Sie sind auf Seite 1von 3

AN INVESTIGATION OF LOW VOLTAGE ARC FLASH EXPOSURE

Copyright Material IEEE


Paper No. ESW2013-30

Albert M. Smoak, P.E. Adam J. Keeth


Member, IEEE Southwestern Electric Power Co.
Southwestern Electric Power Co. 101 W. Township St.
428 Travis St. Fayetteville, AR 72703
Shreveport, LA 71101 USA
USA ajkeeth@aep.com
amsmoak@aep.com

Abstract – The distribution utility lineman, servicer, and Theoretically, arc flash energy intensity is a function of the
meter technician play an active role in the operation, arc’s current, voltage, and clearing time [2]. Before a thorough
installation, and maintenance of 120-volt and 240-volt arc hazard analysis can be performed, it is important to
equipment on a daily basis. The arc flash risks faced by utility understand critical information concerning the clearing time of
workers operating equipment energized at 240 V or less were the arc. The primary objective of this experiment was to create
investigated for activities involving meter enclosures, meter actual scenarios allowing opportunities to observe these
installations, meter maintenance, and the connection of characteristics, specifically the clearing time and self
conductors in energized transformers and power pedestals. sustainability of live arcs with different lengths in phase-to-
The investigation led to conclusions regarding the likelihood of ground and phase-to-phase faults on 120-volt and 240-volt
an injury due to an arc flash exposure to utility workers electrical distribution systems.
performing low voltage work. The investigation included tests
conducted at an installation located immediately adjacent to a II. TESTING METHODOLOGY
substation to achieve fault currents near 12,000 amps, more
than which is typically expected for the daily activities The intent of this investigation was to create and observe faults
performed by utility linemen on voltages 240 Volts and below. It and electric arcs while simulating typical low voltage work
was concluded that the low voltage arc flash energy level to activities, specifically, while working in an energized power
which these workers are exposed is very low. The pedestal and meter socket. A small electrical distribution
methodology and results will be explained. system was constructed adjacent to a distribution substation for
the tests, and the major components of the system included a
Index Terms — Arc hazard analysis, low voltage arc flash, 7.2kV/240-120V transformer, a secondary power pedestal, and
arc sustainability, utility worker. a meter socket equipped with a bypass handle. The faults and
resulting arcs were created by connecting test apparatuses in
I. INTRODUCTION the power pedestal to act as electrodes, and then energizing
the system by closing the 7200 V riser fuse. The test
Utility linemen work in a specialized field where they are apparatuses used as electrodes to create arc gaps were
exposed to many potential hazards to provide their service and constructed of large 600-volt URD cable and 2-hole terminal
deliver a product that has become a necessity in today’s lugs. An insulating material was used between pairs of
society. Linemen are trained to use specialized tools, skills, terminals, which were connected with non-conductive nylon
and techniques to safely mitigate many of these potential bolts, to create precisely measured air gaps to regulate the
hazards. Article 410 in the Work Rules section of the National length of the arcs during the experiments. Teaser filaments
Electric Safety Code assigns employers the responsibility of were placed between the terminals to trigger the fault since a
assessing arc flash exposure hazards associated with the 120-volt arc is not capable of overcoming the dielectric strength
different systems on which employees work, and the of air within the gap widths considered in this experiment.
responsibility of requiring employees to wear a clothing system During the first series of tests, using a 50-kVA transformer, the
that protects against those anticipated hazards [1]. Another investigation began with a bolted 120-volt fault, and then
dangerous hazard faced by utility linemen is heat exhaustion, repeated the process with five air gap widths ranging from 1/24
so it too must be considered with arc flash hazards when of one inch (1.1mm) to 1 inch (25.4mm). The first series
determining an appropriate clothing system. concluded with two 240-volt tests, one of which was conducted
Electrical distribution systems range in voltages from 50 volts in the power pedestal, and the other in the meter socket.
up to 35 kilovolts. The majority of a utility lineman’s low voltage Results are shown in Table I. A second series of tests followed,
work is on 120 V, 208 V, and 240 V systems. Typical duties using a larger transformer to allow even more fault current.
associated with these systems include working in meter Instrumentation was reconfigured to also record arc gap voltage
sockets, installing and removing meters, checking voltage, and for each test. These results are shown in Table II. Thirteen
connecting secondary conductors in power pedestals, tests were conducted in total, nine of which used precisely
enclosures, and secondary compartments of transformers. measured air gaps between electrodes to create known arc
There are arc flash exposure hazards associated with these lengths during the fault conditions. Two tests were bolted fault
distribution systems energized below 300 V. conditions, and two scenarios were nearly-bolted scenarios,

978-1-4673-3039-8/13/$31.00 ©2013 IEEE


TABLE I
Arc Fault Data with 50kVA Transformer

Fig.1. Voltage waveform of a phase-to-ground fault with 1/24-


inch (1.1mm) controlled arc length (peak values shown).
TABLE II
Arc Fault Data with 167kVA Transformer arc flash exposure hazards and calculating incident energy
from the arc to which linemen and other electrical workers could
be exposed on low voltage systems.

B. Hazard Analysis

The intent of this investigation was to evaluate the arc flash


exposure hazard of 120-volt and 240-volt systems for utility
linemen in normal working conditions. Knowing incident energy
resulting from the arc is a desired result in an arc hazard
analysis [3], and industry has developed several methods for
calculating incident energy for higher voltage classes and
whereby the bypass handles were used in meter sockets to higher fault current values. However, these accepted methods
close in on 240-volt phase-to-phase fault conditions. all have constraints and limits of application that prevent them
from being applied to the scenarios observed and data taken in
III. DATA ANALYSIS this investigation. For example, the “Arc in Open Air” formula,
commonly referred to as the NFPA 70E method, is only to be
A. Observed Characteristics used for short-circuit current greater than 16kA [4]. IEEE 1584,
another widely accepted method for calculating incident energy,
The data taken from these tests provided useful information is constrained by constants derived from measured data, and is
pertaining to the characteristics of the arcs created in the open- only to be used for voltages above 0.208kV, with arc gaps
air fault conditions. The test site’s layout and close proximity to equal to or greater than 13mm [3]. Nevertheless, application of
the distribution substation provided a substantial amount of fault these two methods with this investigation’s data, using IEEE
current, higher than that commonly found at 120-240 volts on 1584 for Test 7 from Table I, and NFPA 70E for Test 2 in Table
2
the electric distribution system. Despite this level of available II, yields calculated incident energy levels of less than 1 cal/cm
fault current, as well as the short air gaps considered, the data at a radial distance of 18 inches from the arc. The incident
show that the tests produced arcs that were unable to sustain energy, and therefore the hazard, is greatly minimized by the
themselves long enough to trigger upstream fuse protection. fact that the arc is not able to sustain itself and self-extinguishes
The longest arc duration observed, with an electrode separation in one half of a cycle.
of 1/24-inch (1.1mm), lasted only 0.6 cycles (9.44ms). Fig. 1
illustrates the voltage waveform of the 120-volt rms arc with a IV. CONCLUSION
1/24-inch (1.1mm) length during Test 2 of Table II. The graph
illustrates the arc being initiated and self-extinguishing in 0.4 The safety culture in the electric utility industry is evolving at
cycles (7.23ms). In Test 7 of Table I, the 240-volt, phase-to- an accelerated pace due to advancements in technology and
phase fault with an arc length of 1/8 of one inch (3.2mm) also the desire for every worker to go home safe every day. This
self-extinguished with a duration of less than half of one cycle. series of tests was conducted as part of a safety initiative, to
All nine arcs created in the air gaps, and even one of the nearly ensure that utility linemen and other electrical workers are
bolted fault conditions in the meter socket, self-extinguished in protected at lower voltages. This investigation demonstrated
half of one cycle or less. conclusively that 120-volt and 240-volt arcs are not able to
Overall, data taken during the investigation showed that both sustain themselves and self extinguish very quickly in a utility
120-volt and 240-volt arcs are not self-sustainable for more lineman’s normal low-voltage working environment, greatly
than half a cycle when they are initiated within short air gap minimizing the resulting incident energy and its effect on the
widths in open air. This information is useful when evaluating worker.
V. ACKNOWLEDGEMENT VII. VITA

The authors wish to acknowledge the team of coworkers and Albert M. (Malcolm) Smoak is Vice President, Distribution
colleagues for their contributions to this study, which would not Region Operations for Southwestern Electric Power Company
have been possible without their assistance. The assistance (SWEPCO), a subsidiary of American Electric Power. Smoak
provided by Christopher R. Gray, P.E, Tom Russell, Mark Rath, holds a BSEE from Louisiana Tech University, and is a
and Henry Brown of Southwestern Electric Power Company, registered professional engineer in the State of Louisiana.
and Wayne P. Blackley, P.E., of Associated Training Corp., is His responsibilities include engineering and operations of
greatly appreciated. SWEPCO's distribution system, serving 523,000 customers in
Arkansas, Texas, and Louisiana. During his career, he has
VI. REFERENCES been devoted to improving the safety and working conditions of
SWEPCO employees. He represents NSPE on the NESC
[1] IEEE, National Electrical Safety Code, 2012 Edition, New Subcommittee 8. Smoak is a member IEEE and former
York, NY: IEEE. president of the IEEE Shreveport Chapter. He began his 28
[2] Neal, et al., “Protective Clothing Guidelines for Electric year career in the utility industry as a distribution engineer in
Arc Exposure,” IEEE Transactions on Industry Shreveport, Louisiana, and has served in various management
Applications, vol 33-4, pp 1042-1043, Jul/Aug 1997. roles in the metering, operations, and engineering functions.
[3] IEEE 1584, September 2002, IEEE Guide for Performing
Arc-Flash Hazard Calculations, New York, NY: IEEE. Adam J. Keeth received a BSEE from Louisiana Tech
[4] NFPA 70, Standard for Electrical Safety Requirements for University in 2004, and has since been employed by
Employee Workplaces, 2004, Quincy, MA: NFPA. Southwestern Electric Power Company (SWEPCO), a
subsidiary of American Electric Power. He began his career as
a distribution engineer in Shreveport, Louisiana, and currently
works as the distribution engineering supervisor in SWEPCO’s
Fayetteville, Arkansas District. Keeth serves as a member of
the Louisiana Tech Electrical Engineering Industrial Advisory
Board.

Das könnte Ihnen auch gefallen