Beruflich Dokumente
Kultur Dokumente
Abstract: Steel became a common construction material for bridges, replacing timber and masonry
construction to achieve longer span crossings. These structures are still functioning well, although the
majority of them are now considered to have sub-standard capacity in the 21st Century. Steel bridge
members and components are commonly affected by chemical agents in exposed air, water, and soil.
These chemicals trigger and accelerate the corrosion of steel and the need to have more maintenance
and repairs. Vehicles impacting low clearance bridge members can cause momentous damage to these
structures.
Steel bridges, particularly those with sub-standard vertical clearance, are regularly impacted by vehicles.
This paper will investigate typical damage caused by vehicle impact and discuss examples of repair
methods, using three case studies.
1. MacRobertson Bridge in Melbourne will be used to examine the damage and repairs to a steel truss;
2. Damage to bridge girders will be explained using Point Wilson Road Bridge over Princes Highway; and
3. Heritage listed Mia Mia Iron Girder Bridge (The Redesdale Bridge) will be used to explain the need for
special care and reinstatement for restoring an historic bridge.
Keywords: Steel Bridge Repair, Sub-standard Bridges, Truss Bridges, Arch Bridges, MacRobertson
Bridge, Pt. Wilson Road Bridge, The Redesdale Bridge.
1. Background
Steel construction is usually assembled with welded joints, rivets, or high-tensile steel bolts. Fasteners are
designed for shear as individual members or may be intended to provide a clamping force to an interface
to permit the generation of frictional forces between adjacent components. The durability of the structural
iron and steel depends on the locality in which the structure is built, and on the quality and integrity of the
protective coating.
Steel bridge members and components are commonly affected by chemical agents contained in exposed
air, water, and soil that trigger and accelerate the corrosion of steel, but sudden impact loading by
vehicles impacting structural members can cause heavier damage or even sudden collapse of the entire
structure. For example, in 2013, a bridge in Washington State, USA, was hit by a truck and collapsed into
Skagit River. Although, luckily, no one was killed, the incident raised the awareness of infrastructure
management authorities about managing aging infrastructure, especially sub-standard bridges.
Bridges damaged by vehicle impact can usually be reinstated to their original status but require costly
repairs and replacement to the damaged members, as well as requiring a full investigation into the
performance and reliability of the structure. In addition to damage to the structure itself, this type of
incident could create traffic congestion, delaying commuters and loss of human lives. This paper will
examine three case studies that discuss a variety of damage that occurred from vehicles impacting
overhead sections of steel bridges in Victoria during recent times.
2. Case Study 1: MacRobertson Bridge (Grange Road over Yarra River and City Link)
The MacRobertson Bridge was originally constructed in 1934 for the Grange Road crossing of the Yarra
River from Toorak on the south bank, to Burnley in Melbourne (Figure 1). It was one of two bridges in the
world that were the first to use welded steel trusses (Heritage Victoria, 2016). Later, City Link (Monash
Freeway) was constructed to run underneath the northern span of the bridge (Figure 1). The minimum
vertical clearance over both carriageways of City Link is approximately 5.0m. As a result, Over Height
Vehicles (OHV) travelling on City Link have hit the truss several times. In 2002, vehicle impact damaged
all three bottom cords and a 2004 impact damaged the easternmost bottom cord. Following these major
incidents, and a few other minor hits by OHV, an Over Height Vehicle Detection System (OHVD) was
installed in 2005. However, in June 2015, another OHV, a crane mounted truck which was travelling on
City Link towards Melbourne city smacked and damaged the northern part of the bottom cord of the bridge
(Figure 2). The crane had initially hit the first truss and then bounced back and hit the second truss,
resulting in the most damage being caused to the second truss.
• Special attention was required to evaluate components that are highly stressed;
• Joints and welded connections were evaluated and inspected for any defects;
• Plans and drawings of the structure were reviewed; and
• Members were photographed and compared with both recent and historic inspection reports.
Impacted Area
Subsequently, the top side batten plates were connected back to the side faces of the central plate.
a Damaged and bent bracing b. Restored bracing c. Repaired connection with bracing
Figure 8: Repairs to the bracing
Point Wilson Road Bridge over Princes Highway near Geelong is a steel beam bridge which was
damaged by a moving truck on Princes Highway toward Melbourne in 2010.
a. MT method b. M
MT Field test
Figure 9
9: Magnetic Pa
article Field Test
T
MT is a p popular non-d destructive e examination o of ferromagnetic material. Once the m magnetic field is created,
the magn netic flux willl leak out of the material (Figure 9a) if the disconntinuity is gen
nerally perpeendicular to
its flow, ccracks paralllel to the fluxx will not be detected. Thherefore the test is normaally undertakken at least
twice perrpendicular to o each otherr to detect eve ery possible crack.
3.2 Re
epair and R
Reinstatement
Deformations and fraactures in all tthe girders 1, 2, 4 and 5 on
o both carriageways weere cleaned in
n readiness
for the fla
ame heat ap
pplications an nd the additional X-brace e diaphragmss. The affectted areas we
ere cleaned
by using removal blassting.
Permanent X bracing
Temp
porary bracing
& strengthe
ening plates
a. Tem
mporary bracin
ng b. Bracin
ng diaphragm c. Die grind
der weld prepa
aration
Figure 11: Temporary
T and Restoration
n works
Tempora ary bracing w
was installed at predetermmined areas prior to hydrraulic and Tirrfor loading applications
a
to eliminate additionaal strains to already dammaged memb bers (Figure 11). Flame heating of up to 600oC
was applied in variou us predeterm mined locations in order tto minimise stress
s conce
entration and to prevent
further sttrain or dam
mage. As a part of the prrotective mea asure, flame heat plate d deflecting sh
heeting was
tack-weldded to the o outer flange edge of Girder 1 to prrevent heat damage to electrical co onduits and
cabling.
The placement of a temporary backing plate (20 mm to 25 mm) welded to the under-face of the flange
crack-repaired area and temporary X-bracing was used before attempting flame heat straightening (Figure
11 a). The intention was to assist in the straightening techniques used as well as to prevent further
development of existing cracks or new cracks in both the flange, and the web.
3.3 Risks and Limitations
In order to minimise further strain on already damaged sections, the repair was undertaken in steps, firstly
to Girder 2 and then to Girder 3. The procedure included:
• weld repairs and temporary bracing to Girder. 2;
• straightening to Girder 2 and flame straightening;
• placed temporary X-bracing at the undamaged Girder 3;
• flame straightening to impact damaged Girder 4;
• place and weld web-stiffeners for the fitment of the permanent angle X-Brace diaphragm (between
Girders 3 and 4);
• flame straightening to the weld-repaired Girder 2; and
• flame straightening procedures, the strengthening of the bottom flanges.
The placement of the permanent X-brace diaphragm between Girder 3 and 4 was to sustain the flame and
jacking procedures necessary for completing the repairs to all other girders. After completion of the flame
straightening and weld repairs which included fitting of the web stiffening plates and welding of the X-
bracing diaphragms, plate strengthening to the selected areas of the bottom flanges was undertaken.
The single span, 46m long, Mia Mia iron girder bridge was originally constructed in 1867 and consists of
three (3) wrought iron lattice style through truss girders. The bridge had been damaged by OHV several
times in recent years. Following a similar incident in the late nineties, an extra 400mm bracing section had
been inserted between the arch section and the bracing to create extra clearance for traffic whilst
maintaining the original shape of the structure (Figure 13). A high load impacted the arch-shaped bracing
over the Heathcote-bound lane closer to the Redesdale abutment again in 2014, bending and damaging
the arch (Figure 12.a). The following section will discuss the damage of, and repairs to, the structure after
this recent incident.
Figure 13: The cross section of the arch with the inserted section
5. Summary
This paper demonstrates typical damage to steel bridges, particularly for bridges with sub-standard
vertical clearance, caused by over height vehicle impacts. Three case studies were used to discuss the
typical damage to these structure and various structural members (trusses, beams and overhead bracing),
using examples of repair methods to a variety of members.
A truss example was discussed using MacRobertson Bridge and the damage to the lower members and
the method for replacement and strengthening to better resist impact.
Damage to Point Wilson Road overpass bridge beam demonstrates typical damage to girder beams and
strengthening of the deformed bottom flange and web with carefully applied heat and force. Cross bracing
and welded plates to the bottom flange was the strengthening treatment used in this case.
Damage to overhead bracing and treatments for a heritage listed structure was discussed using the
example of Mia Mia Girder Bridge. Damage caused to overhead riveted wrought iron bracing for a trough
girder bridge was required to be reinstated after removing and repairing some sections in a workshop
before reassembling the structure on site. Riveted joints were used instead of a typical bolt arrangement
to maintain the same appearance.
6. Acknowledgements
The authors would like to acknowledge and, sincerely thank, a number of their colleagues at VicRoads
who were happy to share useful information and reports on these case studies, particularly Mr. Hai Luong,
Mr.Gary Noyes- Brown, Mr. Glenn Bodilly and Mr. Doug Baring
7. References
Standards Australia, “Australian Standard for Bridge Design Part 6 (AS5100.6), Committee BD-090
for Bridge Design, 2004, Sydney NSW Australia
Heritage Victoria, “ Mia Mia Iron Girder Bridge (The Redesdale Bridge)-Greater Bendigo City,2010