Beruflich Dokumente
Kultur Dokumente
The raw materials required for manufacture of cement are calcareous materials such as
limestone, chalk & marls and the argillaceous materials such as clay, shale, slate, blast
furnace slag, etc.
There are two processes of manufacturing of cement dry and wet process.
Dry process is most commonly used now days.
Above materials in definite proportion are mixed together then Crushed to required size.
In wet process water is added after mixing material to get slurry.
The slurry is then fed into huge fire bricks lined Rotary kiln at the temperature around 1400
degree centigrade.
At this temperature sintering takes place and the substance having its own physical and
chemical properties called clinker or nodules is formed.
Clinker is cooled down, crushed and mixed with 3 % of gypsum. This material is passed
through grinding mills till the material of required size is obtained (size between 5 to 30
micron to the extent of 50%).
This product is known as cement.
Note: Limestone and clay are 2 basic ingredients where there are four parts of limestone and
one part of clay.
Lime, CaO 63
Silica, SiO2 20
Alkalies 1
Notes:
1. C3A is responsible for initial setting of cement but does not contribute to development
of strength.
2. C3A generates maximum heat.
3. C3S is responsible for high early strength. About 70% of C3S hydrates in 28
days. Example: rapid hardening Portland cement.
4. Hydration of C2S goes from 7 days to 1 year. It gives later or ultimate strength.
5. For delayed or later age strength higher percentage of C2S should be used.
6. Water cement ratio - 0.4 to 0.5.
1. Fineness:
Fineness is expressed in terms of specific surface. More fine means more specific surface
area that means more surface area for chemical reaction which gives more strength. Fineness
of cement is measured by particle size distribution or by Blains air permeability method. If
cement is excessive finer then its cementing properties may adversly effect due to
prehydration by atmospheric moisture. As per IS SSA of cement should not be less than
2250 cm2/gm and residue should not be more than 10% after sieving on 90 micron IS sieve.
3. Compressive strength:
Compressive strength is determined on cement sand mortar cubes (1:3) having an area of 50
cm square in compression testing machine. For OPC compressive strength after 3 and 7 days
should not be less than 16 and 22 N/mm2 respectively.
4. Soundness:
Unsoundness is the expansion of cement when it comes in contact with water. This
expansion may result in disintegration and cracking.
This unsoundness is due to presence of free line and magnesium. Soundness test are Le-
Chatlier and Autocalve test.
Expansion by Le-chatlier test should not be more than 10 mm and by Autocalve test should
not be more than 0.8%.
5. Heat of hydration:
It is the amount of heat in calories per gram of hydrated cement liberated on complete
hydration at a given temperature. Normally it is 90 to 100 calories per gram in 7 to 28 days.
Types of cement
1) General purpose Portland cement: 33 grade, 43 grade, 53 Grade where 33, 43, 53
are the compressive strength.
2) Special purpose cement: These are modified for special performance requirements.
1. Match List-I with List-II and select the correct answer using the codes given below the
lists:
List-I List-II
A. Fineness of cement 1. Le-Chatelier apparatus
B. Setting time 2. Vicat‘s needle
C. Soundness 3. Air permeability apparatus
D. Workability 4. Slump cone
Codes:
A B C D
(1) 1 2 3 4
(2) 3 1 4 2
(3) 3 2 1 4
(4) 1 4 3 2
2. If ‗p‘ is the standard consistency of cement the amount of water used in conducting the
initial setting time test on cement is
(1) 0.65 p (2) 0.85 p (3) 0.6 p (4) 0.8 p
3. For complete hydration of cement the water cement ratio needed is
(1) less than 0.25 (2) more than 0.25 but less than 0.35
(3) more than 0.35 but less than 0.45 (4) more than 0.45 but less than 0.60
4. Match List-I (Type of cement) with List-II (Characteristics) and select the correct answer
using the codes given below the lists:
List-I
A. Air entraining Portland cement
B. Low-heat Portland cement
C. Hydrophobic Portland cement
D. Rapid hardening Portland cement
List-II
1. Suitable for very large structures
2. Unsuitable for very large masses of concrete
3. Greater resistance to frost attack
4. Safe storage under unfavorable conditions of humidity
Codes: A B C D
*** Vision Engineering Academy, PUNE ***
Centre for Excellence in Civil Engineering Competitive Examinations
Contact No: 7058477771 Page 8
(1) 4 2 3 1
(2) 3 4 1 2
(3) 3 1 4 2
(4) 4 1 2 3
5. Match List-I with List-II and select the correct answer using the codes given below the
lists:
List-I List-II
A. Vicat‘s needle 1. Setting time
B. Michaeli‘s compound lever apparatus 2. Specific surface
C. Le Chatelier‘s apparatus 3. Tensile strength
D. Turbidimeter 4. Soundness
Codes:
A B C D
(1) 1 2 3 4
(2) 1 3 4 2
(3) 2 4 1 3
(4) 3 4 1 2
6. What is the requirement of water (expressed as % of cement w/w) for the completion of
chemical reactions in the process of hydration of OPC?
(1) 10 to 15% (2) 15 to 20% (3) 20 to 25% (4) 25 to 30%
7. A cement bag contains 0.035 cubic meter of cement by volume. How many bags will one
tonne of cement comprise?
(1) 16 (2) 17 (3) 18 (4) 20
8. Which of the following pairs in respect of Ordinary Portland Cement (OPC) are correctly
matched?
1. Initial setting time ... 30 minutes
2. Final setting time ... 10 hours
3. Normal consistency ... 10%
Select the correct answer using the codes given below :
(1) 1 2 and 3 (2) 2 and 3 (3 ) l and 2 (4) 1 and 3
9. High alumina cement is produced by fusing together a mixture of
(1) limestone and bauxite (2) limestone, bauxite and gypsum
a) Silica: Presence of silica prevents shrinkage, cracking or warping of brick. Silica also
gives hardness and durability to brick. However its excess amount reduces Cohesion and may
make brick brittle.
b) Alumina or clay: It can be moulded to any shape when wet and on drying becomes hard
and on burning causes fusion of constituents.
c) Lime: Lime reduces shrinkage on drying and acts as a flex during burning process to fuse
silica with other particles.
d) Oxides of iron: Acts as a flex and provides strength and hardness to brick. It also gives
red or dark brown colour to brick.
e) Magnesia: Magnesia reduces shrinkage and combines with oxides of iron to make brick
yellow in colour.
2. Water absorption: It is equal to the mass of water absorbed by dry mass of brick in
percentage. There are two types of water absorption test
a) 24 hour cold water absorption test: First bricks are dried in oven for 48 hours at 110±5
degree centigrade till they attain constant mass, then after weighing they immersed in water
at room temperature for 24 hours. Then surface dry weight of brick is taken.
For Class I brick water absorption should not be more than 20% (for class II 22% & for class
III 25%).
b) 5 hour boiling water absorption: Water absorption is equal to the mass of water absorbed
by brick after boiling for 5 hours by dry mass in percentage.
3) Efflorescence: Brick if contain salt such as sulphates of sodium and potassium may get
dissolved with water and when water evaporates the salt crystallizes on the surface called as
efflorescence. Brick is immersed in water and observed after two cycles of immersion &
evaporation.
Nil - no perceptible deposit of salt on surface of brick
Slight - Not more than 10% of surface of brick covered with salt
5) Hardness of brick: Brick should be sufficiently hard so that finger nail does not leave any
impression on scratching the brick surface
10 10 12 to 15 Nil
Objectives
1. A good brick should not absorb water by weight more than
(1) 10% (2) 20% (3) 25% (4) 30%
2. The shape of first class bricks are ________.
(1) Sharp straight edges and plain rectangular faces
(2) Sharp straight edges adn rough rectangular faces
(3) Blunt straight edges and plain rectangular faces
(4) Distorted round edges and plain rectangular faces
3. Consider the following statements:
(1) About 25% of alumina in brick earth imparts the plasticity necessary for moulding
bricks into required shape.
(2) Iron pyrite present in brick earth preserves the form of the bricks at high
temperatures.
Classification of rocks
Rocks can be classified into following groups based on various criteria.
Geological classification based on their geological mode of formation natural rocks can be
classified as
1. Igneous rocks: formed by direct cooling of molten lava or magma. Do not contain fossils
or shells. These are solid, massive, crystalline, without stratification. Example Basalt, trap
granite, diorite & syenite.
2. Sedimentary rocks or stratified rocks: are formed due to disintegration and deposition of
original igneous rock through water, wind, ice, etc or by accumulation of organic matter.
After deposition consolidation of layers takes place under pressure by heat or due to
cementious action by chemical agents. Example: laterite, sandstone, limestone, shale.
1. Stratified rocks: This is a layered structure in the natural environment. These are derived
from sedimentary rocks. Example: sandstone, limestone, slate, etc.
Chemical classification
Classification is done based on chemical composition as
1. Siliceous rocks: These are having silica as their main constituent. Example: granite,
gneiss, trap.
2. Argillaceous rocks: clay or Alumina is the main content. Though these rocks are compact,
dense and hard, these are also brittle which can't with stand shocks. Example: slate laterite,
etc.
3. Calcareous rocks: Calcium carbonate is the main constituent. Durability depends upon
atmospheric conditions since these rocks can be acted upon by hydrochloric acid. Example:
Marble, limestone.
Crushing strength
1. Igneous rock, Sedimentary rock and Metamorphic rock are classified as ________.
2. Stratified rock, Unstratified rock and Laminated rock are classified as _________.
3. Siliceous rock, argilaceous rock and Calcareous rock are classified as _________.
4. Soft rock, Medium rock and Hard rock are classified as ________.
(1) Geological classification of rock
(2) Physical classification of rock
(3) Classification based on hardness of rock
(4) Chemical classification of rock
5. The rocks which are formed due to cooling of molten lava are known as _______.
(1) Igneous rock (2) Sedimentary rock
(3) Metamorphic roc (4) Stratified rock
6. The rocks that are formed by denudation and deposition of existing rocks because of the
weathering action are known as ________.
(1) Igneous rock (2) Sedimentary rock
(3) Metamorphic rock (4) Stratified rock
7. The rocks that have undergone considerable changes in their constitution, i.e. in their
shape, structure and sometimes even in mineral compostion is known as :
(1) Igneous rock (2) Sedimentary rock
(3) Metamorphic rock (4) Stratified rock
8. One of the example of Igneous rock is _________.
(1) Granite (2) Marble (3) Lime stone (4) Gneiss
9. One of the example of Sedimentary rock is __________.
(1) Granite (2) Marble (3) Lime stone (4) Gneiss
Objectives
1. The sand passing through I.S. sieve of size 4.75 mm is known as ________.
(1) Coarse sand (2) Medium sand (3) Fine sand (4) Soft sand
2. The sand retained on I.S. sieve of size 4.75 mm is known as _________.
(1) Coarse sand (2) Medium sand (3) Fine sand (4) Soft sand
3. Sand obtained form pits, river beds, shore, sea bed is classified as ________.
(1) Coarse sand (2) Medium sand (3) Fine sand (4) Soft sand
4. Sand obtained from crushing of stone is classified as __________.
(1) Coarse sand (2) Medium sand (3) Fine sand (4) Soft sand
5. Depending upon fineness, the sand is classified into ________.
(1) Four (2) Three (3) Two (4) Zero
Reinforcing Steel
These are circular bars available in different grades like Fe 250, Fe 415, Fe 500, Fe 550
where Fe denotes ferrous and number represents yield strength.
Cast iron and steel are alloys of carbon and steel. Wrought iron is pure iron with carbon
content between 0.02 to 0.03 %.
Objectives
1. Intermediate form between cast iron and wrought iron is known as _________.
(1) Ferrous (2) Copper (3) Steel (4) Aluminium
2. Steel is an alloy of iron and carbon, containing carbon from _________.
(1) 0.25 to 1.25% (2) 0.55 to 1.5 % (3) 0.75 to 1.75 % (4) 0.85 to 1.95 %
3. Mild steel bars are designated as _______ due to yield strength of 250 N/mm².
(1) Fe 415 (2) Fe 250 (3) Fe 500 (4) Ms 250
4. The steel used as reinforcement in R.C.C is known as ________.
(1) Mild steel (2) High tensile steel (3) Tor steel (4) Hard steel
5. Tor steel bars are available in two grades namely ________.
(1) Fe 250 and Fe 500 (2) Fe 250 and Fe 415
(3) Ts 415 and Ts 500 (4) Fe 415 and Fe 500
6. The percentage of carbon in steel is _________.
(1) 0.25 to 4% (2) 0.25 to 3% (3) 0.25 to 2% (4) 0.25 to 1.25 %
7. The reinforcing steel is available in different grades are ________.
(1) 1 (2) 2 (3) 3 (4) 4
Concrete
The word concrete comes from Latin word concretus which means hardened or hard.
There are four basic types of concrete based on cementing material:
a) mud concrete b) lime concrete c) cement concrete d) polymer or special concrete
Cement concrete: It is obtained by mixing cement, sand, crushed stone and water in definite
proportion.
Grade M M M M M 20 M M M M M45
5 7.5 10 15 25 30 35 40
Making of Concrete
Concrete is a mixture of cement, aggregates & water.
Cement: It gives adhesive & cohesive properties to a concrete & binds various ingredients in
compact form.
Strength of concrete
Tensile & bending strength of concrete is 10-15% of it compressive strength & shear is
20% of its compressive strength.
Characteristic strength of concrete is that strength below which not more than 5% of test
results are expected to fall.
Workability of concrete
It is the ease with which concrete can be compacted with regard to mode of compaction &
place of compaction.
Measurement of workability
1) Slump test: Measures both consistency & workability of concrete.
2) Compacting factor test: More accurate than slump test
wt. of partially compacted
Compacting factor
wt. of fully compacted concrete
3) Vee-bee consist meter test: Consistency is given in vee-bee degree in secedes.
Mix design
fcm fck 1.65 σ
fcm = target mean strength
fck = characteristic strength
σ std deviation of the receded values.
Objectives
1. The split tensile strength of M 15 grade concrete when expressed as percentage of its
compressive strength is
21. Match List –I (Admixtures) with List –II (chemicals) and select the correct answer using
the codes given below the lists:
List – I List – II
A. Water-reducing admixture 1. Sulphonated melanin formaldehyde
B. Air-entraining agent 2. Calcium chloride
C. Superplasticiser 3. Lignosulphonate
D. Accelerator 4. Neutralised vinsol resin
Codes:
A B C D
A. 2 4 1 3
B. 1 3 4 2
C. 3 4 1 2
D. 3 4 2 1
21. The mixture of cement, sand and coarse aggregates with an adequate quantity of water
with reinforcing steel is called as _________.
(1) Plain cement concrete (2) Reinforced cement concrete
(3) precast concrete (4) Pre-stress concrete
22. The individual concrete units of various types which are cast in separate form before
they are placed in a structure is known as________.
(1) Plain cement concrete (2) Reinforced cement concrete
(3) Precast concrete (4) Pre-stress concrete
23. Plain cement concrete is very strong in ________.
Advantages of prestressing
1. Section remains uncracked at service load.
2. Full section of concrete is utilized.
3. Shear resistance increases.
4. Useful for water retaining structures.
5. Use of large spans is permitted.
6. Suitable for dynamic & fatigue loading
7. Suitable for precast construction
Objectives
1. One of the best examples of precast is ________.
(1) Hollow concrete block (2) Sand
(3) Cement (4) None of these
2. The method in which the tendons are first stretched to the desired tension in the form by
hydraulic jack is called as ________.
(1) Pre-tensioning (2) Post-tensioning (3) Both (a) and (b) (4) None of these
3. The method in which the tendons are given the required tension after the concrete has
attained the desired strength is called as ________.
(1) Pre-tensioning (2) Post-tensioning (3) Both (a) and (b) (4) None of these
4. In prestress concrete, the concrete is subjected to ________. .
(1) Compressive stresses (2) Tensile stresses
(3) Both (a) and (b) (4) All of these
5. Match the following for the type of cement concrete and the use of it.
List I (Type of Cement Concrete)
A. Plain cement concrete
B. Reinforced cement concrete
C. Precast concrete
D. Post-tensioning
List II (Use)
1. Electric poles, cover of man hole, drainage pipe etc.
2. Foundation masonary, base for foundation, flooring base.
3. Construction of multistoried building
4. Prestressd concrete girder and used in bridge construction
Codes:
A B C D
(1) 2 3 1 4
(2) 4 2 3 1
(3) 4 1 2 3
(4) 4 4 1 2
*** Vision Engineering Academy, PUNE ***
Centre for Excellence in Civil Engineering Competitive Examinations
Contact No: 7058477771 Page 58
6. In post-tensioning, it permits the use of large spans with shallow member greater than
______.
(1) 10m (2) 20 m (3) 30 m (4) 40 m
Objectives
1. The material having one or more properties that can be significantly changed in a
controlled fashion by external stimuli such as stress, temperature, moisture, pH, electric or
magnetic field is called as ________.
(1) Building material (2) Smart material
(3) Ecofriendly material (4) None of these
2. The devices which are made by using smart materials are called as ________.
(1) Piezoelectric material (2) Shape memory alloys
(3) Magnetic shape memory (4) pH sensitive polymers
3. The smart materials which produces a voltage when stress is applied is called as _______.
(1) Piezoelectric material (2) Shape memory alloys
(3) Magnetic shape memory (4) pH sensitive polymers
4. The designed structures made from these ________ can bend, expand, or contract when
voltage is applied.
(1) Piezoelectric material (2) Shape memory alloys
(3) Magnetic shape memory (4) pH sensitive polymers
Recycling of Materials
Recycling means the processing of used materials into new product in order to avoid
wastage of potentially useful materials.
Recycling reduces use of fresh materials, reduces energy usage, reduces water & air
pollution. Reduces the need of conventional waste disposal & low green house gas
emission. Recycling is the third component of ―reduce, reuse & recycle‖ waste hierarchy.
Objectives of Recycling
1) To conserve natural raw material resources.
2) To make optimal use of all form of energy.
3) To adopt clean technology reduce pollution.
Objectives
1. They materials which are used into new products in order to prevent the waste of
potentially useful materials, reduce the consumption of fresh raw material, reduce energy
wage, reduce air and water pollution is called as ________.
(1) Recycling of materials (2) Smart materials
(3) both (a) and (b) (4) None of these
2. The objective of recycling of materials in the construction industry.
(1) To conserve material resources
(2) To conserve valuable land - fill space
Substructure or Foundations
We know that almost all the civil engineering structures including bridges, roads, railway
embankment, dams, etc are supported by earth and those which are not either fly, float or fall
over.
Therefore, the stability of the structure depends on the behavior of supporting ground i.e. soil
which is weaker than any other construction material like, wood concrete, steel or masonry.
So, compared to structural member, a larger area or mass of soil is involved in carrying the
same load.
Foundation the lowest part of structure which generally lies below earths surface and it also
refers to the material whose behavior civil engineer must study so as to provide satisfactory
and economical support to the structure.
If foundation is deficient in design then entire structure may be at risk, so foundation is the
most important consideration while designing a structure.
Function of foundation is to transfer the load to the strata or soil on which it is resting and
against shear failure and without any settlement beyond permissible limits.
Types of foundation
Type of foundation depends upon nature of sub-soil strata and type of super structure.
Broadly foundations are classified as,
1) Shallow foundations & 2) Deep foundations
1) Shallow foundation
Shallow foundation is an arrangement where structural loads are directly carried by
soil or rock under the structure.
According to Terzaghi shallow foundations are those whose depth Df does not exceed
width B.
𝑫𝒇
𝒊. 𝒆.
𝑩
≤ 𝟏 𝒐𝒓 𝑫𝒇 ≤ 𝑩
2) Deep Foundations
Deep foundations are the members which carries load to the firm soil at considerable
depth below G.L.
𝐷𝑓
𝑖𝑓 > 1 𝑜𝑟 𝐷𝑓 > 𝐵 then it is deep foundations
𝐵
1 – 15 => moderately deep
>15 => deep foundations. Exa. Pile foundation
In case of deep foundations, the load is supported by frictional resistance (skin friction
between member and soil) around the foundation and by bearing at the base of found
action.
For a satisfactory performance, foundation must satisfy following three criterion
1) Location and depth criterion
2) Bearing capacity criterion
3) Settlement criterion.
1) Location and depth criterion
Generally foundation depth should be such that the supporting soil is adequate in
terms of bearing capacity and settlement criterion.
However as per IS, minimum depth of foundation should be 50cm,
Allowable Settlements
Effect of settlements
1) Cracks in interior masonry walls and interior plaster walls of buildings.
2) Tilt in structures.
If the structure settles uniformly, it will not cause any structural damage, but when it
becomes excessive utilities such as water supply and sewage lines, electric and
telephone lines, etc. may get impaired. Such type of settlement is called as uniform
settlement where structure settles as a whole.
When one part of the structures settles more than the other then the structure is said to
undergo differential settlement.
The difference in total settlement between any two points is the magnitude of
differential settlement
Angular distortion is the ratio of differential settlement between two columns and the
distance between them.
Deep Foundations
We have studied shallow foundations where load was transferred to the soil directly
beneath the foundations
However, in case the soil at shallow depths in poor, so that it can‘t transfer the load,
hence, the depth of foundation need to be increased till the suitable soil is met. Such
foundations are called as deep foundations.
Examples of deep foundations are piles, piers and wells.
Piles are small diameter shafts driven or installed into the ground by suitable means
Piles are usually installed in groups and are subjected to vertical loads, horizontal loads
or a combination of vertical and horizontal loads.
Necessity of Pile Foundation
Types of piles
Superstructure
It is that part of the structure which is constructed above ground level or plinth level.
Parts of Superstructure
Plinth: Plinth is the part of a superstructure located between the ground level and the floor
level. The plinth height should not be less than 45 cm.
Types of superstructure
1. Load bearing structures
2. Framed structures
3. Composite structures
2. Framed structures
It consists of slabs resting on beam which are supported by a network of columns. Loads
from slabs are transferred to beams and then to columns which transfers load to the soil. All
the walls may or may not be partition walls as none of them bear any load. Framed structures
are suitable for multi storied or high rise buildings. Framed structures are flexible since walls
can be shifted anywhere on the floor. In comparison with load bearing structures framed
structures gives more carpet area. Framed structures are Monolithic.
3. Composite structures
When buildings are constructed with combination of load bearing and framed structures it is
called composite structure. In composite structure external walls are treated as load bearing
Loads on foundation
There are three types of load on foundation
1. Dead load, 2. Live load, 3. Wind load
1. Dead load: The load due to the materials used for all the components of building such as
walls, floors, roofs, etc is called dead load. All permanent loads in the buildings are included
in dead load. For future construction of partition wall the provision of dead load of amount
0.10 KN/m2 of the floor area is made.
1 Bitumen 14.18
2 Brick 17.66
5 Mortar 17
7 PCC 18.84
8 RCC 23.54
2. Live load or superimposed load: It includes all movable load like person standing on the
floor, furniture, weight of temporary stored materials. In design live load is converted into
equivalent dead load.
1 1 floor No reduction
2 2 floor 10
3 3 floor 20
4 4 floor 30
5 5 floor 40
Live load for roof: The flat roof of a building should we design for minimum live load of 4
KN/m2 or 400 Kg/m2. The sloping and curve roofs should be designed for snow load and
rainwater load. For sloping roofs snow load is taken as------ for 1 cm depth of slope.
Wind load effect of wind load should be considered in case of tall buildings the buildings
which are subjected to wind pressure reduces pressure on foundation which are towards
windward side and increases pressure on foundations which are towards leeward side. Wind
pressure depends upon the velocity of wind location of structure and author metrological
factors.
Wind pressure can be given by
P = K V2
Where
P = wind pressure in KG/m2,
*** Vision Engineering Academy, PUNE ***
Centre for Excellence in Civil Engineering Competitive Examinations
Contact No: 7058477771 Page 71
V = velocity of wind in kmph,
K = Coefficient which depends on wind speed, temperature of air, shape of building
Wind pressure can be neglected is the height of building is less than twice of its effective
with and also if building is sufficiently stiff.
Wind pressure can be neglected if the bearing pressure due to wind load is less than 25% of
that due to dead load and live load.
If it exceeds 25% then the combined effect of Dead load, live load and wind load should not
exceed by more than 25% of allowable bearing pressure. generally wind pressure in
horizontal direction is taken as 1 KN/m2.
(1) Carrying the loads to firm strata (2) To offer-stability against uplift forces
Important definitions
Course: course is a horizontal layer of masonry units whose thickness is equal to thickness
of masonry unit plus thickness of joint.
Stretcher: stretcher is a full stone or brick or concrete block laid in such a way that its length
is parallel to face of the wall.
Header: Header is a full stone or brick laid in such a way that its length is perpendicular to
face of wall.
Quoin: The corner or exterior angle of wall is known as quoin. if length of quoin is parallel
to face of wall it is called stretcher quoin. if length of wall is perpendicular to face of wall it
is called header quoin.
Closer: A closer is the portion of brick which is obtained by cutting a brick in such a way
that it's one long face remains uncut.
Queen closer: It is obtained by cutting the brick into two equal parts along its length.
King closer: It is obtained by cutting off triangular portion between centre of one side and
centre of adjacent side.
Spalls - There are the chips of stones used for filling the interseches in stone masonry
Lap - Horizontal distance between two perponds in two successive courses is called lap.
Rubble masonry
The stone masonry in which roughly dressed or undressed stones are laid i suitable morter is
called rubble masonry
Types
1. UCR
Ashlar Masonry
The stone masonry in which proerly cut in uniform size and dressed with fine finish stones
are laid with a mortar of uniform thickness is called ashlar masonry.
1. Ashlar fine
Stones are fine tooted . Height of course is not less than 30 cm. Face stone laid altrnate
header & strecher . Height is not less than widt (H > B) & length is not less than twice height
(L>2H). Thickness of joint not exceed 3mm
Use - Public building, university building, court building
*** Vision Engineering Academy, PUNE ***
Centre for Excellence in Civil Engineering Competitive Examinations
Contact No: 7058477771 Page 84
2. Ashlar Rough
Exposed face of stone are hammered to provide rough surface. Thickness of joint should
not exceed 6 mm
3. Ashlar chamfered
If is similar to ashlar masonry, only difference is that edges at exposed face of stone are
bevelled off at an angle of 45o to depth of 25 mm.
4. Ashlar Facing
Face stone are rough tooled. Backing is made up or brick or concrete etc
Height of stone should notbeless than 20 cm.
Objectives
1. King closers are related to
2. For one cubic metre of brick masonry, the number of modular bricks needed is
3. In brick masonry,
(1) closer (2) squint brick (3) queen closer (4) king closer
5. The number of bricks required per cubic metre of brick masonry is.
16. Modular bricks are of nominal size 20 × 10 × 10 cm and 20% of the volume is lost in
mortar between joints. Then what is the number of modular bricks required per cubic
meter of brickwork?
1. to remove dust
2. to remove air voids
3. so that they do not absorb water from cement mortar
Which of these statements is/are correct?
18. The mortar used for masonry construction are classified based on strength in IS : 2250
and IS : 1905 according to their designations L1 , L2, H1 , H2, M1 , M2. The correct
sequence of increasing order of their strength is
(1) L1, L2, H1, H2, M1 ,M2 (2) L2, L1, M2, M1, H2, H1
(3) M1, M2, H1, H2, L1, L2 (4) L2, L1 ,M1, M2, H1, H2
19. The slenderness ratio for masonry walls should NOT be more than
20. Brick masonry walls and columns of a building are to be protected from earthquake. The
earthquake proofing is done by providing
(3) under-reamed piles (4) a steel band at corners above windows below ceiling
21. When a beam or truss is placed on a masonry wall, it is supported on bed stone or plate.
The bed stone or bed plate is necessary to
(1) add to aesthetic appearance (2) transfer the reaction over a larger contact area
(3) increase stability of beam or truss (4) prevent outward thrust on the wall
24. ________ is that portion of a brick obtained by cutting a bring along its length into two
unequal parts.
(1) Queen closer (2) Bing closer (3) Stretcher quoin (4) All of these
25. ________ is that portion of a brick obtained by cutting off the triangular portion between
the centre of one end and centre of the adjacent side.
(1) Queen closer (2) Bing closer (3) Stretcher quoin (4) All of these
26. ________ is that portion of a,brick obtained by cutting a brick along its width.
(1) Queen closer (2) Bing closer (3) Stretcher quoi (4) All of these
27. When stones are used as building units and are bonded together with mortar, it is known
as ______.
(1) Stone masonary (2) Brick masonary (3) Both (a) and (b) (4) None of these
28. When bricks are used as building units and are bonded together with mortor it is known
as
29. In some brick masonry walls, patches of whitish crystals were found on the exposed
surfaces, also chipping and spalling of bricks took place from the same walls. Which among
the following are the causes of these defects?
30. When a column is supported throughout its length either by masonry walls or by
construction on all the sides, then its slenderness ratio is
31. The minimum wall thickness of any load bearing wall in case of public building built
with mortar, as per IS code, should be not less than
32. Maximum slenderness ratio for load-bearing masonry wall built in cement mortar, as per
IS code, shall not exceed
33. As per masonry code, the stiffening coefficient for walls stiffened by piers, buttresses or
intersecting walls can be
(1) 0 to 1.0 (2) 1.0 to 2.0 (3) Greater than 2.0 (4) Invariantly 1.0
Cement mortars richer than 1 : 3 are not usd in masonry work because
(1) 1, 2 and 3 (2) 1 and 2 only (3) 2 and 3 only (4) 1 and 3 only
35. Which of the following monuments are constructed with stone masonry?
(1) Taj Mahal (2) Red fort Delhi
(3) Shaniwar Wada Pune (4) All of these
36. Which of the following is correct definition of masonry?
(1) The art of distempering the surfaces of wall is masonary
(2) The art of plastering the surfaces of wall is masonary:
(3) The art of construction in stones or bricks is called masonry
(4) None of the above
37. Why are bricks soaked in water before using the brick masonry?
Surveying is the art or science of determining the relative positions of point on above or beneath the
surface of earth with the help of direct or indirect measurements of distances, direction and elevation.
Earth seems to be perfect sphere but its actual shape is oblate spheroid or oblate tri-
axial ovaloid.
Length of the polar axis of the earth is 12713.8 km which is lesser than length of its
equatorial axis (12756.57 km) by 42.77 km.
Earths polar axis is 0.34% less compared to its diameter.
The average radius of earth is taken as 6370 km for all calculations.
If the irregularities on the earth surface are neglected the shape of the earth surface is
curved, every element of which is normal to plumb line.
Thus primary division of surveying is based on whether the curvature of earth is
considered or not.
Plane surveying:
In plane surveying curvature of the earth is not considered and it is assumed as a plane
surface.
All triangles formed by survey lines are considered as plane triangles.
All angles (vertical & horizontal) are planes angles.
The direction of vertical line or plumb line is indicated by the freely suspended plumb bob
and all plumb lines are considered as parallel to each other.
Curved line on the earth‘s surface is considered as straight or horizontal.
Plane surveying is applicable only when extent of area is less than 200 sq km.
Also when the difference between an arc distance of 18.2 km on the earth surface and
corresponding chord distance is not more than 1 cm.
And further when the difference between sum of the angles in spherical triangle & plane
triangles is only 1 second. For a triangle having an area of 195 sq km.
1. Control surveying:
To establish horizontal & vertical position of control points using geodetic surveying
For India, control surveying is done by "Survey of India".
2. Topographical Surveys:
To prepare a plan or map of a region which consists of natural features such as rivers,
streams, hills, lakes, forests etc. and also manmade features like roadways, canals, town &
villages, etc.
Cadastral surveys are done to fix property boundaries, calculation of land area, or for transfer
of land from one owner to another.
This is also done to fix boundaries of municipalities, state & federal jurisdictions.
4. Engineering Surveys:
These are done for engineering works such as structures, roads and reservoirs etc.
Deals with water bodies for purpose of navigation, water supply, harbor works, determination
of water depth, etc.
6. Mine Survey:
7. Astronomical Surveys:
These surveys are done to determine latitude, longitude & Azimuth of a point to get absolute
location on earth.
8. Geological survey:
These surveys are done to find out different strata present in the earth crust.
1. Chain Survey:
2. Compass Survey:
3. Leveling:
This is the graphical method of survey in which taking field observations and plotting proceed
simultaneously.
Alidade is used to direct object while chain or tape is used for linear measurement.
It is less accurate.
Useful in the field where magnetic influence is there and when other instruments like
compass cannot be used.
5. Theodolite Survey:
6. Tacheometric Survey:
7. Photogrammetric Survey:
8. EDM Surveys:
Based on triangulation.
All the sides of triangle are measured with EDM instrument.
Principles of Surveying:
The fundamental principles upon which the various methods of surveying are based are:
After deciding the position of point, its reference must be kept at least from two permanent
objects or stations whose position have already been well defined.
This is to localize minor errors and to prevent accumulation of errors. First a control points
are established with higher precision for large area and minor control points are then
established within the main area with less precise methods.
Plan:
Plan is a graphical representation of the feature on or below the surface of the earth
constructed by using orthographic projections on a horizontal plane without considering the
curvature of Earth.
A plan is drawn relatively to large scale.
When the scale is small plan is called map. A map is generally drawn when extent of area is
large such as city map, district map, country map, etc.
On a map vertical distances are also represented by contours, hatchers, etc.
Projection system other than orthographic system is used.
Scale:
Scale is the fixed ratio that every distance on plan or map corresponds to a distance or ground.
1. Engineer’s Scale:
For example: 1 cm = x m
2. Representative Fraction:
1 unit of length on plan or map represents some number of same unit lengths on ground.
𝟏
For example: 𝑹𝑭 = , 1cm on plan equals to 10m on ground
𝟏𝟎𝟎𝟎
𝑅𝐹 𝑜𝑓 𝑊𝑟𝑜𝑛𝑔 𝑆𝑐𝑎𝑙𝑒
𝐶𝑜𝑟𝑟𝑒𝑐𝑡 𝐿𝑒𝑛𝑔𝑡 = × 𝑀𝑒𝑎𝑠𝑢𝑟𝑒𝑑 𝐿𝑒𝑛𝑔𝑡
𝑅𝐹 𝑜𝑓 𝐶𝑜𝑟𝑟𝑒𝑐𝑡 𝑆𝑐𝑎𝑙𝑒
Field Book
In this book all detailing of survey are recorded. Dimensions: 20 cm x 21 cm. For ordinary field work
double line field book is used whereas for very large scale work single line field book is used.
Objectives
11. The double-line field book is most commonly used for recording
(1) precise work (2) ordinary chain survey work
(3) large-scale plotting work (4) small-scale accurate plotting work
12. The smallest scale adopted for topographical survey is
(1) 1:25,000 (2) 1:50,000 (3) 1:2,50,000 (4) 1: 5,00,000
13. Which one of the following scales is the largest scale
(1) 1 cm = 50m (2) 1:42000 (3) RF = 1/3,00,000 (4)l cm = 50 Km
*** Vision Engineering Academy, PUNE ***
Centre for Excellence in Civil Engineering Competitive Examinations
Contact No: 7058477771 Page 100
Electronic Distance Meter (EDM)
EDM was first introduced in the late 1950‘s. Initially they were complicated, large, heavy,
and suited primarily for long distances. Current EDM‘s use either infrared (light waves) or
microwaves (radio waves). Microwaves require transmitters/receivers at both ends and
infrared use a transmitter at one end and a reflecting prism at the other and are generally used
more frequently.
EDMs are available in long (greater than 100 km), medium (upto 100 km), and short range
(upto 5 km). Range limits up to 50 km
EDM is typically mounted on top of a theodolite, but can be mounted directly to a tribrach.
EDM is very useful in measuring distances that are difficult to access or long distances such
as valleys or steep hills.
Principle of Working
Transmitter sends continuous waves to a receiver from which it is returned. It measures the
time required for a wave to sent to a target and reflect back. The distance between transmitter
and reflector is given by
Note: The range of distance measurement of EDM increases with increase in number of
prisms.
Objectives
1. Turning the telescope in the vertical plane about the horizontal axis is called
(1) Transiting (2) Plunging (3) Swinging (4) Both 1 & 2
10. For measuring a horizontal angle between two lines with better accuracy than that given
by vernier; the method commonly used is
(1) Reiteration (2) Repetition (3) Direction (4) Double sighting
11. If a group of angles are to be taken about a common point, it is called method of
(1) Repetition (2) Reiteration (3) Direction (4) both b & c
Total Station
When digital theodolite is combined and interfaced with EDM and electronic data collector‘s
with built in microprocessors it becomes total station.
Total station is used to measure horizontal angles, vertical angles and sloping distances.
Total station can perform number of operations such as multiple angle and distance
measurements, calculation of coordinates, determination of slope corrections, determination
of distance and elevation between remote points, etc.
1. Space segment
The space segment consists of the orbiting GPS satellites, or Space Vehicles (SV) in GPS
parlance. The GPS design originally consists of 24 SVs. The orbital period is one-half
a sidereal day, i.e., 11 hours and 58 minutes. Now there are 32 satellites in the
GPS constellation, 31 of which are in use.Mminimum four satellites needed for a position.
2. Control Segment
The control segment consist of a master control station (MCS), an alternate master control
station, four dedicated ground antennas and six dedicated monitor stations.
3. User Segment: It consist of receiver in hand or in vehicle. It consists of GPS unit and
users.
In addition to GPS, Russias GLONASS, Indias NAVIC, etc. are under development.
Planimeter
Planimeter is an instrument which measures the area of plan or map of any shape very
accurately. Areas between curved boundaries an a plan or map can be found by planimeter.
Amsler polur planimeter is most communly used.
The error involved in the planimeter measurement are accidental and are mainly due to the
inability of the observer to follow exact boundary of the figure with the tracing point.
Zero circle or circle of correction: The circle round the clrcumference of which if the
tracing point is moved, the wheel will simply slide (without rotation) an the paper without
any change in the reading.
Leveling
Objectives of Leveling:
1) To find the elevations of given points with respect to any given or assumed datum.
(used in planning /design)
𝐶𝑐 = 0.07849 𝑑 2 𝑚, 𝑑𝑖𝑛𝑘𝑚
Correction for refraction: (+ve)
Due to refraction line of sight curves downward, thus reading decreases.
Therefore correction for refraction is positive
1 𝑑2
𝐶𝑟 = 𝑑 𝑎𝑛𝑑 𝑅 𝑖𝑛 𝑠𝑎𝑚𝑒 𝑢𝑛𝑖𝑡𝑠.
7 2𝑅
𝐶𝑟 = 0.01121 𝑑2 𝑚 𝑑 𝑖𝑛 𝑘𝑚
Combine correction for curvature and refraction
6 𝑑2
𝐶 = 𝑎𝑙𝑤𝑎𝑦𝑠 (−𝑣𝑒)
7 2𝑅
𝐶 = 0.06728 𝑑2 𝑚, 𝑑 𝑖𝑛 𝑘𝑚
Special methods of spirit leveling or direct leveling:
1) Differential leveling:
The operation of leveling to determine the elevation of point at some distance
apart is called differential leveling.
Or To determine difference in elevations of two points regardless of horizontal
position of the points with respect to each other.
- Need to set up instrument several times.
- Also called as fly leveling.
2) Profile leveling:
To determine elevations of pts at measured intervals along a given line in order to
detain profile of the surface along that line.
Hypsometers:
The working of hypsometer for determination of attitudes of stations depends on the
fact that the temp at which water boils varies with the atmospheric pressure.
Altimeter is used to find heights based on barometric pressure difference.
Objectives
Contour
2. Indirect Method
Points are selected along a system of straight lines and their elevations are determined.
Contours are then drawn by interpolation. While interpolating it is assumed that slope
between two guiding points is uniform. Selected points are not points on contour except by
coincidence. Less tedious and less time consuming, so preferred for most of the engineering
works.
Objectives
(1) hachures (2) relief shading (3) layer tinting (4) contour lines
2. Match List-I with List-II and select the correct answer using the codes given below:
List-I List-II
A. Vertical cliff 1. Contour lines of different elevations unite to form one line
B. Steep slope 2. Contour lines of different elevations cross one another
C. Hill 3. Contour lines are closely spaced
D. Overhanging cliff 4. Closed contour lines with higher values inside them
Codes:
A B C D
(1) 4 3 1 2
(2) 1 3 4 2
3. Match List - I (Terms) with List - II (Description) and select the correct answer using the
codes given below the lists:
List-I
A. Contour
B. Line of collimation
C. Tie line
D. Magnetic meridian
List-II
1. Line joining magnetic North and South
2. Line joining subsidiary station on the main line
3. Line joining points of same elevation
4. Line joining optical centre of the objective, lens with point of intersection of
cross-wires
Codes:
A B C O
(1) 3 4 2 1
(2) 4 3 2 1
(3) 3 4 1 2
(4) 4 3 1 2