Beruflich Dokumente
Kultur Dokumente
V100R001C02
Commissioning Guide
Issue 02
Date 2010-01-30
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or representations
of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute the warranty of any kind, express or implied.
Website: http://www.huawei.com
Email: support@huawei.com
Related Versions
The following table lists the product versions related to this document.
Intended Audience
This document describes the installation process, including Preparations for the Commissioning,
NE Commissioning Guide, HOP commissioning, system commissioning of the OptiX RTN
910.
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol Description
Symbol Description
GUI Conventions
The GUI conventions that may be found in this document are defined as follows.
Convention Description
Change History
Updates between document issues are cumulative. Therefore, the latest document issue contains
all updates made in previous issues.
Compared with the first release, the updated contents are as follows:
Update Description
6.9.2 Testing Connectivity of the Ethernet Revised the steps of testing Connectivity of
Service the Ethernet Service.
Contents
4 NE commissioning.....................................................................................................................4-1
4.1 Powering On the Equipment...........................................................................................................................4-2
4.2 Configuring Data by Using a CF Card............................................................................................................4-4
4.3 Configuring Data by Using the U2000 LCT...................................................................................................4-4
4.3.1 Starting the U2000 LCT.........................................................................................................................4-5
4.3.2 Creating an NE.......................................................................................................................................4-7
4.3.3 Changing the ID of an NE......................................................................................................................4-9
4.3.4 Changing the IP Address of an NE......................................................................................................4-10
4.3.5 Configuring Logical Boards.................................................................................................................4-11
4.3.6 Creating IF 1+1 Protection...................................................................................................................4-12
5 Hop Commissioning..................................................................................................................5-1
5.1 Aligning the Antennas.....................................................................................................................................5-2
5.1.1 Main Lobe and Side Lobe......................................................................................................................5-2
5.1.2 Aligning the Single-Polarized Antennas................................................................................................5-5
5.1.3 Aligning the Dual-Polarized Antennas..................................................................................................5-7
5.2 Checking the Status of a Radio Link...............................................................................................................5-9
5.3 Checking the IF 1+1 Switching.....................................................................................................................5-10
6 Network Commissioning.........................................................................................................6-1
6.1 Checking the Connection between the Equipment and the NMS Computer..................................................6-3
6.2 Starting the U2000..........................................................................................................................................6-4
6.3 Creating the Network Topology......................................................................................................................6-4
6.3.1 Creating NEs in Batches........................................................................................................................6-4
6.3.2 Configuring NE Data.............................................................................................................................6-6
6.3.3 Manually Creating Fiber Connections...................................................................................................6-8
6.4 Configuring the VLAN ID and the Bandwidth for the Inband DCN..............................................................6-9
6.5 Synchronizing NE Time................................................................................................................................6-11
6.6 Enabling the NE Performance Monitoring Function....................................................................................6-12
6.7 Checking the Optical Power of Optical Interface.........................................................................................6-13
6.8 Configuring Services.....................................................................................................................................6-15
6.9 Testing Service Connectivity........................................................................................................................6-16
6.9.1 Testing Connectivity of the ATM Service...........................................................................................6-16
6.9.2 Testing Connectivity of the Ethernet Service.......................................................................................6-18
6.9.3 Testing Connectivity of the CES Service.............................................................................................6-22
6.10 Testing the Network Protection Switching.................................................................................................6-25
6.10.1 Testing 1:1 MPLS Tunnel Protection.................................................................................................6-25
6.10.2 Testing LMSP Protection...................................................................................................................6-27
A Glossary.....................................................................................................................................A-1
B Abbreviations............................................................................................................................B-1
Figures
Tables
1 Safety Precautions
This section describes the safety precautions that should be taken during operating and
maintaining the equipment or using U2000 NMS (Network Management System). The safety
precautions cover the safety rules related to the human beings and equipment. Adhere to these
safety rules to avoid injury to the human body and damage to the equipment.
CAUTION
l Before performing any operation on the equipment, read the operation instructions and
precautions carefully; during the operation, follow the equipment-specific precautions and
operation instructions provided by Huawei strictly to minimize the occurrence of accidents.
l When performing any operation on the equipment, follow the safety regulations of the local
areas. The safety precautions described in the manual are only supplements to the local safety
regulations.
l The texts introduced by the word "Caution", "Warning", or "Danger" in each manual do not
cover all the safety precautions that must be followed. They are only supplements to the
safety precautions for operations.
l The engineers that are responsible for installing and maintaining Huawei equipment must be
equipped with the general knowledge of safety operation. Therefore, they must have
completed relevant training to familiarize themselves with the proper operation methods and
safety precautions. In addition, they must possess relevant working certificates.
Table 1-2 lists the levels and meanings of the safety symbols.
High Voltage
DANGER
The high voltage power supply supplies power to the device so that it can operate. Direct or
indirect contact (through damp objects) with high voltage and AC mains supply may result in a
fatal accident.
l When installing the AC power supply facility, comply with the local safety regulations.
The personnel who install the AC facility must be qualified for performing high voltage
and AC operations.
l Do not wear articles that conduct electricity, such as watches, chains, bracelets and rings
when performing high voltage operations.
l Switch off the power supply immediately, if you find water in the rack or if the rack is
damp.
l Make sure that the device is kept away from water when being operated in a damp
environment.
WARNING
Non-standard and improper high voltage operations can result in fire and electric shock.
Therefore, you must abide by the local rules and regulations when bridging and wiring AC cables
through a certain area. The personnel who perform high voltage operations must be qualified
for performing high voltage and AC operations.
Power Cable
WARNING
Do not install or remove a live line. Transient contact between the core of the power cable and
the conductor may generate electric arc or spark, which can cause fire or injury to the eye.
l Before bringing the power cable into the power distribution frame (PDF), bind the bare
parts of the power cable with insulating tapes.
l Before installing or removing the power cable, turn off the power switch.
l Before connecting the power cable, make sure that the power cable and label conform to
the requirements of the actual installation.
Short Circuit
The short circuit makes the components fail to work normally and even causes damage to the
entire equipment. During the component replacement, avoid the short circuit that may occur
when you do not operate the tools or boards properly.
Use tools such as a screwdriver according to the regulations. Do not place any tools on the
honeycomb plate of the equipment.
CAUTION
Prevent any screws from falling into the equipment and causing short circuit.
Tools
WARNING
Use special tools when performing high voltage and AC operations.
Drilling Holes
WARNING
Do not drill on the rack without permission. Drilling on the racks does not conform to the related
requirements and may damage the wires and cables inside the rack. If the metal shavings from
the drilling enter the rack, it may result in short-circuit of the circuit boards. It may also damage
the Electromagnetic Compatibility (EMC) performance of the cabinet.
l Before drilling a hole on the rack, wear insulation gloves, and then remove the cables inside
the rack away.
l During the drilling, ensure that your eyes are completely protected. The hot metal shavings
may cause injury to your eyes.
l Ensure that the metal shavings do not enter the rack.
l Non-standard drilling may damage the electromagnetic shielding performance of the rack.
l After drilling, clean the metal shavings.
Thunderstorm
DANGER
High voltage and AC operations, or operations on a steel tower and a mast when there is a
thunderstorm are prohibited.
When there is a thunderstorm, the electromagnetic field generated in the thunderstorm area may
cause damage to electronic components. To prevent the device from being damaged by lightning,
use proper grounding.
Electrostatic Discharge
The electronic components on the board can be damaged by the electrostatic discharge. Thus,
when replacing the board, make sure that the equipment is properly grounded and take proper
measures to protect the components against electrostatic discharge. For example, wear the ESD
wrist strap during the operation.
CAUTION
The static electricity generated by the human body can damage the electrostatic sensitive
components on the circuit board, such as the large-scale integrated circuit (LIC).
Take the following measures to protect the components against electrostatic discharge:
l Make sure that the equipment is properly grounded according to the equipment grounding
requirement.
l Before touching the equipment, board or integrated circuit (IC) chip, you must wear the
ESD wrist strap to prevent the electrostatic discharge on the human body from damaging
the static-sensitive components, and ensure that the other end of the strap is properly
grounded. Figure 1-1 shows how to wear the ESD wrist strap.
CAUTION
Make sure that the metallic portion of the ESD wrist strap is in contact with the skin and
the other end of the ESD wrist strap is properly connected to the anti-static jack.
NOTE
l Wear an ESD wrist strap when operating the ports of boards because they are also static-
sensitive. Discharge the static electricity of cables and protective sleeves before connecting
them to the ports.
l Reserve some board package materials, such as vacuum forming box and antistatic bags in
the equipment room for future use.
1.2.3 Battery
When installing or maintaining the battery, follow relevant safety precautions for the battery to
ensure the safety of human beings and the equipment.
DANGER
Before handling the battery, read the safety precautions and the procedure for connecting the
batteries.
Electrolyte overflow can cause potential damage to the device. It can lead to the corrosion of
metal parts and circuit boards, and damage the device and cause short-circuit of the circuit boards.
General Operations
Before installing and maintaining the battery, pay attention to the following:
l Do not wear metallic articles, such as a watch, hand chain, bracelet and ring.
l Use special insulation tools.
l Use eye protection devices.
l Wear rubber gloves. Wear an apron in case of electrolyte overflow.
l Always keep the electrode upright when handling the battery. Do not place the battery
upside down or tilt it.
Short Circuit
CAUTION
Short-circuit in a battery may cause injury. Though the voltage of a battery is low, high transient
current generated by a short-circuit releases a large amount of power.
Keep metal objects that can cause battery short-circuit away from the batteries. If metal objects
have to be used, first disconnect the batteries in use and then perform any operations.
Harmful Gas
CAUTION
Do not use unsealed lead-acid battery, because the gas emitted from the battery may result in
inflammation or device corrosion. Place the battery horizontally and then fix it properly.
The battery in use may emit flammable gas. Therefore, store the battery in a place with good
ventilation, and take precautions against fire.
High Temperature
CAUTION
High temperature may result in distortion, damage and electrolyte overflow in the battery.
When the temperature of the battery exceeds 60°C, check whether there is acid overflow. If yes,
clean the acid immediately.
Acid Liquid
CAUTION
In the case of acid overflow, absorb and neutralize the liquid immediately.
When moving or replacing a leaky battery, observe the damage caused by the acid. When acid
spill is found, use the following materials to absorb and neutralize it.
l Sodium bicarbonate (baking soda): NaHCO3
l Sodium carbonate (pure alkali): Na2CO3
When using antacids, strictly follow the guide provided by the battery supplier.
1.2.4 Microwave
When installing or maintaining microwave equipment, follow relevant safety precautions for
the microwave equipment to ensure the safety of human beings and the equipment.
WARNING
Strong radio frequency can harm the human body.
When installing or maintaining an aerial on the tower or mast that is installed with multiple
aerials, switch off the transmitter in advance.
Laser
CAUTION
The laser beam launched by the optical interface board or by a fiber can cause damage to your
eyes! Do not stare into the fiber connector without wearing protective glasses during the
installation or maintenance of the fiber.
l Special cleaning solvent (Isoamylol is preferred, propyl alcohol is the next, alcohol and
formalin is forbidden.)
l Non-woven lens tissue
l Special compressed gas
l Cotton stick (medical cotton or long fiber cotton)
l Special cleaning roll, used with cleaning solvent listed in the first item
l Special magnifier for optical connectors
For cleaning steps, refer to OptiX RTN 910 Radio Transmission System Maintenance Guide.
Replacing Fibers
When replacing a fiber, cap the fiber connector of the unused fiber with the protective cap.
Connecting Fibers
Take the following precautions when connecting fibers.
l If the optical power is excessively high, an optical attenuator should be used to protect the
optical interfaces from being damaged.
l When the fiber connector does not match the optical interface, use an adapter to connect
the connector to the optical interface. In addition, ensure that the optical power meets the
specification requirement of the optical interface after the adapter is used because the use
of an adapter introduces certain attenuation.
WARNING
When working at a height, prevent objects from falling down.
DANGER
Do not remove the power cable and the PIU board when the power is on.
For details on how to replace the PIU, see "Replace the PIU".
CAUTION
l Before installing or removing a board, wear an ESD glove or ESD wrist strap.
l Do not remove or install the IF board and the IF cable when the equipment is powered on.
l When holding a board, never touch the circuits, components, cable connectors, and cabling
trough on the board.
l Before inserting a board, make sure that the protective tube on the backplane has been taken
off.
l Before inserting a board, make sure that no fiber or cable is connected to the board.
l Insert a board gently to prevent bending of the pins on the backplane.
l Insert a board along the slide rail of each slot to prevent the components on the board from
touching each other and causing short circuit.
l The interval for removing and inserting a board should be longer than 10 seconds.
After a board is inserted into the equipment, it takes several minutes for the board to enter the
normal running state after the startup.
1.2.8 Miscellaneous
When installing or maintaining Huawei network equipment, you also need to follow the safety
precautions for lifting heavy objects, operating sharp-cornered objects and binding signal cables
to ensure the safety of human beings and the equipment.
WARNING
Do not stand or walk under heavy objects when they are being lifted.
WARNING
When carrying the device, wear protection gloves to prevent injuries that can be caused by sharp
objects.
CAUTION
Bundle the signal cables separately from the strong current cables or high voltage cables. The
space between two adjacent ties must be at least 30 mm.
l On the Windows platform, use the user that is chosen during the U2000 installation, to log
in to the operating system. Do not change the login user of Windows.
This chapter provides guides to the operations that may cause injury on human bodies and
damage on the equipment if they are misconducted during the commissioning and maintenance
of microwave equipment.
I : ON
Procedure
Step 1 Turn off the ODU power switch on the IF board. For details, see 2.1 Operation Guide to the
Toggle Lever Switch.
1 2
DANGER
Do not remove the IF jumper before the ODU is powered off!
----End
Procedure
Step 1 Turn off the ODU power switch on the IF board. For details, see 2.1 Operation Guide to the
Toggle Lever Switch.
1 2
DANGER
Do not remove or install the IF cable before the ODU is powered off!
----End
Procedure
Step 1 Turn off the ODU power switch on the IF board. For details, see 2.1 Operation Guide to the
Toggle Lever Switch.
1 2 3
DANGER
Do not remove or install the IF board before the ODU is powered off!
----End
Before commissioning the equipment, obtain related knowledge on safety precautions, and
prepare required tools, instruments, references and engineering design document.
3.1 Requirements for Commissioning Personnel
This section describes the required network knowledge and commissioning experience for
commissioning the equipment.
3.2 Commissioning Process
This topic describes the commissioning process of the equipment. The commissioning process
involves four phases: the preparations for commissioning, NE commissioning, hop
commissioning, and system commissioning. Each phase has detailed focuses or commissioning
steps.
3.3 References and Instruments Required for the Commissioning
This section describes the references and tools prepared for the commissioning in advance. The
references include reference manuals and engineering design documents, and the tools include
instruments and materials required for the commissioning.
Changing the IP
Address of an NE
Configuring
Logical Boards
Creating IF 1+1
Protection
Testing the
Connectivity of the
Ethernet Cables
Hop commissioning Aligning the Aligning the Single- Required when you
antennas Polarized Antennas use single-polarized
antennas
Configuring NE
Data
Manually Creating
Fiber Connections
Reference manuals
Prepare the following references for equipment commissioning:
l OptiX RTN 910 Radio Transmission System Configuration Guide
l OptiX RTN 910 Radio Transmission System Feature Description
l OptiX RTN 910 Radio Transmission System Maintenance Guide
l OptiX RTN 910 Radio Transmission System Product Description
l OptiX iManager U2000 Installation Guide
l OptiX iManager U2000 LCT User Guide
Tools
Table 3-1 lists the tools required for the commissioning.
NOTE
4 NE commissioning
Prerequisite
l The components of the equipment must be installed and must pass the installation check.
l The power supply must be available and the fuse capacity must meet the requirement of
the equipment.
l The power supply (for example, the power box of the cabinet) must be turned off.
Background Information
Table 4-1 recommended fuse current of the OptiX RTN 910.
Precautions
CAUTION
l The ODU-PWR switches on the front panels of the IF boards are equipped with locking
devices. Hence, you must pull out the switches gently before you turn them. If the switch is
at the "O" position, it indicates that the switch is off. If the switch is at the "I" position, it
indicates that the switch is on.
l If the output voltage of the power supply does not meet the test requirements, reconstruct the
power supply and do not power on the cabinet.
Procedure
Step 1 Set the ODU-PWR switch on the front panel of the IF board to "O".
Step 2 Turn on the power switch of the external power supply.
Step 3 Use the multimeter to test the voltage and polarization of the input power at the access point
(such as the output terminal of the power box on the cabinet). Ensure that the anode and the
cathode are connected correctly.
l When the nominal voltage of the input power is -48 V, the measured voltage should be
between -38.4 V and -57.6 V.
l When the nominal voltage of the input power is -60 V, the measured voltage should be
between -48V and -72V.
WARNING
If the measured voltage is not within the range, you must troubleshoot the power equipment
before proceeding to the next step. The abnormal voltage can cause damage to the equipment
or even personal injury.
Step 4 Check and ensure that the power cable of the chassis is connected to the equipment correctly.
Then, power on the equipment and check the indicators of the equipment. Table 4-2 provides
the statuses of the indicators and their meanings. When the equipment is in normal state, the PIU
indicator and the FAN indicator should be steady green, as shown in Figure 4-1.
Step 5 Set the ODU-PWR switch on the front panel of the IF board to "I".
----End
Prerequisite
The equipment must be powered on.
The CXPAR/CXPBR/CXPGR/CXPHR board must be equipped with a CF card for data
configuration.
Procedure
Step 1 Press the CF RCV button on the CXPAR/CXPBR/CXPGR/CXPHR board for five seconds (The
button is little; you can use a pointed object to press it). Then, the NE is reset, all indicators are
all off, except the PROG indicator.
Step 2 When the NE starts up (8-9 minutes after the reset), the NE starts executing the deployment
scripts. In this case, the PROG indicator blinks in green.
l When the PROG indicator stops blinking and stays green for 10s, it indicates that the
deployment scripts are successfully executed. 10s later, the PROG indicator stays green.
l When the PROG indicator stops blinking and stays red for 10s, it indicates that execution of
the deployment scripts fails. 10s later, the PROG indicator turns green and stays green.
NOTE
On the CXPAR/CXPBR/CXPGR/CXPHR board, the PROG indicator is the second indicator when the indicators
are counted from the left.
----End
4.3.2 Creating an NE
To manage an NE, you must create an NE on the LCT. This topic describes how to create an
NE by searching NEs on the LCT.
4.3.3 Changing the ID of an NE
To ensure that the ID of each NE is unique, you must change the ID of an NE according to the
engineering plan. If the NE ID is changed, the services of the NE are not affected but the
communication between the LCT and the NE is affected.
4.3.4 Changing the IP Address of an NE
After changing the ID of an NE, you can change the IP address of the NE according to the
engineering plan. Changing the IP address of an NE does not affect the services of the NE but
affects the communication between the LCT and the NE.
4.3.5 Configuring Logical Boards
If the physical board is not installed and the corresponding logical board is not added to the slot
layout, you need to add the logical board to the slot layout before configuring the logical board.
If the logical board in the slot layout does not match with the physical board, you need to delete
the board that does not match and add the correct logical board.
4.3.6 Creating IF 1+1 Protection
If the radio link adopts 1+1 HSB/FD/SD protection, you need to create the corresponding IF 1
+1 protection group.
4.3.7 Configuring the IF/ODU Information of a Radio Link
This topic describes how to configure the common IF/ODU information for each radio link.
Prerequisite
l The equipment must be powered on.
l The laptop must be installed with the LCT application. For information about how to install
the LCT, see OptiX iManager U2000 Installation Guide.
l The SQL server must be started.
Context
The U2000 LCT service runs as the background process. The system automatically starts the
U2000 LCT service. You can maintain the service through the System Monitor.
Procedure
Step 1 Start the laptop, and log in to the operating system.
Step 2 Set the IP address of the portable computer. Procedure, which is based on Microsoft Windows
XP, is listed as follows.
1. On the desktop, click the Start, and select Control Panel from the Start Menu. Then, the
Control Panel window is displayed.
2. Double-click Network Connection to display the Network Connection window.
3. In the Network Connection window, right-click Local Connection and choose
Properties. The Local Area Connection Properties dialog box is displayed.
4. Click the General tab. Select Internet Protocol (TCP/IP) from the This connection uses
the following items list.
5. Click Properties to display the Internet Protocol (TCP/IP) Properties dialog box.
6. Select Use the following IP address from Internet Protocol (TCP/IP) Properties.
Configure the IP address and subnet mask of the laptop.
l IP address: The IP address should belong to network segment 129.9.0.0. The IP address
can be set to any IP address in network segment 129.9.0.0. If the system indicates that
the IP address you set conflicts with the IP address of the NE, set another IP address,
which is different from the NE IP address, for the computer.
l Subnet mask: 255.255.0.0.
l Default gateway: null.
7. Click OK.
Step 3 Use a network cable to connect the network port on the laptop to the ETH port of the CXPAR/
CXPBR/CXPGR/CXPHR board. In this case, the green indicator of the ETH port and the green
indicator of network port on the laptop should be on.
CAUTION
When connecting the equipment to the laptop, make sure that the network cable is properly
connected to the ETH port on the CXPAR/CXPBR/CXPGR/CXPHR board so that the
equipment and commissioning tool can be protected against any damage caused by mis-
insertion.
NOTE
The ETH port of the CXPAR/CXPBR/CXPGR/CXPHR board is self-adaptive to crossover and straight cables.
Thus, you can use either a crossover cable or a straight cable to connect the equipment to the portable computer.
Step 4 Check whether the U2000 LCT processes can be normally started.
1. Run the U2000LCT System Monitor server application by clicking the shortcut icon of this
application on the desktop. Then, the Login dialog box is displayed.
2. In the Login dialog box, enter values in the User Name and Password fields, and select a
value for the Server group box.
By default, values for these fields are as follows:
l User Name: admin
l Password: admin
l Server: Local
3. Click Login .
4. Check whether the U2000 LCT processes can be normally started. The process whose
startup mode is the manual mode must be started manually. If the processes can be normally
started, it indicates that the server runs normally.
NOTE
If the U2000 LCT service is not started, you can manually start it by running the startnms.bat file in the
installation directory of the U2000 LCT, that is, the \server\bin directory; If the U2000 LCT service is
started, don't run the startnms.bat file again.
Step 5 Run the U2000 LCT client application by clicking the shortcut icon of this application on the
desktop. Then, the Login dialog box is displayed.
Step 6 Enter values in the User Name and Password fields. Click Login to display the NE Information
List window.
l User Name: admin
l Password: admin
----End
4.3.2 Creating an NE
To manage an NE, you must create an NE on the LCT. This topic describes how to create an
NE by searching NEs on the LCT.
Prerequisite
l The NE must be connected to a computer where the LCT is installed.
l The communication between the LCT and the NE must be normal.
Context
In addition to searching NEs, you can also create an NE by adding an NE manually. When an
NE is configured initially, you may fail to know the NE ID. In this situation, you can create an
NE by searching NEs on the LCT.
Procedure
Step 1 Click Auto Discovery in the NE Information List.
The Equipment Search window is displayed.
Step 2 Click Add and the Input Search Domain dialog box is displayed.
Step 3 Optional: Set Address type to IP Address Range of GNE, IP Address of GNE, or NSAP
Address, and enter Search Address, User Name, and Password. Then, click OK.
NOTE
You can repeat Steps 2 through 3 to add more search domains. You can delete the system default search
domain.
l If you use IP address to search for NEs:
l Usually, the broadcast function is disabled on the routers on a network, to avoid network broadcast
storm. Therefore, by using the IP Address Range of GNE method, only the NEs in the same
network segment can be searched out.
l To search the network segments across routers, the IP Address of GNE method is recommended.
Through a gateway NE, you can search out the NEs in the network segment of the gateway NE.
l If you use NSAP address, you can only select NSAP address.
NOTE
l Select Upload after create. The data related to the NEs are uploaded to the NMS after the
NEs are created.
NOTE
You can select all options in the Search for NE area to search for NEs, create NEs, and upload the NE
data at a time.
Step 6 Optional: If you select Search for NE only, you can select the NEs, which are not yet created,
in the Result list after the search for NEs is complete. Click Create and then the Create dialog
box is displayed. Enter User Name and Password in the Create dialog box, and then click
OK.
----End
Postrequisite
After an NE is created, if you fail to log in to the NE, possible causes are listed as follows:
l The password for the NE user is incorrect. Enter the correct password for the NE user.
l The NE user is invalid or the NE user is already logged in. Change to use a valid NE user.
Prerequisite
You must be logged in to the LCT.
You must be an NM user with "NE Operator" authority or higher. That is, you must be an NE
user with "Operation Level" authority or higher.
Procedure
Step 1 Select an NE from the Object Tree in the NE Explorer window. Then, choose Configuration
> NE attribute from the Function Tree.
----End
Prerequisite
You must be logged in to the LCT.
You must be an NM user with "NE Operator" authority or higher. That is, you must be an NE
user with "Operation Level" authority or higher.
Procedure
Step 1 Select an NE from the Object Tree in the NE Explorer window. Then, choose
Communication > Communication Parameters from the Function Tree.
Step 2 Set the parameters of the NE, including IP, and Gateway IP according to the engineering plan.
----End
Prerequisite
l All the required boards must be installed correctly.
l You must be logged in to the NE.
l You must be an NE user with "System Level" authority or higher.
Procedure
Step 2 Optional: Right-click the slot where the board needs to be added and choose Add XXX from
the shortcut menu, wherein, "xxx" indicates the name of the board to be added.
NOTE
l Before adding an IF board or a service board, you must add the CXPAR/CXPBR/CXPGR/CXPHR board.
l The method of adding a logical board manually is mainly used when the required physical board is not
installed. In this manner, you can configure the board in advance.
Before deleting a board, you must delete the data, including the services, clock, orderwire, and protection
from the board.
1. Right-click the slot where the board needs to be deleted and choose Delete from the shortcut
menu.
2. A dialog box is displayed for confirmation, click OK.
3. A dialog box is displayed again for confirmation, click OK.
----End
Prerequisite
l You must be an NM user with NE operator authority or higher.
l The IF boards and their corresponding ODUs that form the IF 1+1 protection must be added
to the NE Panel.
l The IF boards of an IF 1+1 FD/SD protection group must be configured in two paired slots.
Procedure
Step 1 Select the NE from the Object Tree in the NE Explorer. Choose Configuration > IF 1+1
Protection from the Function Tree.
The parameters Working Mode, Revertive Mode, WTR Time (s), and Enable Reverse Switching must
be set to the same values at both ends of a hop of radio link.
----End
Postrequisite
l In the case of the 1+1 HSB protection and 1+1 SD protection, you need to configure the
IF/ODU information of the active radio link later. The standby radio link automatically
copies the related information of the active microwave link except the transmission status
of the ODU.
l In the case of the 1+1 FD protection, you need to configure the IF/ODU information of the
active radio link and the information of the standby ODU later. The standby radio link
automatically copies the IF information of the active radio link.
NOTE
The default transmission status of an ODU is Unmute. Hence, you need not configure the transmission status
of the standby ODU after creating an IF 1+1 protection group.
Prerequisite
l The IF board and the ODU that connects to the IF board must be added to the NE Panel.
l You must be an NM user with NE operator authority or higher.
Precautions
l In 1+1 HSB/SD protection mode, one protection group corresponds to one radio link. In
this case, you need to configure only the IF/ODU information of the main equipment.
l In 1+1 FD protection mode, one protection group corresponds to one radio link. In this
case, you need to configure the IF/ODU information of the main equipment and the ODU
information of the standby equipment.
l In the case of XPIC radio links, one XPIC workgroup corresponds to two radio links. The
IF/ODU information of the radio links should be configured in the XPIC workgroup.
Procedure
Step 1 Select the NE from the Object Tree in the NE Explorer. Choose Configuration > Link
Configuration from the Function Tree.
Then, the system displays the IF/ODU information of the radio link to which the IF board or the
ODU belongs.
----End
Prerequisite
The cables between the E1 electrical interface board and the digital distribution frame (DDF)
must be installed and routed.
Procedure
Step 1 Connect the 2M connectivity tester to the 2M trunk cable connector of the equipment side.
1 9
TX RX 2 10
3 11
RX TX 4 12
5 13
. . .
E1 cable 6 14
7 15
8 16
2 Mbit/s DDF
bit error 2 Mbit/s connectivity
tester tester
Step 2 Use the BER tester to test each pair of 2M trunk cables on the DDF. The Tx port of the BER
tester should be connected to the Rx port of the trunk cable on the DDF and the Rx port of the
BER tester should be connected to the Tx port of the trunk cable on the DDF. Then, check the
indicators of the corresponding channels on the 2M connectivity tester.
l If the green indicator is on, it indicates that the service is transmitted and received normally.
l If the red indicator is on, it indicates that the transmit end and receive end are connected
reversely.
l If the red indicator and the green indicator are both on, it indicates that the receive end is
normal but the transmit end is not normal.
Step 3 Check the BER tester.
The BER tester should not display any bit errors and should display that the LOS signal is normal.
Otherwise, you must check whether the 2M cables are connected improperly or dry jointed.
Step 4 After all the channels are tested, install the 2M trunk cable connectors of the equipment side on
the equipment.
----End
Prerequisite
The Ethernet service cables must be prepared.
Background Information
You can also test the connectivity of the network cable by performing a loopback on the data
ports (this method is applicable when the equipment is powered on). Specifically, use the
network cable to be tested to connect any two data ports. If the LINK indicators of the two data
ports are on, it indicates that the network cable is normal.
Procedure
Step 1 Connect the Ethernet service cable to the port of the network cable tester.
Step 3 Connect the network cable that passes the test to the Ethernet port of the equipment.
----End
5 Hop Commissioning
Main lobe
First side lobe
Second side lobe
only 0.9° when the signal level drops from the signal peak to zero. Once a signal is detected,
very small alignment adjustments are required to locate the main lobe.
Antenna movement across the main lobe will result in a rapid rise and fall of signal level. Whether
the main lobe is aligned properly can be verified by comparing the received signal peaks.
Typically, the main lobe signal peak is 20-25 dB higher than the first side lobe signal peak.
Figure 5-2 shows the head-on view of a free-space model for radio propagation. The side lobes
take the main lobe as the center and are distributed in the radiate form.
90o
0o
Tracking Path
Side lobe signal readings can be mistaken for main lobe readings when signals are tracked at
different elevations (or azimuths). Figure 5-3 shows a horizontal radio propagation model of
the antenna, and signal levels at three different elevation positions("1-7" represent the measured
signal level values of the received signal strength indicator (RSSI) port of the ODU.)
6 7
C C'
C 6 7 C' 5
4
4 5
B B'
B B'
1 2 3
A A'
2
1 3
A A'
l Line AA' represents that the main lobe of the antenna is almost aligned properly. The main
lobe is at point 2, and the first side lobes are at points 1 and 3. Slightly adjust the azimuth
of the antenna at point 2 until the peak signal appears.
l Line BB' represents that the elevation of the antenna slightly deviates from the main lobe.
The signal peaks appear at points 4 and 5. The signal peak at point 4 is higher than the
signal peak at point 5 because of the antenna characteristics. As a result, point 4 may be
mistaken for the peak point of the main lobe signal. The correct method is to set the azimuth
of the antenna to the middle position between the two signal peaks. Then, adjust the
elevation of the antenna until the three signal peaks of line AA' appear. Slightly adjust the
elevation and azimuth of the antenna at point 2 until the peak signal appears.
l Line CC' represents that the elevation of the antenna completely deviates from the main
lobe and is almost aligned with the first side lobe. The signal peak of the first side lobe at
point 6 and the signal peak of the first side lobe at point 7 appear as one signal peak. As a
result, points 6 and 7 may be mistaken for the peak point of the main lobe signal. The correct
method is to set the azimuth of the antenna to the middle of points 6 and 7. Then, adjust
the elevation of the antenna until the three signal peaks of line AA' appear. Slightly adjust
the elevation and azimuth of the antenna at point 2 until the peak signal appears.
When the side lobe peak at one side is higher than the side lobe peak at the other side, as shown
in Figure 5-4, a common error is to move the antenna left to right along line DD', or top to
bottom along line EE'. As a result, point 1 may be mistaken for the peak point of the main lobe
signal. The correct method is to adjust the elevation in the middle of points 1 and 2 or the azimuth
in the middle of points 1 and 3. Several adjustments are required so that the three signal peaks
of line AA' can appear. Slightly adjust the elevation and azimuth of the antenna at point 2 as
shown in Figure 5-3 until the peak signal appears.
Figure 5-4 Aligning the antenna with the first side lobe
E
1
2
D D'
1 2
D D'
1
3
3
E E'
E'
Prerequisite
l The NE commissioning of the radio equipment at both ends of the radio link must be
complete.
l The weather should be suitable for outdoor work. There should be no rain, snow, or fog
between stations.
l The on-site conditions must meet the requirements for the antenna to operate at heights and
the personnel required to commission the antenna must be trained to work at high altitudes.
l The ATPC function must be disabled (the ATPC function, however, is disabled by default) .
l 4.3.7 Configuring the IF/ODU Information of a Radio Link, setting the Enable AM as
disabled.
Precautions
l If the radio link is configured to 1+1 protection mode and one antenna is shared by the two
ODUs, power off the standby ODUs at both ends before aligning the antennas. After the
antennas are aligned, power on the standby ODUs at both ends.
l If the radio link is configured in 1+1 SD mode, align the antennas as follows:
1. Power on the main ODUs at both ends, and ensure that they are power-on during the
alignment.
2. Power off the standby ODUs at both ends, and align the main antennas at both ends.
3. Power on the standby ODU at the local end. Maintain the position of the main antenna
at the remote end, and adjust the diversity antenna at the local end.
4. Power on the standby ODU at the remote end. Maintain the position of the main
antenna at the local end, and adjust the diversity antenna at the remote end.
l If the radio link is configured in 1+1 FD mode and two antennas are used at each end, align
the antenna as follows:
1. At both ends, power on the main ODUs, power off the standby ODUs, and align the
main antennas.
2. At both ends, power off the main ODUs, power on the standby ODUs, and align the
diversity antennas.
CAUTION
You can adjust the azimuth angle and elevation angle of the antennas by adjusting the related
nuts or screws. For details, refer to the related installation guide.
Procedure
Step 1 Determine the azimuth of the antenna according to the installation position and height of the
antenna. Then, adjust the elevation of the antenna to the horizontal position.
Step 2 Connect a multimeter to the RSSI port on the ODU at the local end and test the voltage value
VBNC.
TIP
It is recommended that you make the test line terminated with a BNC connector at one end in advance
because it is more convenient to test the voltage value VBNC.
Step 4 Repeat Step 2 to Step 3 to adjust the remote antenna. When the remote received signal level
(RSL) reaches the peak value, tighten the remote antenna.
Step 5 Repeat Step 2 to Step 4 for two to four times and ensure that the RSL at the local end and the
RSL at the remote end reach the peak value. Tighten the antennas at both ends.
Step 6 Use the multimeter to test the VBNC voltage at both ends. Obtain the current RSL by referring
to the relation curve between the VBNC of ODUs and the RSLs at both ends.
NOTE
The curve diagram of the VBNC and RSL is put in the carton holding the ODU.
The actual RSL must be the same as planned by the network planning department.
NOTE
l If the VBNC does not meet the requirements, refer to the Maintenance Guide for fault handling.
Step 7 The ODU indicator on the IF board should be off. If the ODU indicator on the IF board blinks
yellow, you need to align the antenna.
Step 8 Tighten all the screws of the antennas.
----End
Prerequisite
l The NE commissioning of the radio equipment at both ends of the radio link must be
complete.
l The weather must be suitable for outdoor work. There should be no rain, snow or fog
between stations.
l The on-site conditions must meet the requirement for performing operations at heights and
the personnel in charge of commissioning the antenna must be trained to work at heights.
l The ATPC function must be disabled (the ATPC function, however, is disabled by default).
Procedure
Step 1 Power off the vertically polarized ODUs at both ends of the radio link, power on the horizontally
polarized ODUs at both ends of the radio link, and thus ensure that the antennas transmit
horizontally polarized signals.
Step 2 Adjust the azimuth angle and elevation angle of the antennas at both ends by referring to 5.1.2
Aligning the Single-Polarized Antennas, and ensure that the main lobe of the horizontally
polarized signals is aligned with the antenna.
Step 3 Measure the RSL (P1) of the horizontally polarized signals at the local end.
1. Use a multimeter to measure the signal level on the RSSI port of the horizontally polarized
ODU.
2. Calculate the RSL (P1) of the horizontally polarized received signals by referring to the
curve diagram in the ODU box.
Step 4 Adjust the feed boom at the local end, and ensure that the RSL of the vertically polarized signals
reaches the lower threshold (P2).
1. Power on the vertically polarized ODU at the local end.
2. Use a multimeter to measure the signal level on the RSSI port of the vertically polarized
ODU.
3. Release the holder of the feed boom a little bit, and turn the feed boom slightly until the
signal level reaches the lower threshold.
4. Calculate the RSL (P2) of the vertically polarized signals by referring to the curve diagram
in the ODU box.
The calculated XPD1 (XPD1 = P1 - P2) should not be less than 30 dB.
Step 5 Record the angle (D1) of the current feed boom.
Step 6 Power off the horizontally polarized ODUs at both ends of the radio link, power on the vertically
polarized ODUs at both ends of the radio link, and thus ensure that the antennas transmit
vertically polarized signals.
Step 7 Measure the RSL (P3) of the vertically polarized signals at the local end by referring to Step
3.
Step 8 Power on the horizontally polarized ODU at the local end, and calculate the level (P4) of the
horizontally polarized signals received at the local end by referring to Step 4.
The calculated XPD2 (XPD2 = P3 - P4) should not be less than 30 dB.
Step 10 Repeat Step 3 to Step 9 to adjust the feed boom slightly (ranging from D1 to D2), and ensure
that XPD1 and XPD2 are not less than 30 dB.
----End
Related Information
In the actual situation of the dual-polarized antenna alignment, you can start with adjusting the
vertically polarized signals.
Prerequisite
The antennas must be aligned.
Procedure
Step 1 Check the Link indicator on the IF board.
1. If the Link indicator on the IF board is on and green, it indicates that the radio link is normal.
2. If the Link indicator on the IF board is on and red, check whether the data configuration of
the ODU is correct and whether the ODU indicator on the IF board is normal.
l If the data configuration of the ODU is incorrect, refer to 4.3.7 Configuring the IF/
ODU Information of a Radio Link to set correct parameters.
l If the ODU indicator on the IF board blinks yellow, refer to 5.1 Aligning the
Antennas to continue with the antenna alignment until the ODU indicator is off.
----End
Prerequisite
l The equipment must be configured in IF 1+1 mode.
l The antennas must be aligned.
Procedure
Step 1 Select the NE from the NE Explorer. Then, choose Configuration > IF 1+1 Protection from
the Function Tree.
Step 2 Click Query.
In Protection Group, the Active Port of Device should be the active IF board.
----End
6 Network Commissioning
This chapter describes the network commissioning items and the commissioning methods.
6.1 Checking the Connection between the Equipment and the NMS Computer
The NMS runs on the NMS computer to manage the NEs. If the NMS computer is incorrectly
connected to the equipment, the NMS cannot manage the NEs. Check the connection between
the equipment and the NMS computer to ensure that the connection is correct. This section
describes how to check the connection between the equipment and the NMS computer.
6.2 Starting the U2000
During network commissioning, use the U2000 to configure the equipment in the network. To
start the U2000, start the NMS computer, start the U2000 server and log in to the U2000 client.
6.3 Creating the Network Topology
According to the actual connections between NEs, create a network topology on the U2000.
After the topology is created, you can use the U2000 to configure services and perform each
commissioning task.
6.4 Configuring the VLAN ID and the Bandwidth for the Inband DCN
The network management (NM) center manages the OptiX RTN equipment through the inband
DCN scheme. That is, the service information and NM information (DCN packet) are transmitted
in the same physical link or tunnel. When the Ethernet port is used to carry the DCN packets,
the NE distinguishes the DCN packets from the service packets by an NM-dedicated VLAN ID.
Therefore, you need to set the bandwidth used by inband DCN and the VLAN ID for the inband
DCN packets according to the actual planning during engineering commissioning.
6.5 Synchronizing NE Time
Adjust the NE time to make it synchronous with the U2000 time so that the U2000 can accurately
record the time when an alarm, a performance event, or an abnormal event occurs.
6.6 Enabling the NE Performance Monitoring Function
Enabling the performance monitoring function for an NE helps perform the following
commissioning operations and monitor new performance events in the commissioning process.
If the performance monitoring function is enabled, you can obtain detailed performance records
during the operation process of this NE so that you can easily monitor and analyze the running
status of the NE.
6.7 Checking the Optical Power of Optical Interface
If the transmitted or received optical power at an optical interface is excessively low or high, bit
errors may be generated on the equipment, and the optical component may even be damaged.
This section describes how to check the transmitted and received optical power at optical
interfaces to ensure that the transmitted and received optical powers at all the optical interfaces
are within the normal range.
6.8 Configuring Services
When the U2000 can maintain and manage the network for commissioning, you can use the
U2000 to configure all kinds of services that the equipment supports. This section describes how
to configure services for conducting the tests of these services.
6.9 Testing Service Connectivity
After services are configured on the U2000, test the connectivity of the services to ensure that
the services are created correctly. This section describes how to test the connectivity of various
basic network services.
6.10 Testing the Network Protection Switching
After the network protection is configured on the U2000, the network protection switching
should be tested to ensure the effectiveness of the network protection. This section describes
how to test the network protection schemes supported by the RTN equipment.
Prerequisite
l The NMS computer must be connected to the equipment through a network cable or LAN.
l The equipment and the NMS computer must be powered on.
l The NMS computer must start up normally.
Procedure
l The NMS computer is connected to the equipment through a network cable.
1. Check the connection of the network cable.
One end of the network cable should be connected to the network interface card of
the NMS computer and the other end should be connected to the network management
interface of the gateway NE.
2. Observe the indicator for the network interface card of the NMS computer and the
indicator for the network management interface of the gateway NE.
The LINK indicator should stay on and green. If there are packets to be sent or
received, the orange ACT indicator should flash.
l The NMS computer is connected to the equipment through LAN.
1. Check the connection of the network cable.
– On the NMS side, one end of the network cable should be connected to the network
interface card of the NMS computer and the other end should be connected to the
LAN switch.
– On the equipment side, one end of the network cable should be connected to the
network management interface of the gateway NE and the other end to the LAN
switch.
2. Observe the indicators beside the interfaces with connection.
The LINK indicator should stay on and green. If there are packets to be sent or
received, the orange ACT indicator should flash.
----End
For details on how to start the U2000, see OptiX RTN 910 Radio Transmission System
Configuration Guide.
Prerequisite
l 6.2 Starting the U2000 must be performed.
l You must be a U2000 user with "NE and network administrator" authority or higher.
l The U2000 must normally communicate with the gateway NE and the gateway NE must
normally communicate with NEs connected to the gateway NE.
Procedure
Step 1 Choose File > Discovery > NE ... from the Main Menu. The Auto Discovery window is
displayed.
Step 2 Click Add and the Input Search Domain dialog box is displayed.
Step 3 Set Address type to IP Address Range of GNE, IP Address of GNE, or NSAP Address, and
enter Search Address, User Name, and Password. Then, click OK.
NOTE
You can repeat Steps 2 through 3 to add more search domains. You can delete the system default search
domain.
l If you use IP address to search for NEs:
l Usually, the broadcast function is disabled on the routers on a network, to avoid network broadcast
storm. Therefore, by using the IP Address Range of GNE method, only the NEs in the same
network segment can be searched out.
l To search the network segments across routers, the IP Address of GNE method is recommended.
Through a gateway NE, you can search out the NEs in the network segment of the gateway NE.
NOTE
NOTE
You can select all options in the Search for NE area to search for NEs, create NEs, and upload the NE
data at a time.
Step 6 Optional: If you select Search for NE only, you can select the NEs, which are not yet created,
in the Result list after the search for NEs is complete. Click Create and then the Create dialog
box is displayed. Enter User Name and Password in the Create dialog box, and then click
OK.
Step 7 Optional: If some NEs are not searched out, it indicates that the DCN channels between these
NEs and the gateway NE are unavailable, or these NEs are faulty. In this case, troubleshoot the
fault with reference to Maintenance Guide.
----End
Postrequisite
After an NE is created, if you fail to log in to the NE, possible causes are listed as follows:
l The password for the NE user is incorrect. Enter the correct password for the NE user.
l The NE user is invalid or the NE user is already logged in. Change to use a valid NE user.
Prerequisite
l The NEs in the network must be created successfully.
l You must be an NM user with "NE and network operator" authority or higher.
Procedure
l To copy the NE data, do as follows:
NOTE
The NE type, NE software version and hardware configuration of the source NE must be consistent
with those of the copied NE.
1. Double-click the unconfigured NE on the Main Topology.
The NE Configuration Wizard dialog box is displayed.
2. Choose Copy NE Data and click Next.
The NE Replication dialog box is displayed.
3. Select the NE in the drop-down list and click Start.
The Confirm dialog box is displayed indicating that the copy operation copies all the
data of the source NE.
4. Click OK.
The Confirm dialog box is displayed indicating that the copy operation results in the
loss of the original data of the NE to which the data is copied.
5. Click OK to start the copy.
Wait for a few seconds. The Operation Result dialog box is displayed.
6. Click Close.
l Upload:
1. Double-click the unconfigured NE on the Main Topology.
The NE Configuration Wizard dialog box is displayed.
2. Choose Upload and click Next.
The Confirm dialog box is displayed indicating that the upload may take a long time.
3. Click OK to start the upload.
Wait for a few seconds. The Operation Result dialog box is displayed.
4. Click Close.
----End
Prerequisite
l You must be a U2000 user with "NE and network maintainer" authority or higher.
l All the NEs in the network are properly configured according to 6.3.2 Configuring NE
Data.
Procedure
Step 1 Click the shortcut icon in the Main Topology and the cursor is displayed as +.
NOTE
When the cursor is displayed as +, right-click to display the Select Object dialog box. Click ok to cancel link
selection.
Step 2 Click the source NE of a fiber connection in the Main Topology, and the Select Fiber/Cable
Source dialog box is displayed.
Step 3 In the Select Fiber/Cable Sink dialog box, select boards and ports that are connected with fibers.
Step 4 Click OK. The cursor is displayed as +.
Step 5 Click the sink NE of a fiber connection in the Main Topology, and the Select Fiber/Cable
Sink dialog box is displayed.
Step 6 In the Select Fiber/Cable Sink dialog box, select boards and ports that are connected with fibers.
Step 7 Click OK. The Create Fiber dialog box is displayed, which displays the related information on
the fiber connection.
Step 8 Click Apply. In the Main Topology, the fiber connection between the source and sink NEs are
displayed.
Step 9 Select the fiber you create, right-click and choose Detect Link from the shortcut menu.
The Operation Result dialog box is displayed indicating the fiber connection information.
Step 10 According to the connections between NEs shown in the engineering diagram, perform Step 2
- Step 9 to create fiber connections between NEs in sequence.
Step 11 Check the network topology in the Main View of the U2000 and make sure that the network
topology is consistent with the engineering diagram.
CAUTION
Incorrect fiber connections result in commissioning errors and affect the services that are
running.
----End
Therefore, you need to set the bandwidth used by inband DCN and the VLAN ID for the inband
DCN packets according to the actual planning during engineering commissioning.
Prerequisite
l Configuring NE Data must be performed.
l You must be an NM user with "NE and network operator" authority or higher.
Context
l When the Ethernet port is used to carry the DCN packet, the NE distinguishes the DCN
packet from the service packet by an NM-dedicated VLAN ID. When the E1 port or tunnel
is used, the NE distinguishes the DCN packet from the service packet by a special MPLS
label. The MPLS label of the DCN packet cannot be modified.
l The bandwidth used by inband DCN is set to limit the bandwidth used to carry the in-band
DCN information on the physical port or tunnel.
l If the set bandwidth is not fully occupied by the DCN packet, the remaining bandwidth can
be used by the service packets.
Procedure
Step 1 On the Main Topology of the U2000, right-click the target NE to choose NE Explorer from the
shortcut menu. Then, the NE Explorer window is displayed.
Step 2 Choose Communication > DCN Management from the Function Tree in the NE Explorer
window.
Step 3 Click the Bandwidth Management tab, and set the VLAN ID for the inband DCN packets and
the bandwidth used by inband DCN according to the actual planning.
For description of bandwidth management parameters of the inband DCN, see Table 6-1.
Ethernet Board VLAN ID 1-4094 Sets the VALN ID used by the DCN packet.
Default: When Ethernet ports are used to carry DCN
4094 packets, you can set this parameter.
Generally, the default VLAN ID is
recommended. When the VLAN ID of the
service packets conflicts with the VLAN ID
of the DCN packets, you can customize the
VLAN ID for the DCN packets. Note that
VLAN ID of the DCN packets in the entire
network must be consistent.
Bandwidth (Kbit/s) 64-2048 Sets the bandwidth used by the DCN. When
Default: 512 Ethernet ports are used to carry DCN packets
among NEs, you can set this parameter.
The default value is recommended.
E1 Port Bandwidth (Kbit/s) 64-2048 Sets the bandwidth used by the DCN. When
Default: 192 E1 ports are used to carry DCN packets
among NEs, you can set this parameter.
The default value is recommended.
Tunnel Bandwidth (Kbit/s) 64-2048 Sets the bandwidth used by the DCN. When
Default: 512 the IP tunnel or GRE tunnel are used to carry
DCN packets, you can set this parameter.
The default value is recommended.
IF Port Bandwidth (Kbit/s) 64-2048 Sets the bandwidth used by the DCN. When
Default: 512 the IF Ports are used to carry DCN packets,
you can set this parameter.
The default value is recommended.
----End
Prerequisite
l All the NEs in the network must be properly configured according to 6.3 Creating the
Network Topology.
l You must be an NM user with "NE and network maintainer" authority or higher.
l You must log in to the NE as an NE user with system level authority or higher.
NOTE
The default NE user root is of system level.
Procedure
Step 1 Make sure that the time zone of the computer where the U2000 server and the U2000 client
operate is correct and the time of this computer is accurately set.
Step 2 Choose Configuration > NE Batch Configuration > NE Time Synchronization from the
Main Menu on the U2000. Then, the NE Time Synchronization window is displayed.
Step 3 Select all the NEs in the left-hand object tree and click . Then, the selected NEs are
displayed in the right-hand list of the NE Time Synchronization window.
Step 4 Select all the NEs in the list and right-click the Synchronous Mode field. Choose NM from the
shortcut menu to set Synchronous Mode of all the NEs to NM, click Apply.
Step 5 Select all the NEs in the list and right-click the NE Name field. Choose Synchronize with NM
Time from the shortcut menu.
Step 6 Click Yes in the displayed Time Synchronization Operation dialog box. Then, the Operation
Result dialog box is displayed indicating that the operation is successful.
----End
Prerequisite
l All the NEs in the network must be properly configured according to 6.5 Synchronizing
NE Time.
l You must be an NM user with "NE and network operator" authority or higher.
l You must log in to the NE as an NE user with system level authority or higher.
NOTE
Procedure
Step 1 Select and right-click the target NE in the Main Topology of the U2000. Choose NE
Explorer from the shortcut menu. Then, the NE Explorer window is displayed.
Step 2 Choose Performance > NE Performance Monitoring Time from the left-hand navigation tree
to display Performance Monitor Time function interface.
Step 3 Enable the 15-minute performance monitoring for the NE.
1. Select the NE in the Performance Monitor Time function interface.
2. Select the check box before 15-Minute.
3. Select the option button before Enable in the Set 15-Minute Monitoring group box.
4. Click to set from. The starting time must be later than the current time of the NE and
NM.
5. If you need to set To, you can select the check box before To and then click to set
To for the performance monitoring.
6. Click Apply. Then, the Operation Result dialog box is displayed, indicating that the
operation is successful. Click Close.
Step 4 Follow Step 3 to enable the 24-hour performance monitoring for the NE.
NOTE
The 24-hour performance monitoring must be started from 00:00:00 (hh:mm:ss). Otherwise, the performance
data obtained in the first period of time is incomplete and invalid for performance analysis.
----End
After the commissioning tasks for the entire network are complete, keep the performance
monitoring function of the NE enabled or disable it according to the customer requirement.
Prerequisite
l All the NEs in the network must be properly configured according to 6.6 Enabling the NE
Performance Monitoring Function.
l You must be a U2000 user with the "NE and network monitor" authority or higher.
l The fibers must be routed to the ODF on all the stations.
Operation Criteria
The mean transmitted optical power and received optical power must be in the corresponding
value ranges that are listed in Technical Specifications of Boards in the OptiX RTN 910 Radio
Transmission System Product Description manual.
Procedure
Step 1 Set the tested optical interfaces of the NE by using the U2000 to make the optical interfaces
work in the running state.
1. On the Main Topology, select and right-click the tested NE. In the shortcut menu, choose
NE Explorer to display the NE Explorer window.
2. Click the NE in the NE Explorer window, and choose Configuration > Interface
Management > Ethernet Interface from the Function Tree.
3. In the General Attributes tab, enable the tested Ethernet optical interface, click Apply.
Step 2 Select a board with the optical interface in the NE Explorer. Choose Performance > Current
Performance from the Function Tree.
Step 3 Set the Monitored Object Filter Condition to All to check the optical powers of all the optical
interfaces in the board.
Step 5 In the Gauge tab, select Transmitted Optical Power and Receive Optical Power in the
Performance Event Type group box, and select Display current Value and Display
Maximum/Minimum Values in the Display Options group box. Then, click Query. The
optical powers of all the optical interfaces in the board is displayed in the lower part of the
window.
Step 6 Check the optical interface type with reference to related engineering documents.
Step 7 Check whether the transmitted and received optical powers are within the normal range.
NOTE
The received optical power must follow the standard: receiver sensitivity + 3 dBm < received optical power
(tested) < overload threshold - 5 dBm.
Step 8 Optional: If the transmitted optical power is not within the normal range, handle the fault with
reference to the following.
1. If the fiber connector is not clean, clean the fiber connector according to OptiX RTN 910
Radio Transmission System Maintenance Guide.
2. Restore the fiber connection at the tested optical interface.
3. Perform Step 2 - Step 7 to check the transmitted optical power of the optical interface
again, until the transmitted optical power obtained is within the normal range.
Step 9 Optional: If the received optical power is not within the normal range, handle the fault with
reference to the following.
l If the received optical power is less than sensitivity + 3 dBm
1. Check whether the fiber connector, the optical attenuator, and the fiber flange are
clean.
2. If the fiber connector is not clean, clean it according to OptiX RTN 910 Radio
Transmission System Maintenance Guide.
3. Restore the fiber connection at the tested optical interface.
4. If the fiber flange or the optical attenuator on the ODF side is not clean, replace the
fiber flange or the optical attenuator.
5. Perform Step 2 - Step 7 to check the received optical power of the optical interface
again, until the received optical power obtained is within the normal range.
l If the received optical power is larger than overload threshold - 5 dBm
1. Check whether the optical attenuator is normal.
2. If the optical attenuator is normal, add an optical attenuator on the ODF side.
3. If the optical attenuator is not normal, replace the optical attenuator.
4. Perform Step 2 - Step 7 to check the received optical power of the optical interface
again, until the received optical power obtained is within the normal range.
Step 10 Check whether the transmitted and received optical powers at all the other optical interfaces of
the equipment are within the normal range one by one with reference to the previous steps.
----End
Prerequisite
6.3 Creating the Network Topology must be performed on the U2000.
Operation Procedure
Table 6-2 lists details on configuration of the network services.
Prerequisite
l An end-to-end ATM service must be configured.
l You must be a U2000 user with "NE and network operator" authority or higher.
Context
Segment End Attribute of LB test for an ATM service specifies the type of the transmitted
OAM cells during the LB test.
l If Segment End Attribute is set to Segment point, seg_LB cells are transmitted.
l If Segment End Attribute is set to Endpoint, e-t-e_LB cells are transmitted.
NE1 NE2
Procedure
Step 1 Set the loopback automatic disabling function to Disabled for the UNI interfaces accessing the
tested ATM service on the NE2 equipment by using the U2000.
1. Choose Configuration > NE Batch Configuration > Automatic Disabling of NE
Function from the Main Menu to display the Automatic Disabling of NE Function
window.
2. Select the NE2 in the left-hand object tree and click . The selected NEs are
displayed in Automatic Disabling of NE Function on the right.
3. Set Auto Disabling to Disabled for SDH Optical/Electrical Interface Loopback of the
NE2.
NOTE
When the automatic disabling function of SDH Optical/Electrical Interface Loopback on the NE is set
to Disabled, the loopback automatic disabling function for all of the SDH optical interfaces, PDH electrical
interfaces and ATM IMA groups on the NE is disabled.
4. Click Apply.
Step 2 Set inloop for the UNI interfaces (to be tested) that access the ATM service on NE2 by using
the U2000.
1. On the Main Topology, select and right-click the NE2 NE. In the shortcut menu, choose
NE Explorer to display the NE Explorer window.
2. In the NE Explorer window, select the NE, and choose Configuration > Interface
Management > ATM IMA Management from the Function Tree.
3. Select the ATM Interface Management tab and then select the IMA group that carries
the ATM service.
4. Double-click the Loopback of the IMA group, and then select Inloop in the shortcut menu.
5. Click Apply.
Step 3 In the NE Explorer window, select the NE1 NE, and choose Configuration > ATM OAM
Management from the Function Tree.
Step 4 Select the Remote Loopback Test tab, and then select the tested ATM service.
Step 5 Set the Loopback Point NE of the tested ATM service to NE2 NE.
Step 6 Click Test to start LB test.
Step 7 After the test is finished, check the Test Result of the tested ATM service.
Normally, the Test Result should be Test succeeded. If not, handle the fault with reference to
the Test Result hint and "" in the OptiX RTN 910 Radio Transmission System Maintenance
Guide.
Step 8 Release the inloop of the UNI interface accessing the ATM service on NE2 with reference to
Step 2.
Step 9 Follow Step 2 - Step 8 to test the connectivity of all the other ATM services on NE1 and
NE2.
Step 10 Set Automatic Disabling to Enabled for SDH Optical/Electrical Interface Loopback on
NE2 with reference to Step 1.
Step 11 Test the connectivity of the ATM services on all the other NEs with reference to Step 1 - Step
10.
----End
Prerequisite
l An end-to-end Ethernet service must be configured.
l You must be an NM user with "NE and network operator" authority or higher.
l You must complete the setting of the basic attributes and Layer 3 attributes of the port.
Figure 6-2 Connection diagram for the Ethernet service connectivity test
NE1 NE2
Tunnel
PW
CAUTION
l Ensure that only the commissioning engineers are present on the test site.
l Do not touch the cables, unless necessary.
l Do not insert or remove any power supply device near the test site.
Procedure
Step 1 On the U2000, check the tunnel that carries the Ethernet service on NE1. For details, see Figure
6-2.
Step 2 Configure a static route on NE2.
1. In the NE Explorer, select an NE and choose Configuration > Control Plane
Configuration > Static Route Management from the Function Tree.
2. Click Create to create the static routes, and then click Apply.
l Route List ID: 1
l Board: 3-IFE2
l Port: 1(Port-1)
l Next Hop IP Address: 10.0.0.1
l Destination Node IP Address: 1.0.0.1
l Destination Node Subnet Mask: 255.255.255.255
NOTE
l When selecting boards or ports, select those that have Layer 3 attributes.
l When the static route is configured, the port IP address and the next hop IP address must be in
the same network section.
l When the last digit of the IP address of the destination is not 0, the subnet mask is
255.255.255.255. For example, if the IP address is 193.168.3.2, the mask of the destination node
is 255.255.255.255.
l When the last digit of the IP address of the destination is 0, the subnet mask is 255.255.255.0 or
255.255.255.255. For example, if the IP address is 193.168.3.0, the mask of the destination node
is 255.255.255.255 or 255.255.255.0.
Step 3 Perform the MPLS OAM ping test on NE1 to check whether the MPLS tunnel for the Ethernet
service is created successfully.
1. In the NE Explorer, click NE1 and choose Configuration > MPLS Management >
Unicast Tunnel Management from Function Tree.
2. Click the OAM Parameters tab and select the tunnel. Click OAM Operation and choose
Ping Test from the drop-down menu. The Ping Test dialog box is displayed.
NOTE
The tunnel supports the ping test only when Node Type is Ingress.
3. Set the related parameters.
4. Click Start Test and then check the ping test result.
Step 4 Check the ping test result to see whether packet loss occurs.
l If packet loss occurs, go to Step 5.
l If packet loss does not occur, go to Step 8.
Step 5 Check for abnormal alarms about the Ethernet service, such as ETH_LINK_DOWN and
ETH_LOS, and handle them according to the Routine Maintenance.
Step 6 Perform Step 3 to Step 4 to re-test the connectivity of the Ethernet service.
Step 7 Perform the MPLS OAM ping test in the scenario where PE2 is the local NE and PE1 is the
remote NE. For details on the operations, see Step 1 to Step 5.
Step 8 Test the connectivity of all the Ethernet services on NE1 and NE2. For details on the operations,
see Step 1 to Step 7.
Step 9 Test the connectivity of the Ethernet services on other NEs. For details on the operations, see
Step 1 to Step 8.
----End
Prerequisite
l An end-to-end CES service must be configured.
l You must be a U2000 user with "NE and network operator" authority or higher.
Tx
Rx
SDH analyzer
CAUTION
l During the test, unrelated personnel should stay away from the test environment.
l Do not touch the cable, unless necessary.
l Do not insert or remove power supply devices near the test environment.
Procedure
Step 1 According to Figure 6-3, connect the interface that accesses the CES service on NE1 to the SDH
analyzer.
TIP
You can configure n 2M CES services on n 2M interfaces (for example, n 2M interfaces on a 2M service
board). Then, test these 2M CES services that are cascaded on the DDF at a time.
The parameters of the cascaded 2M CES services to be tested must be identical. In addition, you must set
inloop for the UNI interfaces (to be tested) that access the CES services on NE2.
Consider the 75-ohm 2M interface as an example. The diagram for testing connections on the NE1
equipment is shown in Figure 6-4.
NE1
……
RX1 TX1 RX2 TX2 RXn TXn The back of
…… the DDF
…… The front of
the DDF
……
TX RX
SDH analyzer
Legend: Note:
2M connector Terminals on the front of the DDF are
connected to the corresponding
2M cable
terminals on the back of the DDF.
Internal connection
of DDF
Step 2 Set the loopback automatic disabling function to Disabled for the tested CES service interface
on the NE2 equipment by using the U2000.
1. Choose Configuration > NE Batch Configuration > Automatic Disabling of NE
Function from the Main Menu to display the Automatic Disabling of NE Function
window.
2. Select the NE2 NE in the left-hand object tree and click . The selected NE is
displayed in Automatic Disabling of NE Function on the right.
3. Set Auto Disabling to Disabled for SDH Optical/Electrical Interface Loopback.
The loopback automatic disabling function for all the PDH electrical interfaces and ATM
IMA groups of the NE2 is set to Disabled.
4. Click Apply.
Step 3 Set inloop for the UNI interface (to be tested) that accesses the tested CES service on NE2 by
using the U2000.
1. On the Main Topology, select and right-click the NE2 NE. In the shortcut menu, choose
NE Explorer to display the NE Explorer window.
2. In the NE Explorer window, select the NE, and choose Configuration > Interface
Management > PDH Interface from the Function Tree.
3. Select the Advanced Attributes tab and then select the interface accessing the tested CES
service.
4. Right-click the Loopback Mode field of the interface, and then select Inloop from the
shortcut menu.
5. Click Apply.
Step 4 Set the SDH analyzer for sending the 2M TDM signals. Perform the 24-hour bit error test.
NOTE
In this case, set the coding to HDB3 and pseudo-random binary sequence (PRBS) to 215-1 for the transmitted
signals of the meter.
If the encapsulation type of the CES service is CESoPSN (that is, structure-aware emulation), you need to
set parameters on the SDH analyzer to make the analyzer transmit structured 2M TDM signals.
Step 5 Observe the SDH analyzer to Check whether the CES service has any bit errors in the 24-hour
period.
l If the CES service has bit errors, go to Step 6.
l If the CES service has no bit errors, go to Step 8.
NOTE
If bit errors are detected during the test of the cascaded CES services, localize the fault to a specific CES service
by using the binary search algorithm.
Step 6 In the case of any abnormal alarm about the CES service, handle the fault with reference to
"Alarm" and "Troubleshooting" in the OptiX RTN 910 Radio Transmission System Maintenance
Guide.
Step 7 Repeat Step 4 - Step 5 to perform the 24-hour bit error test again.
Step 8 Release the inloop of the 2M interface on the NE2 with reference to Step 3.
Step 9 Recover the cable connection of the interface that accesses the tested CES service on NE1.
Step 10 Follow Step 1 - Step 9 to test the CES service on all the other 2M interfaces on the NE1 and
NE2.
Step 11 Set Automatic Disabling to Enabled for Optical/Electrical Interface Loopback on NE2 with
reference to Step 2.
Step 12 Test the connectivity of the CES services on all the other NEs with reference to Step 1 - Step
11.
----End
Prerequisite
l An MPLS tunnel protection group must be created.
l You must be an NM user with "NE operator" authority or higher.
Context
1:1 protection
Normally, services are transmitted over the working tunnel. That is, the services are singly fed
and received. When the working tunnel is faulty, the equipment at the two ends negotiates
through the APS protocol. Then, the transmit end transmits the services over the protection tunnel
and the receive end receives the services from the protection tunnel. In this manner, the services
are switched.
Procedure
Step 1 Check the switching status of the 1:1 MPLS tunnel protection group.
1. On the Main Topology of the U2000, right-click the source NE of the tunnels under test.
Choose NE Explorer from the shortcut menu to display the NE Explorer window.
2. In the Function Tree of NE Explorer, choose Configuration > APS Protection
Management.
3. Click the Protection Group tab, right-click the protection group under test, and choose
Query Switching Status from the shortcut menu to refresh the status of the MPLS tunnel
protection group configured on the NE.
4. Select the MPLS tunnel protection group under test and check the switching status of the
MPLS tunnel protection group. Normally, the status of the protection group is Normal.
l Forced switching: The forced switching is of the highest priority. The switching is performed,
regardless of whether the protection tunnel is in the normal state.
l Manual switching: The switching is performed only when the protection tunnel is in the normal
state.
Step 3 Right-click the protection group under test and choose Query Switching Status from the
shortcut menu. Check Switching Status of the protection group, which should be in Forced
Switching state normally. Then, query Active Tunnel of the protection group. After a normal
switching, Working matches Standby and Protection matches Active.
NOTE
l If Forced Switching is performed at the previous step, the state of the protection group should be
Forced Switching.
l If Manual Switching to Protection is performed at the previous step, the state of the protection group
should be Manual (Working to Protection) Switching.
Step 4 Right-click the protection group under test and choose Clear from the shortcut menu to revert
the services to the working tunnel.
----End
Prerequisite
l You must be an NM user with "NE operator" authority or higher.
l LMSP protection must be correctly configured.
Procedure
Step 1 Check the switching status of the LMSP protection group under test.
1. On the Main Topology of the U2000, right-click the NE configured with LMSP. Choose
NE Explorer from the shortcut menu to display the NE Explorer window.
2. In the Function Tree of NE Explorer, choose Configuration > Linear MS.
3. Click Query and choose Query Protection Group from the shortcut menu to refresh the
configuration of protection groups on the NE.
4. Click Query and choose Query Switching Status from the shortcut menu. Then, check
West Switching Status of the working and protection units in the protection group under
test. West Switching Status of both units should be Normal.
Step 2 Disable the working port of the LMSP protection group under test.
1. In NE Explorer, select the board configured with the LMSP protection and choose
Configuration > Interface Management > SDH Interface from the Function Tree.
2. On the General Attributes tab, select the working port in the LMSP protection group and
set Laser Interface Enabling Status to Close.
Step 3 Check the switching status. If West Switching Status of either the working unit or protection
unit is Switching, it indicates a successful switching.
Step 4 Disable the working port of the LMSP protection group under test with reference to Step 2.
Step 5 Revert the services to the working tunnel of the LMSP protection group.
l If Revertive Mode of the LMSP protection group is set to Revertive, the services are
reverted to the working tunnel when WTR expires.
l If Revertive Mode of the LMSP protection group is set to Non-Revertive, select the
protection group and click the Inter-Board Mapping Relation tab, right-click Protection
Unit in Protection Unit, and choose Manual Switching to Working from the shortcut
menu.
----End
A Glossary
Attenuator A passive component that attenuates the optical power of optical signals.
Backplane A PCB circuit board in the cabinet, which is connected with all the boards
in position.
Binding strap The binding strap is 12.7 mm wide, with one hook side (made of
transparent polypropylene material) and one mat side (made of black
nylon material).
Bit Error An error to some bits in the digital code stream after receiving, generation.
Bit errors accompany the damage to the transmitted information.
Cabling hole A hole which is used for cable routing in the cabinet.
Captive nut A nut in the cabinet, which is used to fix the chassis and can be floating.
Connecting plate A metallic or plastic plate which is used to combine two cabinets.
for combining
cabinets
Diamond-shaped A nut which used to fix the cabinet to the cabling rack.
nut
Downward Cables or fibers connect the rack with other equipment from the bottom
cabling of the cabinet.
Ejector lever A component at the two ends of the front panel of a board, which is used
for inserting or removing the board.
ESD jack Electrostatic discharge jack. A hole in the cabinet or chassis, which
connect the chassis or cabinet to the insertion of ESD wrist strap.
Fault A failure to implement the function while the specified operations are
performed. A fault does not involve the failure caused by preventive
maintenance, insufficiency of external resources and intentional settings.
Fiber connector A device mounted on the end of a fiber-optic cable, light source, receiver,
or housing that mates to a similar device to couple light into and out of
optical fibers. A connector joins two fiber ends, or one fiber end and a
light source or detector.
Fiber jumper The fiber which is used to connect the classis with the ODF.
FEC Forward Error Correction. A bit error correction technology that adds to
the payload at the transmit end the correction information based on which
the bit errors generated during transmission are corrected at the receive
end.
Guide rail A groove in the chassis, which ensures the correct connection of a board
to the backplane.
Layout marking A rectangular paper plate with four holes, which is used to locate the
plate cabinet.
Laser The device that generates the directional light covering a narrow range of
wavelengths. Laser light is more coherent than ordinary light.
Semiconductor diode lasers are the used light source in fiber-optic system.
Main Topology A basic component of man-machine interface for the U2000. The main
topology displays the networking details and the basic information about
NEs, alarms of subnets, communication status.
Mean launched The average power of a pseudo-random data sequence coupled into the
power fiber by the transmitter.
Mounting ear A component on the side of a chassis, which is used to install the chassis
in a cabinet.
N63E cabinet A cabinet which is 600 mm in width and 300 mm in depth, compliant with
the standards of the ETSI.
NE explorer NE Explorer is the main operation interface of the U2000. For easy
navigation, the NE Explorer window presents an expandable directory
tree (Function Tree) in the lower left pane. The configuration,
management and maintenance of the equipment are accessed here.
Packing case A case which is used for packing the board or chassis.
PGND cable Protection grounding cable. A cable which connects the equipment and
the protection grounding bar. Usually, one half of the cable is yellow;
while the other half is green.
Shockproof Fix a cabinet to the cabling rack or the top of the equipment room for
reinforcement reinforcement.
Side trough The trough on the side of the cable rack, which is used to place nuts so as
to fix the cabinet.
Signal cable The cable which is used to transmit electrical signals, different from the
power cable or fiber.
Slide rail A component in the cabinet, which is used to place the chassis.
Subnet mask Also referred to as the network mask off code. It is used to define network
segments, so that only the computers in the same network segment can
communicate with one another, thus suppressing broadcast storm
between different network segments.
Support The frame on the bottom of a cabinet, when installing the cabinet on the
antistatic floor.
T63 cabinet A cabinet which is 600 mm in width and 300 mm in depth, compliant with
the standards of the ETSI.
Upper chassis The chassis close to the top of the cabinet when a cabinet contains several
chassis.
Upward cabling Cables or fibers connect the rack with other equipment from the top of
the cabinet.
Winding pipe A tool for fiber routing, which acts as the corrugated pipe.
Wire-binding bar A metallic bar in the cabinet, used for binding cables.
B Abbreviations
CC Connectivity Check
PW pseudo wire