TESTING AND COMMISSIONING SHEET

ELECTRIC PASSENGER LIFT

1. DESCRIPTION

 Building Name 7 - Sense


 Address Gregory Road, Colombo 07.
 Machine Details L-5
Elevator Type Grearless Traction Machine
Manufacturer Mitsubishi Electric
 Traction Machine
Model No PM011SS
Serial No L1911141577
 Control VVVF
 Operation
 Rated Load 825Kg
 Rated Speed 105 m/min
 Door Type Center Opening
 Door Opening Size 900mm (W) x 2100mm (H)
 Motor (kW) 8.9 kW
 Installation Drawing No.
 Power Supply 400V / 3ph / 50Hz
 Floors Served B2, B1, G, 1, 2, 3, 4, 5, R
 Buffer Type
Car Spring, Hydraulic
Counter Weight Spring, Hydraulic

2. STATIC EXAMINATION

 Does the Mechanical


Safety Gear Operate properly? Yes

 Does the brake sustain the car


With rated load plus 25%? Yes

 Does the phase failure device


Operate correctly? Yes

3. LOAD TEST

Up Down
Load Weight
Speed Voltage Speed Voltage
% (kg) IS (A) IR (A) IS (A) IR (A)
(m/min) (V) (m/min) (V)
0
50
100 840 15.9 16.1 416 0.5 0.1 418

Page 1 of 5
IS - Starting Current IR - Running Current

4. DOOR TESTS

 Door Opening Time 1.83 (s)

 Door Closing Time 2.77 (s)

5. TIME DELAYS

 Car Hold Delay 4.68 (s)

6. CONTROL CIRCUIT VOLTAGES

 Full Load 24 V d.c

7. EARTHING

 Is all the metal work enclosing


Conductors bonded to earth Yes

 Is the car connected to earth Yes

8. GOVERNOR TRIPPING SPEED

 Electrical Up – 2.18 m/s Down – 2.17 m/s

 Mechanical 2.27 m/s

9. LIMIT SWITCHES

 Does the terminal stopping devices


Operate satisfactorily? Yes

 Does the final limit switch operate


Satisfactorily? Yes

10. CLEARANCES & RUNBY

 Will the car clear all obstructions


When run on slow speed? Yes

Page 2 of 5
 Car top clearance 1200mm

 Counterweight top clearance 1000mm

 Bottom run by of car 190mm

 Bottom run by of counterweight 90mm

11. CAR TOP CONTROL STATION

 Speed up 20 m/min

 Speed down 20 m/min

 Is the operation of the car top


Control station correct? Yes

12. FLOOR LEVELLING TESTS

 With rated load in the car, the


maximum inaccuracy for any floor
in both directions 5mm

13. GENERAL

 Is the load indication plate


fitted in the car Yes

 Has the machine room adequate


lighting for maintenance purposes ? No ; No any light available in lift shaft

14. ADDITIONAL FEATURES CHECK

 Car Door Safety Edge In Order

 Ventilation Fan In Order

 Arrival Gong In Order

 Operation & indication of call


Page 3 of 5
buttons & indication panels In Order

 Emergency car light In Order

 Operation of Emergency
Rescue Device. In Order

 Operation of Interphone No

 Fireman’s Switch Operation In Order

15. DECLARATION

We certify that on 10/09/2015 the equipment was thoroughly examined and found to be generally
complying with requirements except the snagging list (Annexure 01).

For Consultant: Signature : ..............................................................

Name : .....................................................................

Date : .......................................................................

For Lift Contractor Signature : ..............................................................

Name : .....................................................................

Date : .......................................................................

Page 4 of 5
Annexure - 01

SNAGGING LIST

1.Emergency/Maintenance lamps shall be fitted at each level of the lift shaft and lamps at

every other floor shall be battery backed.

2. A smoke detector shall be fitted on the soffit of the lift shaft and a remote indicator shall be

fitted at the entrance of the roof floor.

3.Link between the Fire alarm panel shall be established