Beruflich Dokumente
Kultur Dokumente
Email: ndaetwyler@environcorp.com
Abstract: Cable system projects financed by external parties rather than the project
shareholders are likely to be subject to the social and environmental standards of one or more
of the International Financial Institutions involved, such as multilateral development banks,
commercial banks, and export credit agencies. The SEACOM cable system connects South
Africa with India and Europe via landings in Mozambique, Tanzania, Kenya, Djibouti, India
and Egypt, is privately-owned, and is funded in part by project finance arranged through
commercial banks. As a result the project is subject to the Equator Principles, the pre-eminent
financial industry benchmark for determining, assessing and managing social and
environmental risk in project financing. Equator Principles compliance requires conformance
with a range of international standards in addition to the environmental clearance
requirements of the project host countries, as the Principles do not supplant national social
and environmental requirements but rather supplement them. The SEACOM project has
successfully applied the Principles in parallel to the varying requirements of the landing
countries, including challenging circumstances such as landing the cable in a Nature Reserve
(in South Africa) and adjacent to a UNESCO World Heritage Site (in Kenya).
1. INTRODUCTION
The Equator Principles do not supplant
The Equator Principles represent a
national social and environmental
financial industry benchmark for
requirements, but rather supplement them.
determining, assessing and managing
The Principles are based on an external and
social & environmental risk in project
respected benchmark, namely key elements
financing. More than 60 International
of the Environmental and Social Review
Financial Institutions (IFIs) are now listed
Procedures of the International Finance
on the EP website [1] as having adopted
Corporation (IFC), the private-sector
the Principles, including most of the
lending arm of the World Bank Group.
industry’s major project finance providers.
In 2008, it was estimated that Equator
The Equator Principles (EP) were first
Principles Financial Institutions (EPFIs)
adopted in 2003 and were subsequently
covered more than 85 percent of the
revised in 2006 to accommodate
world’s project finance activity [2].
substantial changes in the IFC Review
Procedures. It is the ten current Equator
While many cable system projects continue
Principles and the key elements of the
to be financed through the internal
current IFC Environmental and Social
resources of the project partners, there is a
Review Procedures that are referenced in
trend for projects to look to external
this paper that describes how these
financing, meaning that the Equator
principles were applied to the SEACOM
Principles are likely to be applied to cable
system projects more and more frequently.
projects such as submarine cable systems As is often the case for major Equator
are the Export Credit Agencies (ECAs). Principles projects, the EPFI required that
ECAs are public agencies and entities that SEACOM retain an environmental
provide government-backed loans, consultant to advise on the application of
guarantees and insurance. The major ECAs the Equator Principles. ENVIRON was
are those of the member states of the retained in this role, and an early task was
Organisation for Economic Cooperation to recommend to the EPFI the appropriate
and Development, which have agreed a set Equator Principles classification for the
of common approaches for evaluating the SEACOM project.
environmental impacts of the projects they
support. This framework [6] relies on a Project Categorisation
project categorisation process consistent ENVIRON was at this time working
with that of the IFC Environmental and closely with SEACOM and its principal
Social Review Procedure (and therefore advisor The David Ross Group in planning
with the Equator Principles), and also and securing the necessary environmental
references the environmental standards and approvals in the project landfall countries.
guidelines of the World Bank Group, the In several of these countries it was made
EBRD, the ADB, the AfDB and the IDB. clear by national regulators that any
projects impacting the socially and
environmentally sensitive coastal zone
4. APPLICATION OF THE would automatically be assessed as
EQUATOR PRINCIPLES TO THE projects of the highest sensitivity,
SEACOM CABLE SYSTEM regardless of whether the project itself is
PROJECT relatively benign (as is generally the case
for submarine cable systems). However,
The SEACOM cable system connects
the careful selection of the cable route and
South Africa with India and Europe via
siting of the landfalls and cable stations,
landings in Mozambique, Tanzania,
especially in two areas of particular
Kenya, Djibouti, India and Egypt (see
sensitivity in South Africa and Kenya,
Figure 1). The system is privately-owned,
resulted in the project team concluding that
and is funded in part by project finance
an Equator Principles classification of ‘B’
arranged through commercial banks,
rather than ‘A’ was appropriate. This
including an EPFI.
conclusion was supported by detailed
knowledge of the comprehensive
management and mitigation measures that
are habitually applied by the international
cable system industry. These measures
were, of course, adopted for the SEACOM
project. The recommendation for ‘B’
categorisation was subsequently accepted
by the project’s EPFI.
regulators were fully met, the project (those areas beyond the Territorial
environmental clearances in the various Waters or the EEZ of the landing
landing countries were developed with the countries) are not included in any national
assistance of locally-based specialist social and environmental assessment. As
environmental consultants. the Equator Principles require that the
project as a whole be assessed, for the
The scale and scope of the documentation SEACOM project this shortfall was
required to support these clearances varied addressed through the development of an
greatly from country to country. In India overarching system-level EIA (“EP EIA”),
and Djibouti the co-location of the in parallel with the national
SEACOM system with other cable systems documentation. The EP EIA was
for which permits and landing facilities subsequently disclosed to project
were already in place meant that stakeholders via the SEACOM website [7].
documentation requirements were
minimal. Conversely, in South Africa the In addition to the Equator Principles
formal assessment process lasted for requirement for an acceptable level of
almost 12 months, involving various public social and environmental assessment (or
consultations and the development of four EIA) there are also a number of other
sets of publicly disclosed documentation significant requirements made of the
comprising more than 1,400 pages in all. project developer.
Examples of the environmental clearance
documentation are shown in figure 2. Social and Environmental Management
System and Equator Principles Action
Plan
In accordance with EP4, the SEACOM
project was required to produce an Equator
Principles Action Plan and a Social and
Environmental Management System
(SEMS) for the project. Action Plans may
range from a brief description of routine
mitigation measures to a series of
documents (e.g. resettlement action plan,
indigenous peoples plan, emergency
preparedness and response plan,
decommissioning plan, etc), with the level
of detail and complexity being
commensurate with the project’s potential
impacts and risks. The SEACOM SEMS
was required to be consistent with IFC
Performance Standard 1, and therefore
incorporated the following elements: (i)
Figure 2 Examples of EIA documentation for the Social and Environmental Assessment; (ii)
SEACOM project management program; (iii) organisational
capacity; (iv) training; (v) community
Equator Principles EIA engagement; (vi) monitoring; and (vii)
The national regulators in the landfall reporting. As the need for a SEACOM
countries focus, of course, only on the Action Plan had been identified at an early
project within their area of jurisdiction. stage it was developed as an integral part
However, by the very nature of a major of the EP EIA, and included the many
submarine cable system large parts of the
below the Umlalazi Nature Reserve Figure 4 Fort Jesus, Mombasa, Kenya – a
(Figure 3), over a distance of almost 1km UNESCO World Heritage Site
from the Cable Station to the beach
manhole.
Figure 3 Horizontal Direction Drilling of the Figure 5 Existing cables close to the SEACOM
SEACOM cable below the Umlalazi Nature landfall site in Mombasa, Kenya
Reserve, South Africa
Kenya
In the case of Kenya, the SEACOM cable
comes ashore in Mombasa immediately
adjacent to the 16th century Fort Jesus
UNESCO World Heritage Site (Figure 4).
Several other cables land in this same area
(Figure 5), with the SEACOM landing and
cable station sites being located on the
property of the Swahili Cultural Centres
Figure 6 Reinstatement of the terrestrial cable
(SCC), itself a socially sensitive location route, Swahili Cultural Centres, SEACOM
(but not a World Heritage Site). SEACOM landfall in Mombasa, Kenya
was able to conclude an agreement with
the SCC that has resulted in a cable 6. CONCLUSIONS
landing site that has been carefully
constructed and reinstated (Figure 6). The When sub-sea cable system projects are
cable station itself was sited in consultation financed by external parties (i.e. other than
with the SCC authorities, and considerable the project shareholders), various
effort has been made to render the finished International Financial Institutions may
cable station compatible with its historic become involved, including multilateral
surroundings by constructing an development banks, commercial banks,
architectural façade to the core pre- and export credit agencies. For the
fabricated cable station structure. SEACOM project, as a result of the
Construction of the façade is nearing involvement of commercial banks in
completion. project financing, the project became
subject to the Equator Principles, which
since their establishment in 2003 have
become the pre-eminent financial industry
benchmark for determining, assessing and
managing social and environmental risk in
project financing.