Beruflich Dokumente
Kultur Dokumente
Abstract – The distribution utility lineman, servicer, and Theoretically, arc flash energy intensity is a function of the
meter technician play an active role in the operation, arc’s current, voltage, and clearing time [2]. Before a thorough
installation, and maintenance of 120-volt and 240-volt arc hazard analysis can be performed, it is important to
equipment on a daily basis. The arc flash risks faced by utility understand critical information concerning the clearing time of
workers operating equipment energized at 240 V or less were the arc. The primary objective of this experiment was to create
investigated for activities involving meter enclosures, meter actual scenarios allowing opportunities to observe these
installations, meter maintenance, and the connection of characteristics, specifically the clearing time and self
conductors in energized transformers and power pedestals. sustainability of live arcs with different lengths in phase-to-
The investigation led to conclusions regarding the likelihood of ground and phase-to-phase faults on 120-volt and 240-volt
an injury due to an arc flash exposure to utility workers electrical distribution systems.
performing low voltage work. The investigation included tests
conducted at an installation located immediately adjacent to a II. TESTING METHODOLOGY
substation to achieve fault currents near 12,000 amps, more
than which is typically expected for the daily activities The intent of this investigation was to create and observe faults
performed by utility linemen on voltages 240 Volts and below. It and electric arcs while simulating typical low voltage work
was concluded that the low voltage arc flash energy level to activities, specifically, while working in an energized power
which these workers are exposed is very low. The pedestal and meter socket. A small electrical distribution
methodology and results will be explained. system was constructed adjacent to a distribution substation for
the tests, and the major components of the system included a
Index Terms — Arc hazard analysis, low voltage arc flash, 7.2kV/240-120V transformer, a secondary power pedestal, and
arc sustainability, utility worker. a meter socket equipped with a bypass handle. The faults and
resulting arcs were created by connecting test apparatuses in
I. INTRODUCTION the power pedestal to act as electrodes, and then energizing
the system by closing the 7200 V riser fuse. The test
Utility linemen work in a specialized field where they are apparatuses used as electrodes to create arc gaps were
exposed to many potential hazards to provide their service and constructed of large 600-volt URD cable and 2-hole terminal
deliver a product that has become a necessity in today’s lugs. An insulating material was used between pairs of
society. Linemen are trained to use specialized tools, skills, terminals, which were connected with non-conductive nylon
and techniques to safely mitigate many of these potential bolts, to create precisely measured air gaps to regulate the
hazards. Article 410 in the Work Rules section of the National length of the arcs during the experiments. Teaser filaments
Electric Safety Code assigns employers the responsibility of were placed between the terminals to trigger the fault since a
assessing arc flash exposure hazards associated with the 120-volt arc is not capable of overcoming the dielectric strength
different systems on which employees work, and the of air within the gap widths considered in this experiment.
responsibility of requiring employees to wear a clothing system During the first series of tests, using a 50-kVA transformer, the
that protects against those anticipated hazards [1]. Another investigation began with a bolted 120-volt fault, and then
dangerous hazard faced by utility linemen is heat exhaustion, repeated the process with five air gap widths ranging from 1/24
so it too must be considered with arc flash hazards when of one inch (1.1mm) to 1 inch (25.4mm). The first series
determining an appropriate clothing system. concluded with two 240-volt tests, one of which was conducted
Electrical distribution systems range in voltages from 50 volts in the power pedestal, and the other in the meter socket.
up to 35 kilovolts. The majority of a utility lineman’s low voltage Results are shown in Table I. A second series of tests followed,
work is on 120 V, 208 V, and 240 V systems. Typical duties using a larger transformer to allow even more fault current.
associated with these systems include working in meter Instrumentation was reconfigured to also record arc gap voltage
sockets, installing and removing meters, checking voltage, and for each test. These results are shown in Table II. Thirteen
connecting secondary conductors in power pedestals, tests were conducted in total, nine of which used precisely
enclosures, and secondary compartments of transformers. measured air gaps between electrodes to create known arc
There are arc flash exposure hazards associated with these lengths during the fault conditions. Two tests were bolted fault
distribution systems energized below 300 V. conditions, and two scenarios were nearly-bolted scenarios,
B. Hazard Analysis
The authors wish to acknowledge the team of coworkers and Albert M. (Malcolm) Smoak is Vice President, Distribution
colleagues for their contributions to this study, which would not Region Operations for Southwestern Electric Power Company
have been possible without their assistance. The assistance (SWEPCO), a subsidiary of American Electric Power. Smoak
provided by Christopher R. Gray, P.E, Tom Russell, Mark Rath, holds a BSEE from Louisiana Tech University, and is a
and Henry Brown of Southwestern Electric Power Company, registered professional engineer in the State of Louisiana.
and Wayne P. Blackley, P.E., of Associated Training Corp., is His responsibilities include engineering and operations of
greatly appreciated. SWEPCO's distribution system, serving 523,000 customers in
Arkansas, Texas, and Louisiana. During his career, he has
VI. REFERENCES been devoted to improving the safety and working conditions of
SWEPCO employees. He represents NSPE on the NESC
[1] IEEE, National Electrical Safety Code, 2012 Edition, New Subcommittee 8. Smoak is a member IEEE and former
York, NY: IEEE. president of the IEEE Shreveport Chapter. He began his 28
[2] Neal, et al., “Protective Clothing Guidelines for Electric year career in the utility industry as a distribution engineer in
Arc Exposure,” IEEE Transactions on Industry Shreveport, Louisiana, and has served in various management
Applications, vol 33-4, pp 1042-1043, Jul/Aug 1997. roles in the metering, operations, and engineering functions.
[3] IEEE 1584, September 2002, IEEE Guide for Performing
Arc-Flash Hazard Calculations, New York, NY: IEEE. Adam J. Keeth received a BSEE from Louisiana Tech
[4] NFPA 70, Standard for Electrical Safety Requirements for University in 2004, and has since been employed by
Employee Workplaces, 2004, Quincy, MA: NFPA. Southwestern Electric Power Company (SWEPCO), a
subsidiary of American Electric Power. He began his career as
a distribution engineer in Shreveport, Louisiana, and currently
works as the distribution engineering supervisor in SWEPCO’s
Fayetteville, Arkansas District. Keeth serves as a member of
the Louisiana Tech Electrical Engineering Industrial Advisory
Board.