Beruflich Dokumente
Kultur Dokumente
The
SU RVEYO RS'
CO N STRU CTI ON
HANDBOOK
Update 3 publishedDecember 1999
Update 2 published October1999
Update I published April 1999
Appendix A, Section 2.3 is reproduced from the BuildingCost Information Service publication,
StandardForm ofCostAnalysis: Principles,InstructionsandDefinitions (1969).
.
Update 3 includingbulletin update Dec 99
Amd/i
The
SURVEYORS'
CONSTRUCTION
HANDBOOK
BULLET IN
\AIELCOME TO THE INSTITUTION'S CONSTRUCTION HANDBOOK, WHICH IT IS
life-cycle costing;
• ascertaining loss and expense;
• employer's requirements for design and
build;
• valuationof interim certificates;
• design and building procurement;
• extension of time underJCT contracts; GEOFF BREWER • BREWER CONSULTING
• liquidatedand ascertained damages;
• risk management;
• site resources/off-siteconstruction;
• supplychain management;
• the Disability Discrimination Act;
•
party walls'alert'.
This structure closely reflectsthe structure
of the construction-relatedRICS practice
panels, who have the substantial task and
responsibilityfor drafting the material and
settling it after appropriate consultation.
They are led respectively by: KEITH DEW • JOHN PELLING AND PARTNERS
1 The Co-ordinated Project Information and Maintenance Panel, is available via RICS
I Committee have published Uniclass, a Books. It provides advice on commissioning
classification system for construction infor- and carrying out this type of survey as well as
mation which can be used in libraries, for points to consider when collating and
projects or in a database to organise infor- managingdata.
mation. The RICS is a member of the
Committee which consists of representatives A Guidance on Building Surveys and
from the ICE, RIBA, CIBSE and the 9 Inspections of Commercial and Industrial
Construction Federation. Property is available via RICS Books. The
document covers taking instructions, through
Amendments have been made to preparationand inspection, to composing the
Approved Documents K and N (details report itself.
publishedin CSM Februaryissue).
The Department of the Environment,
The Building Employers' Confederation 1 0 Transport and the Regions has issued a
3 has now been officially reconstituted and consultationdrafton proposedamendments
includes such bodies as the Major to Regulation 7 of the Building Regulations
Contractors' Group, the Civil Engineering 1991 which requires that work is carried
Contractors' Association (CECA) and the out with proper, appropriate materials in a
House Builders' Federation (HBF) and will be workmanlike manner. The aim of the
known as the Construction Confederation.It amendments is to bring Regulation 7 into
becomes the RICS' partner in SMM7. line with its technical counterparts with a
functional Regulation supported by detailed
JCT Limited comes into operation on guidance in the Approved Document.
4 1 April 1998.
A revised draft of the Fire Safety Bill is
The Association of Corporate Approved 11 the subject of consultation between the
S Inspectors has now been recognised by Home Office and other professional groups
the DETR. In addition, its membership has including the RICS. Members will be
been widened to include members of non- informed of progress via CSM following
corporate bodies who act in the Approved further meetings with the Home Office and
Inspectorrole. the RICS.
ParliamentSquare
London SW1P 3AD
web www.rics.org.uk
FOREWORD
The fact that our professionserves a changing worldincreases the need for
it to rely on well thought-outand reliable practicesand procedures. Events
move at an ever-increasing pace, imposing a requirement for quicker
responsetimes. Modem communicationmethodssuch as facsimile and now
e-mail result in the need for information to be available almost instantly.
This is made more difficult by an industry growingin complexity and which
is subject to increasing customer expectations in terms of service and
quality.
ChristopherPowell, FRICS
PRESIDENT, QUANTITYSURVEYORS DIVISION
5
ACKNOWLEDGEMENTS
Foreword
Acknowledgements
Abbreviations
Introduction i
A Aim and Scope of this Handbook 1
B Arrangement of Content 1
C Statusof Content 2
D Currency of References 3
E Invitation 3
F SubscriptionService 3
7
Part 2: Construction Design and Economics 1
Section 2.1: Pre-contract Cost Planningand Cost Management 1
Introduction 1
Appendix B: Obsolescence 1
Introduction 1
2.3.1 Elements 1
Introduction 1
2.4.1 Background 2
2.4.2 Contract Documentation 3
2.4.3 Additional Services 3
2.4.4 Employer's Requirements and Contractor's Proposals
(including contract sum analysis) 5
2.4.5 Design and Build Variants 6
2.4.6 Novation 8
Appendix A: PotentialServices Associated with the Role of Employer's Agent 1
8
Part 3: Construction Planning and Piócurement 1
Introduction 1
4.1.1 What Happens in Practice 1
Introduction 1
Appendix B: Disruption 1
Appendix D: Checklist of Items for which Loss and/or Expense are Allowed 1
Introduction 1
4.3.1 Definitions 2
4.3.2 The Rationale for Risk Management in the Construction Process 2
4.3.3 The Risk Management Process 4
4.3.4 Summary 12
Appendix A: Further Reading 1
9
Part 5: Additional Guidance and Information 1
Index 1
10
LIST OF ABBREVIATIONS
11
RIBA RoyalInstitute ofBritish Architects
RICS Royal Institution ofChartered Surveyors
VAT Value Added Tax
WCD WithContractor's Design
WRC WaterResearch Centre
12
INDEX
Note: referencesareto paragraphs. Figuresand Tables are notincluded
13
capital expenditure 2.2.3.1; 2.2.3.3; 2.2.5.5(f);Part 2 completed part ofthe works4.1.2.18(d)
Section2:AppendixDl, D3,D6 completion
capital income2.2.5.5(d) date seecompletion date
CDM(construction (design and management)) sectional 4.1.6.5(c)
information 5.2 staged4.1.6.4(1)
regulations2.2.1.4; Part2 Section4: AppendixAl; Part 4 see alsoperfectcompletion; two-stagecompletion
Section 1: Appendix Al0 completion date 2.1.4.6; 4.1.2.17(c); 4.2.3.2;4.2.5.13
certificates see final certificates; interim certificates; completion distinctfrom practicalcompletion 4.1.5.1(d);
practicalcompletion 4.1.6.1(f)
certification ofcompletion 4.1.1.1; 4.1.1.3(d)(e)(f) completion for all practical purposes4.1.5.1(b)
change,avoidance of3.1.1.8(g); 3.1.1.14(a) completion process 4.1.2.20(c)
change controloverview3.1.1.14 completion time3.1.1.9(c)
changes 3.1.2.11(e) completion to time 4.1.5.3
after contract let 3.1.1.14(h) components 3.1.2.9(h)
late 3.1.1.8 computeraided design (CAD) 3.1.1.7(f)
prior to construction 3.1.1.14(g) computersoftware, risk analysis 4.3.3.4(b)
see also clientchanges; cost plan;tender documents conflict, dealingwith 1.1.5.4; 2.4.4.2
checklists Constructingthe Team see LathamReport
analysis 3.1.2.10 construction 3.1.2.8(a)
contractor'sproposalPart2 Section 4: Appendix B2 construction completion report4.1.2.20(c)
cost3.1.4.3 construction costs 2.2.1.3
employer'srequirement Part 2 Section 4: Appendix B2 construction (design and management) see CDM
items forwhich loss and/orexpenseallowed Part4 (construction(design and management))
Section 2: AppendixD construction management 3.1.1.4; 3.1.1.5; 3.1.2.5;3.1.2.9;
procurement selection3.1.4.2—3.1.4.3 3.1.3.6
risk4.3.3.3(b)(iii) Construction Task ForceI .2(Intro)
safety5.1 construction time 3.1.2.11(h)
submissions, steps when considering Part 4 Section 2: constructors, appointment of3.1.1.6
Appendix E consultants 2.4.4.9; 3.1.1.5;3.1.1.6
time3.1.4.3 appointment of1.1.7
CITBLevy 5.4.7 lead 2.4(Intro)
civil engineering 2.1 responsibilities of2.4.4.9
cladding Part4 Section 1: Appendix A6 consultants'information 2.1.3.3(h); 2.1.4.3(e)(h);
clerk ofworks2.4.3.4; 3.1.1.13(b); 4.2.5.4(b); Part4 2.1.5.3(e)(h); 2.1.7.3(b)(f)
Section 2: Appendix B2.1;5.2.1 consultation papers 5.3.1
client 1.1; 2.4(Intro); 2.4.4.3;2.4.4.5; 2.4.4.6; 5.2.1 consulting engineers 2.1.5.4(b)
clientand propertycosts 2.2.1.1 contingencyPart 2 Section 3: AppendixA8;3.1.1.8(d);
clientchanges 3.1.1.14(b) 3.1.1.14(1); 4.3.2.3
clientcontext, life cyclecosting 2.2.1 see also time contingency
clientneeds3.1 contingency allowance 1.1.5.3(e)
clientreserve 3.1.1.8 contingencyfunds3.1.1.8(m)
clientresources 3.1.2.11(c) contractadministration 5.5.1
clientsatisfaction3.1; 3.1.2.7 contractadministrator 2.4(Intro);4.1.4.1(a);4.2(Intro);
client systems 3.1.5.8(g) 4.2.1.9; 4.2.3.1(c);4.2.3.2;4.2.3.3;4.2.3.4;4.2.4.1;
clientuniqueness 3.1; 3.1.2.7 4.2.4.2; 4.2.4.3;4.2.4.10; Part4 Section 2:
client'sbrief1.2(Intro); 2.1.1.2; 2.4.4.8 Appendix B2
client's information 2.1.3.3(b)(f); 2.1 .4.3(a)(f); 2.1.5.3(a)(g); contractdocuments 2.4.2;Part2 Section4: Appendix BI;
2.1.7.3(a)(d) 3.1.1.4; Part 3 Section 1: Appendix A; Part4
client's input2.4.4.7 Section 1: AppendixAl
client's involvement 3.1; 3.1.1 contractimplementation and administration 3.1.1.5
client'sobjectives 1.1.1; 1.2(Intro); 1.2.1; 2.4.4.5; 2.4.4.7; 3.1 contractstages (designand build)
clientsrequirements 1.2.1.2; 1.2.6.2; 1.2.7 durationPart 2 Section 4: Appendix A3
client's responsibilities 1.1.5; 2.4.4.6; 2.4.4.7 post-contract Part 2 Section 4: Appendix A4
client'srole 1.1.4; 1.1.6; 3.1.1.6(a) pre-contractPart 2 Section4: Appendix A2
CodesofPractice Part 3 Section1: Appendix A; 4.1.4.1(e) contract sum 2.1.7.2(a); 4.1.3.2(b)
CodesofProcedure 2.4.4.10; Part 2 Section 4: analysis2.3.3.l(c)(d)(e);2.4.4
Appendix A (Intro); 3.1.1.6(b); 3.1.5.5(f) contractterms and conditions 3.1.2.7;4.2(Intro);4.2.1.11;
collateral contracts3.1.1.5(b) 4.2.1.12; 4.2.3.l(c)(d);4.2.3.3;4.2.4.2;4.2.5.13; 4.2.5.15;
commissioning 3.1.1.15 Part 4 Section 2: AppendixC4
competitive tenders 1.1.7.5 seealsocontracts
14
contractor 5.2 criteria
application 4.2.4.10 identification of3.1
loss andlor expense 4.2(Intro); 4.2.1.4;4.2.1.11; 4.2.1.12; primary3.1.2.8;3.1.2.9
4.2.1.15; 4.2.2.1; 4.2.3.1;4.2.3.2; 4.2.3.3;4.2.3.4;
4.2.3.6; 4.2.4.5;4.2.4.8; 4.2.6.4;Part 4 Section2: D
Appendix CI damage to works4.1.2.18(d)
performance monitoring 2.4.3.5 damages4.2.1.1; 4.2.1.2;4.2.1.3;4.2.1.5
responsibilities of2.4.4.9 data
selection of3.1.5.5(d) presentation2.2.5.4
submissions 4.2.4.3; Part 4 Section 2: Appendix E risk 4.3.3.3(b)(vi)
contractor'sinitiative 4.1.4.1(c) sources for costing 2.2.2.4;2.2.4
Contractor's List 4.1.2.10(c)(d) types of2.2.4
contractor'sproposals 2.3.3.1(b); 2.4.3.2;2.4.4;Part 2 dayworks 5.4.5;5.4.7;5.4.10
Section 4: Appendix B dayworkspreliminaries 5.4.7;5.4.10
contracts de minimusrule 4.1.5.l(c)(e);4.1.5.2; 4.1.6.4(g)
breach of4.2.1.1;4.2.1.3 decision-making process 1.1.5.5; 1.2.3.1; 4.3.2.4
rangeof3.1.2.7 decorationworks Part 4 Section 1: Appendix A7
standard3.1;3.1.2.7; 4.1(Intro); 4.1.1.1; 4.1.1.3(d) defects4.1(Intro)
seealsodesignand build contract; and individually,bytitle outstanding4.1.1.3(f); 4.1.2.12(c); 4.1.2.15(c); 4.1.4.2(c);
contractual arrangements3.1.5.7 4.1.4.3(a)
control document 2.1.5.2 remedying 4.1.5.4
controls 3.1.5.8 see alsolatentdefects; patentdefects; schedule ofdefects
conversion 2.1 defectscorrection 4.1.2.20(c)
Corporation Tax 2.2.3.4(a)(b)(c)(f) defectscorrection period 4.1.2.12(d); 4.1.5.1(f)
cost categories Part 2 Section 2: Appendix C defectsliability 4.1.2.1;4.1.2.6(c)
cost checking2.1.6;3.1.1.8(h) defectsliability period 4.1.2.20(c); 4.1.3.1(c)(f); 4.1.4.4(e);
cost checklist 3.1.4.3 4.1.5.2
cost comparison (worked example)2.2.5.5(h) definition ofthe project 1.1.1.7
cost consultant 1.1.7.1; 1.1.7.3 delay 3.1.1.9(f); 4.1.5.3;4.1.6.3(f);4.2.1.4; 4.2.1.7(b);
cost control 3.1.5.8(d) 4.2.2.2;4.2.3.1(f); 4.2.3.3(c);4.2.3.5;4.2.4.3;
cost control overview3.1.1.8 4.2.4.5;4.2.5.4(c)(e); 4.2.5.7;4.2.5.11; 4.2.5.13;
cost criterion 3.1.2.8(b) Part 4 Section 2: Appendix B, C4
cost estimates 1.1.5.3(d) see alsodisruption
cost index5.4.12; 5.5.2 demolish and rebuild,costing2.2.5.6
cost information Part 2 Section 1: Appendix A; 5.5.1—5.5.2 demolition costs Part 2 Section 2: Appendix A4
cost issues 3.1.2.11(f) density ofvertical division Part 2 Section 1:Appendix C;
cost limit2.1.1.3(a) 3.1.1.7
cost management, pre-contract 2.1; 2. 1.1 depreciation 2.2.3(Intro); 2.2.3.2;2.2.3.5(a); Part2 Section
cost models 2.1.4.4 2: Appendix D3, D6, D7,D8
life cycle(worked examples) 2.2.5 design 1.1.4.4; 2.3.1.2;3.1.1.13
cost plan 3.1.1.8(h) client-led2.3.3.1(d)
changes to 2.1.4.7; 2.1.5.6 contractor-led 2.3.3.1(d)
format Part2 Section 1:AppendixB functional analysisof 1.2.7; Part 1 Section 2: Appendix A
modification of2.1.6.4 setting of 3.1.1.7
outline proposals stage 2.1.4 Designand Build 2.1; 2.3.3.1; 2.4(Intro);3.1.1.4; 3.1.1.5;
scheme designstage 2.1.5 3.1.2.5; 3.1.2.9; 3.1.3.9
cost planning, pre-contract 2.1; 2.1.1 background 2.4.1
cost reports 2.1.3.7; 3.1.1.8(j) Code ofProcedure for Selective Tendering 2.4.4.10
cost risk3.1.2.9 contractdocumentation 2.4.2; Part 2 Section 4:
cost studies, preliminary 2.1.2 Appendix B1
cost targets 2.1.4.2; 2.1.5.1—2.1.5.2 design build contract
and
costs-in-use 2.1.1.2(d); 2.2.1.8; 3.1.1.8(e) contractor'sproposals 2.4.3.2; 2.4.4; Part 2 Section 4:
costing Appendix B
calculation 2.2.2; Part 2 Section 2: Appendix A3 employer'srequirements 2.4.3.2;2.4.4
see also life cyclecosting services,additional 2.4.3; Part 2 Section 4: Appendix AS
costs surveyorsas employer'sagent 2.4(lntro)
categories of2.2.2.4 variants2.4.5
excess2.1.6.4 see alsocontract stages (designand build)
indirect 4.2.3.1(b) designand construction period 2.1.4.6; 2.4.4.5
costsversus prices4.2.4.8 designand manage3.1.1.4; 3.1.2.5; 3.1.3.8
15
designbrief 1.2.12.3; 3.1.1.7 employer'sresponsibilities 2.4.4.9; Part 2 Section 4:
designbuild fund and operate(DBFO) 2.4.5.6 AppendixB
designfailure3.1.2.9(f) energyefficiency2.2.1.6
design(frozen) 3.1.1.9(h); 3.1.1.14(d) Engineer2.4.3.4;4.l.2.l2(b)(c); 4.1.2.13; 4.1.2.15(b)
designinput,initialPart 2: Section 4: Appendix Al engineering services2.1.5.4(b); 2.2.5.6(e)
designoptions, life cycle costing (worked examples) entitlement4.2.1.4;4.2.1.5;4.2.1.7;4.2.1.10; 4.2.1.12;
2.2.5.1;2.2.5.2 4.2.3; 4.2.4.5; 4.2.4.7;4.2.4.8;4.2.4.10; 4.2.5.11;
designoverview3.1.1.7 4.2.5.13; 4.2.6.4
entrancesPart 4 Section 1: AppendixA4
designperformance checklist 3.1.4.3
environmental impact3.1.1.7(a)
designprocess 2.1.1.2
designprogramme 1.2.3.3 estimatingand estimates3.1.1.8
evaluation 1.2.13; 2.1.4.4;4.2.1.11
designproposals 2.1.6;2.4.3.7 event 4.2.1.15; 4.2.3.2; 4.2.4.10;Part 4 Section2
designrisk 3.1.2.9(k)
Appendix C3, C4
designsolutionsl.2(Intro);1.2.2.1; 1.2.2.3; 1.2.3.1; 1.2.6.2;
existing building 2.2.5.6(c)(d)(f)
1.2.8.1; 1.2.9; 1.2.10.1(b)
expenditure
design stages1.2.3.1;2.1.1.4; 2.1.5 excess2.1.6.4
design team 1.1.2.2; 1.1.7.1—1.1.7.4; 1.2(Intro);1.2.12.2;
see alsocapital expenditure;revenueexpenditure
expense in buildingprojects4.2
3.1.5.5(c)
designer2.4.6.2;5.2 extension oftime4.1.3.2(d); 4.1.6.3(b); 4.1.6.5(c);4.2.3.2
designer'sinformation 2.1.3.3(c)(g); 2.1.4.3(b)(g); external works Part 2 Section3:AppendixA6; Part 2
2.1.5.3(b)(h); 2.1.7.3(b)(e) Section 4: Appendix B2.5.6;Part 4 Section 1:
developand construct 2.4.5.3;3.1.2.5; 3.1.3.9(b) Appendix A7
developers 1.1.1.3
digests 5.4.9;5.5.5 F
direct,definition of4.2.2.2 factorsbeyondcontrol3.1.2.11(b)
discountrate 2.2.2(Intro); 2.2.2.2; 2.2.2.3;2.2.2.4;2.2.5.1; FASTsee functional analysis systemstechnique(FAST)
2.2.5.2; 2.2.5.4; 2.2.5.5(e);2.2.5.6(b) fault free works 4.1.4.1(f);4.1.4.3(b); 4.1.5.1(a)
averageriskpremium2.2.2.3(c) FCECBlue Form ofSub-contract 4.1.2.16
no risk return2.2.2.3(b)(d) feasibilitystudies 2.1.2
selection 2.2.2.3(e) fees 1.2.8.2
test2.2.2.3(a) lump sum 1.1.7.8
discounting2.2.2.2; 2.2.5(lntro); 2.2.5.1;2.2.5.2 percentage 1.1.7.7
disposalcosts2.2.2.4(g) professional 1.1.7.6; 2.4.6.1
disputes4.1.2.5(c); 4.1.2.11; 4.1.4.1(f); 4.1.4.2(b) time charge 1.1.7.9
disruption 4.1.5.4; 4.2.1.4; 4.2.1.7(b); 4.2.3.1(c);4.2.3.5; fencingand security Part 4 Section 2: Appendix AS
4.2.4.5;4.2.5.4; Part 4 Section 2: Appendix B final certificates 4.1(Intro); 4.1.2.20(c)
seealsodelay FinanceActs 2.2.3.2;Part 2 Section 2: AppendixD3, D6
distribution Part 4 Section 2: Appendix A6 finance charges4.2.5.1;4.2.5.14; 4.2.5.15
documents see contract documents; reimbursement financial resources 3.1.5.3
documents; tenderdocuments financing charges4.1.6.2
Domestic Sub-contract DOM/1 4.1.2.3 financing costs 2.2.2.4(b); Part 2 Section2: Appendix C2
Domestic Sub-contract IN/SC 4.1.2.3(e) finishes 4.1.4.1(f);Part 4 Section 1: AppendixA7
internal Part 2 Section 3: Appendix A3; Part 2 Section 4:
drawings 2.1.4.2; 2.1.5.4;3.1.1.7
Appendix B2.5.3
first year allowances2.2.3.2;Part2 Section2: Appendix D6
E
fitting-out 3.1.1.16;3.1.2.6; 4.1.1.3(e); 4.1.6.4(k)(I);4.1.6.5(a)
early completion 4.1(Intro)
fittingsand furnishings Part 2 Section 3: Appendix A4;
earlypossession 4.1.2.19(c) Part 2 Section4: Appendix B2.5.4
electrical services see mechanical and electrical services fluctuationbonds4.1(Intro)
elementunit quantities Part 2 Section 1: AppendixC forecasting5.5.1
elemental cost analysis Part2 Section 1:Appendix A2.1; 2.3.2 frost damage 4.1.3.2(c)
elemental unit rate basis 2.1.5.4(a) function elements 1.2.7.5; 1.2.7.6; Part I Section 2:
elements for buildings2.3(Intro); 2.3.1 AppendixB
elements for designand build 2.4.4.10; Part 2 Section4: functional analysissystemstechnique(FAST) 1.2.7
Appendix A(Intro) FAST diagram1.2.7; 1.2.8; 1.2.10.1(a)
employer 2.4(Intro) functional decomposition 1.2.7.5
employer'sagent2.4(Intro);2.4.3; Part2 Section 4:
Appendix A G
Employer'sRepresentative4.1.2.14(a) GovernmentContractsGC/Works/1/Edition2 4.1.2.18
employer's requirements 2.3.3.1(a); 2.4.3.2;2.4.4; Part 2 GovernmentContracts GC/Works/1/Edition 3 4.1.2.19
Section 4: Appendix B governmentworks4.1.2.18
16
grants, regionaldevelopment 2.2.3.2 insurance risks 41.4.4(d)
GreenBook 4.1.2.20(a)(c) interestrates 2.2.2.2;2.2.2.3; 2.2.5.1;2.2.5.3;5.2.5.6
grossfloor area 2.1.6.3 interested parties 1.1.5.4
groundconditions 3.1.2.9(c) interim certificates 4.2.4.6
interim payments 2.3.3.1(e); 2.3.3.2
H interim valuations 2.3.3.1(e)
Handbook Introduction; 5.3.2 Intermediate Form 4.1.2.3(e);4.1.2.4; 4.1.2.7—4.1.2.8
handover3.1.1.16; 4.1.2.17(a) investment appraisal1.1.1.6
hazards 5.1; 5.2.1 investment tables (Parry's)2.2.5.7
headoffice4.2.5.1;4.2.5.8; 4.2.5.9;4.2.5.11; Part 4 ISO 90003.1.1.13(c)
Section2: Appendix All, C itemssee admissable items; inadmissable items
healthand safety2.2.1.4;4.3.1; 5.2
see alsosafety J
Health and Safety at Work Act 19745.1 JCT Forms ofBuildingContracts
Health and Safety Executive 4.3.1;5.1 Intermediate Form ofBuildingContract1984(IFC84)
healthand safetypolicystatement 5.1 4.1.2.4
hire charges4.2.5.3(c) NAM/SC Sub-Contract Conditions: for Sub—Contractors
holidays-with-pay 5.4.7 named underthe IFC 84 4.1.2.3(e)
HongKong decision 4.1.5.1(e) JCT 80 StandardForm ofBuildingContract4.1.2.1;
houserebuildingcosts 5.4.12
4.1.6.4(f); 4.2.1.9; 4.2.1.13; 4.2.3.1;4.2.3.2;4.2.3.4;
housingsinking fund 2.2.5.4 4.2.4.1; 4.2.4.6;4.2.6.2;Part 4 Section2:
Hudson'sapproach 4.1.5.3
Appendix D, E
humanresources 3.1.5.4 JCT Agreement forMinorBuildingWorks 1980 (MW8O)
4.1.2.6
I Management Contract 1987 4.1.2.8;4.2.1.13
ICE 5th Edition: Completion Certificate 4.1.2.13 Works Contract/2 4.1.2.9; 4.2.1.13
ICE 6th Edition: Substantial Completion 4.1.2.12; NSC/C NominatedSub-contract Conditions 4.1.2.2
4.1.5.1(f); 4.1.6.4(c) StandardForm ofBuilding Contract 1998 (JCT98)2.3.3.2
ICE Designand Construct Clause48(3) 4.1.2.12(d) Standard Form ofBuilding Contract WithContractor's
ICE Designand Construct Forms 4.1.2.14 Design2.4.2
ICE MinorWorks 4.1.2.15; 4.1.4.2(a); 4.1.5.1 Standard Form ofBuilding Contract WithContractor's
implementation 1.1.2.2; 3.1.2.7; 3.1.2.10; 3.1.5 Design(CD 81) 3.1.3.9(j); 4.1.2.5;4.2.1.13
implementation ofcontract3.1.1.5 Standard Form ofBuilding Contract WithContractor's
implementation process3.1; 3.1.1.3; 3.1.5 Design(CD 98) 2.3.3.1(e);2.4(Intro);2.4.2.1;
inadmissible items 4.2.6 2.4.2.2; 2.4.2.4
incentives 2.2.3; Part 2 Section 2 Appendix D5, D6 Standard Form ofPrime Cost Contract 1992 4.1.2.7
indicesPart2 Section 1: Appendix A2.3 JCT practicenote CDIA 2.3.3.1(a); 2.4(Intro);2.4.2.3;
Indices andForecasts5.4.4
2.4.4.1; Part 2 Section 4: Appendix A(Intro)
industrial buildingPart 2 Section 2:Appendix D4 JCT practicenote CDJB 2.4.2.3; Part2 Section 4:
inflation2.1.3.6; 2.1.4.8;2.1.5.7; 2.2.2.2;3.1.1.8(k); 4.2.5.7
Appendix A(Intro)
information JCT Standard Form: wording 4.2.1.14
general, designand build contractPart 2 Section 4: JCT variant forms ofcontract 4.1(Intro); 4.1.6.4(f)
Appendix B2.1 Joint Contracts Tribunal Part3 Section 1: Appendix A
preparationof2.1.4.4; 2.1.5.5 joint venture/negotiated project2.4.5.5
requirements 2.1.3.3; 2.1.4.3; 2.1.5.3; 2.1.7.3;Part 2
Section4: Appendix B2
seealsocost information; data; documents; recordsof K
costs Keating's analysis 4.1.5.2
information services 5.2—5.5 key decisions1.1.5.5(a); 3.1
initialcontroldocument 1.1.3.2 key elements 2.1.4.4
initial/first year allowances Part 2 Section 2: Appendix D6
inspection 2.4.3.4; 3.1.1.13 L
installations Part4 Section 1: Appendix A2.2 labour, disruption of4.2.5.4; Part 4 Section 2: Appendix
InstituteofChemical Engineers Forms (I Chem E) 4.1.2.20 B1.l
instructions late completion 3.1.2.9(m)
late 4.2.1.7(b); 4.2.4.10(c); 4.2.5.4(e) late finish3.1.1.9(e)
post-completion 4.1.6.3 latentdefects4.1(Intro);4.1.4.3(b)
insurance 3.1.2.9(f); 4.1.6.5(b); Part 4 Section 2: LathamReport2.2.1.3; 3.1.1.6;3.1.1.10
Appendix AlO; 4.3.3.5(b) LathamReview3.1.3.6(d)
insurance (BUILD) 3.1.3.9 legal contracts 3.1.2.2
I_i
liability measurement contracts3.1.3.5
at practical completion 4.1.3.1(a);4.1.3.2(c) mechanical and electrical (M & E) services 2.2.1.7;Part 4
determination of4.2(Intro) Section 1: Appendix A9
see also limitedliability minorworks4.1.2.6;4.1.2.15
life cyclecost mitigation4.2.3.1(e)
appraisal2.2.5.6(a)
payments 2.2.2.4 N
techniques 2.2(Intro) NamedSub-contract NAM/SC 4.1.2.3(e)
life cycle costing 1.2.10.l(c)(d); 2.1.1.2(d); 2.1.4.2; 2.2; NationalInsurance 5.4.7
3.1.1.10; 5.5.1 negligence2.4.3.1; 2.4.3.7
buildinglife 2.2.2.1 new building3.1.2.1
client context2.2.1 New EngineeringContract(NEC)4.1.2.17;4.1.6.4(d)
costingcalculation 2.2.2 new-build 2.1
costs and values Part 2 Section 2: Appendix C NJCC 2.4.4.10; Part 2 Section 4: Appendix A(Intro);Part3
data sources 2.2.4 Section 1:AppendixA
obsolescence 2.2.1.8; 2.2.2.1; Part 2 Section 2:Appendix B no risk returndiscountrate 2.2.2.3(b)(d)
residualvalues 2.2.2.1; 2.2.2.4(g); Part2 Section 2: NominatedSub-contract NSCIC4.1.2.2
AppendixA, C6 novation2.4.6
tax allowances
examples Part2 Section2:AppendixE 0
incentives and businessrates2.2.3 obsolescence 2.2.2.1; Part2 Section 2: AppendixB
tax relief, impacton 2.2.3 obsolescent properties2.2.1.8
terms for taxation Part2 Section 2:AppendixD occupancy 1.2.13; 5.5.5
worked examples 2.2.5 occupancy costs2.2.2.4(f);Part 2 Section 2:AppendixCS
life cycleinformation 2.1.5.5(c) occupation 3.1.1.16
life cycleperiod, mechanical and electrical 2.2.1.7 beneficial 4.1.4.2;4.1.4.4(c)
limitedliability3.1.2.9(g) prior to completion 4.1.6.4
liquidateddamages3.1.2.9(m); 4.1.4.3(c);4.1.4.4(e); readinessfor 4.1.3.6(d);4.1.4.2
4.1.5.3; 4.1.6.5(b)(c) offeringup 4.1.1.3(a); 4.1.2.17(a)
local authorityrequirements Part4 Section 1: offices,centralisation of2.2.5.5
Appendix A2.3 operationofthe building3.1.1.16
loss in buildingprojects4.2 operationcosts2.2.2.4(c);Part 2 Section 2:AppendixC3
lump sum contracts2.4.2.1; 4.1.2.20(a) operatives 5.4.10
lump sum price2.3.3.1(c);3.1.2.5; 3.1.2.9 options
appraisal criteria1.2.3.1(a); 2.2.1.2; 2.2.2
M building 2.2.5.2;2.2.5.6
machineiy see plantand machineiy choiceof3.1.2.lO; 3.1.3
maintenance and repairs5.5.3; 5.5.4 design2.2.5.1; 2.2.5.2
maintenance, costed planned2.2.5.4 maintenance 2.2.5.3
maintenance costs2.2.1.4; 2.2.2.4; 2.2.3(Intro); 2.2.3.2; organisational structure3.1.5.6
2.2.5.5(b)(c); Part 2 Section 2: AppendixC4, D2 organisations 5.2
annual 2.2.2.4(d); Part 2 Section 2: Appendix C4 outlineproposals stage 2.1.4
cyclical 2.2.5.5 overheads 2.2.1.6;4.2.5.8;Part 4 Section 2:AppendixC
example2.2.5.1(c) overlap3.1.2.8(b)
future 2.2.1.4 overrun3.1.2.9(c)
intermittent 2.2.2.4(e); Part 2 Section 2:AppendixC4 cost 3.1
tax relief2.2.3 time 3.1
maintenance ofthe building2.2.1.4; 3.1.1.16 over-specification 3.1.2.11(i)
maintenance option, life cyclecosting(worked example) overspending 3.1.1.8(j)(k)
2.2.5.3;2.2.5.6(h) overview see change control overview; costcontrol overview;
makinggood 4.1.1.3(d) designoverview; quality controloverview; time control
Management Contract 3.1.1.4; 3.1.2.5; 3.1.2.9; 4.1.2.8—4.1.2.9 overview
management contracting 3.1.3.7 owneroccupiers 1.1.1.3—1.1.1.4
manuals Part4 Section 1: Appendix Al0
marketconditions 3.1.1.8(1) P
marketsand marketing 5.3.1 pace 3.1.5.8(e)
materials 2.2.1.4;2.2.2.4;4.2.5.6; Part 4 Section2: packaging deal 2.4.5.2
AppendixA4, BI.3 parameters, quantityand quality 2.1.3.5;2.1.4.15;
matter4.2.1.15 2.1.5.1—2.1.5.3;2.1.5.5;2.1.6.3
measurement seequantities Parry's Valuation and InvestmentTables 2.2.5.7
18
partial possession 4.1.2.4(c); 4.1.2.18(a)(d); 4.1.6.4(j); privatesector3.1.2.7
4.1.6.5(b) proceedings, rightto bring4.1.3.2(a)
partnering1.1.6(c); 1.1.8 processstart-up4.1.2.20(c)
patent defects4.1.5.2; 4.1.5.3 procurement
payments see fees; interim payments; life cyclecost options2.4(Intro); 3.1; 3.1.3
payments process 1.1.2.2; 1.1.4.2; 1.1.4.5
perfectcompletion 4.1.4.3;4.1.4.4(e) publicsector 1.1.8.3; 3.1
Europe 4.1.4.3(b) routes2.1
France4.1.4.3(b) strategy 1.1.7.1;2.4(Intro); 3.1.1.4; 3.1.2; 3.1.2.9; 3.1.2.10
see also fault free works development of3.l; 3.1.1.3;3.1.2
perfection, impossibility of4.1.5.1(d) selection of3.1.4
performance 2.4.4.4; 2.4.4.5; 3.1.2.11(i) professional advice3.1; 3.1.1.6
performance bonds4.1(Intro) professional adviser3.1.1.11(c)
performance criterion3.1 .2.8(b)(c) professionaljudgement4.2.1.9;4.2.4.5
performance failure3.1 professional services 5.3.1
performance requirements Part 2 Section4: Appendix B2.4 profit, loss of4.2.5.12; 4.2.5.13
performance risk 3.1.2.9 profit margins 3.1.1.8(1)
performance tests4.1.2.20(c) profittarget4.2.3.1(f)
periodicpayments 2.3.3.1(e) programme 3.1.1.9(a);3.1.5.8(e)
PFI see Private FinanceInitiative(PFI) progresssee stages ofa project;updating
physicalresources 3.1.5.5 projectbriefl.1.3; 1.1.5.3(a);3.l.1.1l;3.1.1.l3
pipework2.1.5.4(b) projectcharacteristics 3.1; 3.1.2.11(d)
plannedmaintenance, costed 2.2.5.4 project cycle3.1.2.10; 4.3.3.2
plannedmaintenance programme 2.2.5.4 projectevaluation 1.2.13
PlanningSupervisors 5.2.1 projectfunder(s) 1.1.5.3(b)
plant and machinery2.2.3.7;Part 4 Section 2: AppendixA3, project management 1.1.4.3; 1.1.5.2; 1.1.5.3(g); 4.3.2.3;
A4, A6, B1.2, D5 4.3.3.2
plantprojects4.1.2.20(b) Project Manager 1.1.4.2; 1.1.4.5; 1.1.6; 2.4(Intro); 3.1.2.8;
plantingPart 4 Section 1: Appendix A8 3.1.2.9; 4.1.2.17(c);4.1.2.19(d)
possession 4.1.2.17(c); 4.1.3.1(b); Part 4 Section 1: project monitoring 2.4.3.3
Appendix A3 projectobjectives 1.1.5.1(a); 3.1.1.11; 3.1.2.8;3.l.2.ll
fitness for 4.1.5.1 projecttesting 3.1.1.2
see also earlypossession; partial possession project type 1.1.2.2
practical completion project uniqueness 3.1.1.2
case decisions Part4 Section 1: AppendixB protection and safe practice5.1
definitions of4.1.4.2(a);4.1.5 provisional certificate4.1.4.4(c)
effects of4.1.3 PSAII (June 1994)4.1.2.11
methods 4.1.4 public, protection of5.1
objectives Part 4 Section 1: Appendix A publicsectorseeprocurement, publicsector
problemsof4.1 publicationsPart 2 Section 1:AppendixD; Part 3 Section 1:
standard formsand certification 4.1.2 Appendix B; Part 4 Section 1: Appendix C; 5.1
subsidiary issues,determination of4.1.6
see also earlycompletion; substantial completion Q
Practice notes 2.3.3.1; 2.4.2.3; Part 3 Section 1:AppendixA quality see parameters, quantityand quality
practicepanels 5.3 quality assurance 3.1.1.13(c)
Practicestatements 5.3.1 quality control 2.4.3.4; 3.1.5.8(f)
preliminaries Part 2 Section 3: AppendixA7;4.2.5.2; quality controloverview3.1.1.13
4.2.5.3;Part 4 Section 2: Appendix A; 5.4.5 quality/price mechanism 1.1.7.4
prescriptive requirements 2.4.4.4; Part 2 Section 4: quantities 2.1.4.4
Appendix B2.5 approximate 2.1.5.4(a);2.1.6.3
price premiums 3.1.2.9(c) see also element unit quantities
prices4.2.4.8;5.4.11; 5.5.3 quantity see parameters, quantity and quality
construction 3.1.1.8(1) quantity surveyor2.1.4.6;2.1.6.4
tender3.1.1.8(1) ascertainment by 4.2.4.2; 4.2.4.3; 4.2.4.4
pricing 1.2.8; 2.1.5.4(a) role of2.1; 2.1.1.3; 2.1.1.4;4.2(lntro)
pricingand risk 3.1.2.9(i) quantity surveyor's considerations Part 4 Section 2:
PrimeCost Contract4.1.2.7 Appendix B3, C3.2, C4
principal adviser 3.1.2.9(f) quantitysurveyor's information 2.1.3.3; 2.1.4.3;2.1.5.3;
role of 1.1.2; 1.1.4.5; 1.1.7.1;3.1.l.5;3.l.1.10 2.1.7.3; 4.2.6.5;
PrivateFinanceInitiative(PFI)2.2.1.5 Part 4 Section 2: AppendixB2
19
R ProbabilityI Impact matrix4.3.3.4
rebuild,costing2.2.5.6 workshops 4.3.2.5;4.3.3.3(a)(i)(b)(iv); 4.3.3.4(b)
receivership4.1.6.1(a) see alsouncertainty
records ofcosts 4.2.1.9; 4.2.1.11; 4.2.5.4(b); Part 4 risk profile 4.3.3.4
Section 2: Appendix C2 risk reduction 3.1.2.9(h)
rectification ofworks4.1.3.1(f) risk register 4.3.1.7;4.3.3.3(b)(v)(vi)
Red Book 4.1.2.20(a)(c) risk response4.3(Intro); 4.3.1.5;4.3.3.1;4.3.3.5
redevelopment 2.2.5.6(g) risk taker3.1.2.9(j)
refurbishment 2.1; 2.2.1.6;2.2.3;2.2.5.5;2.2.5.6; Part2 risk transfer3.1.2.9
Section 2: Appendix B5; 3.1.2.8(a) Royal InstituteofBritishArchitectsPart 3 Section 1:
regional development grants 2.2.3.2 Appendix A
regulations 5.2.1 Royal Institution ofChartered Surveyors Part 3 Section 1:
reimbursable contracts4.1.2.20(a) AppendixA
reimbursement 4.2(Intro); 4.2.15;4.2.4.5; 4.2.6.1 running charges4.2.5.3(d)
contractural entitlement 4.2.1.2;4.2.1.5; 4.2.3.1 runningcosts2.2.5.1(b)
documents 4.2.3.4
entitlement to4.2.3 S
extensions oftime 4.2.3.2
safety
ofsubcontractors 4.2.3.6 checklist5.1
submission cost 4.2.6.1(b); 4.2.6.4;4.2.6.5
legal duties5.1
writtenapplication4.2.3.3 see also health and safety
relationships (time, quality, cost) 3.1.1.9(g) Safety File Part4 Section 1: AppendixAl0
removalcosts4.2.5.3(b) saving2.1.6.4;3.1.1.8(j); 3.1.1.14(g)
renewalcosts2.2.5.5(g)
scaffolding Part 4 Section 2: Appendix A7
replacement costs 2.2.1.7; 2.2.2.4;2.2.3.4;2.2.5.1(d); Part 2 schedule ofdefects4.1.2.6(d)
Section 2: Appendix C4
Schedule ofRates 5.5.3
research 4.3.3.3(b)(i)(ii)
schemedesignstage 1.2.3
resequencing 3.1.1.9(g)
residualvalues 2.2.2.1;2.2.2.4(g); Part 2 Section 2: security Part4 Section 2: Appendix AS
selection process3.1.1.3; 3.1.2
AppendixA, C6
resources 3.1.5.3—3.1.5.5 sensitivity analysis 1.1.5.3(f); 2.2.5.5(i);3.1.1.8(c)
sequential seetraditionalstrategy
responsibility service engineer's information 2.1.3.3(e); 2.1.4.3(d);
additional Part 2 Section 4: AppendixB2.6
allocation of3.1.2.5;3.1.2.9 2.1.5.3(d)
services
delegated 1.1.6.3(b) mechanicaland electrical(M & F) 2.2.1.7
see also consultant; contractor; employer's
responsibilities provisioncostsPart 4 Section2: Appendix A8, A9
retail buildingsPart 2 Section 2: AppendixB5 standardelementsPart 2 Section3: AppendixAS; Part 2
retention 4.1.3.1(d); 4.1.4.4(e); 4.1.6.5(b) Section4: Appendix B2.5.5
Rethinking Construction I.2(Intro); 1.2.2.2 setting-up costs 4.2.5.3(a)
re-usable materials Part 2 Section 2: AppendixA4 shelland core contract 3.1.2.6
revenue allowances2.2.3.4;2.2.3.7 sinkingfund 2.2.2(Intro) 2.2.5.4
revenue costs 2.2.5.5(c) valuationand investment table 2.2.5.7
revenue expenditure Part2 Section2: Appendix D2 site cost Part 4 Section 2: AppendixA
RIBA PlanofWork 2.1.1.4 site meetings4.2.3.3(c)
RICS BuildingCost Information Service (BCIS) 2.1.3.4(b) site visits 5.1
risk 2.4.3.7; 3.1.1.8(m); 3.1.2.9; 4.3.1.1;4.3.2.9 snagging4.1.1.3(f)
residual3.1.2.9(1) snagginglist4.1.1.3(b)(c); 4.1.5.4
risk allocation 2.4.3.9;3.1.2.5; 3.1.2.9 specialistservices2.1.5.4(b)
risk analysis 3.1.1.8(c); 4.3(Intro);4.3.1.4;4.3.3.1; specification 2.3.3.1(b); 2.4.4.5; Part 2 Section 4:Appendix
4.3.3.3(a)(ii); 4.3.3.4 B2.3, B2.5; 3.1.1.13; 3.1.2.9(h); 3.1.3.9(f)(g)
risk assessment 5.2.1 squareindex Part 2 Section 1: AppendixC
risk averse 3.1.2.9(j) staffcost Part 4 Section 2: Appendix Al, All,C3
risk distribution 3.1; 3.1.2.9(m) stage payments 2.3.3.1(e)
risk identification 4.3(Intro); 4.3.1.3; 4.3.3.1;4.3.3.3 stages ofa project3.1.1.8(g)
risk management 3.1.2.9(j); 4.3(Intro); 4.3.1.2; 4.3.4 standardcontractssee contracts
assessment 4.3.2.6—9 standardelementssee BCISstandardelements
benefits 4.3.2.1;4.3.2.8 standardrules and practices 3.1.1.2
in construction process 4.3.2 standards and requirements 2.4.4.5
definitions 4.3.1 standardsand tests 4.1.4.1(d)
plan 4.3.1.6;4.3.3.2 statutorycontrols3.1.2.9(c)
Page 8 Index (12/99) Effective from 1/1/00 The Surveyors' Construction Handbook
20
statutoxyrequirements Part4 Section 1: Appendix A2 designand build 2.4.4.10
storage4.1.6.5(a) timeof3.1.I.8(l)
straightline allowances2.2.3.2 two-stage 2.4.5.4
Structural Engineer'sinformation 2.1.3.3.(e);2.1.4.3(d); tenderdocuments3.1.1.6(b)
2.1.5.3(d) changes from initial2.1.7.1
structurePart 4 Section 1: Appendix A5 tenderprice index5.4.5
subcontract completion 4.1.2.16 tenderproposals, evaluation of2.3.3.1(d)
Subcontract DOMI24.1.2.3(e) tenderstage 2.1.7
subcontract work4.1.2.2—4.1.2.3;5.4.5 termination 4.1.2.17(b)
subcontractors 3.1.2.9(g); 4.1.3.3 test discountrate 2.2.2.3(a)
domestic 4.1.2.3 tests
named 4.1.2.3(e) atcompletion 4.l.4.1(f)(g)
nominated4.1.2.2; 4.2.3.6; Part4 Section 2: Appendix B3.1 ofplant 4.1.4.1(f)
submission cost 4.2.6.1(b); 4.2.6.4;4.2.6.5 seealsostandards and tests
submissions 4.2(Intro); 4.2.4.3; 4.2.6.1;4.2.6.4; Part4 thirdparty events 3.1.1.8; 4.3.3.5(b)
Section2: Appendix D time 'atlarge' 4.1.6.3(b)
checklist Part4 Section 2: Appendix E timebudget 3.1.1.9(d)
substantial completion 4.1(lntro);4.1.1.3(f); 4.1.2.12; timechecklist3.1.4.3
4.1.2.13; 4.1.2.16; 4.1.5.1(f) timeconstraints3.1.1.9(i)
substantial performance 4.1.5.1(e);4.1.6.4(g) timecontingency3.1.1.9(i)
substructure Part 2 Section 3: Appendix Al; Part2 Section
timecontroloverview3.1.1.9
4: Appendix B2.5.1 timecost models3.1.2.11(h)
superstructure Part 2 Section 3: Appendix A2; Part2 timecriterion3.1.2.8(b)
Section 4: Appendix B2.5.2
timeframework 3.1.1.9(a)
Supervising Officer 4.1.2.18 timeplan 3.1.5.8(e)
supervision 5.1 timerisk 3.1.2.9
surveying and safe practice5.1 timescale 3.1.2.2
Surveying Safely 5.1
timing 3.1.2.11(g)
Surveyor 1.1.1.1
traditionalstrategy3.1.1.4; 3.1.2.5; 3.1.2.9; 3.1.3.4
professional judgement4.2.1.9;4.2.4.5
transfer ofbuilding 4.1.1.3(e)
sustainability see building sustainability
TreasuryBonds 2.2.2.3(b)(c)(d)
systems and controls 3.1.5.8
turnkey2.4.5.2
T two-stagecompletion 4.1.4.4
take-over3.1.1.16 two-stage tender2.4.5.4
takingover 4.1(Intro); 4.1.2.10; 4.1.2.17(b); 4.1.2.20(b) U
taking overcertificate 4.1.2.20(c)
tax allowances 2.2.3 ultimate cost3.1.2.2
applications 2.2.3.6 uncertainty 4.3.2.3
see also risk
categories defined Part 2 Section 2: Appendix D3
expenditure, examples ofPart 2 Section 2: Appendix E underpricing 4.2.3.1(a)
glossary ofterms Part 2 Section2: Appendix D uniqueness3.1; 3.1.1.2
unit quantities see elementunit quantities
types2.2.3.2
variables2.2.3.5 unit ratesPart2 Section 1: Appendix A2.1; A2.2
worked examples 2.2.3.7; 2.2.5.5(f); 2.2.5.6(h) updating3.1.1.7(e)
tax reliefsee tax allowances user functions1.2.7.5; 1.2.7.6; Part I Section 2: Appendix A
taxation user requirements 3.1.1.8
glossary ofterms Part 2 Section 2: Appendix D
issues and adjustments Part 2 Section 2:AppendixAS, V
A6, A7 valuationand investment tables(Parry's)2.2.5.7
seealsoCorporation Tax; VAT (Value Added Tax) value addedtax see VAT (Value Added Tax)
team 3.1.1.2 value categories Part 2 Section2: Appendix C
team development 4.3.2.5 value engineering 1.2(lntro); 2.1.1.5;2.2.1.2;3.1.1.12
temporaryaccommodation Part 4 Section 2:Appendix A2 applicability 1.2.2
temporary disconformity 4.1(Intro) implementation ofthe exercise1.2.4; 1.2.5; 1.2.12
temporary services Part 4 Section 2: Appendix A8, A9 process Part I Section2: Appendix B
temporary works/access Part 4 Section 2: AppendixA4 timing 1.2.3
tender use and function 1.2.1
acceptance of2.1 workshop 1.2(lntro); 1.2.3.1; 1.2.4.4; 1.2.5; 1.2.6;
cost2.3.2.2 1.2.9—11
21
value engineering panel 1.2.4;L2.6.2;-1.2.11.3; 1.2.12.1 waste4.2.5.6
value management 1.2(Intro); 1.2.1.2; 1.2.3.1; 3.1.1.11 water testing Part4 Section 1: Appendix A6
value management facilitator1.2(Intro); 1.2.4.1; 1.2.4.3; With Contractor'sDesignForm 4.1.2.3(e); 4.1.2.5
1.2.4.4; 1.2.6.2; 1.2.10.1(b)(c)(d) workedexamples
value for money 1.1.7.4; 1.2(Intro); 1.2.1.3; 3.1.1.6(c); life cyclecosting2.2.5
3.1.1.14(g) tax allowances 2.2.3.7
values, monetary see discountrate; discounting works
variation works2.4.5;4.1.3.1(f); 4.2.4.10(c); 4.2.5.4(e) outstanding4.1.1.3(f); 4.1.2.10(b); 4.1.2.12(c); 4.1.2.13;
VAT (\Talue Added Tax)1.2.8.2; 2.1.3.2(a); 2.2.3.3; 2.2.5.5(f); 4.1.2.15(c); 4.1.4.2(c);4.1.4.3(a);4.1.5.1(f)
2.4.6.1 packages2.4.5.2;3.1.2.5
vesting 4.1.2.18(d) workshops
risk management 4.3.2.5; 4.3.3.3(a)(i)(b)(iv); 4.3.3.4(b)
w value engineering l.2(Intro);1.2.3.1; 1.2.4.4; 1.2.5; 1.2.6;
wage rates 5.4.7 1.2.9—11
wallto floor ratio Part 2 Section 1: Appendix C 'writingdown'allowance Part2 Section 2: Appendix D7
warranty 3.1.2.9(g) writtenapplication for reimbursement 4.2.3.3; 4.2.6.1; 4.2.6.4
warranty contracts3.1.1.5(b) writtendown value Part2 Section 2: Appendix A6
22
INTRODUCTION
INTRODUCTION
Al The aim of this Handbook is to help both building and quantity surveyors
to provide construction-related professional services effectively and effi-
ciently. It seeks to achieve this by providing guidance which reflects what
is often good custom and practice, and relevantinformation(including ref-
erences to other useful material). It should be appreciated that this
Handbook does not attempt comprehensive coverage of necessary or good
practice. The Handbook is addressed to surveyors providing services to
clients (as defined),not surveyorsundertakingthe role of the client's repre-
sentative who gives instructions to surveyors on behalf of the Client.
B Arrangement of Content
I '.
INTRODUCTION
C Status of Content
Members are not required to follow the advice and recommendations con-
tained in such paragraphs. They should, however, note the following
points.
D Currency of References
The cases cited andthe editions quoted were up-to-date at the time ofwrit-
ing. However,readers should check currentrulings andadditions.
E Invitation
F Subscription Service
25
INTRODUCTION
The Surveyors'ConstructionHandbookSubscriptionService
RICS Books
SurveyorCourt
Westwood Way
CoventryCV4 8JE
1.1.1.1 Client satisfaction will be maximised if the surveyor's advice and actions
reflectthe client's objectives in respect of the project.These objectivesmay
have been defined explicitly as requirements.If not, the surveyorshould be
able to assist with this and, in any event, raise the question with the client
or his appointed representative, although the scope for the surveyor to
reflectthese requirements in his services will dependin part upon the stage
at which the surveyor has been appointed.
1.1.1.2 The type of client will affect the criteria which must be met if the client is
to be satisfiedwith the project.
1.1.1.3 Owner occupiers are usually primarily concerned with building perfor-
mance in terms of functionality and costs in use. They may also be con-
cerned with image and building style. In this sense, value for money is a
keycriterion.Developers, on the other hand, may be drivenby market con-
ditions which enable the project to be let or sold at maximumcommercial
advantage. They may be predominantly concernedwith speed rather than
performance.
1.1.1.4 This is not to say that owner occupiers are unconcerned about time. Indeed,
certainty of completion date may be a key issue. Nor is it fair to suggest
that developers are unconcernedaboutbuilding performanceor cost. There
are market conditions where both ofthese issues maybecome important.
(a) Cost-related
• minimise capital cost
• maximise capital cost/value ratio
• maximise
capital cost/worthto client ratio
• achievenecessary income cash flow profile
• minimise
management costs
• minimisemaintenance andinsurancecosts
• minimisetax liability
• respectcapitalcostconstraint
• be energy efficient
27
PART 1, SEcTION 1
(b) Marketability
• maximiseprompt or future disposal (freehold or otherwise)
(c) Use-related
• optimiseoperationalrequirementsof intended occupier(s)
• providegreatest flexibilityin potentialuses
• reflectintended occupier's requirements/preferences/abilityto afford
• meet social/management/occupier'sspecial needs (e.g. disabled)
(d) Environmental
• minimisehealth andsafety risks
• choose materialswhich reflect sustainability
• aestheticallyplease (e.g. impression on occupier's customers)
• minimiseany alterationsto specific features
• reflectplanningauthority's brief/policies
• minimisepotential opposition
• reflectcorporate style or personal preferences of proposed occupier/
employees
• maximisecomfort of occupants
• minimiseinconvenienceto others during construction
(e) Timing
• constructwithin a defined period
• minimiserisks of delay during construction
1.1.1.6 The importanceof each ofthese criteria will be relative to the objectives of
the client andto the extent to which he is able to cope with risk. It is impor-
tant that the clientseek investmentappraisal advice in respect ofthe project
and that the appraisal considers 'what if' questions to ensure that the
impact of changes of key components in the appraisal is clearly under-
stood.A charteredsurveyorwill be ableto assistthe client in these matters.
However,the giving of advice on some of the requirementslisted above is,
of course, outsidethe competenceof the surveyor.Where such a particular
requirementis importantto the client and outside the client's expertise, the
client shouldbe advisedto seek other professional advice.
1.1.1.7 The C1 believes thatmany construction projects suffer from poor defini-
tion due to inadequatetime andthought being given at an early stage. This
is often because there is a sense of urgencyfuelled by the desire for an
immediatesolution.Investingtime at the beginning of a projectin develop-
ing a completedefinitiontaking account of all the requirements will reduce
the likelihoodof changeslater. The later that changesare madein a project,
the more they are likely to costin both direct andknock-on effects.
1 cm
(1997),Briefing the Team,ThomasTelfordPublishing,London
1.1.2.1 With the potential for the involvement of many consultants and/or con-
structors in a project and the range of contracts associated with their
employment, all but the most experienced client may need advice. The
advice offered should be informed and unbiased and it should be based
upon a logical analysisof the needs of the client, the type andcharacterof
the project and the range of appropriate strategies available.
1.1.2.2 This advice can be offered by a member of the client's design team or can
be a separatefunction. It may be more difficult for a design team member
to remainimpartialin carrying out this process and it is recommended1 that
any expert retainedshould be solely for this purpose.This functioncan be
identifiedas the role of the principal adviserandmay encompass:
(b)identifyingthe characteristics
ofthe project (projecttype)
(c)matchingneeds andproject
characteristics with
appropriateprocurement
strategy (procurementprocess)
1.1.2.3 Possible sources for the appointment of a principal adviser include a suit-
ably qualified and experienced construction professional such as a char-
tered surveyor.
Latham, M., Sir (1994), Constructing the Team: Joint Review of Procurement and Contractual
Arrangementsin the UnitedKingdom ConstructionIndustiy Final Report,}iMSO, London.
29
PART 1, SECTION 1
(a) projectdescription;
(b) how it fits into the client's corporate plan (e.g. it may be part of a larger
planned development);
(c) number of people that are to occupy the building, together with their
space requirements;
(e) standards;
4) 1.1.3.2 This is the initial control document for the early planning of the project;
without it, little constructive work can be done. If all the information
required for the project brief is not readily available, it is better to issue it
in an incompleteform andto updateit progressively1.
.4) 1.1.4.2 The success of any project will depend upon the motivation given by the
client. Experiencedclients maytake a leading role in the procurementpro-
cess; less experiencedclients will need to seek advice or to appoint a prin-
cipal adviserto assist them. Where projects are of a large or complexnature
it may be advisable to considerthe appointment of aproject manager.
'Kelly, J., MacPherson, S. andMale, S. (1992), The BriefingProcess:AReview and Critique, RICS,
Department ofBuildingEngineering and Surveying, Heriot WattUniversity. Thisdocument is outof
print.
Value Management(03.1.1.11)
Procurement ProcurementStrategy
Strategy (3.1.2) Development(3.1.2)
Systemsand Controls*
(03.1.5.8)
ImplementationPolicy
(03.1.5.2)
* Indicatesthe activitywill continue in thenext phase
Indicates thesectionofthis document referringto activity
1.1.4.4 The client has substantial influenceon the design of the project in respect
both of functionalefficiency and of overall appearance, and, therefore, has
to take particularcare to:
(a) understand fully the purpose of the building; ensure that the require-
ments of the users are accommodated; and communicate those require-
ments to the designers; and
satisfy users' requirements and harmonise with and contribute to the quality
of the built environment.The selectionof the right people is emphasised as
a key to success.
1.1.4.5 The accompanying figure indicates the activities in the procurement pro-
cess andwhen activities are usuallyperformed.As can be seen, the client's
role is significant, with a wide range of activities to perform and implement
before both the design and the constructionprocesses. In the performance
of these activities, the client can expect to be supported and advisedby the
principaladviseror (if appointed)the project manager.
(d) controllingtheirimplementation;
(a) the project brief is comprehensive and clear and has the full support of
the users1;
(b) any constraints demandedby the project funder(s) are known and their
impact understood;
1
Kelly, J., MacPherson, S., and Male, S. (1992), The Briefing Process: A Review and Critique, RIICS,
Department of BuildingEngineering and Surveying, Heriot Watt University. This documentis out of
print. CIB (1997), Briefing the Team,Thomas Telford Publishing, London.
3L
PART 1, SECT!ON 1
(d) cost estimates are comprehensiveand include all capital and resource
costs;
(g) plans are in place for adequate project management including systems
for cost, time, qualityandchange control.
1.1.5.4 The client should also co-ordinate and resolve conflicts between all inter-
ested sections ofthe client organisation including:
(d) finance and accounts— who will plan and control expenditureand pay
bills as they arise; and
(e) legal advisers— whowill adviseon and monitor the client's formalrela-
tionships with outside parties.
1.1.5.5 The client is responsiblefor ensuring that all necessary decisions are made
on time. Timely decisions are necessary to avoid delays and increased
costs: the decision-making process requiresas much planningand manage-
ment as any otheractivity. This will include:
33
PART 1, 1
1CTION
1.1.6.1 Due to the complexity of modem buildings and the potentially large
number of parties involvedin the process the client may wish to appoint a
single person to draw the process together and manage it to ensure that the
overall performance, time, costandquality requirementsare achieved. The
project manager may be a member of the client organisation who is given
sole, or predominant, responsibility for the project. Project management
practices also exist to enable appointment to be made on a consultancy
basis. In this case, selection should be based upon resources, reputation,
andprice; andservicesshouldbe clearlyidentified.
1.1.6.3 The client's role upon the appointment of a project manager should
include:
(h) maintaining with the project manager at all times an overview of the
project status in relationto the establishedobjectives.
34
PART 1, SECTION 1
1.1.6.4 The client's relationshipwith a project manager will be crucial to the suc-
cess of the projectandwill requirecareful developmentandnurturingwith-
in the following guidelines:
(a) the client, though taking the project manager's advice, shouldlead, not
follow;
(c) the client should agree with the project manager the precise extent of
anydelegated authority together with those decisions reserved to the client;
(d) where a project manager has been appointed, the client will not form-
ally communicate directly with consultants and contractors employed on
the project: suchcommunications willalways be routed throughthe project
manager, although the contracts willbe direct with the client; and
(e) no matter what may be said in private, the client should publicly sup-
port the project managerandavoidany actions which couldunderminethat
manager's authority over the consultants andcontractors.
1.1.7.1 The process of selecting and appointing the design team and the cost con-
sultant is carried out by the client, but he may seek the advice of his prin-
cipal adviser. Theterms and conditions oftheseappointmentsare governed
by the procurementstrategy adopted forthe project.
1.1.7.2 The followingalternativesexistin selectingthe design team:
1.1.7.3 The selection of the design team and cost consultant (and otherconsultants
as appropriate) will require the client making a balanced judgement on the
followingfactors,listed in order ofpriority:
(a) capability — the experienceof the firm in projects of similar size and
function and the availability within the firm of sufficient, uncommitted
resources for it to meet the demandsof the project; the demands ofthe pro-
jectprogrammemay be particularlyimportant;
(c) staff— the personalcapability and experienceofthe key staff whom the
firm proposes to employ on the project; and
(d) the cost — quoted by the firm; unless large differences exist between
offers from competing firms, this factor should not be critical.
1.1.7.4 Value for money, not lowest price, should be the aim in the selection of the
design team members. The Cm's Selecting Consultants for the Team:
Balancing Quality and Price' provides guidance on establishing a quality!
pricemechanism.
1.1.7.7 Percentage fees based on the out-turn construction costs are not generally
recommendedas they increase when cost overruns occur.
1.1.7.8 Lump sum fees may be the most satisfactory form of remuneration pro-
videdonly that the scope, value and timescale ofthe project can be established
CIB (1997), Selecting Consultants for the Team: Balancing Quality and Price, Thomas Telford
Publishing, London
2 Construction Industry Council (1994), The Procurement ofProfessional Services: Guidelinesfor the
Value Assessment ofCompetitive Tenders, CIC,London
36 Part 1, Seàtion 1(4/98) Effective from 1/6/98 The Surveyors' Construction Handbook
PART 1, SECTION 1
with reasonable accuracy before the appointments are made and that the
servicesto be providedby the consultants can be accurately defined. Where
lump sum fees are to be paid, the client will need to establish systems for
monitoring the consultants' performance to ensure that they provide the
full, specified serviceand do not skimp theirservices to save money.
1.1.7.9 Where time charge fees are to be paid, the final amount of fees payable is
not fixed and there is a substantialrisk that this amount may exceed initial
estimates.
1.1.8 Partnering
1.1.8.1 In recent years there has been much interest in the application of 'partner-
ing' in the constructionindustry. The CIB definesthis "as a structuredman-
agement approachto facilitate teamworkingacross contractual boundaries.
Its fundamentalcomponents are formalisedmutual objectives, agreedprob-
lem resolution methods, and an active search for continuous measurable
improvements". The CB advises that partnering should not be confused
with other good project management practice or with long-standingrela-
tionships, negotiated contracts or preferred supplier arrangements,all of
which lack the structureand objective measures that must support a part-
nering relationship.
1.1.8.2 The CIB states that the critical factor for partnering is the commitment of
all partners at all levels to make the project a success. The result is that the
partnering agreementdrives the relationshipbetween parties rather than the
contract document.
1.1.8.3 The CIB has published a report, Partnering in the Team1, the purpose of
which is to promote the uptake of good practice in partnering between
client and supplier at any point in the supply chain. The report provides a
guide to the disciplined frameworkof partnering, and describes five good
examples which were on site at the end of 1996. It is not a code ofpractice,
as there wasinsufficientexperience of its application in construction at that
time. Nor does it provide detailed step-by-step guidance at the working
level, because the working group identified two other reports well suited
for this purpose: the Reading Construction Forum's Trusting the Team2,
andthe EuropeanConstructionInstitute's Partnering in the Public Sector3,
endorsed by NM Treasury, the DoE, the National Audit Office and the
Audit Commission. This latter report is significant as it demonstrates how
partnering should be applied to projects after award of contract — hence
complyingwith the BC andUKregulations for public sector procurement.
The Surveyors' Construction Handbook Part 1, Section 1(4/98) Effective from1/6/98 Page 11
PART 1, SECTION 1, APPENDIX A
Appendix A: FurtherReading
CIB. Selecting Consultantsfor the Team: Balancing Quality and Price, Thomas
TelfordPublishing,London, 1997
Introduction
The Surveyors' Construction Handbook Part 1, Section 2 (12/99) Effective from 1/1/00 Page 1
39
PART 2
1,SEcTIoN
1.2.1.1 Value engineering has grown in popularity for the simple reason that it
actually works. Construction projects can often take on a life of their own
when membersof the design team become focused on their own particular
problems andtime constraints. Consequently, the true objectives ofthe client
get lost along the way. Value engineeringrelates design proposals directly
backto a client'sbusiness,thus ensuring that amanagement systemis inplace
which forces designers to justify their decisions when tested against the
client's requiredfunction.
1.2.1.2 A value engineering exercise can only relate design proposalsto a client's
businessrequirements ifearly value managementstudies have encapsulated
these requirements withinthe brief.Ifa value engineering exercise is carried
out in isolation from any strategicreview ofthe project requirements, it can
only act as a functional assessmentofthe technicaldesign solutions andtheir
relative cost. However, even in thislimitedfunctionit can still be very useful.
1.2.2 Applicability
High
Essential
Complexi
Optional
Low
Low High
Value
Page 2 Part 1, Section 2 (12/99) Effective from 1/1/00 The Surveyors' ConstructionHandbook
40
PART 1, SECTION2
1.2.3.1 The value engineering exercise should be carried out as early in the design
process as is appropriate to the size andnature ofthe project. For example,
when an experienced client has prepared the brief, or a value management
exercise has already examined the client's requirements, the value
engineering exercise (which will address the proposed design solutions) is
best done towards the end ofthe 'scheme design'. In other circumstances, it
may be usefulto examine the client'srequirements at an earlierstage. Several
workshopsmaybe necessaryat each ofthe crucial decision-making stagesof
a project:
1.2.3.2 This section of the handbookconsiders the evaluation ofa design at the end
of the scheme design phase, but the objectives and the process will be the
same whenever it is carried out.
1.2.3.3 It is importantthat time for the value engineeringprocess and any resultant
redesignis included in the scheme designprogramme at the outset.
The Surveyors' ConstructionHandbook Part 1, Section 2 (12/99) Effective from 1/1/00 Page 3
41
PART
1,SEcTIoN
2
1.2.4.3 The optimum size ofa value engineeringpanel would dependupon the size
•
and complexity ofthe project as well as the skills ofthe facilitator. However,
it is considered that panels of more than twelve members are difficult to
manage and should be avoided except in exceptional circumstances. Panels
with fewer than four members couldbe consideredineffective.
1.2.5.2 The '40-hour workshop' is the classic industrial value engineering standard.
However, two-day workshops at key points during the design process are
more commonin the UKconstruction industry.
1.2.6.1 Prior to the workshop, it is most important that an agenda is agreed by the
panel and distributedby the facilitator.
Page 4 Part 1, Section 2 (12/99) Effective from 1/1/00 The Surveyors' ConstructionHandbook
U--?
PART 1, SECTION 2
Figure 2: FASTDiagram
Sub-function (Al)
r Elemental (Al.1)
Secondary L Elemental (Al.2)
function (A) Sub-function (A2)
Sub-function (A3)
Secondary r
function(B) Sub-functions
Basic
function
(Clientsneed)
Secondary
function (C)
r Sub-functions
Secondary
function (D)
r Sub-functions
The Surveyors' ConstructionHandbook Part 1, Section 2 (12/99) Effective from 1/1/00 Page 5
43
PART 1, SECTION 2
1.2.7.6 A list oftypical user functions for a health centre is included in AppendixA.
Function elements (object functions) are defined in the BCIS publication,
StandardForm ofCostAnalysis: Principles,InstructionsandDefinitions and
iiSection2.3 ofthishandbook.
1.2.8.2 Fees and value added tax (VAT) and other financialand fiscal matters may
also need to be considered.
44
PART 1, SECTION 2
4 1.2.lOlheWorkshop
(b) 'Speculation' is the brainstorming stage which will generate the ideas
from which solutions will be developed. It is importantthat each member of
the panel thinks positively. The facilitator will ensure that no one is allowed
to become overly criticalofanothermember's contribution in orderthat ideas
flow. All ideas shouldbe logged at this stage. However, in order to encourage
ideabuilding,they shouldnot be analysedor rejected. It is important that the
underlying functions ofsuggestions for improvement are listedfor evaluation
later. Design solutions should not be developedat this stage to ensure that
'what is to be achieved'is properly addressed. All optional solutions should
only be considered at the evaluation stage.
The Surveyors' Construction Handbook Part 1, Section 2 (12/99) Effective from 1/1/00 Page 7
45
PART 1, SECTION 2
1.2.11.2 The financial benefit should then be identified against all elements within
categories (i) or (ii).
1.2.13.1 It is important for any clientto carry out a projectreview to demonstrate how
project objectives have been achievedand particularproblems overcome. As
part of the project evaluation process, it should be established whetherthe
project represents best value for money and whether or not key design
changes made as a result of value engineering have achieved the benefits
expected. These should always be set against the cost of carrying out the
exercise.
Page 8 Part 1, Section 2 (12/99) Effective from 1/1/00 The Surveyors' Construction Handbook
LL
PART 1, SECTION 2, APPENDIX A
Providegood
conditions Reception areaofadequatesize
forpatients
Consulting rooms - sufficientnumber
Publictransportavailability
Parking availability
Closeness to patients'homes
Toiletfacilities
Crèche facility
Provide good
conditions Office ofadequate size
for staff
Office efficient/flexible layout
Parking availability
Rest roomfacilities
Provide
suitable Consulting rooms ofadequate size with soothing decor
spaces
Reception areaattractive and comfortable
Ensure
administrative Adequacy ofspace
convenience
Flexibility oflayouttousers
Sufficiency ofrecordstorage/retrieval
The Surveyors' Construction Handbook Part 1, Section 2 Effective from 1/1/00 Page 1
Appendix A (12/99)
47
PART 1, SEcTIoN 2, APPENDIX B
Bi BACKGROUND
For two ofthese projects the client optedfor a design and build contract for
the servicesinstallations (mechanical, sprinklersandelectrical).
Appendix B (12/99)
48
PART 1, SECTION 2, APPENDIX B
Connaughton, John, N., Green, Stuart, D., Construction Industry Research and
Information Association. ValueManagement in Corstruction:A Client Guide, CIRIA,
London, 1996
Kelly, J.R. and Male, S.P. A Study of Value Engineering and Quantity Surveying
Practice, Heriott-Watt University, Edinburgh, 1989
May, Susan, C., College of Estate Management. Value Engineering and Value
Management: A CPD Study Pack, College ofEstate Management, Reading, 1994
Mole, Kelly, Fernie, Grongvist and Bowles. The Value Management Benchmark: Good
PracticeFrameworkfor ClientsandPractitioners.Thomas TelfordPublishing,London 1998
The Surveyors' Construction Handbook Part 1, Section 2 Effective from 1/1/00 Page 1
Appendix C (12/99)
50
PART 1, SECTION 2, APPENDIX C
Smith, J., Jackson,, N., Wyatt, R., Smyth, H., Beck, M., Chapman, K., Shirazi, A.,
Hampson, K., Royal Institution of Chartered Surveyors. Can Any Facilitator Run a
ValueEngineering Workshop?RICS, London, 1998
Introduction
This Sectionof the Handbook sets out procedures which enable pre-
contract cost management of building projects to be carried out from the
client's brief, through the various design stages to the acceptance of a con-
tractor'stender.
Control of costs can oniy be achieved by the actions of the whole project
team, including the client. The quantity surveyor's role is to facilitate the
design processby systematicapplication of cost criteria so as to maintain a
sensible and economic relationship between cost, quality, utility and
appearance which thus helps in achieving the client's requirementswithin
the agreed budget.
The procedures are not designedfor use with civil engineering projects,but
should providea frameworkappropriate to civil engineeringneeds.
52
PART 2, SECTION 1
Inception
Design Stage A Feasibility Outline
L _B Proposals Scheme
(references are to
the RIBA Plan of Work; — — Design Detail
see G2.1.1.4) — D — Design Production
E Information Bills of
itieser
Deliverable Reports
2.1.1.1 DEFINmON
Pre-contractcostplanningis the techniqueby which the budgetis allocated
to the various elements of an intended building project to provide the
design team with a balanced cost framework within which to produce a
successful design. It allows for the redistribution of the budget between
elementsas the design develops.
Cost managementis the total process which ensuresthat the contract sum is
withinthe client's approvedbudget or cost limit. It is the process ofhelping
the design team design to a cost rather than the quantity surveyor costing a
design.
2.1.1.2 OBJECTIVES
(a) To ensure that the client obtainsan economical and efficient projectin
accordancewith the agreed brief andbudget;
(b) To make the design process more efficient, thus reducing the time
needed to producea successfuldesign;
(c) To ensure that all requirements arising from the client's brief to the
design team are includedin the cost planning process (e.g. the engineering
services shouldalsobe subjectto the costplanning process); and
(d) To advise the client and membersof the design team of cost-in-use or
life-cycle costingtechniques.
2.1.1.3 GENERALLY
(a) A general principle applies throughout the cost planning process that
any agreedbudget or cost limit is seen as the maximum cost, andthe quan-
tity surveyorshould,at all times, work with the otherdesign team members
to satisfy the client at a lower cost if possible, whilst still maintainingthe
desired objectivesfor quality andfunction.
(b) If, at any time, sums have been included in the approved budget, for
example, for abnormal site costs which subsequently are found to have
been wholly or partially unnecessary, the consequential saving should
always be notifiedto the client.
2.1.1.4 DESIGNSTAGES
References to Design Stages are to the RIBA Plan of Work (taken from the
RIBA Handbook ofArchitectural Practice and Management) and refer to
the main stagesthrough which a projectdesign typically passes. The links to
the costplanningprocedures outlined in thisSection are summarisedhere:
2.1.3 Budget
2.1.3.1 DEFINITION
Budget is the total expenditureauthorisedby the client whichis the respon-
sibility of the design team at the end of the feasibilitystage (Design Stage
B).
2.1.3.2 OBJECTiVES
(b) To providethe client with a statement of the likely area and quality of
building, which is achievable within the limit of expenditure;
(a) The ideal requirementsfrom the client and membersofthe project team
to the quantity surveyor are given below. On projects where this level of
information is not available, the quantity surveyorshould state clearly any
assumptionsmade.It is possible to produce a typicalelementalestimate for
Note: If the quantity surveyor is not responsible for cost planning the
engineering services, this should be clearly stated in the budget and cost
plan.
The Surveyors' Construction Handbook Part 2, Section 1(4/98) Effectivefrom 1/6/98 Page 5
53
PART 2, SECTION 1
(d) Once the budget has been established,it provides the first cost plan for
the project, and the frameworkfor the actualdesign to be developed.
(a) Quantity
• in addition to the briefed areas, a statementof the allowances (e.g.
circulation)used to calculate a gross floor area;
• the number of storeys of a possible solution;
• the storey height(s);
• the square indexor wall/floorratio (see AppendixC to this Section);
• the density of vertical divisionor partitionlfloorratio (see Appendix
C to this Section);
• proportionof windowarea;
• floor loadings;
• thermal resistancevaluesoffabric;
• air change rates;
• heating and hot-waterloads;
• lighting levels;
• total electricalload;
• areas ofthe brief with
specialfunctionsof significantcost;
• road areaandnumberof car parking spaces;
• pavedpedestrianareas; and
• length of boundary walls or fencing.
(b) Quality
• A general statement of quality and specification which relates to the
rates used for the budget calculation. This should cover specifically
at least the following: foundations, roof, external walls, floors and
vertical circulation,internalvertical division, internal finishes, light-
ing and other services. External works should include roads, paths,
landscape, boundary walls and fences, and service mains, planting
andthe like.
(a) The prediction of future inflation may not be necessary for some
clients, anda statementof costat currentpricesmay be adequate. Where an
assessment of inflation is required for more than a few months ahead, a
range of probable inflationis best provided. This can be calculated using
predictions published, for example by BCIS or the Department of the
Environment,Transportand the Regions. The assumptionsupon which the
predictionis made should be stated.
(b) Some clients, particularlyin the public sector, have their own inflation
controls. Where the client requests that a particular level of inflation be
included in the budget, the quantity surveyorshould inform the clientif he
believesit to be unrealistic.
apparent that the whole of the agreedbudget will not be required,the client
shouldbe informed.
2.1.4.1 DEFINITION
The costplan at outline proposals stage is a statement of the probablecost
ofthe project at Design Stage C which sets outthe cost targets for the main
elements of a building, togetherwith their approximatequantity and quality
parameters.
2.1.4.2 OBJECTIVES
(a) To describe, together with the outline proposal drawings, the chosen
distributionof the resources withinthe budgetto provide a balanceddesign
to meet the client's needs;
(b) To set costtargets for the mainelementsso that, as the design develops,
the targets can be checked and adjustmentsmade so that the overallcostof
the project is managed withinthe budget;
2.1.4.3 INFORMATIONREQUIREMENTS
The basic information requirements from the members of the project team
to be providedto the quantity surveyorare as follows:
The Surveyors' Construction Handbook Part 2, Section 1(4/98) Effectivefrom 1/6/98 Page 9
PART 2, SECTION 1
(a) Quantity
Confirmation of informationprovided at budget stage with the additionof:
• the areas of the accommodationdivided into use classification (e.g.
office/classroom space, sanitary accommodation space, plant-room
space, circulation space), totalledto give gross floor area; and
• a scheduleof those items for which lump sum allowanceshave been
incorporated and a note on the sources ofthis information.
(b) Quality
• a statement of quality and specification, in a similar format to that
provided at budget stage, expandedto incorporate additional infor-
mation. The parameters should follow those included at the budget
stage, and where possible, be based upon the outline drawings and
preferredspecifications.
2.1.4.8 INFLATION
Note: If the cost plan has been produced at an earlier design stage only
updatingmaybe required.
2.1.5.2 OBJECTIVES
(a) To set out for the design team the actual distribution of resources
described bythe scheme design;
(b) To set cost targets for all the elements so that, as the detail design
develops, the targets are checked and adjustments made in order that the
overallcost of the project is managed withinthe budget; and
(c) To provide the whole design team with a control document which
describes, in detail, the costs, quantity, quality and time parameters which
have been adopted.
62
PART 2, SECTION 1
Page 12 Part 2, Section 1 (4/98) Effective From 1/6/98 The Surveyors' Construction Handbook
PART 2, SECTION 1
(a) Quantity
confirmationof the information providedat outlineproposal stage
(b) Quality
a statementof quality and specificationbased on scheme drawings in suffi-
cient detail to provide control of the production informationdrawingsby
the designerand consultants
(c) Life-cycleinformation
a statement of the likely relevantmaintenance,cleaning,and running costs
which are required or implied by the scheme design proposals and the
expectedlife of major components.
4) 2.1.5.7 INFLATION
Any changesin inflationforecasts should be reported.
2.1.6.1 DEFINITION
Cost checking is the process of calculating the costs of specific design
proposals and comparing them with the cost plan during the whole design
process (DesignStages D—F).
4) 2.1.6.2 OBJECTIVES
(a) To confirm that as the design develops, the cost remains within the
budget; and
(b) To reduce the abortive design work and lost time caused through pro-
ceeding too far in the design process before realisationthat the budgetwill
be exceeded.
2.1.6.3 PRINCIPLES
(a) The methods will vary according to the stage reached in the design
process.Normally,however, this takes the form of measurement of approx-
imate quantitiesfrom the consultants' drawingsto provide a check on the
quantity and quality of parameters set down in the appropriate cost plan.
The gross floor areashould always be the first check at any stage.
(b) It is important for the quantity surveyorto maintain records of the cost
checking process, and to set down in summary the value of the elements
cost checked compared with the cost plan targets. Identification of the
drawings and informationupon which the cost check has been based is also
important.
2.1.7.1 DEF1MTION
(a) Action after receipt of tenders is that required at the tender stage
(Design Stage H) in analysingeach tenderandupdatinginformationfor the
clientandconsultants.
2.1.7.2 OBJECTIVES
cDs
PART 2, SECTION 1
2.1.7.3 INFORMATIONREQUIREMENTS
Information to be provided to the quantity surveyoris as follows:
Al OBJECTIVE
A2 SOURCES
A2.3 PublishedIndices
• tenderindices andcost studies on regional variations— BCIS;
• the published indices ofthe Departmentof the Environment,Transport
and the Regions;
• PriceAdjustment Formulaefor ConstructionContracts(NEDO) Indices
Department ofthe Environment,Transport andthe Regions;
—
• Architects'Journal; and
• Building.
A3 TheUse ofPublishedInformation
BI OBJECTIVE
B2 FORMAT
B2.1 The presentationof information to the client and design team shouldbe of
a high standard. Budget and cost plans resultfrom the application of a high
level of professionalskill, and the format of documents should reflect the
importance that the profession attaches to this service.
B2.4 The level of detail to be included in these documents should relate to the
size andcomplexityof projects. Simpleprojects may require less informa-
tion than shownin the example; complexprojects significantly more.
Project
Location
r
Budget serial number:
Site works:
Alterations:
On fees %
TIME
Formation of contract
Construction commencement
Alternative1
Alternative2
AsBudget Cost
Alternative I
Alternative 2
-1I
PART 2, SEcTIoN 1, APPENDIX B
BASISOF BUDGET
Areas
TOTAL FLOORAREA
Quality Standards
Externalelevations:
Internal finishes:
Heating& ventilation:
Lighting:
Site works:
Other (specify):
Exclusionsfrom budget:
Alternative standards
Budget preparedby:
Signature: Date:
Firm:
AppendixB (4/98)
PART 2, SECTION 1, APPENDIX B
BUILDING
Quantity
Grossfloor area m2
Floor/roof zone m.
Structural
Ground bearing pressure kN/m2 Ground water level
Environmental
Fabric'U' values: Roof W/m2C
Walls (average) W/m2'C
Ground Floor W/m2'C
74-
PART 2, SEcTION 1, APPENDIX B
Lightinglevels
(Specify spaces, lux level and load in W/m2)
Special areas with higher than average service or other costs (specify)
Other
External Works
Area m2
Other
1 Substructure
2A Frame
2B Upper floors
2C Roof
2D Stairs
2E External walls
2F Windows and external doors
2G Internal wallsand partitions
2H Internal doors
2 Superstructure
3A Wall finishes
3B Floor finishes
3C Ceiling finishes .
3 Internal finishes
4 Fittings
5A Sanitary appliances
5B Services equipment
5C Disposal installations
5D Water installations
5E Heat source
5F Space heating and air treatment
5G Ventilating systems
5H Electrical installations
51 Gas installations
5J Lift and conveyorinstallations
5K Protective installations
5L Communicationsinstallations
5M Special installations
5N Builder's work in connection
50 Builder's profit and attendance
5 Services
Building sub-total
6A Site works
6B Drainage
6C External services
6D Minor building works
6 External works
7 Preliminaries
8 Contingencies
Construction costs
SPECIFICATION Building
1 Substructure
2A Frame
2B Upper floors
2C Roof
2D Stairs
2E External walls
2H Internal doors
3A Wall finishes
3B Floor finishes
3C Ceilingfinishes
5A Sanitary appliances
5B Services equipment
5C Disposal installations
77
PART 2, SECTION 1, APPENDIX B
SPECIFICATION Building
5D Water installations
5E Heat source
5G Ventilating systems
5H Electrical installations
51 Gas installations
5J Liftandconveyor installations
5K Protective installations
5L Communication installations
5M Special installations
6A Site work
6B Drainage
6C External services
6D Minorbuilding works
AppendixB (4/98)
PART 2, SECTION 1, APPENDIX B
COSTTARGETS
Building Price base 19
7c
PART 2, SECTION 1, APPENDIX C
Where very little quantity information is available at the early stages of a project,
estimates of elemental quantities can be produced using standard formulae and
typical assumptions. Some of the most common formulae and some worked exam-
ples are given here.
WALLTO FLOOR RATIO
SQUAREINDEX
This -is an alternative way of expressingthe relationship betweenthe floor area and
the external walls. It describesthe degree to which the perimeterlength of an actual
building exceeds that of a building of the same area which is a perfect square. Any
single storey building can be described, as can also multi-storeybuildings, with a
constant shape on eachfloor.
DENSITYOF VERTICALDIVISION
ASSUMPTIONS
Substructure
A
— —1350
675 m2
n 2
IA\ —
1350\
=
Upperfloors (n—i) (— (2—1) J 675 m2
2 I
The quantities calculated in this, or similar ways, can then be used with selected
element unit rates to calculate budgets and cost plans for projects in the earliest
stages of design, or for checking the approximate cost difference of alternative
design solutions.
tApercentagecan be used to split 'wall' from 'window', e.g. window anddoor area
externalwalls X w = 945 m2 X 30% = 284 m2.
The Surveyors' Construction Handbook Part 2, Section 1, Effective From 1/6/98 Page 3
Appendix C (4/98)
PART 2, SECTION 1, APPENDIX D
Appendix D: FurtherReading
BOOKS
ARTICLESAND REPORTS
Ferry, D.J.O. "Life CycleCostñg: A Radftá1 Approach". CIRIA Report 122, 1991
Watson, K. Procurement— The Key Area for Cost Control. Construction Computing,
(52)April 1996, 12—13 (2)
Introduction
The life cycle cost (LCC) of an asset is defined as the present value of the
total cost of that asset over its operating life (including initial capital cost,
occupation costs, operating costs and the cost or benefit of the eventual
disposal ofthe asset at the endofits life).
2.2.1.2 VALUEENGINEERING
Value engineering involves preparing structured option appraisals during
the design process so demonstrating value for money for clients. Its use is
1 Latham,M., Sir,
(1994), Constructing the Team: Joint Review ofProcurementand Contractual
Arrangementsin the United Kingdom Construction Industry:Final Report,HMSOLondon
87
be resealed. In purely capital cost terms, the selection of the materials
referred to above may be more expensive than their traditional counter-
parts.
The use of life cycle costing places initial capital cost in the context of
future maintenance expenditure, and helps justify decisions which have
beneficialhealth and safety implications.
Life cycle costs and their accurate prediction, control and reduction are
critical to the successful performance of a PFI deal.
Buildings have not been traditionally designed for anything beyond their
immediate requirement.However, as more are being converted to alterna-
tive uses it is probably only a matter of time before investors in property
callfor propertiesto be constructed with a view to extendingthe building's
usable life, e.g. conversion to house a growingless mobile andaged popu-
lation. Such consideration is more valid the shorter the predicted current
building life, e.g. some light industrial units for English Partnerships have
been designed for a ten-yearlife. Similarly, HertfordshireCounty Council
have housing and nursing homes with a 20-yearlife expectancy.
INTRODUCTION
The calculation generally involves the appraisal of options, each option
having different capital and future costs. To determine and analyse the
future costs it is necessaryto establish:
• the buildinglife;
• the discountrate (which, expressedsimply, is the differencebetween
the interest and inflation rate andis used to convert future payments
to presentvalues);
• the cost and frequency of future payments (at the component,
elemental or total building level as appropriate);
• any tax implications (see 2.2.3).
Typically the relevantbuilding life willbe the period over whichthe organisa-
tion, for whom the study is being conducted, will be expected to hold an
interestin the building, and wouldtake intoaccount the residual value.
At the end of the life of a building, the building (or component) and the
land will have a residual value. In the case of relatively short life cycles or
high value land, residual values can be very significant factors in deter-
mining the optimum life cycle cost options. Residual values are briefly
discussed in AppendixA (and worked example 2.2.5.3 includes a residual
value in the calculation).
When the buildinglife is assessed to be over 40 years, the precise life is not
critical for the purposes of life cycle costing (as discounting, explained
below, minimisesthe effectof such futurepayments).In cases where calcu-
lations are based on a relatively shortbuildinglife, say 20 years or less, the
assessmentofthe time horizons must be consideredwith special care.
cic
As 'money today' has a different value from 'money tomorrow' or 'money
in ten years' time', a technique has to be adopted that will express future
costs or revenues in present values. The process of converting 'future
money'to 'present money' is calleddiscounting.
Interest rates are particular to the client and the degree of risk. It is there-
fore essential to involvethe client (and his accountantif appropriate)in the
process andreach agreementon the discount rate to be used.
Economists, accountants and clients will all have different views about
future levels of inflation and interest rates. Some forecasters may take the
view that as different categories of cost inflate at different rates, these
differences should be taken into account in setting discount rates. These
diversitiesof view 'before the fact' makeit difficultto recommendanyfirm
guidelinesfor surveyorsto adoptfor selectingdiscount rates.
(a) use a rate which 'implies' inflation of future costs and values (in this
casefuture costs and values will be pricedat today's prices);
9!
informationis available, a test.discount rate of 4% is used. This method is
often adopted in the public sector where minimal risk associated with the
investmentis assumed.
No risk return 3%
Constructionpremium risk (8% X ) 4%
—
—
(1 + Treasury Bondrate)
(1 + Inflation rate)
1.08
= 0.02857
2.857%
Estimates for these costs will be based upon assumptions about future
events and should be clearly stated. Indeed an additional advantage of life
cycle costing is that it requires design assumptions to be stated explicitly
ratherthan implied.
Although current costs are generally used, it is important that future cost
assessmentshould reflect any expected divergenceof a specific cost from
the level of inflationallowedin the discount rate. For example, it would be
unwiseto assume that market conditions would remain unchangedfor any
extended period when tender levels for building work are very depressed.
Some allowanceshould therefore be made to adjust current building prices
to more normal market conditions when pricing future building work.
The following costs for each category should be considered and where
necessaryestablishedwith the client.
(a) Capital costs — include land, building, professional fees, furniture and
equipment,or permanentimprovements thereto, which form assets for the
business to use in its operation, with an intended useful life of more than
one year. The significance of any tax benefits and grants should be estab-
lished with the client.
(b) Financing costs — the methodof funding the project should include,
inter alia, the cost effect of alternative sources of funds, the future flexi-
bility of funds in terms of amounts and sources, andgearing. Consideration
shouldalso be givento
• the accountingeffect of capital employed;
• constructionperiod finance charges andlong-term finance costs; and
• the taxationimplicationsof the various options.
The Surveyors' Construction Handbook Part2, Section 2(4/99) Effectivefrom 1/6/99 Page 9
(c) Operation costs — include estimates of rent, rates, energy costs, clean-
ing costs, building related staffing costs andother staffing costs.
(f) Occupancy costs — the cost of performing the function for which the
building is intended (e.g. producing motor vehicles). Occupancy costs are
distinguishedfrom operation costs, as they relate to costs attributableto a
specificprocess undertaken by the client,which may change withinthe life
of the building. As an example, a car manufacturermay change to the
production of heavy goods vehicles. This would impact on his occupancy
costs, whereas his building related operation costs could be relatively
unchanged. Some clients mightnot require the surveyorto take these costs
into account, as not relating directlyto the building.
(g) Residual values and disposal costs — estimate of the resale value and
the cost of disposing of the building, plant, land and other assets after the
expiry of the life cycle. Many buildings, particularly those with an 'open
market value' will have a significantresidual value. Care shouldbe taken in
assessingthis value as it can have a major effect on the life cycle costing
calculations (seeAppendix A).
INTRODUCTION
This Sub-section deals with the effect of taxation allowances and incen-
tives available for expenditure upon property and construction applicable
in the United Kingdom to date, during the life of the asset. A glossary of
terms is included inAppendix D.
Page 10 Effective from 1/6/99 Part 2,Section 2(4/99) TheSurveyors' Construction Handbook
95
a charge on the profit and lois account, which again reduces the tax
payable.
2.2.3.1 The following example shows the net discounted cost, after tax relief, of
£1,000 spent on differingtypes ofexpenditure.
£ £ £ £
Expenditure 1,000 1,000 1,000 1,000
1 i.e. 50%of £1,000 x 25% reducing blancex 35% Corporation Tax withfuture allowancesdis-
counted at 10% per annum (a discounting calculation is required in order to establish the
above figures).
Subsequent to the Finance Act 1997 first year allowances were changed and
at the time of writingwere still being finalised.
Different types of allowances, initial, first year and writing down are
explainedin the Glossary ofTerms (AppendixD).
(a) the CorporationTax and allowancesrate that will be current at the date
of construction of first use;
(b) the future Corporation Tax and allowance rate at the date of replace-
ment;
(d) whether the owner will be liable to tax during the period between the
date of construction or first use and the date of replacement, and if the
ownerwill have sufficienttaxable profits to use the allowances generatedin
any oneyear;
(e) whether the item's economic life will be shorter than the tax write
downperiod. This will either generatean added writedownamountwhen it
is demolished, or if the item or building is to be sold at the end of its
economiclife, its profit or loss on cost. These circumstances will generatea
taxable profit or loss on proceeds above or below the tax write down value
and will attracta balancing adjustment;
(f) the value of the balancing allowances, chargesor taxable profits needs
to be consideredagainst the relevant Corporation Taxrate;
2.2.3.5 DYNAMICS
The surveyor should therefore appreciate the variables and frequent
changesthat occur in respect to the application oftaxationallowances.
These arisebecause:
96
(c) the InlandRevenuepracticesandextra statutory concessionsdevelop to
address specific issues or vagaries.
2.2.3.6 APPLICATIONS
Taxation allowances provide the opportunity for innovative funding
arrangements whereby the tax relief can be 'exported' to a party who can
enjoymorebenefitfrom the entitlement.
Business Rates
Large plant and machinery regarded as an integral part of the building can
attract additionalrates whichcan be influenced by designniceties (such as how
theplantis covered over). Expert advice should be sought in such a situation.
Furtherreadingfor taxation
ct9
Whilst the selection of,data sourcesgiven in AppendixF is not comprehen-
sive, it gives an indication of the level of information available. Trade
literature which is a prime source of detailedinformationis not included.
INTRODUCTION
Life cycle costing can be usedin numerous situations.The intentionof this
Sub-sectionis to give the reader an appreciationof its application, as used
by surveyors in practice, and the relative complexitiesof associatedcalcu-
lations, ranging from a simple elementaloption appraisal to complex total
building analyses.
(c) For maintenance the present cost of £6,040 for new ironmongeryand
repaintingtaking place in, say Year 12 at 4% discount
£6,040 x 0.62459** = £3,773
CapitalCosts
Aluminium Glazed £ 1750.00 m2 35,000 35,000
HardwoodGlazed
Vision Panels £ 1000.00 m2 20,000 20,000
Softwood £ 700.00m2 14,000 14,000
Metal £ 850.0Dm2 17,000 17,000
— — — —
Contingency
Total Year1 Capital Costs 35,000 20,000 14,000 17,000
AnnualRunningCosts
Aluminium Glazed £ 10.89 m2 218 4,927
HardwoodGlazed
VisionPanels £ 9.99 m2 200 4,520
Softwood £ 5.90 m2 118 2,670
Metal £ 17.99 m2 360 8,140
Total AnnualRunningCosts 13,068 4,927 11,988 4,520 7,080 2,670 21,588 8,140
Continued overleaf
0\
PROJECT: Life Cycle Model (continued) SHEET NUMBER: LCCM5
ELEMENT: InternalDoors
Unit: 2Dm2
Total Maintenance/ReplacementCosts 62,560 17,109 47,000 15,776 46,480 15,917 44,400 14,993
Total RunningCosts 75,628 22,037 58,988 20,297 53,560 18,586 65,988 23,132
to2
2.2.5.2 BUILDING SERVICES DESIGN OpnoN: AIR CONDIITIONINGAND UNDER FLOOR
TRUNKING VERSUSHOT WATER HEATING AND RING MAIN ELECTRICS
This example is again provided by Messrs Gardiner & Theobald. The
objectiveis to evaluate the above options for a building of 3,000 m2 floor
area, a life of 60 years anda discountrate of4% (7% interest less 3% infla-
tion). The informationis summarised overleaf with the methodology for
the calculation being exactly as that for the previous example.Any taxation
implicationsare excluded.
DiscountRate of 4% perannum Finish Life Finish Life Finish Life Finish Life
(Interest Rate (7%),Inflation (3%)) 15 Years 25Years
Capital Cost
AirConditioningU/FloorTrunking £ 25Dm2 750,000 750,000
HW Heating & RingMain Electric £ 15Dm2 450,000 450,000
Contingency 5% 37,500 22,500
OPTION3
OPTION4
OPTION4
lcL-
2.2.5.3 MAINTENANCEOPTION: WITHIWITHOUTCLEANING GANTRY
This exampleis kindly providedby Gerald Hall.
Assumedcriteria:
- BuildingLife 25 years
— VAT assumedto remain at current levels with the client
being an 'enduser' under VAT rules 17.5%
—
Gantrycapital cost £30,000
— The gantry will have a residual value £2,000
—
Capital cost for openinglights in lieu of gantry £5,000
— Discountrate (assumingthe interest rate will average 11%
over 25 years andthe inflationrate 6%) 5%
—
CorporationTax 33%
Taxation Calculation
3,199
2,472
The methodology applies for the rest of the 25 years as summarised over-
leaf.
The client initially consideredthat the gantry would pay for itself due to
savings in maintenanceandcleaning cost.
However:
— — — — — — 0 1.000
0 0 30,000 30,000 5,250 35,250 35,250 35,250 35,250
0
0 — — — — — —
1 750 750 131 881 3,199 (2,318) 0.952 (?,207) 33,043
2 — — 750 — — — 750 131 881 0.907
2,472 (1,591) (1,443) — 31,600
3 — — — 750 250 — — 175 0.864
1,000 1,175 2,024 (849) (733) 30,866
— — — 750 — — — 750 131 881 0.823
4 1,518 (637) (524) 30,343
— 750 — — — 750 131 881 0.784
5 1,211 (330) (258) 30,084
6 — 750 1,750 — — 2,500 438 2,938 1,660 1,278 0.746 953 31,037
7 — — — 750 — — — 750 131 881 808 73 0.711 52 31,089
8 — 750 — — — 750 131 881 679 202 0.677 137
N) 31,226
Co 9 — 750 250 — — 175 679 496 0.645 320
CD 1,000 1,175 31,546
0 — — — — — —
0 10 750 750 131 881 509 372 0.614 229 31,775
=
N) 11 — — 750 — — — 750 131 881 454 427 0.585 250 32,024
12 750 — — 438 0.557
1,750 2,500 2,938 1,092 1,846 1,028 33,052
13 — 750 — — — 750 131 881 383 498 0.530 264 33,31
— — — 750 — — — 750 131 881 360 521 0.505 263
14 33,580
——
15 — — 750 250 — — 175 440 735 0.481 354
1,000 1,175 33,933
— — — 750 — .— — 750 131 881 330 551 0.458 253
16 34,186
-—
17 — — — 750 — — — 750 131 881 320 561 0.436 245
- — 34,431
-D
TOTAL PRESENTVALUEAT END OF INVESTMENTLIFE 36,541
N)
lob
0•0
CD COMPARATIVE COMPONENT LIFE CYCLE COSTING (continuation of table on page 21)
1 The capital cost includes allowances for preliminaries and associated 7 Maintenanceand running costs with 100% allowance — ie 1st year 291
builders work. total 3,199
2 Details of the maintenance requirements and cost estimates can be 8 Taxation allowances are subject to negotiation and agreement.
provided upon request.
9 Discount rate:
3 The life cycle costing is based on an agreed investment life of 25 years.
1 (i) Interest rate — 11% average over 25 years;
4 It is assumed that VAT will remain at around 17.5% and the client is the (ii) Inflation rate — 7% average over 25 years:
end user' under VAT rules.
(1+ 11%)
5 There are disposal cost advantages with this option. (1 + 7%) —1 x 100% = 5% discount rate.
-u
U,
C,.)
CD
C-,
0
—I
CD
C,)
CD
0
C)
0
=
C,,
C.,
0
DC
=
0
0
0
0
—4
CD
COMPARATIVE COMPONENT LIFE CYCLE COSTING CLIENT:
C,)
PROJECT TITLE: Retail Development/Shopping Mall
CD
0 JOB NO:
OPTION: Cleaning 'without' a gantry — curtain walling to new facade
C-)
0
C,, TOTAL TOTAL Lesstax NETTOTAL Present PRESENT CUMULATIVE
Costs VAT17.5%
inc VAT allowance value of VALUE PRESENT
C,
Year Capital Financing Operation Maintenance Occupancy Disposal/ £1 VALUE
0 residual value © 5%
Annual Intermittent
— — — — — —
0 5,000 5,000 875 5,875 0 5,875 1.000 5,875 5,875
0
0 — — — — — —
1 1,500 1,500 283 1,763 582 1,181 0.952 1,124 6,999
. — — — 263 582 0.907
2 1,500 1,500 1,763 1,181 1,071 8,070
— — —
3 1,500 1,500 263 1,763 582 1,181 0.884 1,020 9,090
— — — — —
4 1,500 1,500 263 1,763 582 1,181 0.823 971 10,061
— — — — — —
5 1,500 1,500 263 1,763 582 1,181 0.784 925 10,986
— — — — — 525 0.746
6 1,500 1,500 3,000 3,525 1,163 2,362 1,763 12,749
— — — — —. 0.711
- 7 1,500 1,500 263 1,763 582 1,181 839 13,587
— — — — 0.677
I'.) 8 1,500 1,500 263 1,763 582 1,181 799 14,386
C/) — — — — — 263 582 0.645 761
CD 9 1,500 1,500 1,763 1,181 15,147
C.,
— — — — — 582 0.614 725
0 10 1,500 1,500 263 1,763 1,181 15,872
N.) 11 — — — — — 263 582 0.585 690
1,500 1,500 1,763 1,181 16,562
— — — — — 0.557
12 1,500 6,500 1,138 7,638 2,521 5,117 2,849 19,411
. — — — 263 582 0.530 626
13 1,500 1,500 1,763 1,181 20,037
— — — 263 582 0.505 596
14 1,500 1,500 1,763 1,181 20,634
15 — — — — — 263 582 0.481 568
1,500 1,500 1,763 1,181 21,202
16 — — — — — — 263 582 0.458 541
1,500 1,500 1,763 1,181 21,742
— — — — —
17 1,500 1,500 263 1,763 582 1,181 0.436 515 22,257
18 — — 1,500 1,500 - — — 3,000 525 3,525 1,163 2,362 0.416 981 23,239
19
- — —
- 1,500 — — —
1,500 263 1,763 582 — 1,181 0.396 467 23,706
— — — — — 263 582 0.377 445
20 1,500 1,500 1,763 1,181 24,151
21 — — — — 263 582 0.359 424
1,500 1,500 1,763 1,181 24,575
.. — — — 263 582 0.342 404
22 1,500 1,500 1,763 1,181 24,978
— — — — 263 582 0.362 384
23 1,500 1,500 1,763 1,181 25,363
— — — — — 525 0.310 732
24 1,500 1,500 3,000 3,525 1,163 2,362 26,095
— — — 263 582 0.295 349
25 1,500 1,500 1,763 1,181 26,444
tc8/
COMPARATIVE COMPONENT LIFE CYCLE COSTING (continuation of table on page 23)
6 Capital cost as plant and machinery with 100% tax allowance — NIL.
FORECASTER'S ASSUMPTIONS
7 Maintenance and running costs with 100% allowance.
1 The capital cost allows for opening lights now required, without capital
allowances. 8 Taxation allowances are subject to negotiation and agreement.
2 Details of the maintenance requirements and cost estimates can be 9 Discount rate:
provided upon request. (i) Interest rate — 11% average over 25 years.
3 The life cycle costing is based on an agreed investment life of 25 years. (ii) Inflation rate — 7% average over 25 years.
(1+ 11%)
4 It is assumed that VAT will remain at around 17.5% and the client is the
'end user' under VAT rules. (1 + 7%) — 1 X 100% = 5% discount
-I
CD
C,,
0
(a
C)
C
C/)
C
C,
0
=
C-
0
0
0
2.2.5.4 HOUSING SINXINGFuND (BASED UPON COSTED PLANNEDMAINTENANCE)
(a) Background
This example is kindly provided by Ian Sloan of Armour Construction
Consultants.
= £9,013
£9,013 X 0.41726* = £3,761
0 5.11.2.Smokedetectors A A A A 0 A A A A 0 A A A A 0 A A A A 0 A A A A 0 A A A A 0 0
0
5.1.2 COMMUNICATION 5.12.1. Doorentry A A A A A A A A A 0 A A A A A A A A A 0 A A A A A A A A A 0 0
5.12.2. Telephones T T 0 T T 0 0
-tl
DO
o.Q
CD
-U
Do PLANNED MAINTENANCEPROGRAMME (COSTED)
CD
EXAMPLE Date Printed 02/12/98 Years Cumulative
N.)
00 Cost
STRUC- 1.1.2. Floors Timber ) 100 100 100 100 100 100 600
)
TURE 1.1.3. Openinga) Concrete/Brick ) 0
1.2 Stairs 1.2.1. Stairs Timber 25 25 25 25 25 25 150
2.1 Roof 2.1.1. Roof Tiles etc Concrete Tiles 75 75 75 75 75 75 75 75 75 75 75 75 75 75 75 75 75 7575 380 7 5 75 75 75 7 5 75 75 75 75 75 4,555
2.3.3. Painting 100 10 0 10 0 100 100 100 100 100 10 0 100 1,000
2.3.4. Ironmengery inc in inc inc inc inc inc inc inc 210 inc inc inc inc inc inc inc inc inc inc inc inc inc inc ioc inc inc inc inc 210 420
2.4.4. Ironmongery inc in inc ioc Inc Inc inc inc in c 60 inc inc inc inc inc inc inc inc in c inc Inc inc inc mc in c inc in c inc ioc 60 120
3.4.2. Ironmongery inc inc inc inc inc inc inc inc in c mc inc inc inc inc 400 inc inc inc in c ioc inc inc inc inc in c inc in c inc inc 480 960
FITTS 4.1 Fittings & Furnish 4.1.1. Kitchen Units Units/Werktsps 60 60 60 60 60 60 60 60 6 0 800 60 60 60 60 60 60 60 6060 800 60 60 60 60 60 60 60 60 60 800 4,020
-4 10 10 10 10 10 10 10 10 1 0 200 10 10 10 10 10 10 1
0 1010 200 10 10 10 10 10 10 10 10 10 200 870
= FURN 4.1.2. Grab rails etc
CD
Co 5.1 5.1.1. Sanitaryware Wcs, baths,whbs 5 5 5 5 5 5 5 5 5 5 5 5 5 5 450 5 5 5 5 5 5 5 5 5 5 5 5 5 5 450 1,040
Sanitary Appliances
= inc inc in c inc inc 160 485
5.2 ServicesEquipment 5.2.1. Kitchensinks Stainless steel inc inc Inc inc inc ixc inc inc in c 160 inc Inc inc inc 5 inc inc inc in c 160 Inc inc inc inc
C, 5.4.2 inst 5.4.1.1 Pipes& Fittos inc inc inc inc inc inc 0
Disposal
0 5.5 Heatsource 5.5.1 Radiators/fires 20 20 650 20 20 650 1,380
= 5.6 Heatsystem 5.6.1. Boilers/equipment 40 40 40 40 40 40 40 40 4 0 750 40 40 40 40 40 40 40 4040 750 40 40 40 40 40 40 40 40 40 750 3,330
0)
0 5.7 Ventilation 5.7.1. Fanx etc 5 5 5 5 5 5 5 5 5 200 5 5 5 5 5 5 5 5 5 200 5 5 5 5 5 5 5 5 5 200 735
0
0 100 100 1500 100 100 500
0 5.8 Electrical inst 5.8.1. Power and lighting 3,400
-1
PLANNED MAI NTENANCE PROGRAMME (COSTED) (Continued)
cI EXAMPLE Date Printed 02/12/98 Years
Cumulative
CODE ELEMENT SUB-ELEMENT COMPONENT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Cost
5.8.2. Switchgear inc inc mc inc inc inc 0
5.8.3 External Lighting Close Light inc 100 inc 100 inc inc 200
— 0
SER- 5.10 Lift installation
VICES 5.11 Protective inst 5.11.1 TV systemetc 25 150 25 150 25 150 525
5.1.2 Communication 5.12.1. Doorentry n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/s n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/n n /a n/a 0
5.12.2. Telephones 10 10 100 10 10 10 0 240
ii 6.1.1 Landscaping 6.1.1.1. Roads, footpaths 50 50 50 50 50 50 50 50 50 50 50 50 50 50 500 50 50 50 50 50 50 50 50 50 50 50 50 50 50 500 2,400
6.1.1.2. Grass/ planting 100 100 100 100 100 100 10 0 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 10 0 100 100 1 00 750 3,650
6.1.2 Boundaries & 6.1.2.1. Fences and gales 10 10 500 10 10 500 10 10 500 10 10 500 10 10 3000 10 10 500 10 10 500 10 10 500 10 10 500 10 10 3000 10,200
62 Drainage 6.2.1. Pipes & fittings 100 100 100 100 100 500 1,000
C, TOTAL COST PER YEAR £ 518 518 1208 518 1448 1208 51 8 518 1208 4068 518 1208 518 518 9013 518 518 1208 518 8673 1048 518 518 1208 1448 51 81209 518 518 5460 57,902 (Yrs 1—30)
0 PRESENT VALUE 489 461 1014 410 1082 852 34 4 325 715 2272 273 600 243 229 3761 204 192 423 171 2704 308 144 136 298 337 11 4 251 101 96 2692 21241 (Yrsl—30)
r'-3
(at discountrote 086%)
31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60(Yro 31—60) (Yrs 1—60)
Repeat Years
Current Cost peryr 518 518 1208 518 1448 1208 51 8 518 1208 4068 518 1208 518 518 9013 518 518 1208 518 8673 1048 518 518 1208 1448 51 81208 518 51815460 £57902 £115804
(Current coot)
PresentValue 85 80 177 71 188 148 60 51 124 395 48 105 42 40 655 36 33 74 30 471 54 25 24 52 59 20 44 18 17 469 £3701 £24942
(PresentVOlue)
rn
CD
C,
CD
0
3
N
C.,
N
CD
CD
C,
CD
CD
2.2.5.5 CENTRALISATIONOF OFFICESSTUDY
(a) Brief
This exampleis kindly providedby Gerald Hall.
us
(f) Tax Implications
Tax allowances have been excluded on the basis that this study is a minor
part ofthe overall companybusinessandassumptions are notappropriate.
However it is worthnoting that:
ilk
Do
CLIENT WATER COMPANY LIMITED
C,.)
I") JOB TITLE CENTRALISATION OF AREA OFFICE STUDY
JOB NO 3985
DATE 29th MARCH 1996
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 TatalValue
YEAR(SEPT1996)
£000 £000
Capital Coats -
1176 0 0 0 8 0 0 0 0 0 190 0 0 0 0 0 0 0 0 0 300 0 0 0 0 0 0 0 0 0 393 0 0 0 0 0 0 0 0 0 310 2369
BuildingWorks
RelecatienCostsl5.5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00 00 0 00 00 00 00 00 00 00 0 0 16
Capital Income
AnnualRental -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5 -7.5-7.5 -7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5 -7.5 -308
RevenueCents
Fuel 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.41.41.41.41.41.41.41.41.41.4 1.41.41.41.41.41.41.41.41.4 1.4 1.4 57
-U
D) Water 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 492
0000000000000000000 1212
Maintenance 121212 1212 12121212121212121212121212121212121212
C,, 0 0 0 0 0 0
CD Rates 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00 0000000000000000000
1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 9.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.71.71.7 1.71.71.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 70
0 Cleaning
7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.1 7.17.17.17.17.17.17.17.17.17.1 7.17.17.17.17.17.17.17.17.1 7.1 7.1 291
Security 7.1 7.1 7.1
5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.2 5.25.25.25.25.25.25.25.25.25.2 5.25.25.25.25.25.25.25.25.2 5.2 5.2 213
OperatienCnots
StaitCosts 0 0 0 0 0 0 8 0 0 0 8 0 0 0 0 0 0 8 00 0000000000000000080 0 0 0
Value 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.4 27.427.427.427.427.4 7.427.427.427.427.427.427.427.427.427.427.427.427.4 7.4 27.4 27.4 1,123
NetCash Flew 1164.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 209.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.919_S19.9 19.9 19.9 9.9 19.9 19.9 19.9 19.9 12.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 19.9 329.9 8
Present Value of £1@8% 1 0.93 0.86 0.79 0.74 0.68 8.63 0.58 0.54 0.5 0.46 0.43 0.4 0.37 0.34 0.32 0.29 8.27 8.25 8.23 0.21 0.2 0.18 0.17 8.16 .15 0.14 0.13 0.12 0.11 0.1 0.09 0.09 8.08 0.07 0.07 0.06 0.06 .05 0.05 0.05
0165 18 17 16 05 14 13 12 11 10 97 9 8 7 7 6 6 5 5 5 69 4 4 3 3 3 3 2 2 2 41 2 2 2 1 1 1 1 1 1 15 1608
NET PRESENTVALUE
EXPENDITURE NPVC=1,607,896
-I
CD
0)
0
C)
0
00
C.,
0
=
DO
=
0
0
0
0
2.2.5.6 TOTAL BUILDING OPTIciN: DEMOLISH ANI REBUILD VERSUS REFURBISHMENT
(a) Brief
The life cycle cost appraisal is to evaluate the life cycle cost effects of the
followingoptions:
• demolish existing building and rebuild to the client's specific
requirements incorporating 'all-air'air conditioningsystems;
• refurbish the existing building to meet, as far as practicable, the
client's requirements, re-using existing systems wherever possible.
—
[(1.07) 1]
X 100 = 3.88%
[(1.03) 1
(h) Summary
NetPresentValue
£k
OPTIONA
demolish existingbuilding andrebuild to the
client's specificrequirements, incorporating
'all air' air conditioningsystems; 3889
OPTIONB
refurbish the existing building to meet as far as
practicable,the client'srequirements,re-using
systems whereverpossible. 2177
intermittent - - - - - 6 3 - - - 62 3 21 - - 22 3 - - - 86
- - - - - - - - - - - - - - - - - - - - -
Occupancy
- - - - - - - - - - - - - - - - - - - - -
Disposal/ residual value
Total 2154 131 131 131 131 137 134 131 131 131 193 134 152 131 131 153 134 131 131 131 217
N.) Total (inc VAT) 2531 154 154 154 154 161 157 154 154 154 227 152 179 154 154 180 157 154 154 154 257
Co
CD Less Tax allowance 0 102 88 78 70 67 61 57 55 53 74 52 55 48 48 56 49 48 48 48 80
C,
C NET TOTAL 2531 52 66 76 84 94 96 97 99 101 153 105 124 106 106 124 108 106 106 106 177
C
Present value of £1 at 4% 1 .9615 .9246 .8890 .8548 8219 .7903 .7599 .7307 .7026 .6756 .6496 .6246 .6006 .5775 .5553 .5339 .5134 .4936 .4746 .4564
m
CD
C,
CD
C
2
-u
Co
CM
ici
LIFE CYCLE COST SUMMARY
C,
OPTION B
Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Costs £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k
904 - - - - - - - - - • - - - . - - - - - -
Capital
- - - - - - - - - - - - - - - - - - - - -
Financing
- 89 89 89 89 89 89 89 89 89 89 89 89 89 89 89 89 89 89 89 89
Operation
Maintenance:
annual - 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15
- - - - - - - - 45 3 21 - - 32 3 - - - 69
intermittent 17 3
- - - - - - - - - - - - - - - - - - - - -
Occupancy
- - - - - - - - - - - - - - - - - - - - -
Disposal! residual value
Total 904 104 104 104 104 121 107 104 104 104 149 107 125 104 104 136 107 104 104 104 173
Total (inc VAT) 1062 122 122 122 122 142 126 122 122 122 175 126 147 122 122 160 126 122 122 122 203
LessTaxallowance 0 75 66 59 54 56 48 44 43 42 57 41 46 38 38 50 39 38 38 38 63
Presentvalueof1 1 .9615 .9246 .8890 .8548 .8219 .7903 .7599 .7307 .7026 .6756 .6496 .6246 .6006 .5775 .5553 .5339 .5134 .4936 .4746 .4564
at4%
Present value 1062 45 52 56 58 71 62 59 58 56 80 55 63 50 49 61 46 43 41 40 64
-1
CD
0
C)
0
C)
C,
0
=
0
0
0
0
CAPITAL
OPTION A OPTION B
122
OP ERATION
OPTIONA OPTION B
Cleaning
OPTIONA 10500
Budget allowance £7.00 per m2
OPTION B
Budget allowance £9.00 per m2 13500
OPTION A
Budget allowance £50.00 per m2 75000
OPTION B
Budget allowance £42.00 per m2 63000
Insurance
Buildingfabric replacement
OPTION A
Budget allowance 0.2% of building cost 4308
(2154)
OPTION B
Budget allowance 0.2%of building cost 1808
(9O4)
Gas
Heating—Option A 2000 50 1.076** 1500 160 240,000 2582 1500 190 285,000 3067
N)
C/)
CD
C, Electricity
0
N) Lighting 2200 80 5.50 1500 20 52,800 2904 1500 20 52,800 2904
Small Power 2200 100 5.50 1500 10 33,000 1815 1500 10 33,000 1815
Power for mechanical services 2200 60 5.50 1500 58*** 114,840 6316 1500 20 39,600 2178
* NB: formula for kwh = area (d) X energy rate (e) X unit energy cost (c) X building usage (a) x diversity (b)
1000
-vi
Di *** Assume cooling load 120 watts/m2
Dvi
CD Conversion rate electricity to cooling 2.5:1
0,
c.0 Thereforew/m2 for cooling 120/2.5 = 48 ÷ 10 (other mechanical plant) = 58
JL
ANNUAL MAINTENANCE
OPTION A OPTION B
25
-I
CD
0)
CD
INTERMITTENTMAINTENANCE
CD OPTION A
CD
C,, Year 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
C,
CD Costs £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £h £k £k £k
C,,
Roof renewal — — — — — — . — 10
CD
C)
— — — — — — — — — 0.5 — — — — 0.5 — — — — 0.5
CD Externaldecoration (fire escapes only) 0.5
=
Internal finishings:
— — — — — — 3.0 — — — — 3.0 21 — — — 3.0 — — — 14
CD
carpets
CD
— — — — — 5.5 — — — — 5.5 — — — — 5.5 — — — — 5.5
paintwork,etc.
Engineeringservices:
— — — — — — — — — — 42 — — — — — — — — — 42
mechanical(equipment)
— — — — — — — — — — 14 — — — — 14
electrical(luminaires)
— — — — — — — — — — — — — — — 15.5 — — — — —
lifts(majoroverhaul)
0 Totals — — — — — 6 3 — — — 62 3.0 21 — — 21.5 3.0 — — — 86
Costs £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k
Roofrenewal — — — — — — — — — — — — — — — — — — — — 10
External decoration (facades,etc.) — — — — — 11 — — — — 11 — — — — 11 — — — 11
Internal finishings:
— — — — — — 3.0 — — — — 3.0 21 — — — 3.0 — — — 14
carpets
— — — — — 5.5 — — — — 5.5 — — — — 5.5 — — — — 5.5
paintwork,etc.
Engineeringservices:
— — — — — — — — — — 14 — — — — — — — — — 14
I mechanical(equipment)
— — — — — — — i4 — — — — — —
electrical(luminaires)
— — — — — — — — — — — 15.5 — — — — —
lifts(majoroverhaul)
— — — — — 16.5 3.0 — — — 44.5 3.0 21 — — 32 3.0 — — — 68.5
Totals
— — — — — 17 3.0 — — — 45 3 21 — — 32 3 — — — 69
Total £k to life cyclecost summary
C,
aD
CD
TAX
VAT CHARGEABLE
VALUE VAT RATE OPTION A OPTION B
£k % £k £k
Total VAT to
capital costs 377 158.2
Total£k to
life cycle 377 158
cost
summary -________________
VAT is chargeable directlyon all running costs items and appears on the summary.
Corporation Tax
The client currently payscorporation tax at the rate of 31%.
Thispercentagehas been assumed for all calculations.
Tax allowance - running costs
100% tax deductible based upon total inclusiveof VAT*, e.g. running cost £100
VAT £17.50
Total £117.50
Tax allowance 31% £36.43
2J1
-I
CD
0) TAX ALLOWANCE
=
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
£k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k £k
OPTIONA
Capital allowances
Total allowancessee next page
£696k(inc VAT)@25% p.a.
— 174 131 98 73 55 41 31 23 17 13 10 — — — — — — — — —
reducingbalance
Running cost allowances
F;
From LCC summary(inc VAT) 154 154 154 154 161 157 154 154 154 227 157 179 154 154 150 157 154 154 154 257
Total 328 285 252 227 216 198 185 177 171 240 167 179 154 154 180 157 154 154 154 257
OPTION B
-',
Capital allowances
Total allowancessee next page
C,)
CD
C, £482.lk (inc VAT) @25% pa.
— 90 68 51 38 29 21 16 12 9 7 — — — — — — — — —
0 reducingbalance 121
Total 243 212 190 173 180 155 143 138 134 184 133 147 122 122 160 126 122 122 122 203
-ø
CAPITALALLOWANCE Proposed capitalal!owancefortaxationpurposes
Subject tonegotiation and agreementwiththe Inland Revenue on evidence of eventualcosts
OPTION A OPTION B
GFA: 1500m2 Total cost %tax allowable Tax allowable Total cost %tax allowable Taxallowabl Remarks
£k £k £k £k £k £k
2.0 20 0.4 — — —
Fittings/fixtures
Sanitary appliances 9.5 100 9.5 9.5 100 9.5
PublicHealthservices 21 — — 21 — —
8.5 — — 3 — —
Drainage
(% of sub-total) constructioncosts
Contingencies 46.5 27.5 12.8 19.5 45.4 8.9
(%of sub-total)
Total constructioncost 1833 759.5
(% of constructioncost)
VAT 377 27.5 103.7 158 45.4 71.7 Option A—Fees only
Years 2 3 4 5 6 7 8
Years 2 3 4 5 6 7 8
'-
RATEPER CENT
Years 2 3 4 5 6 7 8
A2 There will be one of two situations. Either the building will have reached
the end ofits life, with no alternativeuse, or the building will have reached
the endofthe life for its plannedpurpose, but does have an alternativeuse.
i33
< Appendix B: Obsolescence
B2 Buildingsusually end their 'life' before the end of their physical life. The
most common reasons for buildings becoming obsolete are probably
economic and functional considerations. Buildings designed for a specific
specialised use, with little or no flexibilityfor changing theiruse, are there-
fore likely to have shorter lives than buildings offering flexibility for the
change of functionofthebuilding.
B3 The table below gives definitions and examples of each form of obsoles-
cence:
Definition of Basis for Examples of
Types of typeof assessment of factors leadingto
obsolescence obsolescence buildinglife obsolescence
Deterioration of
suspended concrete
floors, containinghigh
alumina cement, in
multi-storey buildings,
affecting structural
stability.
Economic Life of the How long will The value of the land
buildingto when the building be on which the building
occupation is not economic for stands is more than
considered to be the client to the capitalised full
the leastcost own or rental value that could
alternative of operate? be derived from
meeting a letting the building.
particular
objective. The asset would
achieve a better rate
of return in the
possessionof
another, or in the
redevelopment or
refurbishment scheme.
The following checklist provides suggestions for cost and value categories to be
considered. This list is not exhaustive and items may need to be added or others
disregardedas applicableto anyparticular project.
Cl CAPITALCOSTS
Cl.l Land
Cl.2 Feeson acquisition
Cl.3 Design team professionalfees
Cl.4 Demolition andsite clearance
Cl.5 Constructionprice forbuilding work
Cl.6 Costof statutoryconsents
Cl.7 DevelopmentLand Tax
Cl.8 CapitalGains Tax
C1.9 ValueAdded Tax
C1.lO Furnishings
Cl.ll Other capital costs
Cl.12 Commissioningexpenses
Cl.13 Decanting charges
C2 FINANCING COSTS
C2.l Finance for land purchase and during construction
C2.2 Finance during period of intended occupation
C2.3 Loancharges (public sector)
C3 OPERATION COSTS
C3.l Energy
C3.2 Cleaning
C3.3 Rates
C3.4 Insurances
C3.5 Security andHealth
C3.6 Staff (relatedto the building)
C3.7 Managementand administrationofthe building
C3.8 Landcharges
C3.9 Energy conservationmeasures
C3.lO Internal planting
C3.11 Equipment associated with occupier's occupation
C5 OCCUPANCYCOSTS
C5.1 Client's occupancy costs
C6 RESIDUAL VALUES
C6.1 Resale value— building, land and plant and equipment
C6.2 Related costs — demolition and site clearance and disposal of fees and
charges
C6.3 Capital Gains Taxand balancingcharges
L3TJ
Appendix D: Glossaryof Terms for Taxation
Dl CAPITALEXPENDITURE
Money expendedin acquiring long life assets which includes land, build-
ings, permanent improvements or additions/extensionsto existing assets
including associated professional fees, furniture and equipment thereto,
which are intendedfor use in the carryingout ofbusiness operations. These
assets should have a useful life of more than oneyear.
D2 REVENUE EXPENDITURE
Expenditure incurred as a trading expense e.g. salaries, consumables,
occupancy and regular maintenance costs.
D3 TAXATION'DEPRECIATION'ALLOWANCES(FORTAXATIONPURPOSES)
This is a collective term fortaxation relief affordedto commercial(tax pay-
ing) organisations to offset the cost of capital expenditure incurred upon
assetsused for the purposesoftheirtrade.
D4 INDUSTRIALBUILDING
Industrial buildings or structureswhich qualify for capital allowances are
defined in the statutes CAA 1968 S7 and CAA 1990 S18. These include
factories, manufacturing, storage, docks, tunnels and mines. There are
specific rules which apply where part of the building is used for a non-
qualifyingpurpose.
D5 PLr ANDMACHINERY
This type of tax relief was introducedafter the second world war to provide
an incentive to industry to replaceequipmentused in industry andcommerce.
D6 INITIAL ALLOWANCES/FIRSTYEARALLOWANCES
These were introducedto provide an accelerationto the standard rate of
annual tax relief (depreciation allowance) being a proportion ofthe original
capital expenditure.
D8 BALANCING ALLOWANCE
Upon disposal of an asset a comparisonbetween its value and the written
down amount remaining on the owner's accounts is required.
If the asset is sold for a sum in excess of the vendor's after tax relief cost,
then a 'profit' has arisen which is subject to an adjustmentto the deprecia-
tion allowance (i.e. reductionof tax relief), termed a 'balancing charge'.
Alternatively, if the asset is 'scrapped' or disposed of at low value
(compared with the residual amount) then an additional tax relief is
awarded,termed a 'balancing allowance'.
3c
Appendix E: Examples of Items of Expenditure Likelyto AttractTaxation
Allowances
Item Plant and equipment
Heat source 1. Boilers and equipment, fuel pumps, waterpumps, flue, etc.
(not the pipeworkfrom the boiler)
2. Boiler bases and foundations
3. Oil storage tanks and foundations
4. Fuel hoppers, ash removal plant
5. Control equipment to the heating system
6. Builder's work in connection with the heat source
7. Part cost of boilerroom
Gas installations 1. Gas fires, cookers and equipment including flues and
builder's work in connection
140
Item Plant and equipment
Communications 1. Clocks
installations 2. Sound distribution, bells, signals and the like
3. Fire alarms
4. Burglar alarms
5. Telephone installation
6. Builder's work in connection with communication installations
Data Sources
CIBSE. CIBSE Guide, Section B18, Owning and Operating Costs. Chartered
Institute of BuildingServicesEngineers, London. Gives indicative details ofenergy
consumption, maintenancecosts andrough life spans for plant (currentlybeing
updatedin more detail).
TheSurveyors'Construction Handbook Part 2, Section2, Effectivefrom1/6/99 Page 1
Appendix F (4/99)
HAPM ComponentLife Manual. E & FN Spon. Tel: 0171 204 2481, 1995.
Comprehensivelife-span assessments for over 500 housing components based on
insured life assessments.
Introduction
This section discusses some ofthe uses for elemental information and gives a
complete definition for each element. The elements are also referred to in
other sections ofthe handbook.
2.3.1.2 Elements relate to the design process. Therefore, budget estimates are
normallypreparedin elemental form and developing the designs are normally
described and costed in thismanner.
2.3.2.3 The elemental cost analysis can then be used to estimate futureprojects ofa
similartype.
The Surveyors' ConstructionHandbook Part 2, Section 3 (10/99) Effective from 1/11/99 Page 1
PART 2, SECTION 3
Page 2 Pa't 2, Section 3 (10/99) Effective from 1/11/99 The Surveyors' ConstructionHandbook
t4-S
PART 2, SECTION 3
i
(b) Contractor Proposals
The contractor's proposals should follow the format of the employer's
requirements. The preparation of the specification for materials and
workmanship in elemental form facilitates the development of the
specification alongside the design and tendering process. It also highlights
any amendments to the employer's requirements either proposed by the
contractor or requestedby the client.
(e) InterimPayments
The JCT Standard Form ofBuildingContract With Contractor's Design 1998
(CD98) provides for the use of one of two methods for interim payments.
Alternative Ais by stage payments andAlternative B is by periodicpayments.
If the contractsum analysis has been set out elementally it lends itselfto
Alternative A, as elements and sub-elements provide easily definable stages.
The Surveyors' Construction Handbook Part 2, Section 3 (10/99) Effective from 1/11/99 Page 3
PART 2, SECTWN 3
2.3.3.2 AcTIvITYSCHEDULES
The use of an activity schedule broken down into BCIS standard elements
would also allow an elemental cost analysis to be completed relatively easily
and wouldbe particularly useful ifprojects have beenprocuredwithoutbills
ofquantities.
SUBSTRUCTURE
2 SUPERSTRUCTURE
2A Frame
2B Upperfloors
Upper floors, balconies and structural screeds, suspended floors over or in
basements.
2C Roof
2C1 Roofstructure
Construction, including eaves and verges, plates andceilingjoists,
trusses, gable ends, internal walls and chimneys above plate level,
parapet walls andbalustrades.
2C2 Roofcoverings
Roofscreeds and finishings. Battening, felt, slating, tiling and the like.
Flashings andtrims. Insulation. Eaves and verge treatment.
2C3 Roofdrainage
Gutters where not integral with roofstructure, rainwater heads and roof
outlets. (Rainwater downpipes to be included in 'Internal drainage'
(5C1).)
2C4 Rooflights
Rooflights, opening gear, frame, kerb and glazing. Pavement lights.
2D Stairs
2D2Stairfinishes
Finishes to treads, risers, landings (other than at floor levels), ramp
surfaces, strings and soffits.
2E Externalwalls
External enclosing walls including that to basements but excluding items
included with 'Roof structure' (2C1). Chimneys forming part of external
walls up to plate level. Curtain walling, sheetingrails and cladding. Vertical
tanking. Insulation. Appliedexternal finishes.
2F Windowsand externaldoors
2F1 Windows
Sashes, frames, linings and trims. Ironmongery and glazing. Shop
fronts. Lintels, sills, cavity damp-proofcourses andwork to reveals of
openings.
2F2 Externaldoors
Doors, fanlights and sidelights. Frames, linings andtrims.
Ironmongery and glazing. Lintels, thresholds, cavity damp-proof
courses and work to reveals ofopenings.
3 INTERNAL FINISHES
3A Wall finishes
3B Floorfinishes
3C Ceiling finishes
4 FITTINGSAND FURNISHINGS
4A2 Softfurnishings
Curtains, loose carpets or similar soft furnishing materials.
4A4Equipment
Non-mechanical and non-electrical equipment related to the function
or need ofthe building (e.g. gymnasia equipment).
1s
PART 2, SECTION 3, APPENDIX A
5 SERVICES
5A Sanitary appliances
Baths, basins, sinks, etc. WC's, slop sinks, urinals and the like. Toilet-roll
holders, towel rails, etc. Traps,wastefittings; overflows and taps as appropriate.
SB Servicesequipment
SC Disposalinstallations
5C1 Internal drainage
Waste pipes to 'Sanitary appliances' (5A) and 'Services equipment' (5B).
Soil, anti-syphonageandventilationpipes. Rainwater downpipes. Floor
channels and gratings and drains in ground within buildings up to external
face ofexternal walls.
SD Waterinstallations
5D1 Water— mains supply
Incoming water main from external face ofexternal wall at point of
entryinto building including valves,watermeters,rising main to (but
excluding) storage tanks andmaintaps. Insulation.
SE Heat sourè
Boilers, mounting, firing equipment, pressurising equipment, instrumentation
and control, ID andPD fans, gantries, flues and chimneys, fuel conveyors and
calorifiers. Cold and treated water supplies and tanks, fuel oil and/or gas
supplies, storage tanks, etc., pipework, (water or steam mains) pumps, valves
and other equipment. Insulation.
The Surveyors Construction Handbook Part 2, Section 3 Effective from 1/11/99 Page 5
- ArnndixA (10/99)
PART 2, SECTION 3, APPENDIX A
5G Ventilating systems
Mechanical ventilating system not incorporating heating or cooling
installations including dust and fume extraction and fresh air injection, unit
extractfans, rotating ventilators and instrumentation andcontrols.
5H Electrical installations
5H2Electricpower supplies
All wiring, cables, conduits, switches from local distribution boards,
etc., to and including outletpoints for individual installations.
5H4Electric lightingfittings
Lighting fittings including fixing.
SI Gas installations
Town and natural gas services from meter or from point ofentry where there
is no individual meter: distribution pipework to appliances and equipment.
5J2Escalators
As detailed under 5J1.
5J3 Conveyors
As detailed under 5J1..
5K Protective installations
Paga 6 Part 2, Section 3 Effective from 1/11/99 The Surveyors' Construction Handbook
AppendixA(1O/99)
•L53
PART2, SECTION 3, -APPENDIX A
5K3 Lightningprotection
The complete lightning protection installation from finials conductor
tapes, to and including earthing.
5L Communication installation
Door signals
Timed signals
Call signals
Clocks
Telephones
Publicaddress
Radio
Television
Pneumatic message systems
5M Special installations
All other mechanicaland/or electrical installations (separatelyidentifiable)which
have not been included elsewhere, e.g. chemical gases; medical gases; vacuum
cleaning; window cleaning equipment and cradles; compressedair; treated water;
refrigeratedstOres.
Part 2,Section 3
The Surveyors' ConstructionHandbook
— AppendixA (10/99)
Effectivefrom 1/11/99 Fage 7
'SI-I-
PART 2, SECTION 3,APPENbIXA
6 EXTERNAL WORKS
6A Site works
6A1 Sitepreparations
Clearance anddemolitions. Preparatory earth worksto form new
contours.
6A2Surfacetreatments
Roads and associated footways
Vehicle parks
Pathsandpavedareas
Playingfields
Playgrounds
Games courts
Retaining walls
Landdrainage
Landscape work
6A4Fittings andfurniture
Notice boards, flag poles, seats, signs.
6B Drainage
Surface water drainage. Foul drainage. Sewage treatment.
6C External services
6C1 Watermains
Main from existing supply up to external face ofbuilding.
6C6 Sitelighting
Distribution, fittings and equipment.
7 PRELIMINARIES
8 EMPLOYERS CONTINGENCIES
Notes
Substructure
(a) Where lowest floor construction does not otherwise providea platform,
the flooringsurfaceshallbe includedwith this element (e.g. ifjoisted floor,
floor boarding would be included here).
(b) Stanchions and columns (with relevant castings) shall be included with
'Frame' (2A).
(c) External enclosing walls to basements shall be included with 'External
walls' (2E).
2A Frame
(a) Structural walls which form an integralpart ofthe loadbearing framework
shall be included either with 'External walls' (2E) or 'Internal walls and
partitions' (2G) as appropriate.
(b) Beams which form an integral part of a floor or roofwhich cannot be
segregatedtherefrom shallbe included in the appropriate element.
(c) In unframedbuildings roof beams and trusses and floor beams shall be
included with 'Upper floors' (2B) or 'Roofstructure'(2C1) as appropriate.
(d) If the 'Stair structure' (2D1) has had to be included in this element it
should be noted.
2B Upper floors
(a) Where floor construction does not otherwise provide a platform the
flooring surface shall be included with thiselement (e.g. ifjoisted floor, floor
boardingswouldbe included here).
(b) Beams which form an integral part of a floor slab shall be includedwith
this element.
(c) If the 'Stair structure' (2D1) has had to be included in this element it
shouldbe noted.
2E External walls
(a) Ifwalls are self-finished on internalface,this shallbe stated.
3A Wall finishes
(a) Surfaces which are self-finished .(e.g. self-finished partitions, fair-faced
work) shall be included in the appropriate element.
(b) Insulation whichis awal1 finishing shall be included here.
3B Floor finishes
(a) Where the floor construction does not otherwise provide a platform the
flooring surface will be included either in 'Substructure' (1A) or 'Upper
floors' (2B) as appropriate. Access floors.
3C Ceiling finishes
(a) Where ceilings principally provide a source ofheat, artificiallighting or
ventilation, they shall be included with the appropriate 'Services' element.
4A3 Worksófa1
(a) Where items in this element have,a significant effect on other elements a
note should be included in the appropriate element.
5B Services equipment
(a) Local incinerators shallbe included with 'Refuse disposal' (5C2).
5E Heat source
(a) Chimneys and flues which are an integral part of the structureshall be
includedwith the appropriate structural element.
(b) Local heat source shall be includedwith 'Local heating' (5F4).
The Surveyors' Construction Handbook Part 2, Section. 3 Effective from 1/11/99 Page 11
AppenJAi1D/99)
PART 2, SECTION 3, APPENDIX A
5L Communication installations
(a) Each installation shall be stated separately where appropriate.
(b) The cost ofthework in connection with electrical supply shallbe included
with 'Electricalpower supplies' (5H2).
5M Special installations
(a) The cost ofeachinstallation shall, where appropriate, be shownseparately.
(b) Items deemed to be included under 'Refrigerated stores' comprises all
plant required to provide refrigerated conditions (i.e. cooling towers,
compressors, instrumentation and controls, cold room thermal insulationand
vapour sealing, coldroom doors, etc.)for cold rooms, refrigerated stores and
the like otherthanthatrequiredfor 'Spaceheating and airtreatment' (SF8 and
SF9).
6B Drainage
(a) To include all drainage works (other than land drainage included with
'Surface treatment' (6A2)) outside the building, to and including disposal
point, connection to sewer or to treatment plants.
159
PART 2, SEcTION4
Introduction
This section describes some of the tasks and responsibilities that surveyors
may be asked to undertake when appointed as an employer's agent on a
design and build contract.
At its most basic, the role of the employer'sagent is to act on behalf ofthe
client in the matters specified in the contract. However, in practice there are
a wide range oftasksthat a client may ask an employer'sagentto undertake.
This section is not about procurement options; it assumes that all optional
procurement strategies have been carefully considered by clients and their
advisorsand that the decisionhas been madeto adopt design and build. With
regardto procurement strategies, reference shouldbe made to Part3, Section
1 of this handbook ('Developing an Appropriate Building Procurement
Strategy') which provides extensive guidance on selection of the most
appropriate option for the procurement ofbuildings.
There are a number of 'standard' forms of design and build contracts, but
where specific reference is made in this section, it is to the currentedition of
the Joint Contracts Tribunal (JCT) Standard FormofBuildingContract With
Contractor's Design 1998 (CD 98). This form ofcontractmakes no provision
for a contract administrator (CA) and all matters which would have been
certifiedby the CAare ascribedto either the client or the contractor.
The JCT practice note, CD/lA states that, 'Because the employer will almost
certainly be a corporate body of one kind or another, provision is made for a
person to be named to act as the employer's agent for the purposes of the
contract.The contract treats the acts ofthe agent as those ofthe employer.Unless
therefore the employer specifically otherwise states in his requirements, the
contractor can andmust regard the employer's agent as the duly authorisedagent
ofthe employer for theperformance ofany oftheactions ofthe employer under
The Surveyors' ConstructionHandbook Part 2, Section 4 (10/99) Effective from 1/11/99 Page 1
1br
PART 2, SECTION 4
It should be noted that the prescribed duties of the employer's agent are
restricted to 'access to documents on site' and 'access to works, workshops,
etc.'. Importantly however, the contract also allows the client to delegatehis
responsibilities underthe contract andinpractice this is usuallywhat happens.
• 2.4.1
2.4.1.1
Background
Design and build is not a new concept. Many historic buildings have been
procuredin this way and the technique has been used for simple industrial
shell buildings. However, in recent years the use of design and build has
extended to cover a significant number ofbuildingprojects ofall types.
2.4.1.4 Responsibility for the development ofthe design, as well as the construction
of a project, is firmly placed with the contractor. This is perceivedto clarify
any litigation or disputebetweenthe parties to the contract.
2.4.1.5 Proponents ofdesign and build also claim that it can allow tenderersto bring
their skills to the design which, throughthe competitive process, can deliver
benefits to the client in terms ofbuildabiltiy. Furthermore, tendererscan take
account of current availability of labour, materials and plant in their design
and pricingconsiderations.
Page 2 Part 2, Section 4 (10/99) Effective from 1/11/99 The Surveyors' ConstructionHandbook
PART 2, SECTION 4
2.4.2.1 The JCT Standard Form of Building Contract With Contractor's Design was
first introduced inresponse to demand fora form ofcontract whichallowed the
contractor to cany out a complete contract (including designdevelopment) for
a lump sum.
2.4.2.2 Throughout its life the JCT Standard Form of Building Contract With
Contractor's Design has been subject to many amendments to account for
changes inthe law, regulations affecting building development andincreasing
expectations andinvolvement of clients.
2.4.2.3 Alongside the JCT contracts, there are two relevant practice notes which
should be referred to:
2.4.2.4 In Englandand Wales the contract documents under this form are:
•the employer'srequirements;
•the contractor'sproposals;
•the contract sum analysis; and
•the articlesind conditions set outin the form including optional
supplementary provisions and appendices.
2.4.3.2 The employer'sagent will normally be involvedfrom the outset and will be
instrumental in producing the contract documentation, including the
employer's requirements based on the brief developed with the client.
Thereafter, he can arrange or assistwiththe selection oftenderersandarrange
the formal tendering process. Subsequently he can review the contractor's
The Surveyors' ConstructionHandbook Part 2, Section 4 (10/99) Effective from 1/11/99 Page 3
PART 2, SEcTIoN 4
proposals (including the developed design and the contract sum analysis) to
ensure that all aspects of the employer'srequirements have been met with
particularreference to quality, time and cost issues.
2.4.3.3 Where the employer's agent has been delegatedthe authorityby the client, he is
responsible for ensuring that the project is carried out in accordance with the
conditions of contract, employer's requirements, contractor's proposals and
contract sum analysis. The role willusually include monitoring the construction
processto ensurebestpractice, controllingexpenditureand overseeing contractor
compliance with all current regulations. Typically, it will also involve the
administrationofthe project interms ofdesignand cost by sanctioningall design
issues and by instructingany changes. The employer's agent will be responsible
for checkingthecontractor'svaluationsand confirminginterim and final payment
amounts to the client in accordancewith the contract conditions.
2.4.3.6 The employer's agent should advise the employer on those roles that are
within his competency, which attract a duty of care similar to that under
traditionalprocurement methods and advise the employer on the appointment
of any other consultants requiredto fulfil any additional roles.
2.4.3.7 A recent court decision held the employer's agent responsible for failure to
comment on high risk design elements of the contractor'sproposals and an
ongoing failureto approvethe contractor'sdesign development proposals. It
would be an unusual project arrangement if these essential tasks were not
delegated by the client to the employer's agent. On the other hand, the duty
to approve the contractor's design development and drawing should be
included expressly or by implication in the contractbetweenthe client and the
employer'sagent.
2.4.3.9 Design and build is fundamentally about the allocation ofrisk and responsibility.
Therefore,itis strongly recommendedthat the agent's contractual responsibilitiesas
delegated by the client, together with any additional duties he has agreed to
undertakeonbehalfofthe client, are clearlydefinedandrecorded,andthatthe client
understandsthe position.
Page 4 Part 2, Section 4 (10/99) Effective from 1/11/99 The Surveyors ConstructionHandbook
'
PART 2, SECTON 4
2.4.4.1 The JCT practicenote, CD/lA offers limited guidance on the completion of
the employer'srequirements.
2.4.4.6 The employer's agent should try to encourage the client to concentrate on the
purpose, performance and desired end requirements ofthe project and to avoid
involvement in the constructionmethod.
2.4.4.7 It is, however, most important that the client's input is sufficiently detailed to
enable the production of clear and concise 'employer's requirements' to
achieve the client's objectives. The requirements should also be
comprehensive enoughto avoid amendments duringthe constmctionprocess
as these can be very costly.
2.4.4.8 All relevant parts of the client's brief should be given in the employer's
requirements. Additional requirements arising from meetings during the
tender process shouldbe incorporated into the requirements by amendment.
There should be no misunderstanding as to what comprises the employer's
requirements. Similarly, any amendments to the contractor'sproposals after
they have been submittedshould be incorporated. Any ambiguity between
thesetwo documents could giverise to conflict at a later date.
The Surveyors ConstructionHandbook Part 2, Section 4 (10/99) Effective from 1/11/99 Page 5
164
PART 2, SECTION 4
2.4.4.9 Contractors are only responsible for that whichthey designor specify; in turn
employers or their consultants are responsiblefor all that they design and/or
specify, unlesstherehas been apre-agreedlimitation to the contract. Thus, in
order for the employer to maximise the benefit from design and build, the
extent of any designing and specifying by prescription in the employer's
requirements shOuld be limited to those elements in hich the employer
requiressuch control.
2.4.4.10 The Building Cost Information Service (BCIS) publication, Elements for
DesignandBuildoffers guidance to employer'sagents on the use ofbuilding
elements for structuring the employer's requirements and the contractor's
proposals/contract sum analysis. Elementsfor DesignandBuildis considered
to be important supplementary reading. The list of elements, and their
definition, is also given in Section 2.3 ofthishandbook.
2.4.5.1 The forms of design andbuild contractallow for the production of variation
to the conventional design and buildcontract, for example:
•packagedeal;
•turnkey;
• develop and construct;
•two-stage ten4eT;
•joint venture/negotiated; and
• design buildfund and operate
Page 6 Part 2, Section 4 (10/99) Effectivefrom 1/11/99 The Surveyors' Construction Handbook
tb5
PART 2, SECTiON 4
2.4.5.3 DEVELOPANDCONSTRUCT
2.4.5.4 Two-STAGETENDER
Design build fundand operate (DBFO) contracts have been created as a result
of the private finance initiative. Although this form ofprocurement has been
listed as a design and buildvariantit should be remembered that the end user
never actually owns the building (unless otherwise provided). CD 98 is not
therefore appropriate as part ofthe primary agreement, although itcould feature
in sub-contract. In most instances, the client willappoint a shadow design team
to ensure that user's requirements are properly established and communicated
to the bidders. The shadowtéamchecks the offers received to ensurethat the
user's requirements have been addressed and continues to monitor design and
development with the preferred bidder. Thereafter the shadowteam ensures that
the building incorporates the specified user requirements.
The Surveyors' Construction Handbook Part 2, Section 4 (10/99) Effective from 1/11/99 Page 7
166
PART 2, SECTION 4
246 Novation
2.4.6.1 Novation can be employed on any of the design and build variants and
involvesthe transferofthe client's contractwith his designer(or designers)
to the successful contractor, this arrangement having been included in the
tenderdocuments. The contractor assumesthe responsibility for the payment
of fees and associated value added tax (VAT), and receives the benefit of
continuity ofdesign. Oftenwhennovationis implemented, it is not appliedto
the quantity surveyorwho remains with the client acting as the employer's
agent duringthe designdevelopment andconstruction phase. Novationis not
defined in CD 98, althoughit is widely practised.
2.4.6.2 Where designers are novated it is important for clients to understand that their
designers' allegiance transfers from the client to the contractor. This transfer of
allegiance should be properly explained to the client prior to his deciding to
imp1ementnovation. It is also important that the employer's agent advises on
selecting appropriate designers and contractors and that the transfer of roles
occurs and is maintained.
Page 8 Part 2, Section 4 (10/99) Effective from 1/11/99 The Surveyor's ConstructionHandbook
167
PART 2, SECTION 4, APPENDIX A
The services to be provided should follow JCT practice notes, CD/lA and CD/lB
together with the NJCC's Code of Procedure for Selective Tendering for Design and
Build (1995).
The scope of services should be fuily agreed betweenthe employer's agent and the
client at the outset ofthe commission and all interested parties should be informedas
to the extent ofdelegated authority.
•
Advising on the need for specialist appointments where necessary
including appointments under CDM (Regulations) 1994 (also
competency andresource check).
•
Agreeing with the client the scopeofthe employer'srequirements
(including the need for preliminary design, if any) andensuring that
these are 'signed off'.
•
Examining land transfer documents to clarifyboundary positions
including an assessment ofthe likely impact of existing easements
(including rights oflight, rights ofway, restrictive covenants and so
forth).
•
Initiating measuredsurvey with levels.
•
Preparing or procuring preliminary design for the development.
• Establishing with the client the programme to suit fundingavailability.
•
Assessing suitability and cost effectiveness of general andstructural
design.
• Reviewing scheme under Town and Country Planning Acts including
consultations with local planningauthority leadingto initialoutline
town planningapplication. (Note: Submission offormal full town and
country planning application is normally at a later stage (see A2) and
sometimes this application is by the contractor.)
• On projects involving the refurbishment of existing buildings the
provision ofdesign, cost assessment and submission offormaltown
and countryplanningapplications.
• Investigating/establishing location of existing servicesto site with
local and statutory authorities.
• Initiating and reviewing sub.-soil reports.
• Consulting as appropriate with relevantagencies, for example, English
Nature andEnglish Heritage.
•
Advising on the implementation ofthe ConstructionActandany other
relevantlegislation.
A2 PRE-CONTRACT
•
Advising on the need for further specialistappointmentswherenecessary.
•
Preparing cost estimate/structured cost plan.
•
Advising on need for risk analysisto includemarketresearchto
underpinfinancial viability.
•
Advising on any possible archaeological implications for the site.
•
Reviewing sub-soil reports and commenting on foundation design and
contamination considerations.
•
Assessing environmental impact andadvising generally on
environmental issues.
• Conducting local public investigations as related to town planning,
including consultation with building occupiers prior to submitting a
full town and country planning application.
•
Arranging drawings and performance specification for mechanicaland
electrical services.
•
Arranging design/cost audit at appropriate work stages if appropriate.
•
Advising on the need for provision of Party Wall or Access to
Neighbouring Land ActAgreements.
• Advising on secure by design.
•
Developing projectbrief with client andreflecting same in the
employer'srequirements.
• Establishing with client the format ofthe contract sum analysis.
• Assisting with completion offormal applicationsin connection with
approvalsrelating to funding,necessary consents and other requirements.
•
Advising level ofcontingenciesand preparing appropriatedaywork clause.
•
Advising on tendering options including single- or two-stage tendering,
develop and construct or joint venture.
•
Advising on optional clauses in standard forms ofcontract, in particular
CD 98 supplementaryprovisionswhichprovide both parties with time
and cost certainty.
•
Advising on dispute resolution.
• In consultationwith client finalising the employer's requirements
document and arranging for this to be formally 'signed off' by the client.
• Where applicable, advising (after interview ifrequired) on the
selection of suitable tenderersincluding their capacity, resources,
financial and tax exemption status.
•
Reviewing andreportingon tenders receivedfor the project including
comparison with cost plan andcomment on programmeproposedby
each.
• Advisingon all aspects offuture maintenance ofthe completed
development.
• Advisingon services installation andfuture maintenance to these
services including checking andcommenting upon working drawings
producedby tenderers.
• Advisingon energy ratings, forexample,National Housing Energy
Rating and Standard AssessmentProcedure.
• Ensure access auditis executed (to meet the requirements ofthe
DisabilityDiscrimination Act).
A3 CONTRACT DuRATIoN
The Surveyors Construction Handbook Part 2, Section 4 Effective from 1/11/99 Page
AppendixA (10/99)
170
PART 2, SECTION 4, APPENDIX A
Page 4 Part 2, Section 4 Effective from 1/11/99 The Surveyors' Construction Handbook
AppendixA (10/99)
ill -
PART 2, SECTION 4, APPENDIX A
A4 POST-CONTRACT
A5 GENERALADDITIONAL SERVICES
The Surveyors Construction Handbook Part 2, Section 4 Effective from 1/11/99 Page 5
ppendixA (10/99)
PART 2, SECTION 4, APPENDIX B
The requiredlevel of detail will vary from clientto client and contractto
contractbut it is suggested that information on this checklist wouldbe the
minimum requirement.
Where little design work has been carried out before tenders and proposals
are invited, a performance specification would be normally required.
However, where a great deal of design work has taken place a prescriptive
specificationwouldbe needed.
B2 CHECKLIST
B2. 1 GeneralInformation
• Projecttitle
• Employer
• Employer'sagent
• List ofdrawings andotherinformation accompanying documents
• Location, including a narrative on the proposeduse/userofthe building.
An indication of the employer's business and overall objectives (to
providea feel for the eventual product)
• Access to site
• Site boundary defined
• Form ofcontract
• Permissible modification to standard form ofcontract
• Details ofappendices to the conditions of contract
Form ofcontract sum analysis
The Surveyors' Construction Handbook Part 2, Section 4 Effective from 1/11/99 Page 1
ppendix B (10/99)
'73
PART 2, SECTION 4, APPENDIX B
Basis of design
Design standards
• legislation or standards
• details ofstandards which apply (for examplecodes ofpractice)
• statementofworkmanship
• tolerances
• CDM regulations
Aesthetics
• specific aesthetic needs (otherthan planningrequirements)
Integration ofcomponents
• relationship with each other
• methodsof dealing with interfaces
• methodofdealingwith services installations. For example, level of
concealment of services and architectural treatments to exposed
surfaces
The specifications and design checklist (see Section B2.5) can be used in
preparing employer's requirements or a specification for a contractor's
proposal.
J7Lt
PART 2, SECTION 4, APPENDIX B
Flexibility
•
flexibility of accommodation.
• flexibility of
design
Energy
• energy conservation and heat measures
• insulation values
• Building research establishment environmental assessmentmethod
Loading requirements
Facilitiesfor disabled
• provision statementto comply with building regulations andcurrent
disability legislation
• specific needs of disabled
Building configuration
• written statement and/or drawing
• relationship of accommodation
• size ofaccommodation
• purpose
• layout
• dimensional constraints including clear heights underslabs and beams
• naturallighting - lux levels andmethodofmeasurement
• naturalventilation
• column grid arrangement including projections from walls, etc.
• clear ceilings/soffit heights
• tolerances
• vehicleaccess door heights and widths
• toilet/bathroom/locker room requirements
• kitchen/catering requirements
• restaurant/vending requirements
• plant room configuration
• noise breakoutbetweenrooms
p5
PART 2, SECTION 4, APPENDIX B
Means of escape
Plantrooms
Externalworks
• car
parking
• leisure facilities
• environmental considerations
• visual effects
• waste disposal
• emergency vehicle access
• water features
•
loading bays
• existing site features and treatments
• function
buildingswithinexternals
• site survey
B2.5 SpecjIcationsandDesign
Specification ofperformance, or the form ofconstruction, kind and quality
maybe givenin elemental or otherformat. The standard elementsare listed
below. (Please see Section 2.3 of this handbook or the BCIS publication,
StandardForm ofCostAnalysis for definition ofelements.)
1 Substructure
2 Superstructure
2AFrame
2B Upper floors
2CRoof
2C1 Roofstructure
2C2 Roof coverings
2C3 Roofdrainage
2C4 Roof lights
2D Stairs
2D1 Stairstructure
2D2 Stairfinishes
2D3 Stairbalustradesandhandrails
2E External walls
2F Windows and external doors
2F1 Windows
2F2 External Doors
2G Internal walls and partitions
2G1 WC cubicles
2H Internal doors
3 Internal finishes
lJb
PART 2, SECTION 4, APPENDIX B
3AWall filishes
3B Floor finishes
3C Ceiling finishes
3C1 Finishes to ceilings
3C2 Suspended ceilings
4 Fittings and furnishings
4AFittingsand furnishings
4A1 Fittings, fixtures and furniture
4A2 Soft furnishings
4A3 Works ofart
4A4 Equipment
5 Services +
5A Sanitary appliances
SB Services equipment
5C Disposalinstallations
SC1 Internaldrainage
5C2 Refuse disposal
5D Water installations
5D1 Water mains supply
5D2 Cold water service
5D3 Hot water service
5D4 Steam and condensate
5E Heat source
5F Space heating and air treatment
SF1 Water and/or steam (heating only)
5F2Ductedwarm air (heating only)
SF3 Electricity (heating only)
SF4 Local heating(heating only)
SF5 Otherheating systems (heating only)
SF6 Heating with ventilation (air heated locally)
SF7 Heating with ventilation(air heated centrally)
SF8 Heating with cooling (air heated locally)
SF9 Heatingwith cooling (air heated centrally)
SG Ventilating systems
SH Electrical installations
SH1 Electricsource and mains
SH2 Electricpower supplies
SH3 Electriclighting
5H4Electriclightingfittings
SI Gas installation
SJ Lift and conveyor installations
SJ1 Lifts and hoists
5J2 Escalators
SJ3 Conveyors
5K Protective installations
SKi Sprinkler installation
SK2 Fire-fighting installations
ni
PART 2, SECTION 4, APPENDIX B
5K3 Lightningprotection
5L Communication installations
5M Special installations
Details ofeach installation
5N Builder'swork in connection with services
50 Builder'sprofit and attendance on services
6 Externalworks
6A Siteworks
6A1 Sitepreparation
6A2 Surface treatment
6A3 Site enclosure and division
6A4Fittingsand furniture
6B Drainage
6C External Services
6C1 Water mains
6C2 Fire mains
6C3 Heating mains
6C4 Gas mains
6C5 Electric mains
6C6 Site lighting
6C7 Other mains and services
6C8 Builder'swork in conjunction with external services
6C9 Builder'sprofit and attendance on external mechanicaland
electrical services
6D Minorbuilding work
6D1 Ancillary buildings
6D2Alterations to existing buildings
Siteinvestigations
• soil
survey
•
ground conditions
• topographical surveys
•
existing services
• hazardous waste
•
archaeological features
I7.
PART 2, SECTION 4, APPENDIXB
• factoryinspector
• environmental health officer
• employer's building insurers (ifappropriate)
• Traffic Planning Authority
• utilities
• National Rivers Authority
• Any other authority or statutory undertaker whichhas jurisdiction
with regardto the works
Adjoining premises
• rights ofaccess to adjoining premises
Trespass, nuisance
• contractorto acquire rights as requiredand absolve theemployer of
responsibility
Information requirements
The employer'srequirements should give details of all records, drawings,
etc., requiredto be handedover on completion including:
• record drawings
• maintenance manuals
• CAD data disks
• design calculations
• staff training requirements
• warranties and guarantees
Exclusions
Give details of items not to be designed andlor constructed by the
contractor and the requirements and responsibilities for integrating these
intothe works
Future developments
Provide details ofany provisions requiredfor future developments
The Surveyors' ConstructionHandbook Part 2, Section 4 (10/99) Effective from 1/11/99 Page 7
-
Appendix B (10/99)
PART 3, SEcTIoN 1
This Section addresses these issues and provides, through the form of a
checklist,a process to aid selection.
'
Page 2 Part3, Section 1 (4/98) Effectivefrom 1/8/98 The Surveyors' Construction Handbook
16t
PART 3, SECTION 1
team will work together again, and if it does, the project is likely to be
different. Bach project is, therefore,a prototypeandinvolves a learning
curve. Project testing is rare.
•
selecting the strategy;
•
implementing the strategy; and
•
planningthe administrationofthe contracts necessaryto implement the
strategy.
The processes of selection and implementation are dealt with in 3.1.2 and
3.1.5.
(b) The number and style of contract documents will depend on the
contract strategyselected.
3.1.1.5 (a) Where direct consultant appointments are made, each will be the sub-
ject of a separate contractagreement, but where a design andbuild route is
selected, the designers may be appointedby the contractor. In the case of
construction management, the client will be required to enter into many
individual trade contracts.
EL
PART 3, SECTION 1
contracts may be involved. The principal advisercan assist the client in the
selectionof suitable contracts and the associateddocumentation.
(b) Assistance with the selection, documentation for tender, and advice in
relationto contractissues can be obtainedby the client from his professional
advisers and particularly the principal adviser. There are a numberof codes
of procedure to assist in this process and these are further listed and
referred to in 3.1.5 (Implementation). In broad terms, the factors which
affect the selectionof design and costconsultants shown above (capability,
competence, staffing and cost) will affect the choice of constructors, but the
documents on which selection is made (particularlyfor cost) can be exten-
sive and very complex.
(c) As with the selection of design and cost consultants, value for money,
ratherthan lowest price should be the aim in the selection of constructors.
Where clients regularly build, there may be a case for considering a special
arrangementwith a construction firm. This is increasingly referred to as
'partnering' and is one of the approaches referred to in The Lathani
Report1. Partnering enables both parties to seek 'win-win' solutions by
facilitating long-termrelationships to the mutualbenefit of both2.
(c) No one person has all the design skills for any but the very simplest
project and, therefore, the collaborationof many designers will be neces-
sary. This is particularly the case in specialist buildingsor buildings which
have sophisticatedmechanical and/orelectricalinstallations.
(e) It will also prove valuable for the client to indicate clearly his inten-
tions in respect of the programme and for the design team to respond in
terms of their strategy for meeting this programme. Methods for updating
progressshould also be sought by the client.
(f) As the majority of users, and indeed the client, are likely to find the
readingandinterpretation of design drawingsa difficulttask, it is important
to ensure that the design team present their proposalsin a form that can be
readily understood. (Computer aided design [CAD] may enable three
dimensionalpresentation.) The setting of the design andnot justthe design
in isolation should be taken into account. The client should feel able to
expect alternatives to be offered withinthe fee.
1L
PART 3, SECTION 1
(b) The techniques used to produce estimates vary according to the type
and level of data available at the time of preparation.The general level of
estimating accuracy improves as the design of a project develops.
Notwithstandingthis progressiveimprovement in accuracy, provided that
cost control is being exercised,the generallevel of accuracyofearly estim-
ates can be stated with sufficient precision for them to be valid parameters
for decision makingand for the managementof the project.
(d) The amount included in estimates to cover the uncertain cost of risks
based on the analysesdescribed above is known as the contingency. It is
importantthat contingencies are sufficient to coverrisks and are not eroded
to facilitate anylack of cost control.
(e) A primary concern may be the cost of running and maintaining the
building.The term 'cost-in-use' is used to describe how these costs can be
estimated,enabling the client to takethese matters into account when con-
sidering total project costs and building design. Higher initial costs may
result in lower runningor maintenancecosts during the life ofthe building.
(f) The earlier cost control procedures are instituted, the more effective
they will be. By way ofsimplisticillustration:
• cost varieswith (but not in direct proportionto) size: once the size of
a building is fixed, so is the generallevel of cost;
• the selectionof the most economical design for basic elements such
as foundations,structural frame, external cladding and roofing, is of
far greater costsignificance than the types of finishings; and
• the overall cost of mechanical and electrical systems and the effec-
tiveness of the cost control procedures which can be applied to them
is largely governedby early decisions as to thetype of systemselected.
(g) The methods used for cost control differ radically between the pre-
construction and construction stages of a project. Cost control during the
former depends partiy on the procurement strategy but more on control of
(k) All estimates and cost control proceduresshould take account of infla-
tion (i.e. the increase in constructioncost from the date when the estimate
was prepared to the date when the work is carried out). It is essential for
effectivecost control that:
• allowances be made for inflationin all estimates andthat the assump-
tions onwhich suchallowancé'ere calculated be stated;
• such allowances for inflationbe clearly identified within the estim-
ates and notbe usedto correct other overspending;
The Surveyors' Construction Handbook Part 3, Section 1(4/98) Effectivefrom 1/6/98 Page7 j
PART 3, SECTION 1
(I) The client should distinguish between inflation and the effect on con-
structionprices of market conditions at the time of tender. In simple terms,
contractorsadjust their tender prices by reducing or increasing their target
profit marginsin accordancewith commercialfactors. It is unwise to base
early estimates on any assumptions as to market conditions at the time of
tender as the constructionindustry is subject to wide, comparativelyswift,
changesin workloadin accordancewith economicconditions.
(c) The clientshould be aware of those tasks which are vital to completion
on time andthose tasks where some flexibility may be available. Time for
the approvalprocesses should be included as specific activities in the time
plan for the project. These are invariably vital as the need to obtain
approval is likely to be a prerequisite to further work proceeding on the
project.
(d) The process of time control is in many ways analogous to that of cost
control. Thus, a time control system can embrace:
• time budget — the overall project duration as fixedeither by specific
constraints or by the selected procurement strategy; the period which,
oncefixed, becomes a keyparameterfor management of the project;
(e) If the time taken for an activity exceeds its time allowance there are
essentially only two forms of corrective action available:
• the resequencing of later activities, which may involve abandoning
low priority restraints and/or phased transitions from earlier
activities to later activitieslogicallyfollowingthem; or
• shortening the time allowance for future activities by increasing the
resources to be made availablefor them.
If neitheris done, the overall time budget is likely to be exceeded and the
projectwill finish late.
(f) It should be noted that sometimes certain events are likely to delay the
overall completionof a project. In such cases, provision should be made,
taking cognisanceof the contractualconditions,for the effects to be taken
into account. Other measuresmay be considered,shouldthe clientso wish,
in mitigationof serious delays and associatedcosts.
(h) The client should recognisethat time control is as important during the
design stages of the project as the construction stage. Designers should
work to a series of deadlines at which different elements of the design
should be agreed (i.e. frozen) in order that costs andthe overall programme
be keptunder control.
(i) The client should consider developing (with the help of the project
manager if appointed) a time contingency (reserve), with strict procedures
for allocating the reserve to specific events. This concept is essential on
projects which are subject to externaltime constraints, for example, where
a building has to be available for occupationbefore the lease on another
building expires.
3.1.1.10 LIFE-CYCLECOSTS
(b) The techniques associated with life-cycle costing are often complex
andpredictive.The principal adviser will be able to advise the clientofthe
availability of their application in eachcase.
(b) Value managementis usually carried out at the concept and feasibility
stages of a project with the objectof ensuring that:
• aproject is commissionedin response to a careful analysisto balance
needs;
• a wide range of options and alternatives to meet those needs is con-
sidered;and
• the project objectives are made explicit and are commonly under-
stood by all parties.
(a) This occurs later in the development of the project and is concerned
with how value is achieved rather than what the relative values are as
definedin the project brief and objectives.
Latham, M., Sir, (1994), Constructing the Team: Joint Review of Procurementand Contractual
Arrangements in the UnitedKingdom Constructionindustry: FinalReport,HMSO,London
(b) Value enginering studies are planned, formal reviews of the design
philosophy and the detailed design solutions at one or more stages of the
design development.They are sometimes carried out by firms or individuals
not connected with or employed on the project and are short exercises
intended to review the detailed design solutions against the objectives and
to establishwhether they can be achieved in a more costeffectivemanner.
(b) Client changes (as distinct from design development) are changes
which are made either by:
• the design team, with the approval of the client, to a design feature
which, it has been decided, should be frozen, or 'improved', or
altered to overcomedesign errors andinconsistencies; or
• the client after the design briefhas been agreed. The most significant
of these are changes to the scope of the works.
(c) Client changes can be relatively minor, such as adding a few extra
power points, or can have major cost implications,such as the addition of
an extrastorey.
(d) The cost of client changes depends largely on when they are made, for
example:
• before the construction contract has been let, the cost can be con-
tained to that of the changedfeature itself, and perhaps some nugatory
resourcecost; and
• after the construction contract has been let, the cost will be dispro-
portionate to the value of the change, it can disrupt the contractor's
work and invariably gives rise to a higher cost thanifthe change had
been included in the contract as let. Many minor changescan have a
cumulative and serious effect: disruption claims caused by a large
number of small changes are common.
3.1.1.15 C0MMIssI0NmTG
(a) Once the building work is complete, the systems which will support
comfortmust be commissionedto ensure they are working effectively and
reliably.
(b) For large projects, the client may wish to arrange for the nominationof
a member of the departmentto act as occupation managerto manage this
activity or may appoint a facilities manager. Occupationplans should be
establishedduring the design stages of the project and should cover:
• the operation ofthe building on a regular on-going basis;
• the hand-over andacceptanceofthe building from the contractor(s);
• the progressivefinal fitting-out(if any); and
• the physical occupationof the building with minimum disruptionto
the client's operations.
43> 3.1.2.2 Procurement strategy is the outcome of a series of decisions which are
made during the early stages of a project. It is one of the most important
decisionsfacing the client. The chosen strategy influences the allocationof
risk, the design strategy and the employment of consultants and
contractors. Risks are also allocated by means of the associated legal
contracts. Procurement strategy has a major impact on the timescale and
ultimate cost of the project.
43> 3.1.2.3 Generally,clients can choose from several different strategies. A successful
strategy is one which leads to a completed building which meets the
client's objectives. The preferred aim is for contributingparties to work
together for a qualityresultrather than competing againsteach other.
43> 3.1.2.4 Where the developmentof design does not maintain the pace anticipated,
or the programme is otherwise affected by unexpected occurrences, the
selected strategymust be reviewed. It is most importantthat the strategyis
reconsidered at key times in the progress of the project such as when
planning approval is given, before the contract strategy has been finally
decided and beforethe constructioncontract(s) has (have) been let.
3.1.2.6 On some projects it may be necessary to use more than one strategy to meet
the project's objectives. For example, a traditional approach may be used
for completing the building structurally with main services installed. This
is known as a shell and core contract. Aseparate strategy, for example, con-
struction management, may be used to fit out the building with ceilings,
raised floors, carpets, partitions and electrical fittings. The use of two
strategies allowsthe client more time to finalisethe user's detailedrequire-
ments, withoutdelaying the start of construction.
3.1.2.7 When the choice of procurement strategy has been made, the resultant
contractstrategy and form of contract must be chosen (i.e. the terms and
conditions of the contract). To avoid the need for fresh legal drafting each
time, various standardforms of contract are available. Most ofthe standard
forms of contract are published by professionalbodies in the construction
industry and have been developed largely for private sector clients. The
rangeofcontractsavailable is referred to in 3.1.5 (Implementation).
The Surveyors' Construction Handbook Part 3, Section 1 (4/98) Effectivefrom 1/6/98 Page 15
194
PART 3, SECTION 1
(b) The clientmust decide the relative importance of the three main types
of criteria—time, cost and performance:
o time: earlier completion can be achieved if construction is started
before design is finished. The greater the overlap between the two,
the less time will be requiredto complete the project;
o cost: with the exception of simple 'standard' buildings and certain
'design andbuild' strategies, a final constructioncontractsumcannot
usuallybe establisheduntil the design is complete. Overlap between
design and constructionmeans that constructioncan start before the
cost is fixed: this increases the importance of accurate cost
forecasting;and
performance (design): the quality and performance characteristics
required from the completed building determine both the project
time and cost. Some strategies reduce the client's ability to control
and make changes to the detailed building specification after the
contracts have been let.
(c) Performance includes the function of the building, its quality and
appearanceand other factors such as durability, cost in use and flexibility.
The relative importanceof each objectivemust be given careful considera-
tion because decisions throughout the project will be based on balances
between the other objectives (see the figure illustrating the relationship
between primary criteria).
S
S
S
S
S
S
S
S
. S
S S
S
S S
S
S S
S S
••
I..1.
IS
S
•\.'
Cost Performance
(priceor cost certainty) (design,quality)
The strategy should also reflect the client's technical ability and resources
and the amount of control over the process which he wishes to exert directly
or through his projectmanager(if appointed).
In each case, the strategy can be to transfer the whole risk to another
throughthe medium of contract.This is possible but will attract high price
premiums or will exposethe transferee to risks which they may not be able
to 'own' or insure and therefore the party transferringthe risk will remain
exposed.
(d) Ideally, risk and responsibility should go together, so that the party
responsiblefor performing a task is accountable. Each risk shouldbe allo-
cated to the party with the greatest ability to own the risk andto manageits
effects. If, for example, the client considers it critical that the price for the
building is fixed before construction commences, the risk of meeting that
objective could be passed to contractors, making them contractually
responsiblefor completionto an agreed design and specificationfor a lump
sum price.
(g) Some design work may be carried out by subcontractors who may or
may not continue to pay design liability insurance premiums and usually
will have limitedliability status. Liabilityfor their design work is commonly
passed by warrantiesbut these are less secure.
Equally, where time risks are passed to a contractor his attempt to transfer
themto small subcontractors may fail where the capacity to own or accept
the risk is limited.
(i) Whilst the transfer of risk provides an incentive for the receivingparty
to minimiseits impact, the client should avoid transferringrisks when the
receiving party has no control over them or no capacity to absorb them.
Generally, the more the risk of cost and time slippage is allocated to other
parties, the higher the tendered cost. In pricing the project, tenderers may
over-estimate the size ofthe risk or add a high safety margin to an accurate
estimate and thereby increasethe project's costs unnecessarily.
(j) Risks are inherent in the data usedby the client in the preparationof the
brief; they are inherent in the characteristics of the project; and they are
inherent in the procurementstrategy which is selected.
Since the latter will have a cost the client should also be advised of the
expenseof managingrisk.
Where lump sum price is fixed by the contractthe responsibility rests with
Time
•
FIGURE SUMMARISING THE PRIMARY RISKS, BY EXAMPLE
[referred to in
Cost
3.1.2.9(k)]
Performance
function
Summary (Risk)
Procurement strategy must therefore reflect the ability to place risk, and
where possible risk shouldbe managed out.
Until construction contracts are let, the client, with help from his principal
adviser, must systematically ensure that the strategy is on course to meet
the project's objectives. This is important because objectives sometimes
change.
ZoO
PART 3, SECTION 1
3.1.2.11 IMPORTANTCONSIDERATIONS
• interest rates;
• inflation;
• changes in output of constructionindustry affecting tender price levels;
and
• legislation.
The novelty potential factor means that estimates of time, cost and perfor-
mance are all subject to the possibility of greater error with an increased
probabilityof one or moreofthe project's objectives failing.
It is preferable to identify the total needs of the project during the early
stages but this is not always possible. Rapidly changing technology often
means latechanges.Changes in the scope of the project very oftenresult in
increased costs, especiallyif they arise during construction. Changes intro-
duced after the design is well advanced or construction has commenced
often have a disproportionateeffect on the project, in terms of cost, delay
and disruption, compared with the change itself. The design process goes
through a progressiveseries of 'freezes' as it develops but the client should
set a final design freeze date after which no significant changesto require-
ments or design are allowed.
(g) Timing
• The programme of the project is influenced by many of the above
factors. A particularly large and/or complex project is likely to
require more time for design, specification and construction than
would a simple smallbuilding.
• It is ofvital importanceto allow for adequate design time in terms of
the total project. This is particularly the case if design is requiredto
be complete before construction commences (where perhaps cost
certaintyis required).
• In the process of the
appointment of the design team assurances
should be obtained about resource levels and the ability to meet key
dates orprogrammes.It is not usual to impose contractualdatesupon
designers, althoughtheirprogress is probably the key to the overall
completiondate.
• Decisionsto progresswith a project may be influencedby the gaining
of planning approval, by the successful operation of compulsory
purchaseorder, by land purchase or by some other non-specific but
The Surveyors' Construction Handbook Part 3, Section 1(4/98) Effective from1/6/98 Page 23 J
PART 3, SEcTIoN 1
(i) Pei'formance
• The required performanceof the project measuredboth in terms of
its response to the needs of the client and the quality of individual
elements should be clearly identified. Ifperformance is over-specified,
a premium will be paid for exceeding actual requirements, thereby
affecting the costobjective. Over-specification will also leadto time
overruns. Conversely, failure to recognise the true performance
objective leads to an unsatisfactory product.
• If quality and performance are particularlyimportantthe client will
probably want to keep direct control over the development of the
design. This can be achievedby employingthe design team directly.
3.1.3.1 When all the factors influencing the project have been identified and the
project requirements analysed, the final strategy for the project must be
developed.
Average
80 ConstructionTime
'
a)
ci)
70
60
50
Good
ConstructionTime
ci)
E 40
F-
C
0 30
C.,
20
U,
00 10
0
0 5 10 15 20 25 30
(
-
ConstructionCost Millions)
In
90
80 — —
— —— — ——
ConstructionTime
Good
ConstructionTime
70 -.-
ci) 60
E
I-
0 40
C.,
= 30
U)
20
00 10
0
0 5 10 15 20 25 30
Construction Cost ( Millions)
(Continued)
It is likely that there will be more than one way to achievethe requirements
ofthe project. It is importantto consider carefully each option,as each will
address the various influencing factors to a different extent. In developing
strategies,a potentialdanger is that only the most obvious course of action
maybe considered— this is not necessarily the bestin the longerterm.
OfficeFacilities
120 ________ New_Purpose_Built
100
—— — Average
________ ________ ConstructionTime
Good
U)
ConstructionTime
80
a)
E 60
/—
V
I—
20
0
0 5 10 15 20 25 30
ConstructionCost ( Millions)
Average
Construction Time
U)
Good
Construction Time
a)
E
I-
C
0
0
U)
C
0
C.)
0 5 10 15 20 25 30
ConstructionCost ( Millions)
205
-
Effectivefrom1/6/98 - TheSurveyors' Construction Handbook
PART 3, SECTION 1
• thecontractual relationships;
• the advantagesanddisadvantages;
• the sequential nature ofthe process; and
• the dominantrisks categorisedbroadly(as high, medium or low).
(b) The contractor assumes responsibility and financial risks for the
building works whilst the client takes the responsibility andrisk for design
team performance.Therefore, if the contractor's works are delayed by the
failure of the designteam to meet their obligations,the contractormay seek
recompensefrom the client for additional costs and/ortime to completethe
project. In turn, the client couldseek to recover thesecosts from the design
team membersresponsible,ifnegligence could be proved.
(c) Clients are ableto influencethe developmentof the design to meet their
requirements because they have direct contractual relationships with the
design team. Whenconstructionbegins, they usually have a singlecontrac-
tual relationshipwith a main contractor and, therefore, are able to influence
(butnot control) the constructionprocess through a singlepoint ofcontact.
(d) The strategy may fail to some degree if any attempt is made to let the
work before the design is complete. Such action will probably result in
many post-contractchanges which could delay the progress of the works
and increase the costs. Where a traditionalstrategy is chosenbecause of its
particular advantages, the temptationto let the work before the design is
complete shouldbe strongly resisted.
CONTRACTUAL RELATIONSHIP
CLIENT
CONSULTANTS
(fee
contracts)
MAIN CONTRACTOR
lumpsum contract)
(standard
SUPPLIERS
(variouscontracts)
SUBCONTRACTORS
(standard lump sum)
ADVANTAGES DISADVANTAGES
SEQUENCE
RISK
LOWCOST RISK
MEDIUM TIME RISK
LOWQUALITY/DESIGN RISK
Page 28 Part 3, Section 1(4/98) Effective from 1/6/98 The Surveyors' ConstructionHandbook
207
PART 3, SECTION 1
2c2
PART 3, SECTION 1
CONTRACTUAL ARRANGEMENT
__ CLIENT
1
CONSULTANTS
(fee contracts)
MAIN CONTRACTOR
(standard measurement contract)
SUPPLIERS
[ (various contracts)
SUBCONTRACTORS
(standard contracts)
ADVANTAGES DISADVANTAGES
SEQUENCE
brief design
competition construction
RISK
MEDIUM COST RISK
MEDIUM TIME RISK
MEDIUM QUALITY/DESIGN RISK
work is carried out by trade contractors through direct contracts with the
clientfor distinct trade or workpackages. The construction manager super-
vises the construction process and co-ordinates the design team. The
construction manager, whohas no contractual links with the design team or
the trade contractors, provides professional construction expertise without
assuming financial risk, and is liable only for negligence by failing to per-
form the role with reasonable skill andcare, unless some greater liability is
incorporated in the contract.
(b) On appointment, the construction manager will take over any prelimin-
ary scheduling and costing information already prepared and draw up a
9
PART 3, SEcTIoN 1
(c) Withthis contract strategy, design and construction can overlap.As this
speeds up the project, constructionmanagement is known as a 'fast track'
strategy. Although the time for completioncanbe reduced, price certainty
is not achieved until the design and construction have advanced to the
extent that all the constructionwork (trade) packages have been let. Also,
design developmentof later packages can affectconstruction work aheady
completed. The constructionmanager should, therefore, have a good track
record in cost forecasting and costmanagement. A package is made up of
work for which one of thetradecontractorsis responsible,e.g. foundations,
concrete, electrical installationor decorating. These packages are tendered
individually, for a lump sum price, usually on the basis of drawings and
specification.
1 Latham,M., Sir, (1994), Constructing the Team: Joint Review of Procurement and Contractual
Arrangementsin the UnitedKingdom Construction Industry:Final Report, HMSO, London
CONTRACTUAL ARRANGEMENT
CLIENT
Fee contracts
(no standard formfor CM)
CONSULTANTS
including
CONSTRUCTION MANAGER
Lump sum contracts
(non-standard)
WORK orTRADE
CONTRACTORS
ADVANTAGES DISADVANTAGES
time saving potentialfor overall projecttime no cost certainty atoutset
trade packages let competitively needs informed client, able to take an
SEQUENCE
brief design
construction
RISK
MEDIUM COST RISK
MEDIUM TIME RISK
LOWQUALITY/DESIGN RISK
packageshave not been let and earlier awardedpackages are not too
adversely affected; and
the client has direct contracts with trade contractors and pays them
directly. (There is some evidence that this results in lower prices
because of improvedcash flow certainty.)
3.1.3.7 MANAGEMENTCONTRACTING
(c) With the agreement of the client, the management contractor selects
works contractors by competitive tender to undertake sections of the
construction work. The client reimburses the cost of these work packages
to the managementcontractorwho,in turn, pays the works contractors. The
management contractor co-ordinates the release of information from the
designteam to the works contractors.
212
PART 3, SECTION 1
CONTRACTUAL ARRANGEMENT
CLIENT
MAIN CONTRACTOR
•
(fee contract)
CONSULTANTS
(fee contracts)
'V
WORKS CONTRACTORS
(standard lump sum contracts)
ADVANTAGES DISADVANTAGES
time savingpotential for overall project time need forgoodqualitybrief
SEQUENCE
brief design
construction
RISK
MEDIUM COST RISK
MEDIUM TIME RISK
LOWQUALITY/DESIGN RISK
213
Page 34 Part 3, Section 1(4/98) Effective from1/6/98 The Surveyors'Construction Handbook
PART 3, SEcTION 1
3.1.3.8 DESIGNANDMANAGE
3.1.3.9 DESIGNANDBUILD
(a) Under a design and build strategy,a singlecontractor assumes the risk
and responsibility for designing and building the project, in return for a
fixed-price lump sum.
(c) Design and build is a fast-track strategy. Construction can start before
all the detailed designis completed, but at the contractor'srisk.
The Surveyors' Construction Handbook Part 3, Section 1(4/98) Effective from 1/6/98 Page 35 J
PART 3, SECTION 1
(f) The contractor develops the design from the specification submitting
detailed proposalsto the client to establishthat they are in accordancewith
the requirements of the specification. Clients are, therefore, in a strong
position to ensure that theirinterpretationof the specification takes prefer-
ence over the contractor's.
(h) The client will oftenemploy a design team to carry out some prelimin-
ary design and prepare the project brief and other tender documents.
Sometimes, the successful contractor will assume responsibility for this
design team and use them to producethe detailed design. If a design and
build strategy is identifiedas a possibility at an early stage, then the basis
of the appointment of the design team should reflect this possibility. If it
does not, the client may have to pay a termination fee to the design team.
The client may wishto retain the independentservicesof a costconsultant
throughout the contract for early cost advice involvement in the bidding
process and costreportingduring construction.
(J) Current forms of contract for design and build vary their treatment of
design liability. UnderJCTCD 81 with Contractor's Design,the contractor
undertakes to design to the same standard 'as would an architect if the
employer had engaged one direct'. So the client gets the same 'skill and
care' liability for design as would normally be available under traditional
andmanagementstrategies when employingthe architectdirect.
Page 36 T Part 3, Section 1(4/98) Effective from 1/6/98 The Surveyors' ConstructionHandbook
PART 3, SECTION 1
Turnkey I I I I I I I I I I I I ii
Package deal
The range of options enablesthe procurement arrangementto be used for a wide range of
client types, and for clients to be involved to a greater or lesser extent.
Client involvement
Contractor involvement ii I I I I I II I I I II
(p) The project organisationstructure for design and build is shown in the
relevantFigure. Contractors may use their own firms' resources for under-
taking the design (in-house design and build), or may subcontractthese to
one or more professionalfirms whilst retaining control.
CONTRACTUAL ARRANGEMENT
CLIENT
. I__
DESIGN AND BUILD CONTRACTOR
SUPPLIERS
(various contracts)
SUBCONTRACTORS
(standard lump sum contracts)
ADVANTAGES DISADVANTAGES
single point contact and responsibility relatively fewer firms (less real competition)
inherent buildability clientneedsto commit himself before design
early firm price possible is complete
reducedtotal project time in-house design and buildfirm is an entity
(compensationfor weak parts not possible)
no design overviewunlessconsultants appointed
difficultfor clients to prepareadequate brief
bids difficultto compare
design liabilitylimited by standardcontract
clientdriven changescan be expensive
SEQUENCE
construction
RISK
LOWCOST RISK
LOWTIME RISK
HIGH DESIGN/QUALITY RISK
2rj
PART 3, SECTION 1
• suitable in the light of the client's needs, the project type and the
client's exposure to risk; and
• feasible in the light of the client's expertise, internal management
structure,resource andfunding facility.
218
PART 3, SECTION 1
3.1.4.3(a) METHOD
CHECKLIST 1: TIME
2. Does the answer to question1.1 suggest a faster than 'normal' total pro-
jecttime in the judgementof the adviser?
3. How long is it in months from the date of completionof this protocol
untilthe desired 'move in' date?
5.1 Is the need for completion by a specific date or within a specific time
more importantthan certaintyofconstructioncostbefore work starts?
2t9
PART 3, SECTION 1
5.2Is the need for completion by a specific date or within a specific time
more important than spending an extendedtime on design?
7. If the building is completed later than the specified or desired time will
the client:
7.1 stay in his existing premises?
7.2 find temporary accommodation?
7.3 close down?
7.4 adopt some other course.
CHEcKLIST 2: DESIGN/PERFORMANCE
1. Has the client clear ideas about building functionality and its desired
design?
2. Does the site (if selected) pose any particular problems for the designer
in respect of:
2.1 shape or topography?
2.2 access?
2.3 storage space?
CHECKLIsT 3: COST
3. Will the client need to have a fixed contractprice for the construction
element of his budgetor will a reasonablyaccuratebudgetbe adequate?
CHECKUST 4: ANALYsIs
221
PART 3, SEcTIoN 1
Having established whether the project is both feasible and viable, the
importance oftime, cost anddesignhas now been reviewed.
Design-led projects have the greater capacity for cost and time overrun,
whereas the potential capacity for design shortcomings may rest with
product-ledsystems.
3.1.5 Implementation
The Surveyors' Construction Handbook Part 3, Section 1 (4/98) Effective from1/6/98 Page 43 j=
222
PART 3, SEcTIoN 1
principal adviser will carry out most or all of the necessary functions in
achievingimplementationand the client's role will be to formally approve
the principal adviser's actions.
Notwithstanding the role of the principal adviser, the client should ensure
that he puts in place the necessary resources, organisational structure,
contractual arrangements, systems and controls necessary for a successful
project outcome.
(a) In this Section, the funding function has been regarded as a matter for
the client. It is a vital function and by the time the procurementstrategyis
set, sufficient funding should be available at appropriatetimes in the pre-
constructionandconstructionprocess.
223
PART 3, SEcTIoN 1
(c) The criteria for the selection of the design team have been outlined in
Part 1, Section 1 of this Handbook based upon the factors of capability,
competence, staff and cost, with value for money, rather than cost being the
major influence in selection.
(d) The criteriafor the selection of contractors have also been referred to in
Part 1, Section 1 of this Handbook and are broadlythe same, but tend to be
a much more complex process and are dependent upon the procurement
strategy selected.
3.1.5.6 ORGANISATIONALSTRUCTURE
(a) The client has a dual management role, part of which is to manage the
client input; to co-ordinate functional and administrative needs; to resolve
conflicts; as well as to act as the formal pointof contact for the project.
(b) This will require the creation of an organisational structurefor the life
of the project to enable communicationto occur and to facilitate effective
decision-making.
22L.
PART 3, SECTION 1
3.1.5.7 CONTRACTUALARRANGEMENTS
This may mean delegating elements of the process to the project manager
(if appointed) or ensuring that existing company systems are specifically
adapted.
(c) Controls are also important to ensure that cost is controlled within
budget, pace is controlledwithin programme, quality is controlled within
standards set, and systems are properly employed.
225
PART 3, SECTION 1
(e) Pace can be monitored against a programmeor time plan and can be
controlled by the imposition of contract completion dates. Programming
can be provided by a project manager or developedwith the advice of the
principal adviser.
(g) Controlling the client systems to ensure that they are appropriately
applied and not abused is a matter for the client's management team —
perhaps this is the keymanagementinput from the client.
22
Effectivefrom1/6/98 Page 47 j
PART 3, SECTIoN 1, APPENDIX A
The Joint Contracts Tribunal produces a range of standard forms of contract for use
betweenclient and contractor or contractor and subcontractor.A number of Practice
Notes are also availableto assist in the selection of the appropriateform of contract
andits usage.
For the purposes of this document the standard contracts are not listed but the
sourcesof advice are.
The RIBA, RICS and ACE have their own standard conditions appropriatefor the
appointment of an architect, surveyoror cdnsulting engineer.
Codes of Practice prepared by the NJCC are available to assist in the process of
tenderingfor constructionwork.
JCT SIMPLE GUIDE AND FLOW CHART FOR SELECTING TIlE APPROPRiATE FORM OF JCT
CONTRACT.
JCT PracticeNote 20
R1BA ArchitectsAppointment RoyalInstitute of
BritishArchitects
Appendix B: FurtherReading
2.23
PART 3, SECTION 1, APPENDIX B
Green, S.D., andPopper, P.A. Value Engineering:The Search for Unnecessary Cost,
CIOB, Ascot, 1990
22
PART 3, SECTION 1, APPENDIX B
HMSO. The White Paper "COmpetitiveness: Helping Business to win ", HMSO,
London, 1994
RICS. A Client'c Guideto Successful Building: The Role ofthe Chartered Quantity
Surveyor, RICS,London, 1990
The Surveyors' Construction Handbook Part 3, Section 1, Effective from 1/6/98 Page 3
Appendix B(4/98)
23Ci
PART 3, SECTION 1, APPENDIX B
2.3
PART 4, SECTION 1
Introduction
231
PART 4, SECTION 1
(b) SnaggingList
• Either in advance of the contractor's notice mentioned above, or
prompted by it, the architect, engineeror contract administrator will
prepare a list of defects and outstanding works which will be issued
to the contractor.
• Often, but not always, this list is prepared during a joint inspection
with the contractor.
(d) Certification
• Eventually a point will be reached where completion can be certified
in the opinion of the architect, engineer or contract administrator.
Although not defined as such in the majority of standard forms (see
4.1.2), the most commonly held belief is that this should occurwhen
the employer can enjoy beneficialoccupationand use ofthe building
or facility, and that the making good of any remaining works or
removal of snags will notunduly impede that occupation.
• Such an approachis supportedby caselaw (see4.1.5).
233
PART 4, SEcTIoN 1
where many of the standard forms, strictly speaking, fail the industry,
since they do not cater for such 'qualified' practical or substantial
completion (seecomments on JCT 80 in4.1.2.1).
Nonetheless,the industry at large takes a fairly cavalier approachto
this, issuing completion certificates endorsed or annotated with
reference to outstanding defects. Equally often, the certificate will
make no reference to outstanding works even though a lengthy snag
list may remain outstanding.
In the main, rectification of the defects or outstandingworks after the
certificate of completion is done on 'trust'. Rarely is a separate
agreement entered into at this point identifying the outstanding
works and the manner and timing within which they are to be corrected.
These provisions have often been used to support the argument that
practical completion cannot be certified under JCT 80 unless all known
(patent) defects have been resolved.This is becausethe duty of the contractor
to rectify defects during the defects liability period is limited to those
defects appearing afterpractical completion.
1 Includes
provisionsintroducedby Amendment 12: 1993
234
PART 4, SECTION 1
(a) The architect will not issue any certificate to confirm separate
completionof domestic sub-contractworks. However, it is quite instructive
to appreciatethe procedureswhich have been established under DOM/1 to
identify dates for completionby domestic sub-contractors.
(c) If the main contractordoes not dissent from that date within 14 days of
receiving the sub-contractor's notice, practical completion is deemed to
have occurredon the date notifiedby the sub-contractor.
PartialPossession
(d) If the main contractordoes dissent, the date must either be established
by agreement, or referred to arbitration. Otherwise, the sub-contract works
will be deemed to have reached practical completion at the same time as
the main contractworks.
(c) Though in its basic form the IFC 84 contract does not provide for
partial possession,the JCTpublish an additional clause 2.11 and practice
note IN/i which caters for this. The effect is similar to the partial posses-
sionprovisionsofJCT80 (see 4.1.6.5).
The Surveyors' Construction Handbook Part 4, Section 1(4/98) Effective from1/6/98 Page 5
PART 4, SECTION 1
(a) The JCTMinor Works form provides a crisp, clear statementwhich has
the same effect as the provisionsfor the main JCT forms.
(a) Under clause 2.14 of the WC/2, the management contractor is required
to issue separate certificates of practical completion for each works
contract. The management contractor is, however, obliged to obtain the
1 William Tomkinson& Sons Ltd v. The Parochial Church Council ofSt Michael and Others (1990)
8-CLD-08-O1
231
PART 4, SECTION 1
(a) The ACA form is probably the standard form which most closely
follows that which generallyhappens in practice.
"When, in the opinion of the Contractor, the Works are, or will be,
subject to the completionof any outstanding items of work, fit and
ready for Taking-Over by the Employer, he shall so notify the
Architect. Such notificationshall, if appropriate,be accompanied by
a list (referredto as 'the Contractor'sList') of any outstandingitems
of work requiredto render the Works fit and ready for Taking-Over
by the Employer. The Architectwithin ten working days of receiptof
suchnotificationmay then (subject always to the first proviso to this
Clause 12.1) either:
(a) issue a
certificate that the Works are fit and ready for
Taking-Over by the Employer. Such certificate is referred to in
thisAgreementas a 'Taking-Over Certificate'; or
(b) notify the Contractor of any items of work which are in the
Architect's reasonable opinion required to render the Works fit
and ready for Taking-Overby the Employer (referred to as the
'Architect'sList');
23
PART 4, SECTION 1
If any items of work are required under paragraphs (b), (c) and (d)
above, the Architectshall forthwith issue a Taking-Over Certificate
when the Contractor shall have completedthe same. 'Taking-Over'
of the Works shall be deemed to have occurredon the date stated in
the Taking-OverCertificate.
239
PART 4, SECTION 1
The clause gives the engineer a discretion and, as in other forms, his
decisionmay be reviewedby an arbitrator.
It should also be noted that the ICE 6th edition form caters expressly for
the circumstances where the employeruses or occupies the works or part of
the works prior to a 48(2) certificate being issued.
Note: The ICE Design and Construct Clause 48(3) provisions in respect of
operation andmaintenance instructionsare not presentin the 6th edition.
Clause 49(2) ofthe 5th edition also allows a mechanismfor the finishingof
works outstanding at the date of completion.
(a) The ICE Minor Works is unique amongst standard forms in that it
defines completion against the readiness of the works to be used by the
employer.
4.5 (1) Practical completion of the whole of the Works shall occur
when the Works reach a state when notwithstanding any
defect or outstandingitems therein they are fit to be taken
into use of possessionby the Employer.
(c) Clause 4.7 deals with the completion of outstanding works or defects
afterpractical completion has occurred.
Page 10 Part 4, Section 1(4/98) Effective from1/6/98 ' TheSurveyors' Construction Handbook
PART 4, SECTION 1
(a) The NEC eschews the system set out in the ICE forms which reflects
currentpractice,namely the contractor offering up the works and completion!
handover occurring together with clear provisions for dealing with
outstanding works anddefects.
(b) Instead it may be thought that the NEC is in some respects closer to
JCT: completion takes place when the project manager decides so. As if
completion was not vexed enough already, the NEC gives the project
manager three terms to deal with: 'Completion', 'taking over' and
'termination'.
35.2 The Employer need not take over the Works before the
Completion Date if it is stated in the Contract Data that he is
not willing to do so. Otherwise the Employer takes over the
Works not more than two weeks after Completion.
35.3 The Employer may use any part of the Works before
Completion has been certified. If he does so, he takes over the
part of the Works when he beginsto use it.
The Surveyors' Construction Handbook Part 4, Section 1(4/98) Effective from 1/6/98 Page 11
242
PART 4, SECTION 1
35.4 The Project Manager certifies the date upon which the
Employertakes over any part ofthe Works within one week of
the date.
"42 (1) The SO shall from time to time certify the sums to which the
Contractor is entitled under Conditions 40 and 41. The SO
shall also certify the date on which the Works are completed
to his satisfaction and after the end of the said maintenance
period he shall issue a certificate when the Works are in a
satisfactorystate."
2L
PART 4, SECTION 1
"The contractor shall, at all times, keep the Site tidy and free from
debris, litter and rubbish and shall not later than Completion of the
Works, remove from the Site all Things for incorporation in the
Works or any relevant Section which are unused, together with all
Things not for incorporation.The Contractor shall by the due date
clear andremoveall rubbish anddeliver up the Site and the Works in
all respects to the satisfactionof the PM ["the Project Manager, who
is the official of the Authority"]. The Contractorshall comply at his
own cost with any Instructionsrelatingto the removal of any Things
and rubbish."
(c) Similar provisions to edition 2 also exist for early possession under
condition 37 of edition 3. Here again, the project manager is required to
certify completionof the works to his satisfaction.
(b) The I Chem E forms recognise that on large process plant projects or
similar,the concepts of completionandtaking over have distinctly separate
ramifications, from both contractual and safety points of view. These are
reflectedin the contractualproceduresprovidedin the I Chem E forms. The
procedures, therefore, are closer to a true contractual definition of
completionthan can be found in any other standardform. There are three
aspects of significance which are considered:
• compliance with the specification
with the descriptionof works
• time finishing tasks according to
programme or with reference to
financialincentives
• transferofresponsibility.
244
PART 4, SECTION 1
(a) liability to pay damages for delay ceases (whether liquidated and
pre-ascertained,or unliquidated);
(b) possession of the site returns to the employer and the risk of security
and damage to the works and third party liability transfers back to the
employer(butnot damage to the works causedby the contractorduring the
defects liability period under JCT 80, clause 20.3);
2L5
PART 4, SECTION 1
4.1.3.2 Dependentupon the form of contract, certain other factors are conditional
upon the certificate of completion.For example,under JCT 80:
(a) the employer may assign the right to bring proceedings in his name
(clause 19.1.2);
(c) liability for frost damage is transferred from the contractor to the
employer (clauses 17.2, 17.3 and 17.5); and
(d) the period for finalreview of extensions of time expires12 weeks from
this date (clause 25.3.3).
4.1.3.3 These factors also impact upon sub-contractors. For example, the sub-
contractors'protection under the main contractall-risks'policyends.
The remedy available to the employeror contractorin the event they con-
sider the certificate has been wronglyissued or withheldis to arbitrate.This
option is used in the traditional JCT contract.
(b) Adjudication
The Surveyors' Construction Handbook Part4, Section 1(4/98) Effectivefrom 1/6/98 Page 15
24-b
PART 4, SECTION 1
This is the model used in DOM/l, further developed to deal with the
'dissent' of the recipient under a main contractor and sub-contractor
relationship.
(d) DefinitionofStandards
(e) It is possible that this could be dealt with as a 'code of practice' bound
within the contract documentandexpressly referredto in the conditions,in
similar fashion to the code of practice for opening up and testing under
clause 8.4.4of JCT 80.
(f) The I Chem B forms come closest to this option, by prescribing tests
and standards to be achievedby the installedplant prior to completion. It is
suggested, however, that to define completion similarly for universal
application in building or civil engineeringprojects would be extremely
difficult. The primary area of difficulty lies in aspects of subjective
evaluation such as finishes, and it is doubtful whetherthis would be less-
ened by a definition which called for "100% fault free works" (see
4.1.4.3) since there will always be disputeson quality issues.
(g) Appendix A offers a number of practical tests for judging the state of
completion.
Page 16 Part 4, Section 1(4/98) Effective from 1/6/98 The Surveyors'Construction Handbook
2)-ri
PART 4, SECTION 1
(a) Here completion would not be granted until all outstandingworks are
completedand defects rectified.
(b) This is not a favoured option in the UK, and the Courts have given
credence to the view that it is a difficult, if not impossible, yardstick to
apply. Nonetheless, it is closer to the model applied in other European
countries,andthe increase in the use of latent defects or 'build' insurance
(such as the mandatory decennial type liability in France) may bring a
movetowards 'fault free' buildingsat completion.
(a) Various models have been suggested for a two-stage process for the
certification of completion.
(b) Clearly, the intent is to divide into two the numerous benefits and
obligationswhich fall uponthe contractorandemployerat completion (see
4.1.3).
(d) At this point, the employer would re-take possession and insurance
risks aretransferred.
(e) The second stage would be perfect completion of the works. Only at
thispoint wouldthe contractor be released from liability for liquidated and
ascertained damages. This would also mark the commencement of the
defects liability period.It is thoughtthat the first release of retention would
alsonotoccuruntil thispoint.
4.1.5 Definitions
4.1.5.1 Generally, as can be seen in 4.1.2, the standard forms of contract do not
provide definitions of what constitutes practical completion, although the
ICE Minor Works form contains a useful development of the term by
stating it is contingent upon the works being "fit to be taken into use or
possession".
The Surveyors' Construction Handbook Part 4,Section 1(4/98) Effectivefrom 1/6/98 Page 17
PART 4, SECTION 1
Page 18 Part ', Section 1(4/98) Effectivefrom 1/6/98 The Surveyors' Construction Handbook
ZL.9
PART 4, SECTION 1
(e) SUBSTANTIALPERFORMANCE
• These arguments applied to practical completion have been used in
explaining the doctrine of substantialperformance. This doctrine is
concernedwith establishingwhen payment will be due of an amount
payable under an 'entire'contract:
• It has recently been held by the Court of Appeal in Hong Kong that
practical completion should be interpretedin a similar mannerto the
doctrine of substantial performance.
(f) SUBSTANTIALCOMPLETION
• Definitionsof the term 'substantial completion'appearingin the ICE
forms havebeen similarto those appliedto practical completion.
This term (or equivalent words) used in clause 48(1) of the ICE
6th Edition form" ... substantially completed ..." now appears
25
PART 4, SECTION 1
1
EngineeringLaw and the ICE Conditions,Fourth Edition, MaxWAbraliamson, at page160
5i
PART 4, SECTION 1
4.1.5.4 REMEDYINGDEFECTS
Finally, another ingredient which it is suggested affects practical
completionis the extent of disruptionan employerwould incur in allowing
access to a contractor to remedy defects or complete works outstanding
afterthe issueof a practicalcompletion certificate.
1
Keating'sBuilding Contracts,5thedition, atpage 528
2Hudson'sBuilding andEngineeringContracts, eleventheditionatpage 1109
Ibjd, atpage 1130
4Commentaryby editorsofBuilding LawReports,52BLR atpage 111.
253
PART 4, SECTION 1
(a) The case ofEmsonEastern Ltd v. EME Developments Ltd (1991)1 con-
sidered the situation where a main contractor goes into administrative
receivership after practical completion, leaving both a claim for unpaid
sums due under the contract, and a substantial counterclaimfor defective
works.
Until after completionof the works under clause 27.4.1 the employer
shall not be bound by any provision of this contract to make any
furtherpaymentto the contractor
(d) The employer was, thus, arguing that 'completion' had not occurred
until all known defects had been corrected and the obligations during the
defects liabilityperiodbrought to an end.
(e) The Court had to decide whether 'completion' in clause 27.4.4 meant
the same as 'practicalcompletion' (which hadalready occurred)or whether
it meant completion of all the continuing obligations as contended by the
employer.
(f) The conclusion of the Court was that there was no room under JCT 80
for 'completionas distinct from practical completion'.
(g) This meant, under the scheme of clause 27, that if after practical
completionthe contractis determined:
Since the works will be deemedto have been completed, the employer
cannot rely upon clauses 27.4.1 and 27.4.4 to enable him to employ
other contractors and claim the cost of employing them from the
contractor, nor can he claim exemptions from making payments to
the contractor for works carried outbefore practical completion.1
(h) Thus, any rights which the employerhas against the contractorwill not
derive from the termsof the contractbut will be under commonlaw.
2
The Surveyors' Construction Handbook Part 4, Section 1(4/98) Effectivefrom1/6/98 Page 23
PART 4, SECTION 1
As I read the clauses, given that (on the clauses in the form which
they take in the contract now before us) successive applicationsare
made at reasonableintervals. I can see no reason why the financing
charges should not continue to constitute direct loss or expense in
which the contractor is involved by reason of, for example, a
variation, until the date of the last application made before the last
issue of the certificate issued in respect of the primary loss or
expenseincurredby reasonofthe relevantvariation.
But I can for my part see no good reason for holding that the
contractorshould cease to be involved in loss or expensein the form
of financing charges simply because the date of practical completion
has passed.
(b) This brings about the absurd situation of contractors' claims for
extensionof time after practical completion, or arguments that time is 'at
large' in order to defeat the imposition of earlier delaydamages.
(b) Certain standard forms of contract contain clauses that expressly state
this to be the case.
The Employer may use any part of the works before Completionhas
been certified. If he does so, he takes over the part of the workswhen
he begins to use it.
1 Chartered
QuantitySurveyor June 1990(RefQ/89/136)
(e) It has been argued that since some standard forms expressly deal with
this subject as above, then those forms of contract which do not include
similar express provisions should be interpreted to the effect that no
assumptionof deemed practicalcompletionmay be made upon occupation
or use ofpart or all of the works. In other words, the express requirements
of the contractshould be considered to be exhaustiveof the circumstances
wherebypractical completion canbe established.
(f) The JCT forms of contract, including JCT 80, do not expressly provide
for 'automatic' practicalcompletion upon use or occupation by the employer
of a part or whole of the works. On the contrary, clause 23.3.2 of JCT 80
provides for use or occupation in circumstanceswherepractical completion
or partial possessionwill notoccur(see4.1.6.5(a)).
(h) A somewhat different view was held in Hoenig v. Isaacs2, where Lord
Denning said:
There, by entering into possession and using the fitted furniture, the
employer was held to have waiveda condition precedentof entire perfor-
mance andcouldno longer rely on it.
(i) In English Industrial Estates v. George Wimpey3, the Court held that
occupationdid not amount to completion.
(1) In spite of the employer's tenant installing and using machinery and
storing large quantities of paper in parts of the works, the court of first
instance and the Court of Appeal found that partial possession had not
occurred and held the contractorand his insurers liable for damage caused
by a fire occurringduringthe employer'soccupation.
1
Big island Contracting(HK)Ltdv. SkinkLtd(1990), CAIlK 52BLR 110
2Hoenig v. isaacs(1952) 2AllER 176
English Industrial EstatesCorporationv. GeorgeWimpey & Co Ltd (1973) CA7 BLR 122
4Mtltiplex ConstructionPlyLtdv.AbgarusPlyLtd (1992)APCLR
Page 26 Part4, Section 1(4/98) Effectivefrom 1/6/98 The Surveyors' Construction Handbook
PART 4, SECTION 1
(a) The firstlevel is use or occupationof the site or a part thereof generally
for storageor fit-out.
It can be seen that such a mechanismis consensual and that the insurers
also must confirm theirconsent to the occupation. Clause 23.3.3 provides
that any increase in the insurancepremium which results must be added to
the contractsum.
253
PART 4, SEcTIoN 1
2s°i
PART 4, SECTION 1, APPENDIX A
A2 COMPLIANCEWITH STATUTORYREQUTREMENTS
A2.1 All relevant statutory requirements should have been complied with,
including all appropriaterequirements for health, safety, means of escape
and the requirements ofthe statutory suppliers, including confirmationthat
all planning conditions and building control matters have been satisfac-
torily resolved.
A2.3 Where appropriate (e.g. under design and build arrangements) the
contractorshall have satisfied all local authority requirements with regard
to, for example, refuse collection andpostaladdress confirmation.
A3 THE SITE
A3.l External works should be substantially complete so that the occupier has
unfettered access. Normally, all building impediments such as skips and
site huts should have been removed from the site, such that no potential
safety hazardremains present. (Note: Particular attention shouldbe paid to
this when considering sectionalcompletion for anypart ofthe works.)
A4 ENTRANCES
A4.1 It is normally expected that the entrance to the premises and access way
would be clear and complete, sufficient for the client to operate for all
intents andpurposesin a normal fashion.
A5 STRUCTURE
A5.l Structuralworks shouldbe complete and no part of the structureshould be
unsafe.
A6 CLADDING
A6.l The building should be wind and watertight and the cladding should be
properly secured. Under normal circumstances, roofs andcladdings would
be tested by the elements.If, for some reason this has not taken place, then
zbo
PART 4, SEcTIoN 1, APPENDIX A
A7 FINTSHES
A7 1 This is the area of works where most reasons for delay in the issue of a
certificate of practical completiontendto arise.
A8 PLANTING
A8.•1 If, in the specification, externalplanting is included andit is acknowledged
that practical completion may takeplace during a period when undertaking
planting may be impractical, then the documentationshould state this to
enable such worksto be undertakenwithoutdetrimentto the parties.
A9 MECHANTCAL ELECTRICALSERVICES
A9.l The origins of all the appropriate commissioning and test certificates
should be issued to the architect or contract administrator. For such
elements as air conditioning, a definition which allows for balancing to
take place following occupationshouldbe considered.
AlO MANUALS
AlO.1 The requirement for the provision of operating and maintenancemanuals
and as-installed drawings should be considered closely. Manufacturers'
warranties may well be nullified if mechanical plant is not maintained in
accordance with their instructions during the warranty period. Particular
attention will be requiredto be paid to the CDM regulations which callfor
the 'Safety File' to be producedprior to practicalcompletion.
1. BigIslandv. Skink(1990)
Occupation did not mean practical completion.
Appendix C: FurtherReading
BOOKS
ARTICLES
2b
PART FOUR: CONSTRUCTION ADMINISTRATION AND
MANAGEM ENT
Introduction
The purpose ofthis Section is to provide practical advice to those who are
required to ascertain the amounts due in reimbursement of direct loss
and/orexpenseincurredin building projects.
Surveyors are particularly reminded that their role in these matters is set
out in their building contract and is normally limited to determining
quantum; it does not usually extend to determiningliability.
Equally, it is not the quantity surveyor's role (to whom the task of ascer-
tainmentis usually given)to seek to get away with as little a payment as he
can. The contractor, for his part, may understandably press hard for a
significant figure and on occasions overstate his case either in words or
money or both. Too often the quantity surveyor is seen, or even sees him-
self, as being at the opposite end of a tug-of-war rope to the contractor.
This is incorrect.Whilst the quantity surveyor is perfectlyentitled to probe
such submissionsby weighingall the contrary evidence, his ultimate taskis
to determine a proper ascertainment in accordance with the conditions of
contractandthe circumstancesthat have prevailed.
2
aggrievedparty, "he is, so far as money can do it, to be placed in the same
situation with regardto damages,as ifthe contracthad been performed".1
<j> 4.2.1.3 Nor are such damages intended to recompense the aggrievedparty for all
losses whatever their nature. In the case of Hadley v. Baxendale2 it was
established that damages ought to be of a kind which "shouldbe such as
may fairly and reasonably be considered either arising naturally, that is,
according to the usual course of things, from such a breach of contract
itself, or such as may reasonablybe supposedto have been in the contem-
plation of both parties, at the time they made the contract, as the probable
result of the breach of it".
4.2.1.4 Where building contracts contain clauses dealing with the entitlement of
the contractorto recover direct loss and/or expensefor any delayor disrup-
tion to the regular progress of the Works caused by the clientor his team or
other designated causes, such clauses have been developed against this
general background.
4.2.1.5 There are important distinctions to be drawn between the express provi-
sions in a form of contract on the recoveryof direct loss and/or expense,
and recovery of damages at common law. In the case of the former the
requirementslaid down in the contractmust be rigidly adhered to; if they
are, then reimbursement is a contractual entitlement and does not require
judgement of the Court or an arbitrator.
4.2.1.6 The provisions of the loss and/or expense clauses are generally without
prejudice to any other rights and remedies which the contractor may
possess, and which he may wish to pursue through arbitration or the
Courts. This considerationis, however, outsidethe scope of this Section of
the Handbook.
<i)> 4.2.1.7 To determine the contractor's entitlement one must calculatethe difference
between the costs arising from the application of the following two
questions:
(a) What is the reasonable cost of carrying out the particular element of
work in the delayed or disruptedcircumstances that were created directly
as aresult ofthe matterunder consideration (for examplelate instructions)?
(b) If that delay or disruption had not been so caused what would those
costs have been?
Page2 Effective from1/6/99 Part 4, Section 2(4/99) The Surveyors' Construction Handbook
the work that was carried outitoes notfollow necessarily that all such
costs were properlyincurred.
4.2.1.9 Thus, even if the form of contract refers to 'ascertaining' the loss — as does
the JCT form (see 4.2.1.13)— complete proof in the way of invoices or
verified cost records is unlikely to be available. Indeed, as outlined else-
where in this Section, the surveyor is not required to establish 'complete
proof' but is instead required to use professional judgement. This should
not, however, detract from the critical importance of ensuring that proper
and reasonable records are maintained by the contractor and contract
administrator.
4.2.1.10 The primary purpose of this guidance is not to provide a legal treatise on
the matter of claims but to providepractical comment on how to go about
determining, as reliably as possible,the contractor's monetary entitlement.
4.2.1.11 The correct ascertainment of the amount of any direct loss and/or expense
to be reimbursed to the contractor requires sound knowledge and
experience of building practice, careful study of the conditions of the
relevant contractand an understandingof their legal application, together
with knowledge of the relevant and up-to-date case law. In addition, the
person undertakingthe evaluation requires access to the best records and
otherinformationthat is available on that particular contract.
4.2.1.13 This guidance is based predominantlyupon the provisions of the 1980 edi-
tion of the Standard Form of Building Contract, published by the Joint
ContractsTribunal — referred to as JCT 80. The wording used in the form is
either identical, or very similar, to that adopted in many of the other forms
published by the JCT, for examplethe Works Contracts used in association
with the JCT Standard Form of Management Contract and the JCT
StandardForm of BuildingContractwith Contractor Design.
<3> 4.2.1.14 It should be noted that in thistext extracts from printed forms are frequently
paraphrased. Readers therefore should in all cases check the precise
wording used in the particular form with which they are involved in
practice, particularly where the form is not one of those promulgatedby the
JCT. It may even be that, although a JCT Standard Form has been used,
particularclauseshavebeen amended.
4.2.1.15 Followingthe terminology used in the JCT forms, an event or failure which
gives the contractor grounds for seeking reimbursement of any resultant
loss and/or expenseis referred to as a 'matter'; whereas an event or failure
•
completionof the works is referredto in this Section as an 'event' (also see
4.2.3.2).
4.2.2 Definitions
4.2.2.2 DIRECT
"The direct consequence of the act giving rise to the claim",1 or "that
which flows naturally from the breach, without other interveningcause".2
Clearly this word 'direct', when used in conjunctionwith the words 'loss
and/or expense', is a very restricting one and disqualifies all costs and/or
expenses that do not arise as a direct result of the matter under complaint.
Thus, any costs due, for example, to mismanagement,to other causes not
recognisedas matters by the wording ofthe contract or to other concurrent
delays should be excluded from those reimbursable to the contractor as
they are not the direct result of the matter under consideration.
4.2.2.3 ASCERTAINMENT
<j>
The definition of this word should be seen in the context of the subject of
the ascertainment. Given that judgement is a]most always called for (see
<> 4.2.1.5 and<.4.2.1.6) it follows that 'to ascertain' can rarely mean to
prove comprehensivelywith invoices andrecords but ratherto establishby
the use of such facts as are available andby the use of expertjudgement.
4.2.3 Entitlement
4.2.3.1 LIMITATIONS
AppendixD provides a checklistof items on which entitlement is allowed
under JCT80.
(a) The loss and/or expense must arise directly as a result of one of the
matters referred to under the terms of the contract. Such matters do not
usually extend to the contractorunderpricing the rates to be used in valuing
variations.Thus, losses arising from any suchunderpricingare not usually
reimbursable.
4.2.3.3 WRITTENAPPLICATION
Before the contractoris entitled to any reimbursementin respect of loss
and/or expensehe should first have made an application,at the appropriate
time, to the appropriateparty namedin the conditions of contract.The pur-
pose of this written applicationis to enable the contract administratorto
form his opinion on whetheror not there has been, or will be, loss and/or
expense incurredwhich wouldnot be reimbursedunder any otherprovision
in the conditionsof the contract.In addition, it should be noted that, with
reference to the matterof applications:
2
adjusting the contractsum. Thiwi1Liric1ude documents in support of
ascertainments of the contractor's entitlement to reimbursement of loss
and/or expense (see clause 30.6.1.1). Moreover, clause 26.1.3 requires the
contractor to supply to the contract administrator or quantity surveyor,
upon request, such details as are reasonably necessary for the ascertain-
ment of any reimbursableloss and/or expense. But note that these details
have to be requestedandclearly, for suchdetails to be of maximumuse, the
request for them should be madeat the earliest opportunity.
4.2.3.5 In practice, what is going to be adequate data will depend upon the nature
of the disruptionor delay. Thus, the request for the contractorto keep such
details shouldnot only be timely but should alsobe as specific as possible
as to the data required.
4.2.4 Ascertainment
4.2.4.1 RESPONSIBILITYFORASCERTAINMENT
Under JCT 80 the responsibility for ascertaining the amount due is the
contractadministrator's,unless he instructs the quantity surveyorto under-
take this task. Where the contract administrator so instructs the quantity
surveyor this instruction should be in writing, to be copied to the
contractor, and be specific as to the matters which are covered in such an
instruction. However, the contract administrator cannot delegate to the
quantity surveyor, or anyone else, the task of forming an opinion on
whether or not there is a case in principle for loss and/or expenseto be
ascertained. A checklist of steps required under JCT 80 is included at
Appendix E.
4.2.4.4 In general the surveyor should ensure that the basis, calculations and
evidential records used in the ascertainment are recorded in writing. This
may be a mandatory requirementon public sectorcontracts.
4.2.4.6 Clause 26.1 of JCT 80 requires that ascertainment is made from time to
time. This means that ascertainment should be an ongoing process where
the facts are sufficientlyestablishedto make a proper andfinite calculation.
Moreover, clause 30.2.2.2 of JCT 80 states that any amount ascertained
under clause 26 should be includedin interimcertificates.
(a) It is necessary that each application conforms fully with the rules
written into the contractaboutthem (for exampletiming, in writing, sent to
the contract administrator).
(b) The contractormust keep such records as are necessary for the ascer-
tainment ofthe amountdue.
(c) Only where the effect of a series of matters (for examplethe lateissue
of a number of instructions or the instructingof a numberof variations) is
such as to create extra costs which by their nature are indistinguishable
from one another can an application on a global basis be entertained.
Simply because there is, for example, a series of variation instructions
which create overlapping or contiguous disturbance, it does not follow that
all other matters on that project can be addedin to make a global claim. A
global approach to ascertainment should be restricted solely to events
which create indistinguishable effects. Thus, no contractor should be
penalised by being deniedreimbursement simplybecause extra costs were
incurred which could not by their nature be particularised. On the other
hand, the facility of global ascertainment shouldnot be used to mask facts
and figures that couldproperlyhavebeen particularised and presented.
4.2.5.1 GENERAL
A list of possible items admissible as part of an ascertaimnentof loss
and/or expense (which is to be read as includingthose attributableto sub-
contractors)is as follows:
• extended and/or increased use of 'preliminaries', for example more
supervision,moreplant etc.;
• reduced labour outputs;
• extra waste or abortive purchaseofmaterials;
• increasein the price of resources,i.e. inflation;
• increasedcostof head officeoverheads;
• loss ofprofit; and
• financecharges.
More often than not the dominant items will be the first two from the above
list.
4.2.5.2 PRELIMINARIES
A representativelist of the items normally comprisingthe preliminariesis
given atAppendixA.
272
4.2.5.3 When ascertaining the extra costof 'preliminary' items (but see4.2.4.8)
it is importantto break each item down into the following components:
273
(d) Recognisethat.there is a learning curve in all activities. The advantage of
this can be lostif a new gang of men is brought in to undertake work which
has become familiarto others; the resultant extracost will be reimbursable.
Moreover, if additionallabour has to be recruited at short notice it may be
necessary to pay premiumrates which wouldin principle be reimbursable.
(f) Recognise that great economies can flow from a repetitive task, for
examplefixingpartitions in a series ofidentical dwellings,the interruption
ofwhich can result in far-reachinglosses.
4.2.5.5 A list of items relevant to the calculation of reimbursable extra costs of
disruptionis given at AppendixB.
4.2.5.7 INFLATION
If work is executed later than otherwise would have been possible as a
result of a relevant matter and if inflation has caused the costto rise then,
providedthat such costs are not reimbursableunder the fluctuationsclause,
they will form part of the ascertainment.Even where the contract contains
a fluctuationsclause, if it contains a non-adjustableelement, a delay in the
execution ofwork might well increasethe non-recoverableelement, which
wouldbe reimbursable.
1 Tate & Food and DistributionCo. Ltd & Another v. Greater London Council & Another (1982)
Lyle
1WLR 149
L
managing the project as a result of the matters giving rise to a claim.
Appendix C gives further guidance on the components and methodsof such
an ascertainment.
4.2.5.10 Account should also be takenof the extent to which extra costs are already
being reimbursed through the pricing ofthe variationaccount.
1 StModwen
Developments Ltdv. Bowmer& KirklandLtd(1996) 1996CILL1203
2 Construction Ltdv. FoundationsLtd(1970) 1 BLR 114
(Liverpool) McKinney
GMinter Ltdv. Welsh HealthTechnical ServicesOrganisation (1980) 13 BLR 1
Page 12 Effective from 1/6/99 Part 4, Section 2 (4/99) TheSurveyors' Construction Nandbook
275
4.2.5.15 Finance charges are recoverable from the date that the primary loss and/or
expense was incurred up to the time that the certificate, which included the
payment of that loss and/or expense, was issued, provided, as always, that
the conditions in the contractin that respect have been met (see 4.2.3.3
(c)).
4.2.5.16 The rates and manner of interest jayable should be those actually incurred
(or being earned on capital).
4.2.6.1 GENERALLY
It is not possible to list all the items which are inadmissible.However, it
might be helpful to comment upon certain items which are occasionally
claimed as being reimbursable when they are not. Among these the most
usual are:
4.2.6.5 Where, however, he provides the data which might be required by the
quantity surveyor under clause 26.1.3 the cost of so doing may be
reimbursable.
Al STAFFAM) ADMINISTRATION
Note: This includes security and welfare personnel and the supervisory
time of trades foreman andthe like.
Consider:
A2 TEMPORARY ACCOMMODATION
Consider:
Append4/99L
• generalsite wear; and
• progressphotographs.
A3 PLANT
This covers plant owned by the contractor or hired from a subsidiary or
specialist company. It is advised that the conditions of hire are examined.
There is often a guaranteedminimum period of hire which would have
been paid for in any case. When long delays have occurred, loss must be
mitigated by use elsewhere or the terminationof the hire contract.
Consider:
• tower cranes;
• mobilecranes;
• banksmen and slingers;
• weighbridge;
• wheelwashingfacilities;
• compressors;
• mixers;
• pumps;
• hoists;
• site surveyingequipment;
• site/craneradio system;
• concretetesting;
• general site equipment;
• small plant and tools; and
• rubbishremoval(skips).
A4 TEMPORARYWORKS/ACCESS
Consider:
A5 FENCINGAI'D SECURITY
Consider:
A6 DISTRIBUTION
Consider:
21?i
• telescopic hoists, including driver;,
• internal site transport; and
• hoist drivers.
A7 SCAFFOLDING
Consider:
• extrahire;
• adaptations; and
• additional work — for example safetyrails where scaffolding removed.
A8 TEMPORARY ELECTRECS
Consider:
A9 TEMPORARY WATER
Consider:
AlO INSURANCE
Consider:
Bl.2 Plant
Refer to invoicesto indicate additionalcostsdueto:
• relocationofplant, on or off site;
• additionalplant;
• additionaltools;
• alterationsor additionsto scaffolding;and
• standingtime.
Bl.3 Materials
Extra costs can be incurred due to the:
• double handlingof materials;
• waste anddamageofmaterials;
• return ofmaterialsto the store or supplier; and
• substitutionof materials.
280
• the immediateeffect upon workingtrades;
• the knock-on effectupon succeedingtrades, particularlysub-contractors;
• the effect upon allied tradesworkingin the vicinity;
• the inability to divert labour elsewhere (i) on the site, and (ii) to other
contracts;
• evidence of efforts made to divert labour to other contracts, or to other-
wisemitigate the costs of construction and effectsofdisruption;and
• the relationship with nominatedfirms and sub-contractors and records
from themto substantiatethe claimof disruption.
B3.2 There may be further items not covered above which the contractorcould
bring to the notice of the quantity surveyor. In making an assessment of
disruption,the quantity surveyormayrequire the tender progressintentions
of the contractor, and to examine data on which projections of progress
were based in order to indicate the effect that changeshave had upon the
planning. The information may include critical path analyses and similar
information.
B3.3 The quantity surveyor shouldgive careful consideration to all this informa-
tion andjudge its relevance to the particularmatters being examined (but
see 4.2.4.2).
• percentage;
• lump sum(s) (specify how compiled); and
• spread in rates ofall items.
C3 ASCERTAINMENTOFTHESE COSTS
C3.l Check:
• time records or diaries which may indicate additional time spent with
consequentialfinancial disbursements (this should be time arising from
relevant events over and above that which would have been spent on
ordinary administrationof the contract);
• proofofpayment made on all admissible items; and
• details showingbuild-up of generalhead office costs at the relevanttime
or throughoutany relevantperiod.
C3.2 For a contractorto succeed,it is recommendedthat the quantity surveyoris
reasonably satisfiedthat:
• time expendedwas additional to thatreasonably to havebeenexpected;
• the extra costs have not been recoupedin other ways (for examplefrom
set-off or other arrangementswith sub-contractors);
• any loss and/or expense sought has not been avoided by re-deployment
of resources on other contracts;
• additional costs have not been recovered through rates for measured
works;
• additionalcosts have not beenrecoveredin dayworks; and
• head office staff costs have notbeen recoveredelsewhere.
C4.2 What were the relevantevents givingrise to delays under the conditions of
contract?Were head office costs applicableto those events?
C4.3 To what extent was the head office involved in, for example, site visits,
meetings etc.?
C4.4 Was there a need to employ additional head office staff whether or not a
delayhadoccurred?
C4.5 How effectivelydid the firm employ staff on this contract as against other
contracts that they were undertaking?
C4.6 What was the size of the contract in relation to the size of the firm and,
therefore,the impact ofthe delay to progresson the business of the firm?
The contract clause numbers referred to in this form are from JCT 80.
Contract
clause
number Item Tick
The contractclause numbers referredto in this form are from JCT 80.
Contract
clause Comments from the
number Item quantity surveyor Tick
26.1 The contractor has applied in writingstating:
he has incurred/is likelyto incur direct
loss and/orexpensenot reimbursed by
any other contract provision
progress has been/is likely to be
materially affected by the items listed in
clause 26.2
26.1.1 The contractor has made application as soon
as it was reasonablyapparent that:
the regular progress of the works/orpart
of the works has been/is likelyto be
affected
25
Appendix F: Further Reading
BOOKS
Parris, John. The StandardForm ofBuilding Contract JCT80, 2nd Edition, Collins,
1985
BuildingLaw Reports
Court of Exchequer
King's Bench
Introduction
The risk management process outlinedin this section can be appliedto any
procurement route and to new build or refurbishment-based projects,
regardless of cost or technical complexity.
The Surveyors' ConstructionHandbook Part 4, Section 3 (12/99) Effective from 1/1/00 Page 1
287
PART 4, SECTION 3
4.3.1 Definitions
4.3.1.1 Risk: An uncertain event which, should it occur, will have an effect on the
achievement of the project's objectives. A risk can be measuredin terms of
likelihood (probability) andconsequence (impact).
4.3.1.2 Risk management: A structured and auditableprocess for the benefit of all
members of the project team which is dedicated to the sole purpose of
controlling andmitigatinguncertainty in a project.
4.3.1.7 Risk register: A document listing all the risks identified for the project,
explaining the nature of each risk and recording information relevant to its
assessmentandmanagement.
Page 2 Part 4, Section 3 (12/99) Effective from 1/1/00 The Surveyors' Construction Handbook
288
PART 4, SECTION 3
The Surveyors' ConstructionHandbook Part 4, Section 3 (12/99) Effective from 1/1/00 Page 3
289
PART 4, SECTION 3
4.3.2.7 Risk management, together with other services provided, should be flexible,
adapting to the circumstances ofthe client'sneedsandthe project. Someclients
require a snapshotofthe risks at the outset ofthe project, with an initial risk
assessment, the provision of a one-offrisk register and a quick estimate ofthe
combined effect. Other projects may require a full risk management service
with risk being continually addressed throughout the project.
4.3.2.8 A concern often voiced by clients is how to quantify the benefits of risk
management. Since risk management has a major emphasis on reducing
potentially detrimentaleffects, itis notusually politic to demonstrate its effective
application as having minimised the impact ofcost overrun to, say, 15 per cent.
4.3.2.9 Furthermore, the actual impact of risk is unique to a project even though its
presencemay be commonplace. The risk management process may not be at
faultjust because risks were realised. Indeed, if no risks were realised, the
effectiveness of risk assessment would be questionedbecause without risk
there wouldbe no opportunity.
There are three basic steps to the risk management process; identification,
analysis and response.
Page 4 Part 4, Section 3 (12/99) Effective from 1/1/00 The Surveyors' ConstructionHandbook
290
PART 4, SECTION 3
4.3.3.2 The risk management process also needs to be integrated into the project
management process. Since any risk management workshopor assessment is
a snapshot in time, the process has to be undertaken on a repetitive basis.
Essentially, the risk management process should be commenced as early as
possible in a project life cycle and each of the three stages repeated as
necessary to effectively managethe risks associatedwith that project. At the
commencement ofthe process a risk management plan shouldbe developed.
The risk management plan is similar in nature to the project execution plan
and may form part ofthat document.
(a) Methodology
The Surveyors' ConstructionHandbook Part 4, Section 3 (12/99) Effective from 1/1/00 Page 5
291
PART 4, SEcTIoN 3
(b) Techniques
(i) Research
While exactlythe same projectwill nothave beenexecutedbefore,something
similar will have been. Investigationinto projects on neighbouring sites or
projectspreviously undertakenby the client shouldbe instigated.
(ii) Structuredinterviews/questionnaires
Interviews with key members of the project team (including client and
suppliers) will elicitthe greatestinsight into risks to the project and how they
areperceived by individuals. Interviews allowa greaterdepth ofunderstanding
to be achievedthan group discussions butdo take up a lot oftime.
(iii) Checklists/promptlists
A simple and effective way to stimulate the team into thinking about risk is to
use achecldist.An easy way to starta checklist is for eachteam member to write
down allthe variation orders ontheir lastproject, withthe reasons fortheirissue.
Page 6 Part 4, Section 3 (12/99) Effective from 1/1/00 The Surveyors' ConstructionHandbook
292
PART 4, SEcTION 3
The probability andimpact of the risk cthi also be shown; the importanceof
these factors is discussed in Section4.3.3.4(a).Finallythe responsetothe risk
canbe shown.
The risk register is a very useful format for showing a wide range of
information in the risk management process. If the register is placed on a
computer spreadsheet it is easy to sort the risks in a variety of ways, for
instance by category or magnitude ofprobability.
The Surveyors' ConstructionHandbook Part 4, Section 3 (12/99) Effective from 1/1/00 Page 7
293
PART 4, SECTION 3
bE
bE
Page 8 Part 4, Section 3 (12/99) Effective from 1/1/00 The Surveyors' ConstructionHandbook
294
PART 4, SECTION 3
IMPACT
Veryhigh High Medium Low Very low
Veryhigh
High
Medium
Low
Very low
Before the risks can be plotted on to the matrix, a scale has to be set for the
probabilityandimpact dimensions.Settingacommon scalewillensureaconsistent
approachtoplacingnewly-identifiedrisksonthe matrixatalater stageintheproject
life cycle.An indicative layout fordefining scales is showninfigure 3.
PROBABILITY IMPACT
Cost Time
The Surveyors' ConstructionHandbook Part 4, Section 3 (12/99) Effective from 1/1/00 Page 9
295
PART 4, SECTION 3
The method ofhavingthe probability scale linear andthe impact scale non-
linear emphasisesthe significance oflow probability/high impact risks. The
matrix allows each risk to be ranked and comparedon an even basis. Where
resources are scarceit also allows attention to be focusedon those risks which
sit in the high-riskcategory ofthe matrix.
The Probability/Impact matrix is the easiest technique to use and allows all
projectteam membersto participate inthe process via a risk workshop. More
sophisticated tools and techniques may be applied to provide a better
understanding ofthe identifiedrisks. Thereare a wide range ofsuch tools and
techniques available, many of which are supported by computer software
packages:
• Monte Carlo simulation modelling of cost andtime risks;
-
• cost movementforecast;
• decisiontrees;
• sensitivityanalysis;
• hard/sofimoneyanalysis;
• 'what if?' analysis;
Page 10 Part 4, Section 3 (12/99) Effective from 1/1/00 The Surveyors' ConstructionHandbook
296
PART 4, SECTION 3
• influefice dirms;
• simulation packages;
• multipleestimaterisk analysis(MERA);
•
spider diagrams;
• multi decisioncriteria analysis;
• linear regression;
•
spreadsheets; and
• flowcharts.
4.3.3.5 RISKRESPONSE
(a) Methodology
The tools available are not usually related purely to risk management. For
instance, most surveyors wouldrecommend to their clients that the contractor
has thirdparty insurance for the project. This is a risk management response
designed to reduce clients' exposure to claims for damages if a particular
The Surveyors' Construction Handbook Part 4, Section 3 (12/99) Effective from 1/1/00 Page 11
2q7
PART 4, SECTION 3
4.3.4 Summary
Page 12 Part 4, Section 3 (12/99) Effective from 1/1/00 The Surveyors' Construction Handbook
PART 4, SECTION 3, APPENDIX A
Chapman, C., and Ward, S. Project Risk Management: Processes, Techniques and
Insights, John Wiley andSons, Chichester, 1997
The Surveyors' Construction Handbook Part 4, Section 3 Effective from 1/1/00 Page 1
AppendixA (12/99)
299
PART FIVE: ADDITIONAL GUIDANCE AND
INFORMATION
Note: Section 5.1 reproduces exactly the material contained in the RECS
leaflet Surveying Safely.
300
NO COMPROMISE ON SAFYFY
SIR IDRISPEARCE
301
A message from Dr John Cullen Chairman, Health
and Safety Commission
Dt JOHN CULLEN
302
-
SAFETY YOUR LEGAL DUTIES The health and safety policy statement
The statement should clearly state what every
The HealthandSafety atWorkAct 1974 protects
employee 's responsibilities are and to whom
peopleat work. It requiresthat all chartered they are accountable: It should be signed and
surveyorsensure 'so far as is reasonably dated by a partner or director If it is revised,
practicable' the health and safety of both then all employees should be notified.
themselves and others.
You must ensure that all new employees get
a copy and that they have read and under-
Your main duties stood it.
Youmustunderthelawensurethat:
• the places in whichyou workare safe; If you need help, the Health and Safety
• safe Executive has produced a leaflet on how to
workingpractices must be clearlydefined,
prepare the statement. Ask your local
organised and followed;
• iirstaidequipment must always be availableboth Executive officerfor a copy of 'Writing your
in theoffice and for surveyorswho aretravelling; health and safelypolicy statement'.
• that you do not endangeryourself or others.
Whetheryou are a manager, employee, partner
or director, whetherornotyou are self-
employed, this is your legal duty. Youmayalsobe liablefor damages under
common law. For example, in Clay vAJ Crump
The people you must protect and Sons, the professionalin charge of a site was
As a chartered surveyor, thelawsays you must liablefor some of the damagespaid to an injured
protectthe safety of: labourer.
• anyonewho usesyour services; Finallyifyou employfiveor more people, you
• thepeople whoworkforyou. This includes must under the lawhave awritten healthand
casualandpart-timeworkers, trainees, and safety policy statement.
sub-contractors;
• anyone who may be affectedbyyour work. This
includesneighbours, passers-by andthe public; TAKING THE LEAD ON SAFETY
• visitors to your offices — they may also have Wehave aclear responsibilityunder the lawfor
redress in the case of an accident. the safety of ourselves, our clients, our colleagues
Ifit appearsthat theAct is notbeingfollowed, and the public.
in any aspect of yourworking life, then you How canchartered surveyors effectivelytake
should say so. Ifnecessary get advice from your the lead on improvingpracticewithinthe
local Health and Safety Executive (HSE) office, industry?
listedin the Phone Book.
A safe routine
Familiarity with otherregulations Safety should become a working routine.
You must also makeyourselffamiliarwith the Beforeworkbegins you should:
legislation that applies to specific kinds of
• identifythe likely hazardsassociated with the
premises. For example, you may need to be project;
familiar with the FactoriesAct 1961 or the • commission protectiveworks beforea survey
Offices, Shops and Railway PremisesAct 1963. ofespecially dangerous premises goes ahead.
Quarrying and agriculture also have specific Acts Clearrubbish,providetemporary props, struts
andregulationsthat set standards. andguardrails. Clean and disinfect if
necessary;
The penalties • ensure safe access andmeans of escape;
Ifyou have exposed peopleto avoidable danger, • inform everyone— colleagues,consultants,
criminal chargesincluding manslaughter may be contractors— of the hazards and of the means
broughtagainstyou. of escape.
303
Whencommissioningwork, you SUPERVISING OTHERS
should: Youhavea specialresponsibilityfor peoplein
• make the contractor's reputationfor safetyone your charge, particularlythose in trainingor who
of the criteria when assembling tenderlists; are inexperienced.
• ensurethat contract documents list items • Make sure that surveyorsin your chargetake
that are essential for health and safety and the right equipmentwiththemon visits. Check
encouragecontractors to price the appropriate thatthey know how to use it.
clauses; • Ensure that scrupulousrecords are kept of
• warn contractors ofdangerousworkbefore- surveyors' movements.
hand, suchas asbestos removal. • Keep availablerecords of hazardson
particularsites. Make sure that all relevant
Duringwork, you should: peopleare notified.
• useproper equipment, protectivegear and • Make sure that a supply ofthe right
clothing. Cameras orbinocularscan be usedto equipment is available. Helmets,steel capped
avoidclimbing onroofs for example; shoes, ear muffs, face masks, overalls,torches
• bring in specialist help.Steeplejacksand other andbatteries— all theseshould be in your
trained operators shouldbe brought in when office and in good condition.
needed; • Make sure that your offices are safe. Are there
• keep clientsinformed of hazardsand safety fireprecautionsandmeans of escape?Washing
issues; facilities? Is electrical equipmentup to date
• supervise professional work to a safe andsafe?Do you prepare and store food and
completion. drink safely?
• refuse to implement instructionsthat expose
you or anyone elseto danger. Finally, the best way to ensure safepractice by
people in your chargeis to set a good example.
Aftera survey,theproperty should be left
secureand hazardfree.You should makesure PROTECTING YOURSELF
at all timesthat someonein the officeor at Some ofus take better careofother peoplethan
homeknows where youwill be, especially we do ofourselves.
whenworking in remote places or empty Please don't over work. Don't squeeze in an
buildings by establishingan open diary extrajob at the end of the day. Don't take
regime. unnecessary risks on site. Trynot to drink
heavilyat lunchtime. Don't overworkin great
Protecting the public heat and keep warm in cold weather.
This is one of themostimportantaspectsofyour • Make sure that business vehicles are well
safetyroutine. maintained. Don't try to drive long distances
Youmayneedto informadjoining owners,ten- when you are tired. Keep a copy ofthe
ants inthe samebuilding, people working nearby HighwayCode in the office. Have you had
or even the general public about aspects ofyour anti-tetanus vaccinations?
work. The caseofSuzy Lamplugh brought homethe
• Make surethat signs are postedthat informof needtobe wary of escorting strangersaround
dangers, temporary diversions, hazardous oper- emptypremises. Carry personal alarms and
ations suchas asbestos removal, or anything telephones. Make sure people know where
that mightaffectgeneral safety. you are going andwith whom you are going.
• Make surethat therelevantpublicauthorities Workin pairs if visiting particularlydangerous
are informed. Sometimes the Health and Safety areas.
Executivemayneedto be told aboutparticular Surveying can be a dangerousbusiness and
operations. Ask their advice. members are asked to takeparticular carein
OL
mattersofpersonalsafety. A detailed checklistof • Floorboards, joists and buried timbers
potentialhazardsis included as an appendix and weakened by age, decayor attack
can be pinned to office or site noticeboards for • Projectingnails and screws. Broken glass
reference at all times. • Glazing in windows andpartitions may be
loose,hinges and sashcords weak or broken.
KEYPOINTS Glass panels in doors and winglights may be
You should: paintedover
• ensurethat you comply with the provisions of
the HealthandSafety atWork Act, including Roofs
• Fragileasbestoscementandplastic coverings
the productionoftherequiredPolicy Statement;
• comply with the office safetfpolicyandinpar- Fragilerooflights (oftenobscured by dirt or
ticularemployers shouldprovide equipment temporarycoverings)
• Low parapetsor unguarded roofedges. Loose
and establishsafe workingroutines;
• refuse to condone unsafeworking practicesby copings
• Rusted, rotten ormoss covered fire escapes,
othersand distribute informationon hazards;
• ensurethat your advice to clients will minimise access ladders and guardrails
the risk to the health and safety of others. • Rotten roofdecking andjoists
•
Slippery roofcoverings (slates, moss or algae
In other words, follow the dictates ofcommon covered slopes)
sense. • Broken accesshatches
• Mineral wool dust,mortardroppings and birds'
CHECKLIST nesting material and excrement in roofvoids.
Cornered birds and vermin
IDENTIFYINGPARTICULARHAZARDS • Insects, bugs andlice. Bee and wasp colonies
• Watercoolingplantmay harbour legionella
• Unguarded flat roofs
Representatives ofalltheRICS Divisionshave
contributed to the following checklist. Individual
• Broken, loose, rottenandslippery crawling
members will recognise the hazards they boards and escape ladders
encounterregularly, and most will benefit from • Weak flat roofs anddust covered rooflights
the advicegivenwhenworkingin unfamiliar • Slippery roof surfaces
• Highwindsduringroofinspection
surroundings. Itis the natureof safety matters
that no checklist like this canbe entirely • ill-secured or flimsy, collapsible, sectionalor
comprehensive. fixed loft ladders
• Concealed ceiling joists and low purlins
The following itemsmay create danger: • Ill-litroofvoids
306
• Slurryponds, lagoons,tanks and other filled Farm machinery
areas • Packingand gradingmachines
• Noisy and dusty conditions • Stones and debris thrown from swipes and
• Railways and internalhaulroads hedgecutters
• Dangerfrom the quarrying operation and • Cranesandthe lifting equipment
mobileplant
Livestock
Tips andLandReclamation Sites • Anyentire male animal: bulls, boars andrams
• Unstable slopesandground • Anyfemaleanimal with young — calf proud
• Waterlagoons, ponds and otherwaterfilled cowsandfarrowing sows
areas • Gameparks and wild animals
• Slurryand quicksandareas • Horses
• Burning areas wheretips are heatingor on fire • Dogs
• Hazardous or harmful chemicals, liquidmatters
andwastes, contaminated land Diseasesand pests
• Explosive andtoxic gases and vapours • Tetanus, Brucellosis
• Weil'sDisease (fromstagnantwater andponds,
Gas and Oil Wells haystoresetc)
• Pipes and othergroundlevelhazards
• Flare stacks
• Separating lagoons Sporting
• Firearms (mustbelicensed and properly stored
• Explosive atmospheres andused)
• Dangerfrom the drillingoperations
IN FORESTS
Exploration, Drilling and Gantry Sites
• Hot muds • Tree fellingwork eitherin thinningor clear
• Flyingrock, dustand debris
• Waterhazards felling operations
• Unsafeplant • Tree surgery work
• Dangerousand damaged trees, especiallyif
liableto shed limbs
ONFARMS • Any work in woodlands in high winds
• Hand tools, axes andswipes
Farm buildings and land •
• Grain storage andhandlinginstallations, Chain saws
• Sawmillingand cuttingequipmentin saw
particularly movingaugersand conveyors mills and woodyards
• Underground slurrystores, slurry lagoons, • Timber handlingequipment e.g. overhead
drains, deep ditches, wells,tower silos, sewage
tanks and silageclamps(note: risk oftoxic extraction lines
• Forklift vehicles and cranes
gases)
• Dusthazardsin grain, mill and mixand
intensive livestockbuildings OFFSHORE
• Overgrown areas: concealed manholes
• Poorlymaintained buildings — especially loft • Moving and often slippery decks of ships and
floors— and fittings oil rigs
• High voltage electric fencing • Poorlysecuredequipment, includingcoffee
• Stored hazardous chemicals cups andtools nearsensitivemachinery
• Rivers,lakes, reservoirs, dangerous bridges, • Firehazardsand flammable materials
• The hostiledeckenvironment
bogs, quicksands, unstablecliff edgesandthe
sea • Highpressure air gases and gas storagecylinders
• Chemicals, poisons • Hydraulicoil leakage
307
BIBLIOGRAPHY 16 Safety in working with power operated
mobile workplatforms.
1* Writing a Policy Statement: Advice to HSE Guidance Series HS(G)19:
Employers; HSE 1985; (HSC6 Rev). ISBN 0.11.993628.5.
2* Guidance on the Implementationof Safety 17 TowerScaffolds.
Policies; HSE 1987 (IAC/Li). HS42: ISBN 0.11.883941.1.
3 Writing Your Health and Safety Policy 18 Suspended AccessEquipment.
Statement: How to prepare a Safety Policy HSE GuidanceNote PM3O:
Statement For a Small Business; ISBN 0.11.883577.7.
ISBN 0.11.883882.2. 19 Deadly Maintenance: A Study of Fatal
4 Positive steps — help and advice for women Accidents at Work.
on personal safety. ISBN 0.11.883806.7.
20 Blackspot Construction: A Study of Five
MetropolitanPolice
5 Years Fatal Accidents in the Building and
Managing Health and Safety in
CivilEngineeringIndustries.
Construction;HSC Coniac Guidance:
ISBN 0.11.883992.6.
Principles and Application to Main
21 Avoiding Danger from Buried Electricity
Contractor/Sub-Contractor projects.
ISBN 0.11.883918.7 Cables.
GS33: ISBN0.11.883612.9.
ManagementContracting: 22 ProtectionAgainst Electric Shock.
ISBN 0.11.883989.6.
GS27: ISBN 0.11.883583.1.
6 Children on Construction Sites:
23 AsbestosandYou.
GS7 ISBN 0.11.883055.4.
7* ConstructionIndustrySummarySheets. IND(G) (18)(C). Availablefrom the Health
and Safety Executive.
8* ConstructionSite Safety Checklist.
24 FirstAid at Work.
9* Health HazardInformationSheets.
10* ConstructionList ofHSC/E References. (HS(R)11): ISBN 0.11.883446.0.
25 A Guide to the Safety Signs Regulations
11 ConstructionSafety Manual.
1980. ISBN 0.11.883415.0.
Published by BuildingAdvisory Service of 26 HSE Guidance on Construction
(Head
the BuildingEmployers Confederation.
Protection)Regulations 1989.
12 Entry into Confined Spaces. HSE Guidance ISBN 0.11.885503.4.
Note GS5; ISBN 0.11.883067.8. 27 CONIAC Guidance on The Control of
13 Safety in Roofwork. Substances Hazardous to Health in the
HSE Series Booklet MS(G)33: ConstructionIndustry.
ISBN 0.11.883922.5. ISBN 0.11.8855263.
14 General Access Scaffolds. HSE Guidance
Note GSI5; ISBN 0.11.88345.9.
15 Safe Use of Ladders, Step Ladders and
Trestles. HSE Guidance Note GS31: *All available free from HSE Offices and
ISBN 0.11.883594.7. LibraryServices.
3o
PART 5, SECTION 2
Regulations
Accident Awareness/Statistics
Risk Assessment
Clients
Clerk of Works
310
PART 5, SECTION 2
Designers
CDM Regulations Case Study Guidance for Designers: An Interim Report, CIRIA,
1995 [0860174212]
Planning Supervisor
CDM Documents
3u
PART 5, SECTION 2
ConstructionSheet No. 44: The Health andSafetyFile, HSE, 1995 [CIS 44]
Comprehensive Guidance
Specific Hazards
Contractors
312
PART 5, SECTION 2
Audio Tapes
3j3
PART 5, SECTION 2
5.3.1 Practice panels of selected Members have the following roles in respect of
definedspheres of surveying services:
KI) 5.3.2 The practice panels principally responsiblefor producing material for this
Handbook andtheir respective spheres of activity are shownhere, with the
names ofthe supporting membersof staff shownnext to each.
3LS
PART 5, SECTION 3
5.4.2 BCIS collates and analyses unique data submitted by membersand incor-
porates material from all other relevant sources. The informationis inter-
preted by BCIS professional staff and presented to subscribers in two
accessibleandpractical formats: the comprehensive BCISBulletinService,
which provides hard copy data, and BCIS Online for those preferring to
receiveit electronically.
5.4.3 The publications listed below are available on separate subscription but
those marked (*) are all included in the BCIS Bulletin Service; those
marked (•) are alsoincluded in BCIS Online.
The Surveyors'Construction Handbook Part5, Section4 (4/98) Effective from 1/6/98 Page 1
38
PART 5, SECTION 4
•K 5.4.8 News(*)
BCIS News accompanies each BCIS Bulletin. It takes the form of a
newsletter, highlighting items contained in the latest Bulletins. It also
summarises items of economic significance and reports on BCIS plans and
activities. BCIS Online has its own news pages.
K$ 5.4.9 Digests(*)
This annual Guide covers the daywork rates for 43 grades of operative.
Each rate (1,436 in total) is calculatedin accordancewith the BCIS inter-
pretation of the appropriate Definition of Prime Cost of Daywork. An
updating service is offered which enables subscribers to be certain they
alwayshave the latest information.
5.4.13 Annual subscription rates, further details, up-to-date prices, special prices
for extra copies and special offers to chartered surveyors and educational
institutions are available by contacting:
BCIS Ltd
12 Great George Street
London SW1P3AD
Tel: 0171 222 7000
Fax: 0171 695 1501
e-mail: bcis@bcis.co.uk
The Surveyors'
Construction Handbook Part 5, Section 4 (4/98) Effectivefrom1/6/98 Page 3
32o
PART 5, SEcTIoN 5
The BMI Building Maintenance Price Book is the only annual guide to
estimating and pricing exclusively for building maintenance and repairs.
The Price Book gives labour constants and measured rates for over 1,300
items as well as current wage rates and materials prices. It contains
guidance on letting maintenance work. It is a valuable working document
for all those involved in estimating, checking and negotiating rates for
maintenance and repair work. It is widely used as a Schedule of Rates to
ensure competitiveprices.
The Surveyors' Construction Handbook Part 5, Section 5(4/98) Effectivefrom 1/6/98 Page 1
PART 5, SECTION 5
5.5.6 Annual subscription rates, further details, a full list of BMI Special
Reports, up-to-date prices and special rates for chartered surveyors are
available by contacting:
BMI
12 GreatGeorgeStreet
London SW1P3AD
Tel: 01712227000
Fax: 0171 695 1501
e-mail: bmi@bcis.co.uk
322
UPDATE 1
(dated 4/99)
Please note:
• apages carry the same 'effective from' date (i.e. 1/6/99).
CONTENTS LIST
UPDATE 1(1/99)
Section Remove Pages Insert Pages
Titlepage existing Title page new Title page
Bulletin Update — 1 to 2
Contents 1 to 2 1 to 3
Section 2.2 — 1 to 60
Section 4.2 — ito 28
Index lto5 lto8
3Z3
The
SURVEYORS'
CONSTRUCTION
HANDBOOK
Bulletin Update • April 1999
ELCOME TO THE FIRST SET 1 The main JCT contracts have been updated
OF UPDATES TO THE SURVEYORS'
I to incorporate the amendments that cover
the provisions of the 1998 Housing Grants,
CONSTRUCTION HANDBOOK. Construction and RegenerationAct. The new
contracts were published in late 1998 and are
knownas id 98, WCD98, IFC 98 and MW 98.
This update to the Handbookcomprises two
new sections: CIRIA is working with the Building Services
2 Research and Information Association
SECTION2.2: 'Life cycle costing'; and (BSRIA) and the Water Research Council (WRC)
on guidance on the use of rain water, grey
SECTION &2: 'Ascertaining the amount of water and combined
systems. Points include
loss and expense incurred in building projects'. how to select and install systems in different
types, maintenance,health and safety,
'Life cycle costing' is based upon the 1986 building
water quality, and economicand environmental
Guidance Note A Guide for Life Cyde Costing issues.
for Construction. It has been updated by the 1999 with Monitoring projectswill run until autumn
the final output expected in the
Construction Design and Economics Practice
year 2000.
Panel and includes new worked examples,
which were originally available in the accom- The Government consultation paper is out
panying document Life Cycle Costing: A 3 for comment to relevant bodies on the
Worked Example, published in 1987. Disability Discrimination Act 1995 and the
responsibilities off service providers and trade
'Ascertaining the amount of loss and expense organisations. The enforcement dates pro-
incurred in building projects' is a revision of
posed are October 1999 for reasonable
Contractor'sDirect Loss and/orExpense, pub-
adjustment and 200L for physical improve-
lished in 1987. It has been amended by the
ments to a building structure.
original author in conjunction with the
ConstructionAdministrationand Management The amended Building Regulations and
Panel. 4 related 'Approved Document Part M:
Access and Facilitiesfor Disabled was
It is hoped that subscribers will find this published on 3 November People' 1998. The
guidance, which has been the subject of Regulations amend the limits on application
numerous requests, a valuable tool, whether so that the
scope of Part M will extend to new
as an aide-mémoire or as a re-introduction to from 25 October 1999 (the 1992
dwellings
an area that has not been visited for some edition of the
Approved Document will be
time. withdrawn on the same day). It should be
noted that the Regulations include a new
requirement specifically related to sanitary
conveniencesin new dwellings and transitional 1 The Common Arrangement of Work
provisions. This is intended to complement the I 3 SectionsforBuildingWorks (CAWS) is now
provisions under the Disability Discrimination available from RICS Books.
Actand ensure betteraccess to newdwellings.
Appointing a Quantity Surveyor: A Guide
CIRIA is working on a project to minimise 14 I forClients andSurveyors,a Guidance Note
risk on contaminated land. It will cover which incorporates the provisions of the
aspects such as current UK practice on the Housing Grants Act, is now available from RICS
apportionment of financial risk between Books. Documentation for the appointmentof
involved parties, and assess the usefulness, a building surveyor, which is being updated to
efficiency and cost ofcollateral warranties and incorporate the provisions of the Act, is also in
other financial risk management products. In preparation.
addition it will provide guidance to clients,
The Building Regulation and Control,
engineers, contractors, professional advisors
and funders on the mediation or redevelop- 1S I Commercial Property, and Health and
ment of ground-fill sites. Safety Practice Panels are currently being
consulted on Government proposals to amend
The RICS has been consulted by the the Fire Regulationsunder the Fire Precautions
B Government on a draft discussion paper (Workplace) Regulations consultation docu-
prepared by Oscar Faber on the reduction of ment 1997. The consultation document gives
CO2 emissions from buildings. RICS members details of the Govemments proposals to amend
from the Building Regulation and Control the Are Precautions(Workplace) Regulations to
Practice Panel also took part in Live brain- comply with the EuropeanFramework Directive
storming workshops. Suggested ideas included 89-391-EEC. It also discusses the best way to
improvements to wall and window values and proceed to deal with the consultative and leg-
the introduction of performance-testing the islative overlap between the amended regula-
completion to check building performance tions and existing regulations, where steps
with design. should be taken to reduce this latest overlap,
and the operation and effectiveness of the
The Construction Act Working Party is enforcement regime set out in the Fire
7 continuing to provide articles in CSM on Regulations. The response to this draft docu-
various aspects of legislation related to the ment was sentto the Government in November
Construction Act. An Owlion tape is planned, 1998 and the amended regulations are expect-
as are seminars in London and Coventry. ed to be in place before the end of 1999.
The Healthand Safety PracticePanel will be The membership of the Government
8 holding a seminar in March 1999 at the 16
I working group on combating cowboy
RICS in London on changes to the Asbestos builders has been announced and includes
Prohibition Regulations 1992 and the members from the constructionindustry. This
approved Codes of Practice that support them. group will work with four sub-groups dealing
with proposals such as the introduction of a
The Civil Engineering Contractors' Association's
9 (CECA) Schedulesof Dayworks Carried Out badge of quality and the foundation of
incidentalto Contract Work is now available. approved builder lists. The membership of
For more informationphone 017133L1 3776. sub-groups will be mixed between those
standing members of the main working party
and additional external experts. It is expected
1 A The Dilapidations Practice Panel is plan-
I U fling to continue a series of Dilapidations that a draft scheme for consultationshould be
Seminars in 1999. available in the spring of this year.
325
The
SURVEYORS'
CONSTRUCTION
HANDBOOK
Bulletin Update October 1999
WELCOME TO THE LATEST SET
OF UPDATES TO
THESURVEVORS' CONSTRUCTION HANDBOOK
-
Design and Build Guidance for Employer's Agents looks at some of the tasks and responsibilities
that surveyors maybe asked to undertake when appointedas an employer's agent on a design and
build contract, It also provides a useful checklist of matters which should be considered when
compilingemployer's requirements.
It is hoped that subscribers will find this guidance a valuable tool, whetheras an aide-memo/re or as a
re-introductionto an area that has not been visited for some time.
The nextupdate will be published in December 1999 and will includetwonew sections on risk
management and value engineering.
3l
NEWS
321
The
SUR V EV 0 R 5'
CONSTRUCTION
HAND BOOK
Bulletin Update • December 1999
WELCOME TO THE LATEST SET
OF UPDATES TO
THE SURVEYORS' CONSTRUCTION HANDBOOK
Value Engineering looks at undertaking value engineering on a construction project. It considers the
benefits that can be gained from such an exercise, as well as when and howit should be carried out.
The various stages of a value engineering workshopare also examined. The aim of this section is to
assist surveyors both in advising clients on the use ofvalueengineering and takingpart in a value
engineering exercise as part of the design team.
The Managementof Risk examines howto deal effectively with the risks associated with construction
projects. It considers the reasons for establishing a risk management strategyand the benefits that
can be gained from such a strategy. It also looks at howto identify,analyse and respondto risk. It is
aimedat surveyors whoneed an overview of the principals of risk management.
It is hoped that subscribers will find this guidance a valuable tool, whether asan aide-mëmo!re or asa
re-introduction to an area that has not been visited for some time.
329