Beruflich Dokumente
Kultur Dokumente
costain.com
LNG plants may provide potential for decarbonisation
via carbon capture and storage implementation.
Jorge Arizmendi-Sanchez, Ben Eastwood, Costain,
along with Jasmin Kemper, IEA-GHG, explain.
A
s a key contributor to global energy supply, the LNG supply chain is
expected to be subject to global environmental requirements for the
reduction of greenhouse gas emissions. LNG liquefaction plants
produce a significant proportion of the total CO2 emissions of the
LNG supply chain.
Representative power requirements of a typical baseload liquefaction
plant, with a nominal capacity of 5 million tpy of LNG, are of the order of
230 MW (~185 MW for mechanical drive, ~45 MW for power generation). The
required capacity of the CO2 capture plant would be of the order of 3000 tpd
of CO2, equivalent to approximately 1 million tpy of CO2. This is comparable
to existing full-scale capture plants where post-combustion carbon capture
and storage (CCS) projects have been implemented, so a similar plant size and
associated investment could be anticipated. This shows that LNG plants may
provide an opportunity for potential decarbonisation via CCS
implementation.
CO2 sources and emissions CO2 is potentially limited to compression and
The gas turbines driving the refrigerant cycle purification (mainly dehydration) of the low-pressure
compressors and in power generation service are CO2 that is otherwise vented. This assumes a low
typically the major emmiters of CO2. Based on the proportion of H2S and sulfur compounds. Otherwise,
typical range of baseload liquefaction specific power of the acid gas stream from the AGRU may need to
0.3 – 0.4 kWh/kg and the performance of gas turbine undergo incineration, resulting in high levels of oxygen
drives, CO2 emissions for LNG plants are typically and SO2 and requiring additional processing to purify
0.2 – 0.28 t of CO2/t of LNG for industrial heavy-duty the residual CO2 stream.
gas turbines. The emissions can be reduced by Reservoir gas fed to liquefaction terminals typically
approximately 25% if aeroderivative gas turbines are contains around 2 mol% of CO2. Higher CO2 content in
used. feed gas will result in substantially larger volumes of
CO2 is separated from the feed gas in an acid gas CO2 being vented, providing a good basis upon which a
removal unit (AGRU) to avoid solidification in the case for CCS implementation can be built.
liquefaction process. Infrastructure for sequestration of Combined emissions are in the approximate range of
0.3 – 0.4 t of CO2/t of LNG for typical
Table 1. Economic evaluation summary plants with relatively low CO2 content in
feed gas (<2 mol%) and up to approximately
2 mol% CO2 in 14 mol% CO2
feed gas in feed gas 0.7 t of CO2/t of LNG for plants with a
high CO2 content (14 mol%, representative)
From AGRU 0.27 1.86
in feed gas (Figure 1).
From fuel gas combustion 1.09 1.09
Total LNG plant 1.35 2.95 CO2 capture routes and
CO2 emissions Associated to capture 0.18 0.18 technology
(million tpy) plant Based on the nature of the LNG industry,
Captured and stored 1.24 2.84 only well-proven technologies are
expected to be considered for CO2 capture
Emitted1 0.29 0.29
in LNG plants, with schemes that minimise
Avoided 1.06 2.66
risk of disruption to LNG production.
Capital cost2 €755 million €872 million Post-combustion capture is considered
CO2 capture
from AGRU and Operating cost3, 4 €567 million €783 million
to provide comparable performance to
post‑combustion other routes (i.e. oxyfuel and
Specific capture cost €42.5/t of CO2 €23.3/t of CO2 pre-combustion), with reduced technical
Capital cost2 €30 million €144 million risk and process complexity.
CO2 capture Operating cost3, 4 Post-combustion capture can be installed
from AGRU only €68 million €384 million
without affecting the availability of the
Specific capture cost €14.7/t of CO2 €11.3/t of CO2 liquefaction process. This route requires a
Notes: minimum number of modifications to the
1 CO emission costs excluded in this estimate.
2 liquefaction plant – mainly consisting of
2 Engineering, equipment, bulk materials, construction, contingency, fees, interest,
the installation of tie-ins, and potentially
capital spares, chemicals, start-up costs, owner’s costs.
3 Lifetime costs (25 years) including insurance, taxes and fees, operation and the installation of additional waste heat
maintenance, power, steam, chemicals, waste disposal, CO2 transport and storage. recovery (WHR) on gas turbine exhausts
4 Assumed gas price is €6/GJ and discount rate of 8%. For other assumptions, refer – hence reducing risk. This makes
to IEA-GHG study reference IEA/CON/16/235. post‑combustion capture appropriate for
new LNG plants or as a retrofit to existing
plants.
The technologies with the highest
potential for immediate implementation
are chemical absorption processes. These
are proven technologies, with the main
disadvantage being the energy
requirements to regenerate the solvent.
However, the heating duty could be
provided by WHR, which should be
available in excess in an LNG plant.
Perceived operational challenges, such as
solvent degradation, solvent volatility and
losses, corrosion, etc., can be managed
within acceptable limits using solvent
Figure 1. Representative CO2 emissions from an LNG liquefaction plant. formulations that are commercially
available.