Sie sind auf Seite 1von 1

SECTION:

TATA CONSULTING ENGINEERS LIMITED APPENDIX


TCE.M9-PCS-13
PROCEDURE FOR REVIEW OF DOCUMENTS FROM
SHEET 11 OF 11
VENDOR/CONTRACTOR AND CLIENT/COLLABORATOR
APPENDIX 1
VENDOR DOCUMENT REVIEW STATUS CODES
FORMAT FOR STAMP AND STICKER
TATA CONSULTING ENGINEERS LIMITED
VENDOR DOCUMENT REVIEW STATUS
□ CAT-1 Approved.
□ CAT-2 Approved with Comments. Contractor may proceed with
construction/manufacture taking care of the comments.
Resubmission of Drawings/Documents is required for
for final approval.
CAT-3 Not approved. Resubmit revised drgs/ Docs. Incorporating
comments/ Modifications, as noted, for approval.
CAT-4A Record and Reference with comments (Final copy to
be submitted).
✔ CAT-4B Record and Reference without comments.
Approval conveyed herein neither relieves Vendor/Contractor of his contractual
obligations and his responsibilities for correctness of dimensions, materials of
construction, weights, quantities, design details, assembly fits,
system/performance requirements and conformity of supplies with Indian
statutory Laws as may be applicable, nor does it limit the Purchaser’s rights
under the contract.
Digitally signed by SUBHAYU
MUKHERJEE
DN: cn=SUBHAYU MUKHERJEE,
o=TATA CONSULTING
ENGINEERING LIMITED, ou=CIVIL,
email=smukherjee@tce.co.in, c=IN
Reason: I have reviewed this
document
Location: Kolkata Transmittal No. TCE.5968A-CO-DIL-689
Date: 2011.06.02 16:22:16 +05'30'
Reviewed by: Date: 02-06-2011

Das könnte Ihnen auch gefallen