Urban Higway Project start end

SITE SETTING 07/01/19 07/18/19


site clearance 07/01 07/04
fencing 07/05 07/08
surveying 07/09 07/11
build temporary storage room 07/12 07/18
build temporary office 07/12 07/18

WEST ABUTMENT 07/22/19 09/23/19


pile 07/22/19 08/28/19
excavation for pile cap 07/22 08/05
dressing the ground 08/06 08/07
marking for piles 08/08 08/10
drilling for piles 08/11 08/20
placing of reinforcement cage & p... 08/21 08/25
setting period for piles 08/26 08/28
pile cap 08/29/19 09/11/19
laying of pcc 08/29 08/29
placing of form-work 08/31 09/04
placing of steel cage 09/05 09/06
concrete pouring 09/07 09/07
setting period for concrete 09/08 09/10
removal of concete 09/11 09/11
stem wall 09/12/19 09/23/19
placing of form-work 09/12 09/16
placing of reinforcement cage 09/17 09/18
concrete pouring 09/19 09/19
setting period for concrete 09/20 09/22
removel of concrete 09/23 09/23

ballast wall 09/24/19 10/08/19


placing of form-work 09/24 09/28
placing of steel cage 09/29 09/30
pouring of concrete 10/01 10/01
setting period for concerte 10/02 10/04
removal of form-work 10/05 10/05
water proofing at rearface 10/06 10/06
back filling (granular soil) 10/07 10/08

EAST ABUTMENT - -

pile 07/22/19 08/25/19


excavation for pile 07/22 08/05
dressing the ground 08/06 08/06
marking for piles 08/07 08/09
drilling for piles (excavation) 08/10 08/19
placing pile cage & concrete pouring 08/20 08/24
setting period for piles 08/25 08/25

pile cap 08/26/19 09/07/19


laying of pcc 08/26 08/26
placing of formwork 08/27 08/31
placing of reinforcement cage 09/01 09/02
concrete pouring 09/03 09/03
setting period for concrete 09/04 09/06
removal of concrete 09/07 09/07

Stem Wall 09/08/19 09/20/19


placing of form-work 09/08 09/12
placing of steel cage 09/13 09/14
pouring of concrete 09/15 09/15
setting period for concrete 09/16 09/18
removal of form-work 09/19 09/20

ballast Wall 09/21/19 10/06/19


placing of form-work 09/21 09/25
placing of reinforcement cage 09/26 09/27
pouring of concrete 09/28 09/28
setting period for concrete 09/29 10/01
removal of form-work 10/02 10/02
water proofing at rearface 10/03 10/03
back filling (granular soil) 10/04 10/06

WEST PIER - -

pile 07/26/19 09/12/19


7/19 8/19 9/19 10/19 11/19 12/19 1/20
30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19

excavation for pile cap 07/26 08/12


marking for piles 08/16 08/19
drilling for piles 08/23 09/01
placing steel cage & concrete pouring 09/06 09/09
setting period for concrete 09/10 09/12

pile cap 09/13/19 09/27/19


laying of pcc 09/13 09/13
placing of form-work 09/14 09/16
reinforcement placing 09/20 09/21
concrete pouring 09/22 09/23
setting period for concrete 09/24 09/26
removal of form-work 09/27 09/27

Pier (Column) 09/28/19 10/11/19


scaffolding and form-work setting 09/28 09/30
placing of reinforcement 10/04 10/05
concrete pouring 10/06 10/07
setting period for concrete 10/08 10/10
removal of formwork 10/11 10/11

EAST PIER - -

pile 07/27/19 09/13/19


excavation for pile cap 07/27 08/11
dressing the ground 08/17 08/18
marking for piles 08/24 08/25
drilling for piles 08/31 09/01
placing of steel cage & concrete pour... 09/07 09/08
setting period for piles 09/09 09/13

pile cap 09/14/19 09/28/19


laying of pcc 09/14 09/14
placing of form-work 09/15 09/15
placing of steel cage 09/21 09/21
concrete pouring 09/22 09/22
setting period for concrete 09/23 09/27
removal of formwok 09/28 09/28

pier (Column) 10/05/19 10/21/19


scaffolding and form-work 10/05 10/06
placing of steel cage 10/12 10/13
concrete pouring 10/14 10/18
setting period for concrete 10/19 10/20
removal of formwork 10/21 10/21

beam 07/22/19 10/25/19


fabrication of pre-stressed beam 07/22 10/13
shifting to site condition 10/14 10/25

ERECTION OF BEAM 10/26/19 12/11/19


placing of bearings 10/26 10/26
first phase beam launching 10/27 10/31
second phase beam launching 11/01 11/11
third phase beam launching 11/16 12/01
form-work for continuity beam 12/03 12/04
placing of reinforcement 12/05 12/06
concrete pouring 12/07 12/07
setting period for concrete 12/08 12/10
removal of form-work 12/11 12/11

SLAB 12/13/19 01/19/20


placing of form-work 12/13 12/16
placing of reinforcement 12/17 12/22
pouring of concrete 12/23 12/24
setting period for concrete 12/25 12/28
removal of form-work 12/29 12/30
placing of expansion joint 12/31 01/02
foot path and parapet laying 01/03 01/07
water proofing layer laying 01/08 01/09
asphalt layer laying 01/10 01/12
drinage system fixing 01/13 01/14
traffic signal and light fixing 01/15 01/19