Sie sind auf Seite 1von 4

Vacuum Breaker Simulation for Switching

Overvoltage Study
Daniil I. Ivanchenko and Nikita G. Novozhylov

Abstract—Overvoltage is one of the most common types of


electrical interferences in power supply systems. Significant
part of overvoltages is caused by switching off the high induc-
tive load, such as transformers, reactors and electrical ma-
chines. This paper is dedicated to vacuum circuit breakers
switching off process modeling in Simulink MATLAB for the
purpose of power quality problems estimation. Model of the
vacuum circuit breaker implements simulation of transient
recovery voltage, current chopping and electrical arc. Devel-
oped model was used for simulation of overvoltage on example
of mine electric power system. Obtained results were compared
to available experimental data.

Index Terms—Vacuum circuit breaker, electrical arc, over-


voltage, transient voltage recovery.

I. INTRODUCTION
Vacuum circuit breaker switching off overvoltage is one
of the most common reasons of overvoltages in electric Fig. 1. Diagram of mine power supple sustem.
power supply systems. These kinds of overvoltages are
caused by switching off the high inductive or capacitive have phase-controlled switching and prone to overvoltages
load, such as transformers, reactors and electrical machines. due to current chopping.
Those overvoltages are especially relevant for ungrounded In order to address possible electric power quality
neutral systems without phase-controlled switching which problems caused by breaker switching off, estimation of
are typical for mine power supply systems. possible overvoltage is required. Experimental analysis of
Problem of overvoltage is especially critical for under- this process is difficult to establish, so the most applicable
ground coal mine electric power supply systems. Over- way to solve this problem is by means of mathematical
voltage causes the degradation of insulation, which is fol- modeling circuit breaker operation. Developed model must
lowed by electric faults and in worst case by fire and represent main processes during the breaker switching off,
explosion of methane or coal dust. Underground power such as arc ignition, existence of chopping current electric
supply systems are usually ungrounded and have long arc and arc re-ignition in case then circuit breaker is unable
6–10 kV cable lines supplying clustered electric drives to withstand the transient recovery voltage.
connected. Power consumption of underground excavation There are model of vacuum breakers [2], [3] in
site may exceed 3–5 MVA [1]. EMPT/ATP environment, but there is no similar works for
Main consumers are electric drives of conveyor lines, Simulink MATLAB. Authors of papers [4], [5] provided
coal plough-machine, ventilators and pumps. Simplified simulation of transient recovery voltage of vacuum
structure of mine section electric power supply is repre- breakers, but did not simulate electric arc. Also, available
sented in Fig. 1. Mine is supplied by 100 kV aerial line. simulations of electric arc in Simulink MATLAB [6]–[8]
Energy is distributed from main transformer station are based on controlled current source model and are not
110/6 kV to surfaced and underground facilities. Under- applicable for breaker modeling. This paper represents an
ground consumers are supplied by two cable lines through attempt to simulate all vacuum circuit breaker switching off
mine section transformers rated 6/0.6 kV. Mine section processes for the purpose of power quality estimation.
transformer station № 1 supplies three asynchronous drives
of conveyor rated 500 kW each, cutting-loading machine II. VACUUM BREAKER MODELING
rated 536 kW and pumping station rated 1000 kW. There Modeling the vacuum breaker switching off is
are two vacuum circuit breakers QF at the beginning and the complicated by difficulty of physical processes and their
end of line. Vacuum circuit breakers are used because of mathematical description. In order to represent them in
their reliability and fire-explosions safety, but usually do not SimPowerSystem Simulink MATLAB two models were
made: one-phase vacuum circuit breaker model simulates
D. I. Ivanchenko and N. G. Novozhylov are with the Electrical dynamic arc current-voltage characteristic; breaker control
Engineering department, National state mineral resources university model simulates transient voltage recovery and chopping
(University of Mines), 21st line 2, 199106 St.Petersburg, Russia (e-mail:
dan87332@mail.ru, nikita_novozhilov@mail.ru).
current.

978-1-5090-1564-1/16/$31.00 ©2016 IEEE


A. Transient Voltage Recovery Simulation by variable initial gap Lo between contacts. Electric strength
After physical separation of breaker’s contacts the electric of the gap between contacts was considered 50 MV/mm,
arc is ignited. Arc exists until current drops to the chopping chopping current was considered 5 A.
current value Ic. It varies from 3 A to 15 A depending on a B. Electric Arc Simulation
contact surface material and is approximately 2÷5 A for
As the one of the main processes during the breaker
Cu-Cr contacts [4]. After arc extinguishing the recovery
switching off is an occurrence of electric arc between the
voltage Ur is formed between the contacts of the breaker:
main contactors, it also was simulated.
Ur = U g − Ul , (1) There are different approaches for electric arc modeling.
Thermodynamic based models of arc were proposed by
where Ug – electric grid voltage, Ul – load voltage. various authors such as Mayer, Cassie, Schwarz, Schave-
Load voltage Ul depends on energy that is stored in maker, Habedank and many over [6]–[8].
inductive load in switched off part of circuit, can be All models implement arc with non-linear electric
calculated according to formula: conductance, where momentary arc conductance is a func-
L0 I c2 , tion of power, supplied through the arc plasma channel, but
W= (2) are based on different concepts of arc column. As Mayer
2
model is best applied for a low current arc and conductivity
where L0 – inductance of switched off part of circuit, decay near current zero, it was considered as more suitable
Ic – chopping current. for vacuum circuit breaker simulation case.
Stored energy is transferred from inductance L0 to Simulation is based on the generalized model of the pro-
capacitance C0 and back causing the oscillations with cess in electrical arc, described in static with equation [9]:
frequency fo:
U arc st (iθ )
1 . (3) u arc = Rst (iθ )i + U c = i + Uc , (5)
fo = iθ
2π L0C0
where uarc – arc column voltage, i – arc column current, iθ –
Maximum overvoltage corresponds with peak value Up of arc state current, Rst – static arc column resistance, Uarc st (iθ)
oscillating load voltage Ul. It can be calculated as: – static arc current-voltage characteristic, Uc – voltage drop
L0 I c2 . at contactors.
Up = (4) For low current arc voltage loss at contacts can be
C0 neglected and current-voltage characteristic can generally
If recovery voltage exceeds discharge voltage between approximated for static process as follows:
contacts of breaker, electric arc will re-ignite and the n
i 
process will be repeated multiple times. The recovery U arc (iθ ) = U 0  θ  , (6)
voltage increase in accordance with contacts movement  I0 
speed and availability of electrical charge in arc extinguish-
where U0, I0 – are reference points of static arc current-
ing chamber [9].
voltage characteristic, n – parameter based on the type of an
This process was modeled in Simulink Matlab as a
arc characteristic.
breaker state control subsystem represented in Fig. 2. It is
For the case of static arc with characteristic (6) for Mayer
activated for closing operation when Breaker control
arc model the arc conductance is assumed to vary with a
singular signal is recieved and formulates Arc control signal
passage of time around current-zero, in accordance with
in accordance with measured recovery voltage, breaker
current and previous state of breaker. Breaker state control 1 dg  u arc i  1 , (7)
subsystem generates singular Arc control signal for two = − 1
g dt  P τ
cases. First is then recovery voltage is higher than discharge
voltage. Second is then recovery voltage is lower than where τ – Mayer arc time constant, P – arc power losses,
discharge voltage, but arc current is higher than chopping g – momentary conductivity of arc.
current. Otherwise this signal is equal to 0. Results of analytical calculation of (7) with assumption of
di/dt being constant when arc current is equal to zero are as
follows [9].
Momentary arc column voltage:
P t /τ
uarc = . (8)
τ k (t / τ ) − 2(t / τ ) + 2
2

Dynamical arc column resistance:


P 1
Rdyn = . (9)
τ k (t / τ ) − 2(t / τ ) + 2
22 2

Fig. 2. Circuit breaker state control subsystem. Dynamical arc column resistance when arc current i = 0:
In order to simulate this process several assumptions were P 1
made. It was considered, that contacts movement and Rdyn 0 = . (10)
dielectric strength of gap are constant so discharge voltage
τ k (t / τ ) − 2(t / τ ) + 2
2
2 2

increases linearly. Initial dielectric withstand was modeled


These equations are representing inertial model of electric
arc which makes simulation of the dynamical processes of
breaker switching off with higher precision possible, as it
allows to estimate possible harmonic distortions [10].
In order to simulate breaker with arc ignition in Simulink
SimPowerSystem the model represented in Fig. 3 was
developed in accordance with (7).

Fig. 4. Arc voltage (a) and current (b) simulation result.

Fig. 3. Circuit breaker model with electric arc implementation.

The model is based on controlled voltage source and


represents voltage drop at closed, open and arc conditions of
vacuum breaker. Breaker switch is triggered by Breaker
control signal and turns breaker from closed state to open
state if control signal is 0. Arc switch is triggered by signal
from Arc control subsystem and turns breaker from closed
state to arc state if control signal is 1. Arc inertia is
modelled by means of Transfer Fcn block. In order to avoid
singularity at current zero crossing, viscous friction function
was used.
Results of calculation of arc current and voltage dynamics Fig. 5. Three phase vacuum circuit braker model.
are shown in Fig. 4. Distortion of current, caused by non-
linear arc resistance can be observed. Results of arc simula- lated by means of SimPowerSystems Simulink MATLAB.
tion correspond with experimental data obtained by various Purpose of experiment was to investigate processes in
authors [8], [11]. circuit breaker switching off. Disconnection of mine section
Developed models were integrated into singular three- with belt conveyor shown in Fig. 1 was taken as an example.
phase vacuum circuit breaker model, represented in Fig. 5. Deenergized part of the circuit consists of underground
It consists of three one-phase breakers and breaker control transformer station Tr-r2 with three transformers 6/0.66 kV
subsystems, one per phase. It is activated by Breaker control rated 630 kW each, cable line 0.66 kV L-3, and motors (IM)
signal and provides measurement of recovery voltage Ur and of conveyor electric drive. All other consumers were repre-
breaker current I. sented by equivalent RLC load (Load). Line section is
switched off by vacuum circuit breaker (VB) on command
III. BREAKER SIMULATION RESULTS by breaker control block (BC). Phase currents and circuit
Developed model of vacuum circuit breaker was tested in breaker voltage measurements are presented on oscilloscope
electric circuit of underground mine section (Fig. 6) simu- (Osc.).

Fig. 6. Model of mine power supply system.


Model also includes three-phase power source, aerial line ignition of electric arc with nonlinear current-voltage
110 kV (L-1), and main power transformer 110/6 kV (Tr-r1) characteristic; overvoltages, caused by existence of chop-
and cable line 6 kV (L-2). Capacitance of cable and aerial ping current; electric arc re-ignition in case then circuit
lines was modeled by conductance C1, C2, C3. breaker is unable to withstand the transient recovery
Main parameters in model of power supply system are: voltage.
Power source: Ul–l = 110 kV; f = 50 Hz. Vacuum circuit breaker model was tested for the case of
switching off mine section circuit, including high powered
Areal line 110 kV: R0 = 0.414 Ohm/km; L0 = 9⋅10–4 H/km; conveyor electric drives. Simulation results indicated
C0 = 10–8 F/km; L = 20 km. possibility of overvoltage in mine power supply system,
Main power transformer: 16 MVA, 110/6 kV (Y – D11). and correspond with available experimental data.
Cable line 6 kV: R0 = 0.0845 Ohm/km; L0 = 22⋅10–5 H/km; Developed model could be applied for vacuum circuit
C0 = 8.7⋅10–9 F/km; L = 12 km. breaker switching simulations in order to estimate possible
Underground section transformer: 630 kVA, effect on power quality in power supply systems.
6/0.66 kV (Y – D11).
Cable line 0.66 kV: R0 = 0.0405 Ohm/km; REFERENCES
L0 = 113⋅10–6 H/km; [1] S. Volotkovsky, Y. Razumny, G. Pyvnyak, Power Supply of Coal
Mines. Moscow. Nedra, 1984.
C0 = 8.7⋅10–9 F/km; L = 1.5 km. [2] A. Borghetti, F. Napolitano, C. Nucci, M. Paolone, M. Sultan, and
Induction motors: 4 × Pn = 250 kW, Un = 666 V. N. Tripaldi, "Transient recovery voltages in vacuum circuit breakers
generated by the interruption of inrush currents of large motors,"
Other load: Pn = 6000 kW; Qn = 2764 kvar. Proceedings of International Conference on Power Systems Transi-
At the time 0.4 s breaker control block sends switching ent, (IPST2011) in Delft, Netherlands, Jun. 14–17, 2011.
off signal. Fig. 7 represents oscillograms of breaker voltage [3] P. Navalkar and G. Gajjar, "Modeling of vacuum circuit breaker and
its use for studying medium voltage reactor switching," Proceedings
rated to nominal line voltage 6 kV for vacuum breaker with of Eighth International Conference on Switchgear & Controlgear
phase-controlled switching and without it. (SWICON 2011), Mumbai, India, Nov. 24–25, 2011, pp. 258–262.
[4] T. Kuczek and M. Florkowski, "Vacuum circuit breaker switching in
photovoltaic power plants – overvoltage analyses for various topolo-
gies and network conditions," Zeszyty Naukowe Wydziału Elektro-
techniki i Automatyki PG, no. 36, 2013, pp. 529–551.
[5] G. Chystyakov, E. Glushkin, and N. Zybkov, "Modelling of pulsed
overvoltage caused by vacuum breaker switching off in MATLAB
for electromagnetic environment estimation," Electro, 6, 2012,
pp. 46–50.
[6] L. Yuan, L. Sun, and H. Wu. "Simulation of fault arc using conven-
tional arc models," Energy and Power Engineering, 5, 2013,
рp. 833—837.
[7] N. Marković, S. Bjelić, J. Živanić, and U. Jakšić, "Numerical simula-
tion and analytical model of electrical arc impedance in the transient
processes," Przegląd Elektrotechniczny, R. 89, Nr 2a/2013, 2013,
pp. 529–551.
[8] S. Nitu, С. Nitu, С. Mihalache, Р. Anghelita, and D. Pavelescu, "Com-
parison between model and experiment in studying the electric arc,"
Journal of optoelectronics and advanced materials, vol. 10, 2008,
pp. 1192–1196.
[9] E. Vereshago and V. Kostuchenko, "Electric arc imitational model,"
Electrical engineering, 6, 2014, pp. 36–42.
[10] Y. Varetsky, "Transient overvoltages during filter circuit switching-
off," Proceedings of Modern Electric Power Systems 2010 sympo-
sium, Wroclaw, Poland, 2010, pp. 1–4.
[11] V. Singh, Examination of Electric Arc Behavior in Open Air, Master
thesis, Aalto University, Finland, 2012, 93 p.
[12] W. Sima, M. Zou, Q. Yang, M. Yangand and L. Li, "Field experi-
ments on 10 kV switching shunt capacitor banks using ordinary
Fig. 7. Simulation of voltage on vacuum breaker without controlled and phase-controlled vacuum circuit breakers," Energies, 9, 88, 2016,
switching off (a) and with controlled switching off (b). pp. 1–14.
[13] A. Bazavluk, L. Sarin, G. Mikhailovsky, I. Naumkin, and V. Gogolyk,
As it can be seen in Fig. 7, in case of phase-controlled "Overvoltages caused by vacuum breaker commutations," Energy
switching, overvoltage on circuit breaker exceeds nominal expert, 2, 2011, рp. 27–32.
line voltage 2 times. For the case without phase-controlled
switching, overvoltage are 6 times higher than nominal
voltage. High level of overvoltage is caused by switching of
high power motors with low nominal voltage and requires Ivanchenko Daniil Ivanovich was born in Leningrad, RSFSR, USSR
the usage of surge arresters and other means of limitation. in 1987. He received the M.Sc. degree in electrical engineering from
Results of measurements correspond with experimental data National state mineral resources university in 2010. He received candidate
of science degree in electrical engineering from National state mineral
provided in [12], [13]. resources university in 2013. He works as a Teacher in Energy department
of National state mineral resources university.
IV. CONCLUSION Novozhilov Nikita Gennadievich was born in Kirishi, RSFSR, USSR
This paper presented modeling techniques of vacuum in 1990. He received the M.Sc. degree in electrical engineering from
National state mineral resources university in 2013. He studies as a
circuit breaker in Simulink Matlab. Following processes Postgraduate Student in Energy department of National state mineral
corresponding to the breaker switching off were simulated: resources university.

Das könnte Ihnen auch gefallen