CATCH - UP PLAN (SAMPLE)

PROJECT NAME: CONSTRUCTION OF FLOOD CONTROL, F.S. CATANICO


PROJECT LOCATION: F.S. CATANICO, CUGMAN, CDO
DATE COVERED:

ITEM MANPOWER TARGET


ITEM DESCRIPTION QUANTITY UNIT EQUIPMENT NEEDED MATERIALS NEEDED
CODE NEEDED DATE
1 - Backhoe 2 - Spottter
1 - Dumptuck
103 STRUCTURE EXCAVATION 65.00 cu.m. N/A 20-Aug-19

1 - Backhoe 1 - Spottter Boulders


1 - Mini- Dumptruck 6 - Labor Cement
506 STONE MASONRY 35.00 cu.m. 23-Aug-19
1 - Bagger Mixer 2 - Mason Washed Sand

Prepared by: Checked by: