Beruflich Dokumente
Kultur Dokumente
Process Analysis
West
Inclined
~ 110 m
Bucket Elevator
Process Briquetting
Gas Plant
Heat
Exchanger Process Gas
Electrical Compressor
Iron Substation&
Ore Control Fired Gas Heaters HBI Product
Fines Room
~ 160 m
Engineering drawing
Session 03 Process Analysis
OPM 1 Term 2, B2014-16, Oct-Dec 2014 Prof. Kedar P. Joshi
Elements of a Process Figure 3
Activities
• Carried out by resources
• Add value and are required
for completion of the flow unit
• May or may not carry inventory
• Have a capacity (maximum number
of flow units that can flow through
the activity within a unit of time)
Arrows
• Indicate the flow of the flow unit
• Multiple flow unit types possible
Inventory / Buffers
• Do NOT have a capacity; however,
there might be a limited number of
flow units that can be put in this
inventory space at any moment of time
• Multiple flow unit types possible
Pre-Heater
Lock
Pre-Heater 1st Reactor 2nd Reactor
Hoppers
Flash
Briquetting Discharge
Heater
Finished Goods
Dis-
Lock 1st 2nd charge
Pre-Heater
Hoppers Reactor Reactor
Briquet-
Flash
ting
heater
Pile of Iron
ore fines
Finished
goods
Lock
Pre-Heater 1st Reactor 2nd Reactor
Hoppers
Flash
Briquetting Discharge Heater
Finished Goods
Bottleneck Bottleneck
Input Capacity Input Capacity
Flow Flow
FlowRate
Rate
FlowRate
Rate
Demand
Excess Excess
capacity capacity
Demand
Wait time is the time that a Idle time is the unused time
part waits not for a resource that represents the cycle
but for another part so that time less the sum of the
they can be assembled setup time, processing time,
together queue time, and wait time
Capacities
• Preheater 120 tons/hour
• Lock Hoppers 110 tons/hour
• 1st (cfb) Reactor 112 tons/hour. Processes 28 tons every 15 minutes
• 2nd (fb) Reactor 100 tons/hour. Processes 400 tons every 4 hours
• Flash heater 135 tons/hour
Process Capacity
• Discharge 118 tons/hour
• Briquetting 165 tons/hour = min{120,110,112,100,135,118,165}
= 100 tons/hour
Session 03 Process Analysis
OPM 1 Term 2, B2014-16, Oct-Dec 2014 Prof. Kedar P. Joshi
The cycle time of circored plant in Trinidad
80% Bottleneck
70% Imbalance relative
To bottleneck
60%
50%
40%
30%
20%
10%
0%
Preheater Lock CFB Stationary Flash Pressure Briquetting Total
Hoppers Reactor heater let-down machine process
system
100%
75%
50%
0%
Preheater Lock CFB FB Flash Discharge Briquetting Overall
Hoppers Heater process
Session 03 Process Analysis
OPM 1 Term 2, B2014-16, Oct-Dec 2014 Prof. Kedar P. Joshi
STEPS FOR BASIC PROCESS ANALYSIS WITH ONE TYPE
OF FLOW UNIT
Find the capacity of every The resource with the
resource, if there are lowest capacity is called the The flow rate is found based
multiple resources bottleneck. Its capacity on Flow Rate= Minimum
performing the same determines the capacity of (Available input. Demand,
activity add their capacities the entire process (Process Process capacity)
together. Capacity).
Similarly we find the utilization of each We find the Utilization of the process as :
resource as Flow rate
Consulting
Staff Verified Applications
File
File
Internship
Contact
Contactprior
prior
employers
employers Confirmation
Confirmation
letter
letter
Benchmark
Benchmark
grades
grades
Extensions required Use different Note that capacity Compute the work- Step with highest
for working with Colors to mark levels may differ load across all implied utilization
multiple flow units Flow units depending on product types
product type