Beruflich Dokumente
Kultur Dokumente
ON CONCRETE DAMS
STRUCTURES
SURINAME
UK
Questions to be asked when checking the deterioration of a
concrete dam (apud USBR)
• When was the structure constructed?
• What are the properties of the concrete (to the extent known)?
• What construction equipment and methods were used and what
potential “defects” may have resulted from these methods?
• What are the environmental conditions and loading on the structure?
• What deterioration mechanisms (if any) may be acting on the
structure?
• Is the structure resisting these deterioration mechanisms?
• What is the rate of deterioration?
• What dam failure modes are being affected by this deterioration?
dw2018 | 3
MAJOR PROBLEMS
• DETERIORATION OF CONCRETE
Deterioration of concrete consists of a progressive reduction in
its properties which can ultimately prevent it from fulfilling its
purpose of use. It can reach the limit state.
• UPLIFT
Water pressure can impart the safety of a concrete dam whether
acting in the foundation or in the construction (lift) jonts
dw2018 | 4
TOPICS
1. ACCIDENTS
2. CONCRETE DEFICIENCIES
3. MECHANICAL PHYSICAL DETERIORATION
• Erosion / Abrasion / Cavitation
• Cracking
• Thermal cracking
4. CHEMICAL REACTIONS HARMFUL TO CONCRETE
• AAR
• DEF
• Leaching
5. LEAKS / SEEPAGE/ UPLIFT
dw2018 | 5
CAUSES OF CONCRETE DETERIORATION
AGENTS: PRIMARY AND SECONDARY
• Accidental loading (eg. Emas) • Erosion
• Chemical reactions: • Abrasion
• Acid attack • Cavitation
• Attack by aggressive waters • Settlements and displacements
(including ettringite-ESA) • Shrinkage (plastic and drying)
• Alkali-silica reaction • Temperature variations
• Alkali-carbonate reaction Internally generated
• Other types of chemical attacks Externally generated
• Building mistakes • Fire
• Corrosion of embedded metals • Weathering (includes freezing and
• Design errors thawing)
• Inadequate structural design
dw2018 | 6
SERIOUS DEFICIENCIES IN CONCRETE DAMS
(from TADS)
CONCRETE DAM
Randon open, crumbly Seal the cracks; seal exposed
concrete along cracks, Alkali-aggregate reaction surfaces; initiate an immediate
silica gel and deeper study of the problem
Crest and faces
Tilting or movement of For extreme conditions: lower
reservoir level; restrict operation;
piers or other portions of Expansion of concrete extensively reconstruct or
structure demolish the dam
dw2018 | 7
SERIOUS DEFICIENCIES IN CONCRETE DAMS
(from TADS)
Location Type of Deficiencies Possible causes Possible corrective actions
CONCRETE DAM (continued)
Exposed, rusted
reinforcing; cracked and Remove damaged concrete, clean
Buttress dam: Weathering; sulfate attack;
swollen concrete; steel, add new reinforcing, patch with
face slab or alkali-aggregate reaction;
excessive pitting or epoxy mortar or new concrete;
arched facing rusted reinforcing
spalling; noticeable partially reconstruct slab or block
leakage
Remove damaged concrete, clean
Exposed, rusted
steel, add new reinforcing, patch with
reinforcing, cracked and Weathering; sulfate attack;
Butresses epoxy mortar or new concrete;
swollen concrete, large alkali-aggregate reaction
partially reconstruct or strengthen and
spalls
brace buttresses
OUTLET WORKS
Chemical attack, erosion,
Generalized cracking; Repair and reconstruct damaged
Inside surface of cavitation, deformation due
spalling; air bubbles or lining, patch with concrete or epoxy
concrete lining to high loads from earth
holes mortar
embankments
dw2018 | 8
SERIOUS DEFICIENCIES IN CONCRETE DAMS
(from TADS)
dw2018 | 9
SERIOUS DEFICIENCIES IN CONCRETE DAMS
(from TADS)
Cavitation; due to
Rough patches; loss of irregularities or Chip out damaged concrete, patch
Discharge
concrete; exposed extremely rough with concrete or epoxy mortar, grind
channel smooth to gradually varying surface
reinforcing surface or erosion
from carried debris
dw2018 | 10
SERIOUS DEFICIENCIES IN CONCRETE DAMS
(from TADS)
Location Type of Deficiencies Possible causes Possible corrective actions
Visible scour holes (more Remove the damaged concrete and all
Heavy debris not swept structures located in bucket, rebuild
Flip bucket (non- than 30 cm in diameter),
out of bucket during bucket concrete to specified finish;
submerged) blocks of broken concrete; prevent damaging objects from
operation
exposed reinforcing entering bucket
dw2018 | 11
TYPES OF CONCRETE DAMS (apud TADS)
dw2018 | 12
HPP LAJEADO – CONSTRUCTION PHASE
dw2018 | 13
GRAVITY DAM
Typical section of a gravity block with static acting forces
(cf.Cifu)
Silting
dw2018 | 14
ARCH DAM – FUNIL HPP
Paraiba do Sul River
dw2018 | 15
BUTTRESS DAMS – Right Wing ITAIPU
dw2018 | 16
PROBLEMS ON CONCRETE DAMS (apud TADS)
dw2018 | 17
PROBLEMS ON CONCRETE DAMS (apud TADS)
dw2018 | 18
PROBLEMS ON CONCRETE DAMS (Ex: Malpasset)
dw2018 | 19
The three major causes of dam failures
(ICOLD - International Commission of Large Dams)
• Overtopping due to floods (earth dams);
• Failures in foundation (mainly in concrete dams);
• “Regressive erosion" or “Piping" (earth dams)
Foundation
Overtopping Piping
dw2018 | 20
MAIN CAUSES OF FAILURES IN THE USA
(Fonte: National Performance of Dams Program)
dw2018 | 21
ACCIDENTS AND INCIDENTS IN DAMS
SOME DAMS THAT COLLAPSED IN BRAZIL
PAMPULHA (MG) - Earth 1954
dw2018 | 22
SOME DAMS THAT COLLAPSED IN BRAZIL
FERNANDINHO (MG-Tailings dam) 1985
PICO SÃO LUIZ (MG-Tailings dam) 1985
CATAGUAZES (MG-Tailings dam) 2003
CAMARÁ (PB - RCC) – Concrete, Foundation 2004
MIRAÍ (MG-Tailings dam) 2007
APERTADINHO (RO) - Concrete, Foundation (friable
sandstone) 2008
ESPORA (GO) - 2008
ALGODÕES (PI) – Concrete, Overtoping 2009
dw2018 | 23
PIPING IN US DAM
dw2018 | 24
FAILURE OF SANTA HELENA DAM
Before
After
dw2018 | 25
ALGODÃO DAM I - PI
dw2018 | 26
CARLOS HENRIQUE MEDEIROS
ALGODÃO DAM I – PI
(May/2009)
dw2018 | 27
(RO)
PCH APERTADINHO – RO
Jan/2008
dw2018 | 28
PCH ESPORA / GO
Jan/2008
Isolated cities, flooded farms and caused environmental prejudices and
material damages to the population.
dw2018 | 29
CAMARÁ DAM
Originally designed as an
embankment dam, DOWNSTREAM VIEW
switched to 48m high RCC
gravity dam after majority
of explorations were
completed.
dw2018 | 30
dw2018 | 31
dw2018 | 32
Reservoir filled to
within 5 m of full pool CAMARÁ - PB
quickly in early 2004 Could the failure have been avoided?
due to heavy rains.
Filling continued
into June 2004.
Reports of material
carried by drain flows,
plugged drains, and
wet spot d/s toe left
abutment during this
time period.
Dam failed June 17,
2004
dw2018 | 33
CAMARÁ - PB
dw2018 | 34
CAMARÁ DAM
(Photo: Hermínio Bernardo, Saulo Porto, Silas Porto)
dw2018 | 35
CAMARÁ - PB
Consequences:
• 7 dead, 20 missing and 3300 homeless
• 810 homes destroyed or flooded.
• The cities of Alagoa Grande and Mulungu were without telephone
communication, without water supply and without electricity for 15
days
• In 2017 a Federal Court blamed the government of the State of
Paraiba, Brazil, for the accident .
• The dam was rebuilt
dw2018 | 36
Teton Dam, EUA (1976)
Rexburg (80% destroyed in 1976) and situation in 2001
dw2018 | 37
INTERIOR OF CONCRETE FOUNDATION GALLERY
dw2018 | 38
INTERIOR OF CONCRETE FOUNDATION GALLERY
dw2018 | 39
INTERIOR OF CONCRETE FOUNDATION GALLERY
dw2018 | 40
INTERIOR OF CONCRETE FOUNDATION GALLERY
dw2018 | 41
INTERIOR OF CONCRETE OUTLET GALLERY
dw2018 | 42
Organize and keep good
state of conservation all
information and
documentation of the design,
construction, operation,
maintenance and
deactivation.
dw2018 | 43
DEFICIENCIES IN CONCRETE
The predisposition of the structure, or of one of its parts, to present deficiencies
in the concrete can originate during the design phase, construction or be
acquired in the phase of operation.
dw2018 | 44
PHYSICAL-MECHANICAL DETERIORATION
EROSION
Erosion is the mechanical wear work carried out by the
water flow, or variation of the upstream water level.
dw2018 | 45
ABRASION
Action of solid particles (clay, sand, gravel, debris, wood) loaded by
water, especially in regions subjected to high water velocity.
dw2018 | 46
ABRASION
dw2018 | 47
CAVITATION
Rough surface with aggregates in sight, giving the appearance
of “honeycombs"; surface with numerous shallow holes
eventually showing that the aggregate was pulled.
Formation and subsequent collapse of micro vacuum bubbles
that produce shock waves on the surface of the structure and
destroying, initially by points, the continuity of the structure. The
repetition of this phenomenon produces several holes in the
surface of the structure, even in high quality concrete and,
depending on the magnitude, can cause the concrete to spall,
create holes, etc.
dw2018 | 48
CAVITATION
dw2018 | 49
CAVITATION (example: Ilha Solteira HPP)
dw2018 | 50
CAVITATION
dw2018 | 51
CAVITATION
dw2018 | 52
PHYSICAL-MECHANICAL DETERIORATION
CRACKING
It is inevitable that the concrete presents cracking.
Cracks can be caused by:
• Shrinkage of concrete;
• Corrosion of reinforcement;
• Excessive loading;
• Thermal variation of concrete;
• Alkali-aggregate reaction;
• Delayed ettringite formation;
• Sulphate attack.
dw2018 | 53
TYPES OF CRACKING - HARDENED CONCRETE
CORRECTIVE ACTION
TYPES OF SECONDARY COMMON
PRIMARY CAUSE SYMPTOM (in all cases reduce the
CRACKING CAUSE LOCATION
restraint)
Excessive Parallel cracking Reduce the water content in
Drying
shrinkage; usually thinner if Slabs and thin the concrete and improve
shrinkage over Insufficient joints
unsatisfactory the concrete is walls curing process; decrease
time
curing reinforced joint spacing
dw2018 | 54
TYPES OF CRACKING - HARDENED CONCRETE
CORRECTIVE ACTION
TYPES OF SECONDARY COMMON
PRIMARY CAUSE SYMPTOM (in all cases reduce the
CRACKING CAUSE LOCATION
restriction)
Alkali-
Reactive aggregates plus high Crocodile skin To eliminate the causes
aggregate Humid places
alkali cement cracks use pozzolanic material
reaction
dw2018 | 55
TYPES OF CRACKING - HARDENED CONCRETE
CORRECTIVE ACTION
TYPES OF SECONDARY COMMON
PRIMARY CAUSE SYMPTOM (in all cases reduce the
CRACKING CAUSE LOCATION
restraint)
Structures in
Crocodile skin Use suitable concrete;
contact with
Sulphate action Expansion due to ettringite cracks provide structure
water / sulfate
protection
soil
Excessive heat
generation Parallel cracking is
Early thermal usually thinner if Mass concrete
Fast cooling Reduce heat or insolation
shrinkage Excessive the concrete is and thick parts
temperature reinforced
gradient
dw2018 | 56
CRACKING AND LEAKAGE AT DAM (in São Paulo, Brazil)
dw2018 | 57
CONCRETE SHRINKAGE
• Plastic Shrinkage
It occurs by the loss of water from concrete through bleeding in its
fresh state. This process is accelerated by the exposure of its
surface to inclement weather such as wind, low relative humidity
and increased ambient temperature.
The measures necessary to reduce evaporation of water on the
concrete surface are:
• Decrease concrete temperature on hot days;
• Reduce wind speed on concrete surface;
• Keep concrete’s moisture.
This type of crack appears in a distributed form and cuts off each
other.
dw2018 | 58
SHRINKAGE OF CONCRETE
It occurs with the concrete already in the hardened state.
dw2018 | 59
CONCRETE SHRINKAGE
• Chemical or autogenous shrinkage
It occurs due to the reduction of volume from the moment of
hydration, because the products are generated according to
volume that begins hydration, as they are responsible for the
hydration.
The chemically combined water (22 to 32%) undergoes a
contraction of 25% of its original volume. This type of shrinkage is
proportional to cement consumption per cubic meter of concrete
and to the amount of water stoichiometrically required for cement
hydration.
dw2018 | 60
CONCRETE LEACHING
The leaching corrosion consists of progressive dissolution of the
compounds of hardened cement paste by aggressive substances.
Easily soluble compounds can be washed from the concrete or
cement paste by continuous access of the water, and loss of the
material is verified.
dw2018 | 61
CONCRETE LEACHING
The main leaching agents are:
• Acidic substances (eg sulfuric acid, sulphurous acid, carbonic
acid, humic acid, acid rain or condensation water from
industrial processes);
• Alkaline substances (eg caustic soda);
• Pure or low salt waters (rainwater, groundwater of great
depths, marshy waters few salinas.);
• Fungi and bacteria.
dw2018 | 62
CONCRETE LEACHING
• Up to 20% loss of Ca (OH2) the strength decreases a little
• Itaipu case
• Jordao River Dam Case
dw2018 | 63
THERMAL CRACKING
The occurrence of thermal cracking is directly related to volumetric
variations that occur in the concrete, due to the heat generated by
the hydration of the cement and to the restraint that exists
They are related to the leakage of water that occur in galleries,
downstream faces among other places.
dw2018 | 64
SCHEME OF CONCRETE BLOCK SUBMITTED TO
THERMAL VARIATIONS
T1
T 2 > T1
T3 < T2
dw2018 | 65
CONCEPT OF MASS CONCRETE
fck=25MPa → fct=2,5MPa (~10% fck)
Ambient Temperature (AT) = 25°C
E=20.000MPa (modulus of elasticity)
=10-5/°C (coefficioent of thrmal expansion)
Cement content =250kg/m³
Thermal efficiency =0,10°C/kg/m³
Restraint (R) = 1,0
Creep (f) = 1,0
Factor of Safety = 1,0
dw2018 | 66
CONCEPT OF MASS CONCRETE
→Hipothesis A T (ºC)
Placement temperature=30°C
Δt=Tmáx - AT
Delta T =55-25=30°C
=20.000x10-5x30x1x1 30ºC
= 6MPa 20ºC
10ºC
TL3= 10°C
→Hipothesis B
Compression TIME
Placement temperature=10°C
Δt=Tmáx - AT Tension
TA=35-25=10°C
=20.000x10-5x10x1x1
CRACK
=2MPa
dw2018 | 67
THERMAL CRAKING IN BRAZILIAN CONSTRUCTIONS
dw2018 | 68
THERMAL CRAKING IN CCR DAMS – BRAZIL
Downstream step
dw2018 | 69
THERMAL CRAKING AT BRAZILIAN DAM
dw2018 | 70
GALESVILLE DAM (USA)
dw2018 | 71
GALESVILLE DAM (USA)
dw2018 | 72
UPPER STILLWATER DAM (USA)
dw2018 | 73
UPPER STILLWATER DAM (USA)
dw2018 | 74
dw2018 | 75
TUCURUÍ HPP
Height = 95m
Concrete volume = ~ 8.000.000 m3
Placement temperature (1st phase 1981) = 14ºC to 16ºC
Placement temperature (2nd phase 2006) = 23ºC to 27ºC
TUCURUI HPP SPILLWAY
dw2018 | 77
dw2018 | 78
TO DO OR NOT TO DO A THERMAL STUDY:
THAT IS THE QUESTION!
dw2018 | 79
MAIN GOALS OF A THERMAL STRESSES STUDY
Determine:
• Avoid thermal cracking and delayed ettringite formation (DEF)
• Spacing of concrete joints;
• Height and placement interval between lifts;
• Removal time of the formwork;
• Concrete placement temperature;
• Cooling methodology:
• Precooling
• Post-cooling
dw2018 | 80
FACTORS AFFECTING THERMAL CONDITIONS IN
CONCRETE
1. Climate conditions 2. Concrete properties
• Placement temperature • Cement
• Exposure conditions during • Pozzolanic materials
construction • Aggregates
• Exposure conditions during • Thermal properties of
operation concretes
• Final stabilization • Elasto-mechanical
temperature characteristics of concrete
• Seasonal temperature
variation
dw2018 | 81
FACTORS AFFECTING THERMAL CONDITIONS IN
CONCRETE
3. Design and construction 4. Construction speed
• Section dimensions and • Lift height
shape • Concrete Intervals
• Contraction joints • Placement temperature
• Type of formwork / removal • Seasonal limitations
• Type of curing 5. Restraint (internal and
• Cooling external)
• Sun protection • Foundations
• Structural design • Walls
• Temperature differentials
dw2018 | 82
NECESSARY INFORMATION ABOUT CONCRETE
• Adiabatic temperature rise
• Coefficient of linear thermal expansion
• Specific heat
• Thermal diffusivity
• Strain capacity
• Tensile strength
• Modulus of elasticity and Poisson's coefficient
• Creep
dw2018 | 83
THERMAL CRACKING
• Cracks due to thermal stresses appears at lifts close to
structures with high modulus of elasticity, such as a foundation
or an old concrete.
dw2018 | 84
THERMAL CRACKING
The cracks caused by the restraint tend to propagate to the top of the
structure.
dw2018 | 85
THERMAL CRACKING
The heat of hydration is directly influenced by:
• Type of cement;
• Cement content;
• Fineness of the cement.
dw2018 | 86
THERMAL CRACKING
The cracking tendency is minimized when:
• The difference between the peak temperature of the concrete
and the ambient temperature is small;
• The concrete’s coefficient of thermal expansion, modulus of
elasticity and degree of constraint are low;
• The strength of the concrete is high.
dw2018 | 87
THERMAL CRACKING
Thermal cracking damage can impair the durability and safety of
the structures, as they allow the ingress of aggressive agents and
the leakage of water through them.
dw2018 | 88
THERMAL STUDIES
Thermal studies are important to avoid cracking of concrete
structures and through them it is possible to determine the best
construction methods.
dw2018 | 89
THERMAL STUDIES
Temperature changes are not exact due to variations in the
thermal properties of the concrete and ambient conditions, but it
can be said that the temperatures obtained through the thermal
studies are relatively accurate, as can be seen in the comparison
between the values obtained in the calculations and the values
measured through thermometers at the construction.
dw2018 | 90
THERMAL STUDIES
Evolução das Temperaturas
60
55 Simulation
50
Measured
45
Temperatura(°C)
40
35
30
25
20
15
10
10 15 20 25 30 35 40 45 50 55 60
Time (days)
Tempo(dias)
dw2018 | 91
SOFTWARE - FEM
Finite element meshes generated through B4cast software.
dw2018 | 92
EXAMPLES- FEM
The results obtained through the B4Cast software can be shown
in the three directions (x, y and z).
dw2018 | 93
PRODUCT = TEMPERATURES AND STRESSESS
The software allows to obtain the evolution of temperatures and
stresses as a function of time and hence reach the best method
of construction.
Temperatures evolution
Time (hours)
Lift
dw2018 | 94
PRODUCT = TEMPERATURES AND STRESSESS
Example of the evolution of stresses at three critical points of
study. Having the compressive strength and the tensile strength
of the concrete it is possible to verify the possibility of cracking at
the structure.
Tensile strength
dw2018 | 95
PRODUCT = INSTANTANEOUS CRACKING
In this example it is possible to check the moment when cracking
occurs.
Crack
Tensile strength
dw2018 | 96
THERMAL STRESSESS STUDY OF A SPILLWAY OF
A SMALL HYDROELECTRIC POWERPLANT
(Presented at PCH 2010 - CBDB)
Eduardo I. Funahashi Jr and Selmo Kuperman, DESEK
dw2018 | 97
THERMAL STRESSESS STUDY OF A SPILLWAY OF A
SMALL HYDROELECTRIC POWERPLANT
SPILLWAY
dw2018 | 98
THERMAL STRESSESS STUDY OF A SPILLWAY OF A
SMALL HYDROELECTRIC POWERPLANT
INSPECTION
dw2018 | 99
PARAMETERS AVAILABLE FOR SIMULATION OF THE SPILLWAY
dw2018 | 100
THERMAL STRESSESS STUDY OF A SPILLWAY OF A SMALL
HYDROELECTRIC POWERPLANT
70
65
63,6ºC
60
55
47,5ºC
50
Temperatura (°C)
45
40
35
30
25
20
15
10
0
0 50 100 150 200 250 300 350 400 450 500 550 600 650
Tempo (horas)
Classe I Classe II
dw2018 | 101
THERMAL STRESSESS STUDY OF A SPILLWAY OF A
SMALL HYDROELECTRIC POWERPLANT
PLACEMENT CONDITIONS
Plac Int =3 days Wind velocity=5m/s Wood forms
Plac.temp=32°C AT= 25°C Curing with water
dw2018 | 102
THERMAL STRESSESS STUDY OF A SPILLWAY
OF A SMALL HYDROELECTRIC POWERPLANT
FINITE ELEMENTS MESH – (SOFTWARE-B4CAST)
Galley
Foundation
dw2018 | 103
THERMAL STRESSESS STUDY OF A SPILLWAY
OF A SMALL HYDROELECTRIC POWERPLANT
dw2018 | 104
THERMAL STRESSESS STUDY OF A SPILLWAY
OF A SMALL HYDROELECTRIC POWERPLANT
ANALYSIS OF RESULTS
Evolução das Temperaturas
Evolution of temperatures
70
65 Peak
60
55
(°C)(°C)
50
45
Temperature
40
Temperatura
35
30
25
20
PT=32°C
15
10
5
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Time
Tempo(days)
(dias)
dw2018 | 105
THERMAL STRESSESS STUDY OF A SPILLWAY
OF A SMALL HYDROELECTRIC POWERPLANT
ANALYSIS OF RESULTS
Influence of placement Evolução das Temperaturas
on upper lifts Evolution of temperatures
70
65
60
55
Stresses (MPa)
50
PT=32°C
(°C)
45
40
Temperatura
35
30
25
20
Placement
15 Interval
10
Curing
5 Period of 3 days
0
5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
Tempo (dias)
Time (days)
C-III(1,15m) C-IV(2,75m) C-V(4,25m) C-VI(5,85m)
dw2018 | 106
THERMAL STRESSESS STUDY OF A SPILLWAY
OF A SMALL HYDROELECTRIC POWERPLANT
ANALYSIS
Possibility of Cracking
EvolutionOF RESULTS
of temperatures
Stresses (MPa)
Time (days)
dw2018 | 107
THERMAL STRESSESS STUDY OF A SPILLWAY
OF A SMALL HYDROELECTRIC POWERPLANT
CONCLUSIONS
dw2018 | 108
THERMAL STUDIES
The galleries have a significant dissipation effect. The galleries
are essential for heat dissipation in concrete structures.
dw2018 | 109
THERMAL STUDIES
Zoning of concrete placement temperatures.
dw2018 | 110
CHEMICAL REACTIONS DAMAGING CONCRETE
• Alkali-Aggregate Reaction (RAA)
dw2018 | 111
AAR OFFICIALLY DISCLOSED IN BRAZILIAN DAMS AND
OTHER STRUCTURES
• 1920 • 1950
Ilha dos Pombos Sá Carvalho
• 1930 Mascarenhas de Moraes
Billings-Pedras Paulo Afonso I
Jurupará Pirapora
Pedro Beicht Ribeirao do Campo
Salto do Meio • 1960
• 1940 Furnas
Peti Paulo Afonso II
Traição Pedras
dw2018 | 112
RAA OFFICIALLY DISCLOSED IN BRAZILIAN DAMS AND
OTHER STRUCTURES
• 1970 TA-6 (Cantareira )
Atibainha Tapacurá
Cascata • 1980
Jaguara Bridges
Jaguari (CESP) • 1990 to 2018
Jaguari (SABESP) Foundations of buildings, subways,
Joanes II flyovers, precast elements
Moxotó
Porto Colombia
Paiva Castro
Paulo Afonso III
Paulo Afonso IV
dw2018 | 113
SOME RECENT BRAZILIAN CASES
JJJ
Building 9 years old (2008) - ASR Building where construction stopped – ASR + DEF - 2009
cockroach
dw2018 | 114
BUILDING WITH AAR + DEF IN BRAZIL - 2011
dw2018 | 115
TYPES OF ALKALI-AGGREGATE REACTION
• Alkali-Silica (ASR) reaction: better known and occurs faster
(The old Alkali-Silicate Reactivity was incorporated into ASR)
dw2018 | 116
MECHANISM OF THE ALKALI-SILICA REACTION (RAS)
Tetrahedron of
silica
Atomic arrangement of silica group minerals with ordered structure and well
crystallized, with disordered and poorly crystallized structure (Collins, 2007)
dw2018 | 117
MECHANISM OF THE ALKALI-SILICA REACTION (ASR)
dw2018 | 118
MECHANISM OF THE ALKALI-SILICA REACTION (ASR)
Silanol groups (Si-OH) are disrupted by SiO- ions released are attracted by the alkaline
OH- ions in ions of SiO-, on the surface solutions of the pores, forming alkali silicate gel
of the aggregate (Collins, 2007) around the aggregate. Si-OH + Na + + OH¯ → Si + O
+ Na + H2O (Collins, 2007)
dw2018 | 119
MECHANISM OF THE ALKALI-SILICA REACTION (RAS)
Large aggregates with RAA in the
aggregate interface/cement matrix
(Pecchio et al., 2006). Apud
Munhoz
Reaction edge.
Stereoscopic microscope.
Magnification 9x (ABCP
Collection). Apud Munhoz.
dw2018 | 120
MECHANISM OF THE ALKALI-SILICA REACTION (RAS)
Couto - 2008
dw2018 | 121
MAJOR FACTORS AFFECTING ASR
Main Factors
• Reactive silica
• Alkalies
• Moisture
Other Factors
• Temperature
• Compressive stresses
• Mineralogical variations of reactive aggregates
• Dimensions and distribution of reactive aggregates
• Alkali migration of concrete pore solution
• Cement paste strength and toughness
dw2018 | 122
AAR - FACTORS
dw2018 | 123
AAR - FACTORS
dw2018 | 124
HIWASSEE HPP (TVA + Hatch – Dodson & Curtis)
dw2018 | 125
HIWASSEE HPP (TVA + Hatch – Dodson & Curtis)
dw2018 | 126
ALTO CEIRA DAM (Portugal)
Source: Antonio Batista
dw2018 | 127
ALTO CEIRA DAM (Portugal)
New construction and demolition of the old dam due to ASR (2013)
dw2018 | 128
CHICKAMAUGA HPP AND SLUICE GATE
(Source: TVA, ICOLD Workshop, Aug 2013 – Niznik & Curtis)
dw2018 | 129
CHICKAMAUGA HPP AND SLUICE GATE
(Source: TVA, ICOLD Workshop, Aug 2013 – Niznik & Curtis)
dw2018 | 130
CHICKAMAUGA HPP AND SLUICE GATE
(Source: TVA, ICOLD Workshop, Aug 2013 – Niznik & Curtis)
1943 Surface cracking developed in the lock junction portion of the lock.
1964 Significant cracks were found in the upper river approach wall and supporting piers.
1965 Three slots were cut in the upper river approach wall to relieve stress from upstream expansion and to allow for future
expansion. Supporting piers for blocks 27 and 28 were post-tensioned to restore structural integrity.
1977 The expansion slots in the upper approach wall were found to have closed due to continued expansion of the lock.
Considerable diagonal cracking was discovered in the concrete piers between the discharge ports in the lower riverwall. A
significant crack was observed in the end block of the lower river approach wall.
1977/78 The crack in the lower approach wall was grouted and post-tensioned. A slot was cut in the lower approach wall to
isolate it from the lock.
1979-1980 The existing slots in the upper approach wall were re-cut and an additional slot was added. Post-tensioned
reinforcement was added to piers 29, 30, 31, and 32.
1980 A diving inspection found that the diagonal cracking in the piers between the discharge ports had worsened.
19811982 Five-inch steel bars were installed in the piers by grouting them into drilled holes.
dw2018 | 131
CHICKAMAUGA HPP AND SLUICE GATE
(Source: TVA, ICOLD Workshop, Aug 2013 – Niznik & Curtis)
1983 Horizontal cracks at similar elevations to cracks that were observed in the cable tunnel were found during the unwatering inspection.
Overcore drilling was performed in the unwatered lock chamber at monolith blocks 41 and 46 to determine the stress in the lower portions
of the blocks.
1984 A horizontal crack in the culvert roof showed significant deterioration. Horizontal and vertical post-tensioning with high-strength bars
and tendons was completed as an emergency repair.
1995 The lower landwall gate hinge assembly almost failed because vertical growth in the landwall monolith caused the hinge pin to nearly
pull from the gate. An unscheduled lock closure was held while repairs were completed.
1995 Upper approach wall slots 3 and 4 were recut, and all four keys in the upper slots were removed and replaced. The lower approach
wall slot was also recut.
1999 Install piezometers along landwall earth fill. Obtain and performed shear tests on concrete samples.
2000 Installed pendulums in gate monoliths and Highway Bridge support monoliths. Rehab existing pendulum in dam junction block.
2001 A diving inspection noted increased damage around the discharge ports at the lower riverwall with spalling of the existing cracks.
Overcore testing in 6 monoliths.
2003 Flooding in May covered the lower approach walls. After the flood water receded, a 1- inch transverse offset was observed in the
lower approach wall slot. Realigned mooring bit tracks.
dw2018 | 132
CHICKAMAUGA HPP AND SLUICE GATE
(Source: TVA, ICOLD Workshop, Aug 2013 – Niznik & Curtis)
2004 Overcore drilling from the unwatered lock floor was completed in blocks 13 and 46.
Results were compared to the 1983 tests to determine increases in stress in the lower portions of the blocks.
2005 Lower portion of downstream approach wall removed for construction of new lock.
Finite element analysis of embedded miter gate anchorages.
2010 Install vertical replacement post-tensioning in upstream guide wall and horizontal post- tensioning between valve & bulkhead
slots. Grout placed in cable tunnel near upper sill and on the landwall upper and lower valve pits.
2011 Lower landwall gate anchorage replaced. Reinforced horizontal joints in upper guide wall. Installed 10 Shape Array Accelerators
and performed shear tests on concrete samples.
2012 Replace/adjust quion block gaps on downstream gate monoliths. Rehab lower riverwall discharge ports.
dw2018 | 133
FONTANA DAM - USA
dw2018 | 134
ASR RETARDING AND MITIGATING ACTIONS
• Retarding Actions
• Drainage (Billings)
• Impediment of moisture ingress with surface treatments: membranes,
sealants, impregnants, penetrating
dw2018 | 135
MOXOTO HPP
dw2018 | 136
MOXOTO HPP
Movement direction (55o)
Mathematical modelling
Before After
1984 = SAP IV
Relative position between the 1986 = SAP 90
turbine runner and the discharge 2002 = ANSYS
ring
Sources: Cavalcanti
and Silva (CHESF)
dw2018 | 137
MOXOTO HPP: EXAMPLES OF INSTRUMENTATION
Alongameter base
Plumbline
dw2018 | 138
BEHAVIOUR OF THE WATER INTAKE OF JAGUARI
HYDROPOWERPLANT AFFECTED BY ALKALI-
AGGREGATE REACTION
Flavio M. Salles, Julio C. Pínfari, Camilo Mizumoto CESP-
Companhia Energetica de Sao Paulo
flavio.salles@cesp.com.br
Selmo C. Kuperman
DESEK
selmo@desek.com.br
dw2018 | 139
WATER INTAKE
SPILLWAY
POWERHOUSE
dw2018 | 140
JAGUARI HPP
SPILLWAY
EARTH DAM
dw2018 | 141
Water intake during construction Water intake in 2009
Slab in 2008
dw2018 | 142
MONITORING
• Rod extensometers (3 rods)
• Triortogonal crack meters (7)
• Cracks openings (24)
• Laser sensor (1)
• LVDT (linear variable differential transformer) (1)
• Geodetic surveys
dw2018 | 143
ROD EXTENSOMETERS
dw2018 | 144
TRIORTOGONAL CRACK METERS
2000 2010
2008
dw2018 | 145
EXAMPLE OF INSTRUMENTATION OF ONE PILLAR
dw2018 | 146
PEDRA HPP
dw2018 | 147
PEDRA HPP
Analysis: mathematical model (FEM) – ANSYS
Probable rate of expansion = 38x10-6/year
dw2018 | 148
PEDRA HPP
Slot cutting for expansion joints (4 slots)
Sealing the expansion joints with geomembrane
Carpi
geomembrane
sealing the
expansion joint
Source: Cavalcanti, Tristão, Santos, Silva - 2011
dw2018 | 149
PEDRA HPP
Instrumentation: 5 direct plumblines, 7 rod extensometers, 4 water
flowmeters, 31 triorthogonal crack meters, 16 alongameter bases,
12 reference marks
Reference marks
Triortogonal
crack meter Direct plumbline
Direct plumbline
Rod
extensometers
dw2018 | 150
FURNAS HPP
Beginning of construction: 1958
Conclusion / Beginning of operation:
DAM: 1963; Stage 1: 1965; Stage 2: 1974
1st signs AAR: 1976 (with 13 years)
Aggregate: Quartzite
dw2018 | 152
Procedures
• Monitoring: first-order leveling line and planimetric trilateration
network, vibrating wire strain gages, triorthogonal crack
meters, rod extensometers, piezometers.
• Visual inspections.
• Repairs on cracked areas (use of high-performance mortar
and polypropylene fiber in spillway).
• Adjustments in the wear ring.
• Simulation with tridimensional FEM model RAS3D (software
from COPPE/UFRJ-FURNAS)
• Rates of expansion: 22x10-6/yr (1976) and 8x10-6/yr (1995).
dw2018 | 153
Billings-Pedras Dam Operation
Start = 1937 / Discovery ASR = 1992 / Containment difficulties = 1996
dw2018 | 154
BILLINGS PEDRAS DAM
• Aggregates = gneiss
• Cement = similar to ASTM Type I
• Petrographic analysis confirmed AAR
• FEM simulations in 1992
• Monitoring: triorthogonal crack meters, rod extensometers,
convergence meters, reference marks
• Repairs:
• 1996
• 2002
• 2007
dw2018 | 155
ASR RETARDER AND MITIGATING ACTIONS
Drainage
Water
dw2018 | 156
ASR RETARDER AND MITIGATING ACTIONS
Waterproofing
dw2018 | 157
ASR – BRAZILIAN CASES
Water Intake (TA-6-Sabesp)
dw2018 | 158
ALCALI-AGGREGATE REACTION (AAR)
• Concept
• Factors that affect AAR
• Prevention and neutralization / utility of NBR 15577
• Methods of testing
• Delaying and mitigating actions (foundations, decks, guard
rails)
• Detection and control
• Historical cases: power plants, foundations (bridges, towers,
buildings, sluice)
• Future (research and events)
dw2018 | 159
EVIDENCE OF AAR OCCURRENCE
• Non-oriented cracking pattern, in simple concrete;
• Elongated and oriented cracks in reinforced concrete and
prestressed concrete;
• Efflorescence and gel exudation;
• Deterioration of concrete;
• Concrete shifts;
• Misalignment and deformations of metallic structures.
dw2018 | 160
PREVENTION AND NEUTRALIZATION OF RAS -
BRAZILIAN PRACTICE
• 1960 - First studies = Jupiá Hydroelectric Plant, CESP
• Beginning of the use of artificial pozzolans and fly ash to neutralize ASR in
dams and other structures
• Late 1970s = use of pozzolanic and blast furnace cements to neutralize RAS
• Late 1980s = use of active silica
• Early 2000 = metacaulim use
• 2005 = RAS in foundation blocks in the city of Recife
• 2008 = Brazilian Standard NBR 15577 "Aggregates - Alkali-Aggregate
Reactivity"
• 2010 = use of rice husk ash (??)
• 2014 = Brazilian standard revision = IBRACON committee
• 2018 = approval of the complete revision of the standard NBR 15577
• Structures that did not use preventive measures have ASR
dw2018 | 161
IMPORTANT ASPECTS:
• A risk analysis must be performed by the engineer
before accepting the type of aggregate or the
concrete produced with this aggregate (the
engineer is responsible for this decision);
• Potentially reactive aggregates can be used in any
work, provided that AAR mitigating measures are
employed;
• Every quarry must perform AAR tests: every 6
months or after producing 150,000 m³ of
aggregates; petrographic analyzes and physical
tests should be performed.
• About 85% of the aggregates used for conventional
concrete in Brazil are granites, 10% are limestone
and 5% correspond to other lithologies (apud
Sbrighi-ANEPAC)
dw2018 | 162
SOME TESTS OF AAR CARRIED OUT IN THE
LABORATORY OF CESP- ILHA SOLTEIRA
dw2018 | 163
IMPORTANT ASPECTS:
• 1997 - "I Symposium on alkali-aggregate
reactivity in concrete structures", CBGB-
FURNAS-IBRACON, Goiânia, Brazil
• 2006 - "II Symposium on alkali-aggregate
reaction in concrete structures", IBRACON-
CBGB-FURNAS, Rio de Janeiro, Brazil
• Several workshops, symposia, lectures,
publications, courses
• 2014 to 2018 - IBRACON Committee -
Review Standards and publication Best
Practices
• 2017: IPT Symposium, São Paulo
dw2018 | 164
15th ICAAR - São Paulo, 2016
• More than 200 papers were received from
participants from 21 countries. This work
was submitted to an International Board of
Reviewers, with 129 chosen, 103 for oral
presentation and 26 for presentation in
poster session. The event counted on 196
registered participants, being 80%
foreigners, coming from 21 countries,
among them some of the best experts in
AAR. In addition to the oral sessions and
poster sessions, 6 thematic lectures and a
technical visit were held.
dw2018 | 165
DETECTION OF ASR IN CONCRETE STRUCTURES
• Carry out field inspections and tests
• Extract samples from concrete - petrographic evaluation with
emphasis on RAS
• Conduct investigations in the laboratory (E, fc)
• Will expansions continue to occur?
• Assess the situation - consult the project
• Structure Monitoring - Expansion Rate
• Assess the risks involved, if the AAR has continuity
dw2018 | 166
IDENTIFICATION OF ASR IN THE FIELD -
CHEMICAL CONTRAST METHODS
• Uranyl acetate + UV (SHRP
method - Photo Spectroline, USA)
dw2018 | 167
Field research Sampling Petrographic analysis
Diagnosis: No
Are the damages or anomalies due to AAR?
dw2018 | 168
IDENTIFICATION OF ASR IN THE LABORATORY -
PETROGRAPHIC ANALYSIS
• Scanning Electron Microscope
(SEM)
dw2018 | 169
ALKALI-AGGREGATE REACTION
• Why is it searched?
• What is known?
dw2018 | 170
WHY IS IT SEARCHED?
• New events in various parts of the world and in Brazil
• Changes in available materials
• Changes in constructive practices
• Existing problems in infrastructure works (dams, bridges,
viaducts, ports, pavements, etc.)
• Problem complexity due to mixing components
• Lack of transmission of knowledge to the technical
environment and to the younger generation
dw2018 | 171
WHAT IS KNOWN?
• Basic Mechanisms of AAR, from Stanton (1940)
• How to avoid reaction and expansions
• How to choose the aggregates (not always): petrographic
analysis, tests with accelerated mortar bars, concrete prisms,
accelerated concrete prisms
• Pozzolanic materials reduce expansion (their control is still
uncertain)
dw2018 | 172
WHAT IS NOT KNOWN OR LESS KNOWN?
• Effect of gel composition (depending on the type of aggregate,
effect of additions, etc.)
• Alkalies of the aggregates (how to test, how they dissolve, how they
influence the alkalinity of the medium, etc.).
• Correlation between the reactivity of the aggregates and the alkali
content of the mixture (different aggregates require different
amounts of alkalis)
• Effect of leaching on AMBT, CPT and ACPT results
• Real effect of moisture reduction
• Reactions on carbonate aggregates (will it be silica?)
• How to test concrete mix performance?
• How to better spread the word?
dw2018 | 173
Comparison between exposure blocks and concrete prisms test
(from a presentation by Folliard, U of Texas)
dw2018 | 174
TEST BLOCKS AT ILHA SOLTEIRA HPP (Brazil)
Long time testing
1970 2014
1970 2014
Pictures from presentations by Borge Wigum (Norway) and Kevin Folliard (USA)
dw2018 | 176
WHAT TYPE OF RESEARCH OR ACTION IS
REQUIRED?
• There is a lot of isolated research, spending time and money
• Need for a forum to exchange information
• Need for coordination of research
• Alkalies in the aggregates
• Carbonate Aggregates - Understanding the Mechanism
• Concrete Mixing Tests
• Studies of long-term reactions
• Mitigation methods
• Performance of actions to reinforce or restore structures over time
dw2018 | 177
COMMENTS
• Broad dissemination of ASR required
• Careful examination of affected works
• Appropriate studies of aggregate deposits
• Use of cements containing adequate quantities of materials that
neutralize ASR: pozzolans, blast furnace slag, active silica,
metakaolin, etc.
• Research to determine expansion rates, duration of ASR and
methods to neutralize the reaction, when it is already installed
dw2018 | 178
SYNTHESIS OF ETTRINGITE GENERATION PROCESSES
• Etringite = Ettringen mineral - description: Lehmann 1847.
dw2018 | 179
ETTRINGITE CRYSTALS
dw2018 | 180
PRIMARY ETTRINGITE FORMATION
• Solubilization of C3A:
dw2018 | 181
SULFATE ATTACK
SULFATE ATTACK
ATMOSPHERIC UNDERGROUND
MIXING WATER AGGREGATES
POLLUTION WATER
dw2018 | 182
ETTRINGITE CRYSTALS
Extreme case of sulphate attack Concrete previously of high resistance after attack and
on the infrastructure of a bridge in formation of taumasite. The outer 50mm were made
contact with clay containing pyrite into paste. Taumasite halos can be seen around
aggregates (see BRE Special Digest 1-2005). Bridge
and moisture after 30 years (see
Glocestershire, England, built in 1968. 5% pyrite in soil.
BRE Special Digest 1-2005).
dw2018 | 183
FORMATION OF ETTRINGITE OR TAUMASITE BY ATTACK OF
EXTERNAL SULFATE (ASE)
ETTRINGITE (Candlot-1887) TAUMASITE
(3CaO · Al2O3 · 3CaSO4 · 32H2O) (CaSiO3·CaCO3·CaSO4·15H2O) requires:
requires: • Source of sulfates or sulphides in soil
• Source of sulfates or sulphides in • Water in motion
soil • Source of C3S / C2S, present in cement
• Water in motion • Presence of carbonates
• Ca (OH)2 and C3A in cement • Low temperatures (usually <15oC)
• pH> 10 • pH> 10.5
dw2018 | 184
REQUIREMENTS FOR CONCRETES EXPOSED TO
SOLUTIONS CONTAINING SULPHATES
(Brazilian Standard NBR 12655)
dw2018 | 185
GENERATION OF ETTRINGITE BY THE ACTION OF INTERNAL
SULFATES (ASI)
ASI - ISA - RSI
• Aggregates containing iron sulphides (pyrite,
pyrrhotite, etc.)
• Humidity + oxygen = oxidation and formation of
sulfates, iron oxides and hydroxides as well as sulfuric
acid
• Formation of ettringite and gypsum
• Volume of materials formed> original volume
dw2018 | 186
GENERATION OF ETTRINGITE BY THE ACTION OF
INTERNAL SULFATES (ASI)
DEF
• T> 65C - monosulfate formed and few ettringite
• After curing and hardening - sulphates and aluminates form
ettringite
• In the presence of humidity it can be expansive
• SO3/ Al2O3 ratio > 0,5;
• SO3 > 2,6% and C3A between 7% and 11%.
• Wetting and drying;
• Alkalies content > 3kg/m3 help more the formation of DEF.
dw2018 | 187
FACTORS INVOLVING DEF
Humid
ambient
Type of cement
Temperature
dw2018 | 188
GENERAL SCHEME PROPOSED FOR THE MECHANISM OF DEGRADATION
DUE TO LATE ETTRINGITE – (BRUNETAUD, 2005).
dw2018 | 189
PREVENTION AND MITIGATION OF DEF
• Reduce concrete temperatures:
• Decrease cement content
• Decrease fck (concrete strength)
• Use admixtures to reduce cement content
• Cool the concrete
• Limit Tmax to 65°C
• Limiting contact with water (waterproofing needs to be redone,
periodically!) = Not a definitive solution
dw2018 | 190
DEF - DELAYED ETTRINGITE FORMATION
DEF
• 1987/1989 - Attention to cases in precast elements subjected to thermal curing
(Germany and Finland)
• 1991 - Former Czechoslovakia
• 1992 - Australia and South Africa
• 1995 - USA
• 1997 – Beginning of a massive problem in France at massive parts of bridges
cast in place (pillars, beams, foundation blocks, etc.)
• 2000 -Problem requires attention worldwide
• 2004 - Sweden
• 2008 - France - 30 bridges affected by DEF, without AAR. Time for discovery =
5 to 10 years after construction
• 2008 - Portugal - Fagilde, Pracana, Fratel dams
• 2010 to 2018- Brazil
dw2018 | 191
DEF – FAGILDE DAM (PORTUGAL)
dw2018 | 192
CASES OF DEF IN RAILWAY SLEEPERS
(PORTUGAL, apud Santos Silva, and SWEDEN)
PORTUGAL
•Production = 1996
•Discovery = 2003
•Cracks opening ~ 4mm
•T ~ 70°C to 80°C (steam curing + summer)
•Cement content~ 440 kg/m³
•Soluble alkalies = 3kg/m³
•Reactive aggregates but almost imperceptible ASR
•Conclusion of tests = DEF SWEDEN
• Cement content = 470kg/m3
•T~60ºC
•SO3/Al2O3 = 0,84
•Production = early 1990
dw2018 | 193
CASES OF DEF IN BRAZIL
dw2018 | 194
CASES OF DEF+AAR IN BRAZIL – Dam built 1970
Trunnion
dw2018 | 195
DEF CONSEQUENCES
• Increasing cracking
• E Reduction
• Loss of resistance
• Destruction of cement paste
dw2018 | 196
Leaching
• Leaching is the name of the whole process of dissolving and transporting substances
out of the concrete
• When solid material is leached, the porosity will increase and the amount of OH" -ions
will decrease in the pore solution and in the pore walls. When the porosity increases,
the water permeability will increase and the leaching process will accelerate. When
the porosity increases, the strength will also decrease. When the permeability in
different parts of a concrete dam changes, internal pore pressure will also change in
the same way. The decreasing strength but also a changed pore pressure may lower
the stability for parts of or for the whole dam
• When coming out from the surface, the leached Ca(OH)2 reacts with CO2 in the air
and a hard calcite-Iayer is formed (CaCO3)
• However , this may not always be the case.
• Leaching may decrease the strength, increase concrete permeability, increase the
intemal forces in a dam, etc.
dw2018 | 197
Leaching x Strength Loss
When cement and water combine, one of the
compounds formed is hydrated lime, which is
readily dissolved by water (often made more
agressive by the presence of dissolved carbon
dioxide) passing through cracks, along
improperly treated construction planes. or
through interconnected voids. The removal of
this or other solid material by leaching may
seriously impair the quality of concrete.
dw2018 | 198
Leaching x Strength Loss
(USBR-Tests in Hoover dam (was Boulder dam)
Percentage of strength between leached specimens
and normally cured specimens
dw2018 | 199
Is this a problem? Leaking joints
Stalactite
Stalagmite
dw2018 | 200
Leaking construction (lift) joints
• May cause a failure if the joint is unbonded
• Joints that leak are not necessarily totally unbonded
• Check construction records to get a sense for how likely the
joints are to be bonded
• Good joint treatment would include water curing tops of lifts,
waterblasting before next pour, green-cutting laitance, etc.
• Cores must be taken to show the bond between lift joints
• Eventually there may be no cohesion and only friction
• If factors of safety (sliding, overturning, flotation) are lower than
the desirable, remedial actions must be taken
dw2018 | 201
Leakage in RCC dams
(apud Schrader)
dw2018 | 202
Rio Jordão Dam
(apud. Santi, M.R.A – MSc Thesis – 2008)
Water level
Loss of ionic mass
Water level
Loss of mass (kg/month)
Flow (l/min)
dw2018 | 204
LEAKAGE / INFILTRATIONS
Saco de Nova Olinda Dam - PE
dw2018 | 205
LEAKAGE / INFILTRATIONS
Saco de Nova Olinda Dam - PE
dw2018 | 206
PLATANOVRISSYI
dw2018 | 207
PLATANOVRISSYI
dw2018 | 208
PLATANOVRISSYI
dw2018 | 209
UPLIFT
Example: Capivara HPP (Brazil)
dw2018 | 210
Case of Capivara HPP
• Technical assumption during the
design: null uplift values at the
foundation on the upstream
extremity of the power house
block;
• Lack of monitoring instruments and
drainage system at the foundation
of the power house;
dw2018 | 211
Case of Capivara HPP
dw2018 | 212
REPAIR AND RECOVERY
To determine the repair and recovery of dam deterioration, it is
necessary to:
• Project Knowledge
• Knowledge of predicted behavior and alert levels
• Adequate documentation of non-conformities and solutions
adopted
• Evaluation of materials
• Analysis of performance and instrumentation in time
• Complementary tests
dw2018 | 213
FREEZING AND THAWING
dw2018 | 214
CORROSION OF REINFORCEMENT
The deterioration of concrete by corrosion occurs through chemical
reactions that are predominantly of expansion, generating internal
tensile forces and, consequently, cracking or leaching or dissolution
accompanied by washing.
dw2018 | 215
CORROSION OF REINFORCEMENT
dw2018 | 216
CAN AN ALLIGATOR BE A SIGNIFICANT PROBLEM FOR THE DAM ?
dw2018 | 217
THANK YOU FOR YOUR ATTENTION !
Selmo Kuperman
selmo@desek.com.br
(+5511 99175 2583)
dw2018 | 218