FOR
FIRE FIGHTING SYSTEMS PIPE FABRICATION &
INSTALLATION
(ALL METALLIC GROOVED/THREADED PIPING)
VIJAY ARABIA FIRE AND SECURITY SYSTEMS
(Contract No: PLL/P5QA01/PROJ/WO/096)
MECHANICAL WORKS
DOCUMENT REVIEW STATUS
□ Status 1 : Work May Proceed
□ Status 2 : Revise & Resubmit. Work May Proceed Subject To Incorporation of Comments
Indicated
□ Status 3 : Revise & Resubmit. Work May Not Proceed
□ Status 4: Review Not Required. Work May Proceed
___________________ _________________
Overseas Bechtel, Inc. Date
Page 1 of 7
INSPECTION & TEST PLAN
FOR FIRE FIGHTING SYSTEM
PIPING FABRICATION AND INSTALLATION
Contract No: 25045-000-FC1-C000-00016 / Contract Title: Fuel System. ITP Sequence No:25045-C5100-16-ITP-M-50 Rev No: 3
PLL/P5QA01/PROJ/WO/096
9
Discipline : MECHANICAL Reference Procedure / Method Statement / Specs:25045-16-3PS-D-02572, 25045-C5100-16-3PS-A- Page 2 of 7
13955, 25045-5100-16-3PS-M-13915
Frequency Inspection
Verifying
Activity Activity Controlling Character to of
Acceptance Criteria Documents
No. Description Document be checked Testing/ S/C PLL OBI
Inspection
1. Submittals 25045-C5100-16- Method • Approval by OBI Code 1 or Code 2 Each Area Material R R R
3PS-D-02572 Statement Test
25045-C5100-16- Reports,
Drawing • Approval by OBI Code 1 or Code 2
3PS-A-13955
25045-C5100-16-
3PS-M-13915
25045-C5100-16- Material • Tested and certified
3GS-M-50 • Mill test reports certified by manufacturer
for chemical and physical properties.
H - Hold Point: Written notification required. W – Witness: Written notification S – Surveillance: No notification required but R – Review: Record / Documents
Contractor may not proceed beyond this point required but Contractor may proceed if activity may be subjected to OBI Surveillance review.
without written confirmation of the Engineer. OBI does not attend. / Monitoring.
INSPECTION & TEST PLAN
FOR FIRE FIGHTING SYSTEM
PIPING FABRICATION AND INSTALLATION
Contract No: 25045-000-FC1-C000-00016 / Contract Title: Fuel System. ITP Sequence No:25045-C5100-16-ITP-M-50 Rev No: 3
PLL/P5QA01/PROJ/WO/096
9
Discipline : MECHANICAL Reference Procedure / Method Statement / Specs:25045-16-3PS-D-02572, 25045-C5100-16-3PS-A- Page 3 of 7
13955, 25045-5100-16-3PS-M-13915
Frequency Inspection
Verifying
Activity Activity Controlling Character to of
Acceptance Criteria Documents
No. Description Document be checked Testing/ S/C PLL OBI
Inspection
Material
External • As per material specification, size, Inspection
3. Identification, 25045-C5100-16-
coating schedule, etc. Each Area Report W W S
Labeling, 3PS-M-13915,
Handling and 25045-16-3PS- • Pipe and fittings, valve etc. will be tagged
stocking of 02572,25045-16- or label.
Stocking • External coating free from any kind of
pipe, fittings & 3PS-02551
valves visible damage.
• 10” dia pipe & 8” and smaller dia pipe
racked 2 sections and 4 section maximum
respectively.
• All fittings and valves kept in a covered dry
storage area until ready for installation.
5. Fabrication
Drawing • Grooved joints number marking in Fit-up
25045-16-3PS-D- marking isometric drawings by piping engineer. Inspection W W S
02572 Each Area Report
25045-16-3PS-A-
Pipe cutting • By circular saw and by grinding.
13955
25045-16-3PS-M- Grooving • By machine cutting/grinding and grooving.
13915 Fit-up and • As per approved AFC
joining • Provision for suitable support to avoid
preparation. distortion.
H - Hold Point: Written notification required. W – Witness: Written notification S – Surveillance: No notification required but R – Review: Record / Documents
Contractor may not proceed beyond this point required but Contractor may proceed if activity may be subjected to OBI Surveillance review.
without written confirmation of the Engineer. OBI does not attend. / Monitoring.
INSPECTION & TEST PLAN
FOR FIRE FIGHTING SYSTEM
PIPING FABRICATION AND INSTALLATION
Contract No: 25045-000-FC1-C000-00016 / Contract Title: Fuel System. ITP Sequence No:25045-C5100-16-ITP-M-50 Rev No: 3
PLL/P5QA01/PROJ/WO/096
9
Discipline : MECHANICAL Reference Procedure / Method Statement / Specs:25045-16-3PS-D-02572, 25045-C5100-16-3PS-A- Page 4 of 7
13955, 25045-5100-16-3PS-M-13915
Frequency Inspection
Verifying
Activity Activity Controlling Character to of
Acceptance Criteria Documents
No. Description Document be checked Testing/ S/C PLL OBI
Inspection
Hydrostatic
H - Hold Point: Written notification required. W – Witness: Written notification S – Surveillance: No notification required but R – Review: Record / Documents
Contractor may not proceed beyond this point required but Contractor may proceed if activity may be subjected to OBI Surveillance review.
without written confirmation of the Engineer. OBI does not attend. / Monitoring.
INSPECTION & TEST PLAN
FOR FIRE FIGHTING SYSTEM
PIPING FABRICATION AND INSTALLATION
Contract No: 25045-000-FC1-C000-00016 / Contract Title: Fuel System. ITP Sequence No:25045-C5100-16-ITP-M-50 Rev No: 3
PLL/P5QA01/PROJ/WO/096
9
Discipline : MECHANICAL Reference Procedure / Method Statement / Specs:25045-16-3PS-D-02572, 25045-C5100-16-3PS-A- Page 5 of 7
13955, 25045-5100-16-3PS-M-13915
Frequency Inspection
Verifying
Activity Activity Controlling Character to of
Acceptance Criteria Documents
No. Description Document be checked Testing/ S/C PLL OBI
Inspection
7. Pressure NFPA 13,14,15,16 Test Pressure Test pressure as specified in specification, Each Area test report.
testing and NFPA 25. AFC Drawing. H H H
No Leak or Pressure Drop.
Hydrostatic pressure test procedure will be
submitted later.
H - Hold Point: Written notification required. W – Witness: Written notification S – Surveillance: No notification required but R – Review: Record / Documents
Contractor may not proceed beyond this point required but Contractor may proceed if activity may be subjected to OBI Surveillance review.
without written confirmation of the Engineer. OBI does not attend. / Monitoring.
INSPECTION & TEST PLAN
FOR FIRE FIGHTING SYSTEM
PIPING FABRICATION AND INSTALLATION
Contract No: 25045-000-FC1-C000-00016 / Contract Title: Fuel System. ITP Sequence No:25045-C5100-16-ITP-M-50 Rev No: 3
PLL/P5QA01/PROJ/WO/096
9
Discipline : MECHANICAL Reference Procedure / Method Statement / Specs:25045-16-3PS-D-02572, 25045-C5100-16-3PS-A- Page 6 of 7
13955, 25045-5100-16-3PS-M-13915
Frequency Inspection
Verifying
Activity Activity Controlling Character to of
Acceptance Criteria Documents
No. Description Document be checked Testing/ S/C PLL OBI
Inspection
H - Hold Point: Written notification required. W – Witness: Written notification S – Surveillance: No notification required but R – Review: Record / Documents
Contractor may not proceed beyond this point required but Contractor may proceed if activity may be subjected to OBI Surveillance review.
without written confirmation of the Engineer. OBI does not attend. / Monitoring.
INSPECTION & TEST PLAN
FOR FIRE FIGHTING SYSTEM
PIPING FABRICATION AND INSTALLATION
Contract No: 25045-000-FC1-C000-00016 / Contract Title: Fuel System. ITP Sequence No:25045-C5100-16-ITP-M-50 Rev No: 3
PLL/P5QA01/PROJ/WO/096
9
Discipline : MECHANICAL Reference Procedure / Method Statement / Specs:25045-16-3PS-D-02572, 25045-C5100-16-3PS-A- Page 7 of 7
13955, 25045-5100-16-3PS-M-13915
Frequency Inspection
Verifying
Activity Activity Controlling Character to of
Acceptance Criteria Documents
No. Description Document be checked Testing/ S/C PLL OBI
Inspection
H - Hold Point: Written notification required. W – Witness: Written notification S – Surveillance: No notification required but R – Review: Record / Documents
Contractor may not proceed beyond this point required but Contractor may proceed if activity may be subjected to OBI Surveillance review.
without written confirmation of the Engineer. OBI does not attend. / Monitoring.