1.0 NEW/UPDATED STANDARD


TITLE: GS 2-1-1 Noise
REVISION DATE & NO.: July 2004 Rev. 2

2.0 SPEC(S) USED PRIOR TO NEW/UPDATED STANDARD


TITLE: GS 2-1-1 Noise
REVISION DATE & NO.: February 1999 Rev. 1

3.0 PRIMARY AUTHOR(S):


(Name / Dept) Ahmad Zidni Mat / PPD

4.0 REVIEWERS:
(Name / Dept) Ungku Hishamuddin Tahir / Surface Technical Dept.
Larry W Dubose / Surface Technical Dept.
Colin Sanderson / Machinery
Ayob Yahaya / POD
Ho Wing Kwong / PPD

5.0 SUMMARY OF CHANGES

CHANGE IMPACT
Blank = None, P=Positive,
D=Detrimental
INTERNATIONAL STANDARDS EXCEPTION
NATIONAL STANDARDS EXCEPTION

CONSINDER FOR RETROACTIVE


APPLICATION (YES/NO)
COST IMPACT (USD K)
ENVIRONMENTAL

EMEP EXCEPTION
SAFETY/HEALTH

OPERABILITY
CORROSION
SCHEDULE

CHANGE DESCRIPTION REASON FOR CHANGE


RISK

(Indicate Para # from new/updated DIM/GS)

NO NO 3.0: Corrected "Lp" to "Lp" , Added to correct


"Lp = 20 log10 (P1/P0) dB" to mathematical expressions.
"Lp = 20 log 10 (P1/P0) dB ", and "2 x 10-5 Pa" to
"2 x 10-5 Pa" Clarification only.
NO NO 3.0: Corrected "Lw" to "Lw" , Added to correct
"Lw = 20 log10 (W1/W0) dB" to mathematical expressions.
"Lw = 20 log 10 (W 1/W 0) dB ", and "10-12 W" to
"10-12 W" Clarification only.

update data sheet GS 2-1-1 1


DESIGN PRACTICES AND STANDARDS
o DIM o GS
SUMMARY DATA SHEET

NO NO 3.0: Added " It can be written mathematically as: Added to improve the
contents and consistency.
1 n L ( i) / 10
LeqT = 10 log 10 [( ∑10 )]
T i =1
Clarification only.

where summation is taken over n events of


exposure time t(i) hours, and personnel are
exposed to known sound pressure levels L(i) over
an average working day of T hours (an average
working day consisting of n events lasting t(i)
hours).

NO NO 4.2: Added " .........except the engines of Firewater Industry is not ready to
Pumps and emergency generator for which the limit provide emergency
shall be 105dBA." measure below 105dBA.

Clarification only.

6.0 LIST OF UPDATED INTERNATIONAL & NATIONAL STANDARDS AND PRACTICES REFERENCED IN THE
DIM/GS.
NIL

7.0 CHECKLIST FOR NEW/UPDATED STANDARDS

Item No. Yes/No/NA Notes*


1. Does this DIM/GS require approval from Steering
Committee or Deputy Production Manager ? No

4. Conform to applicable National standards Yes

5. Conform to EMEP NA Applicable only after rollout is


completed
6. Meet or exceed applicable regulatory requirements or Yes
PETRONAS guidelines

7. Embody responsible requirements where regulations NA


do not exist

8. Reflect latest developments and lessons learned Yes

9. Consider facilities abandonment requirements (Refer to NA


PETRONAS Guidelines for Platform Decommissioning)

10. Consider Human Factor requirements (Refer to MOH No


Industrial Hygiene Checklist)

11. Consider effects of new/updated industry standards Yes

12. Consider applicable Project Change Notice (PCN) Yes


forms

13. Incorporate approved DIM/GS Permanent Change NA No PCR raised during this period.
Recommendation Forms

14. Consider relevant DIM/GS Bulletins Yes

update data sheet GS 2-1-1 2


DESIGN PRACTICES AND STANDARDS
o DIM o GS
SUMMARY DATA SHEET

Notes* - Include PCN No., Safety Bulletin Ref. No., Lesson Learned Ref. No. and GS/DIM Bulletin Ref. No.

8.0 APPROVAL TO ISSUE THE NEW/UPDATED STANDARD


(Refer to Section 4.3 in DIM 0-1 / GS 0-0-1 for approval level required)

Approved by: _____________________________ Date:


Param Kandiah
EMM Manager

update data sheet GS 2-1-1 3


DESIGN PRACTICES AND STANDARDS
o DIM o GS
SUMMARY DATA SHEET

COST-ADD IMPACT OF DIM/GS CHANGE


EVALUATION FORM

DIM/GS No & TITLE: GS 2-1-1 Noise - June 2004 - Rev 2.0

DESCRIPTION OF CHANGE IN DIM/GS REQUIREMENT:


Requirements before change:

Requirements after change: See Section 5, Summary of Changes

EVALUATION OF LIFE CYCLE COST IMPACT:


COST ESTIMATE (US$ 'K)
COST COMPONENTS
Before Changes After Changes Impact
CAPEX
- Design
- Fabrication
- Materials
- Testing / Commissioning
- Others (describe below):

Total CAPEX Impact:

OPEX (Typical Annual Cost)


Operations & Maintenance:
- Painting
- Repair
- Consumables
- Manpower Services
- Others (describe below):

Annual OPEX Impact: NA NA

BASIS FOR COST ESTIMATES:


All CAPEX costs are based on Class V estimates for each item that has changed in the Summary Section. No feedback
from vendors was obtained and the estimates are based on estimates from within the I&E Design Group. All costs are
estimated incremental costs.

PREPARED BY: Ho Wing Kwong / Ahmad Zidni


Mat - July 2004
[name & date]

REVIEWED BY: REVIEWED BY:


EPD Manager Operation Supt
[CAPEX Portion] [OPEX Portion]

APPROVED BY: APPROVED BY:


PPD Manager Operations Manager
[CAPEX > USD250K] [OPEX > USD100K]

update data sheet GS 2-1-1 4


DESIGN PRACTICES AND STANDARDS
o DIM o GS
SUMMARY DATA SHEET

update data sheet GS 2-1-1 5

Das könnte Ihnen auch gefallen