate early foundation work Calling 3D printers robots might in just the right sizes. No extras, no
on construction sites by deploying seem like a stretch, but that’s just a off-cuts, no waste. “Yes, you can
unmanned aerial vehicles (UAVs), matter of scale. A 20-foot tall, 33-foot save money,” says Whaley, “but you
or drones, to scan jobsites and send wide, 132-foot long machine with a can also have a positive impact on
data to unmanned bulldozers and giant extruder arm, which Chinese the big picture without added cost.
excavators. That interface will allow company WinSun used last year to That is huge.” n
ACKNOWLEDGEMENTS:
The authors wish to thank our premier partner. the U.S. Department of
Veterans Affairs—and, in particular, Rick Bond and Renée Tietjen at the VA—
whose vision and support have made this report possible.
Dodge Data & Analytics
We would also like to thank the eight individuals who participated in the
Main Website : construction.com
in-depth owner interviews, including both those who went on the record and
Dodge : construction.com/dodge
those who spoke anonymously. Their insights bring greater depth and clarity
Research & Analytics : to the findings of our study.
construction.com/dodge/
dodge-market-research.asp In addition, we thank Hal Jones at Skanska, Jim Barrett at Turner Construction
Sweets : sweets.com and Doug Rowe at Lend Lease for sharing their expertise and insights and
helping us to create an effective, meaningful survey instrument. We also
SmartMarket Reports :
analyticsstore.construction.com thank the American Institute of Architects (AIA), including the AIA Technology
in Architectural Practice Knowledge Community (TAP) and the AIA Large Firm
Roundtable, as well as Microsol Resources and VDCO Tech, for helping us to
widely disseminate the survey.
Finally, we would like to thank all the individuals who provided information
and insight for our sidebars and case studies.