Beruflich Dokumente
Kultur Dokumente
wo bridge examples introduce and a constant-depth bridge, respec What makes the SBWM such an at
64 PCI JOURNAL
tion, exterior compression struts are
installed and the deck slab is widened.
Additional transverse internal pre
stressing tendons and longitudinal ex
ternal prestressing tendons are in
stalled and stressed. Widening from
Stage 2 to Stage 3 construction is sim
ilar. The deck slab is again extended
(cantilevered), and additional trans
verse internal prestressing tendons and
longitudinal external prestressing ten
dons are installed and stressed.
The structural system varies depend
ing on whether the bridge is variable
depth or constant depth. A variable-
SECTION AT MIDSPAN
depth bridge (Fig. 1) has all compres
sion struts at the same distance from STAGE 1 — 2 LANES IN YEAR 2003
and the same angle to the deck surface.
This means that interior compression 17500
depth may be governed by the com 450 I 3000 3700 3700 3700 3700 3000 I 450
span-to-depth ratios.
Although strutted boxes have been
widely used in the past as solutions for
both segmental bridges and cable-
stayed bridges, this represents the first
7 C
C
C
C
time (to the author’s knowledge) that C
November-December 2003 65
The two bridge examples in this
paper were designed for live load ac 13800
I I
cording to the Canadian Code 3 be
’
2
cause they are similar to the North
450
[J 2500
SHOULDER
, 3700
LANE
3700
LANE
3000
SHOULDER
450
E
River Bridge was for the steel alter
nate, representatives of Kiewit indi
cated to the author that their bid prices
for the concrete and steel alternates
324 D STEE
COMPRESSION STRUT I
were very close. This is especially en SECTION AT MIDSPAN I SECTION AT PIER
couraging because the owner re STAGE 2 — 3 LANES IN YEAR 2020
quested that the bids be based solely
on the initial cost, and not the widen I- 21700
ing costs or the life-cycle costs. 450 I 3000 3700 3700 i 3700 3700 3000 i I 450
LANE LANE LANE LANE SHOULDER
Clearly, if the concrete alternate can SHOULDER
66 PCI JOURNAL
SECTION AT MIDSPAN SECTION AT PIER
Fig. 4. The top slab thickness for slab thickness for Stage 2 is constant m (29.5 in.) at the pier. The midspan
Stage 1 varies from 0.250 m (9.8 in.) at 0.225 m (8.9 in.), while the top slab bottom slab thickness and fillet width
at the center of the box to 0.500 m thickness for Stage 3 varies paraboli and thickness dimensions are those re
(19.7 in.) at the web and 0.225 m (8.9 cally from 0.300 to 0.200 m (11.8 to quired to accommodate the bottom
in.) at the end of the cantilever. The 7.9 in.). span tendons. The pier bottom slab
fillet width and thickness dimensions The soffit width is 9.0 m (29.5 ft). thickness is that required to resist the
shown are those required to accommo The bottom slab thickness varies from maximum compression during bal
date the cantilever tendons. The top 0.250 m (9.8 in.) at midspan to 0.750 anced cantilever construction (which
November-December 2003 67
II I I I
iIIIII
LLLLUJJIJLII
8 x 25—150 I
I I
68 PCI JOURNAL
Bending Moment Diagrams for Stage 2 (widening from 2 lanes to 3 lanes)
E
z
C SDL
a)
S LL+
0
LL
C)
C
C
6)
X Distance (m)
90
60
E
z 30
a) SDL
E 0 LL+
0
LL
C) -- —-PT
-30
a)
-60
-90
60 120 180 240 300 360
Fig. 8. Bending
X Distance (m)
moment diagrams
(Example 1).
the Stages 2 and 3 widenings are prestressing so that there is a reserve Table 1 gives a comparison of the
shown in Fig. 8. Individual moment of compression everywhere. live load, including the number of traf
diagrams due to dead load, superim The stress diagrams for the Stages 2 fic lanes and the reduction in live load
posed dead load, positive live load, and 3 widenings are shown in Fig. 9. intensity as provided by the Canadian
negative live load, and prestressing are The stresses at the top and bottom of 3 and two AASHTO Specifica
’
2
Code
plotted. In proportioning the prestress the section are shown. Note that the 5 According to the Canadian
’
4
tions.
ing, a good first step is to load-balance reserve of compression varies from Code, the bridge has to be designed
the dead load moment and allow the approximately 0 to 2.4 MPa (0 to 348 for three, four, and six lanes with re
axial compression to offset the super psi) for most of the bridge, except near duction factors of 0.80, 0.70, and 0.55,
imposed dead load and live load mo the ends, where the reserve reaches 5 respectively. The AASHTO Standard
ments Example 2 discusses an alter MPa (725 psi) at the bottom and a and AASHTO LRFD Specifications
nate method of proportioning the very small tension at the top. require the bridge to be designed for
November-December 2003 69
Stress Diagrams for Stage 2 (widening from 2 lanes to 3 lanes)
Co
0
CO
CO
8)
Cl)
X Distance (m)
1.0
0.0
-1.0
CO
- -f top
-2.0
Cl)
bot
a)
C,)
-3.0
-4.0
-5.0
60 120 180 240 300 360
Fig. 9. Stress
X Distance (m)
diagrams
(Example 1).
three, four, and five lanes; the reduc cent according to the Canadian Code LRFD Specifications are considered,
tion factors given by the AASHTO and 11.1 percent according to the the results are even better at 2.0 and
Standard Specifications are 0.90, 0.75, AASHTO Standard Specifications to 27.5 percent. In all cases, this repre
and 0.75, while those given by the achieve a 50 percent increase in traffic sents a very good return (in traffic ca
AASHTO LRFD Specifications are capacity. When widening from two to pacity) over investment (in structural
0.85, 0.65, and 0.65. four lanes (Stages 2 and 3 combined), capacity).
What is of interest here is the in the increase in live load is 37.5 per Table 2 gives a load summary com
crease in live load (as a percentage) cent according to the Canadian Code parison when widening from two to
for each code when going from Stage and 38.9 percent according to the three lanes (Stage 2). The loads, mo
1 to Stage 2 and Stage 3. When widen AASHTO Standard Specifications to ments, and shears are given for the ini
ing from two to three lanes (Stage 2), achieve a 100 percent increase in traf tial two-lane bridge, the one-lane
the increase in live load is 16.7 per- fic capacity. When the AASHTO widening, and the resulting three-lane
70 PCI JOURNAL
bridge. The increase is expressed as a Table 1. Live load comparison.
percentage of the one-lane widening Construction Live load Increase
over the two-lane bridge. Note that the stage (lanes) (percent)
dead load of 391.15 kN/m (26.8 k/ft) Canadian Code
23 -.
variable-depth bridge. Looking at indi Stage 2 4 x 0.70 = 2.80 0.40/2.40 = 16.7 percent
vidual components, the dead load in Stage 3 6x0.55=330 0.90/2.40 = 37.5 percent -
4x035=30O O=II.lpercent
7
.
2
O3O/
16.7 percent. Although the live load Stage 3 5 x 0.75 = 3.75 1.05/2.70 = 38.9 percent
increase is 16.7 percent, the traffic ca AASHTO LRFD Specifications
5
pacity increase is 50 percent, or three Stagel 3x0.85=2.55 —
times this value. Since the live load is Stage 2 4 x 0.65 = 2.60 0.05/2.55 = 2.0 percent
a small fraction of the dead load, the Stage 3 5 x 0.65 = 3.25 0.70/2.55 = 27.5 percent
required increase in superstructure
moment and shear capacity varies
from 8.6 to 10.0 percent, while the two-lane bridge, the two-lane widen cent, and the live load increase is 37.5
traffic capacity increase is 50 percent, ing, and the resulting four-lane bridge. percent. In this table, the required in
or five times this value. Again, the increase is expressed as a crease in superstructure moment and
Also given in Table 2 are a load percentage of the two-lane widening shear capacity varies from 17.1 to 20.2
summary comparison when widening over the two-lane bridge. Looking at percent, while the traffic capacity in
from two to four lanes (Stages 2 and 3 individual components, the dead load crease is 100 percent, or five times
combined). Here, the loads, moments, increase is 12.7 percent, the superim this value.
and shears are given for the initial posed dead load increase is 27.9 per- The SBWM is a very effective solu
November-December 2003 71
Fig. 10. Bridge elevation (Example 2).
tion in this example, because for an steel pipes with end plates that frame loads). The web thickness is 0.450 m
additional investment of 10 or 20 per into concrete buildouts (blisters) and (17.7 in.).
cent in superstructure moment and transfer the load directly to the bottom The segment layout and strut loca
shear capacity, the respective return is slab from triangular shaped exterior tions are shown in Fig. 12. Each bal
50 or 100 percent in traffic capacity. longitudinal T-beams at the deck anced cantilever has a 1.8 m (5.9 ft)
level. The top slab thickness for Stage pier segment and eight 3.6 m (11.8 ft)
1 varies from 0.250 m (9.8 in.) at the typical segments on each side of the
EXAMPLE 2 center of the box to 0.500 m (19.7 in.) cantilever. Closure segments are 0.6 m
Consider a six-span constant-depth at the web and 0.225 m (8.9 in.) at the (2.0 ft). The end spans have a 1.5 m
precast segmental bridge built by the end of the cantilever. The top slab (4.9 ft) abutment segment and three
balanced cantilever method of con thickness for Stage 2 is constant at 3.6 m (11.8 ft) typical segments which
struction (see Fig. 10). The interior 0.225 m (8.9 in.), while the top slab are assembled on falsework. The con
spans are 60 m (196.9 ft), while the thickness for Stage 3 varies paraboli struction sequence proceeds from one
exterior spans are 42 m (137.8 ft), giv cally from 0.300 to 0.200 m (11.8 to end of the bridge to the other, building
ing an overall length of bridge of 324 7.9 in.). cantilevers P1 to P5 in succession, and
m (1063.0 ft). The depth of the section The soffit width is 8.0 m (26.2 ft). pouring closures in the backspan as
(see Fig. 2) is 3.2 m (10.5 ft), which The bottom slab thickness varies from construction proceeds. At the comple
gives a span-to-depth ratio of 18.8 and 0.200 m (7,9 in.) at midspan to 0.400 tion of construction, the bridge super
a strut angle of 33 degrees. The sec m (15.7 in.) at the pier. The midspan structure sits on fixed bearings at P3
tion depth is governed by the com bottom slab thickness is a minimum and expansion bearings everywhere
pression strut geometry rather than the value, while the pier bottom slab else (see Fig. 10). Note that the strut
span-to-depth ratio in this example. thickness is that required to accommo locations are always 2.1 m (6.9 ft)
The cross section dimensions and date the maximum compression dur away from the edge of the segment.
compression strut details are given in ing balanced cantilever construction This simplifies the casting cell opera
Fig. 11. The compression struts con (which is greater than the maximum tions since the strut locations are al
sist of 0.3 24 m (12.8 in.) diameter compression due to the Stage 3 service ways at the same location in the cast-
72 PCI JOURNAL
42000 60000 60000
10800 8 AT 3600 28800 8 AT 3600 = 28800 8 AT 3600 = 28800 8 AT 3600 = 28800 8 AT 3600 = 28800
_99p 600 900 900 600 900 900 600 900
H.l.I.i.lJ.LLLLLIlI.Ll.I.LlJJI.l.Ll
--
€ ()
T 8 AT 3600 = 28800
60000
8 AT 3600 28800
TH 8 AT 3600 28800
60000
8 AT 3600 28800
T 8 AT 3600
42000
= = = = 28800 II 10800
600 600 600
II.I.l.l.I.lI.i.I.l.I.I.I.l.II.I.l.l.p l.l.lIlLLIILIIILIIIIIIlIIIII[
c1
llIIIIIIIIIIIllI
IIIIlIlIIlIIIIlI
November-December 2003 73
Bending Moment Diagrams for Stage 2 (widening from 2 lanes to 3 lanes)
12
z 4
C SDL
Ii)
E 0 H--—- LL+
0 H --
0)
L—PT I
C
C -4
a)
£0
-8
-12
54 108 162 216 270 324
X Distance (m)
E
z
C SDL
8)
E
0
0)
C
-D
C
a)
£0
shows the disposition of all prestress the Stage 2 and 3 widenings are shown of various analyses in a spreadsheet,
ing tendons in the bulkhead. There are in Fig. 15. Individual moment dia which is linked to an interactive
14 cantilever tendons per web near the grams due to dead load, superimposed graphical plot of the stresses (Fig. 16).
pier and six bottom span tendons per dead load, positive live load, negative The results of the dead load, superim
web near midspan, which are an live load, and prestressing are plotted. posed dead load, and live load analy
chored in the anchor blocks. The The stress diagrams for the Stage 2 6 in
ses (as well as thermal analyses,
draped external tendons are at the bot and 3 widenings are shown in Fig. 16. cluding positive thermal gradient,
tom of the section near midspan and at The stresses at the top and bottom of negative thermal gradient, temperature
the top of the section near the pier. Fi the section are shown. Note that the rise, and temperature fall) are im
nally, there is provision for future con reserve of compression varies from ported into the spreadsheet, along with
tingency tendons. Again, an open cel approximately 0 to 0.6 MPa (0 to 87 unit load cases of draped prestressing
lular abutment and interior lighting are psi). in the exterior spans and the interior
recommended. The prestressing has been propor spans. In this way, multipliers for the
The bending moment diagrams for tioned here by combining the results exterior span prestressing and interior
74 PCI JOURNAL
Stress Diagrams for Stage 2 (widening from 2 lanes to 3 lanes)
1.2
0.6-
00
Co
0
--
flop.
Co
ci)
U,
-1.2 -
-1.8
X Distance (m)
1.2
0.6 —
0.0
CU
0
-. -.
-0.6
10
11)
(1)
-1.2
-1.8
-2.4
0 54 108 162 216 270 324
Fig. 16. Stress
X Distance (m) diagrams
(Example 2).
span prestressing are adjusted to im it was only 6.8 percent in Example 1. shear capacity varies from 13.6 to 13.9
mediately see the effect on the This makes sense because the overall percent in Example 2, whereas it
stresses. The optimum amount of pre dead load is smaller for a bridge hav varies from 8.6 to 10.0 percent in Ex
stressing is proportioned to have a re ing shorter spans, meaning that the ample 1. When widening from two to
serve of compression everywhere at percentage increase of the widened four lanes, the required increase in Su
the top and bottom of the section bridge is larger. The superimposed perstructure moment and shear capac
while using the least amount of pre dead load increase and the live load ity varies from 27.1 to 28.1 percent in
stressing. increase are the same in both exam Example 2, whereas it varies from
It is interesting to compare the ples at 13.0 and 16.7 percent, respec 17.1 to 20.2 percent in Example 1.
loads, moments, and shears in Exam tively. Again, this makes sense be To summarize, Examples 1 and 2
ple 2 (Table 3) with those in Example cause the superimposed dead load and require an increase in superstructure
1 (Table 2). When widening from two live load are the same in both exam moment and shear capacity of 10 and
to three lanes, the dead load increase ples. The net effect is that the required 14 percent, respectively, to achieve a
is 13.1 percent in Example 2, whereas increase in superstructure moment and 50 percent increase in traffic capacity
November-December 2003 75
Table 3. Load summary comparison for Example 2.
Widen from two to three lanes (Stage 2) Widen from two to four lanes (Stages 2 and 3 combined)
Two-lane One-lane Three-lane Increase Two-lane Two-lane Four-lane Increase
bridge widening bridge (percent) bridge widening bridge (percent)
DL (kN/m) 202.030 26.450 228.480 13.1 percent 202.030 49.508 25 1.538 24.5 percent
Loads SDL (kNIm) 56.142 7.326 63.468 13.0 percent 56. 142 15.642 7 1.784 27.9 percent
LL (lanes) 3 x 0.81) = 2.40 0.40 4x0.70=2.80 16.7 percent 3x0.80=2.40 0.90 6 x 0.55 = 3.30 37.5 percent
Moment, DL 32921 4310 37.23 1 32.921 8.067 40.988
Span 2 SDL 9.148 . 1.194 10.342 9.148 2.549 11.697
(MN-rn) LL 10754 1.792 12.547 10.754 4.033 14.787
Total 52.823 7.296 60.119 13.8 percent 52:823 4
j 4.649 67.472 27.7 percent
Moment, DL —62.672 —8.205 —70. 877 —62.672 —15.358 —78.030
Pier 2 SDL —17416 —2.273 —19.688 —17.4 16 —4.852 —22.268
(MN-m) LL —15.434 —2.572 —18.007 —15.434 —5.788 —21.222
Total —95.522 —13.050 —108.572 13.7 percent —95.522 —25.998 —12 1.520 27.2 percent
Moment. DL 29.795 3.90) 33.696 29.795 7.301 37.097
Span 3 SDL • 8.280 1.080 3(1 8.28)) 2.307 1(1.587
(MN-in) LL 11.369 1.895 13.264 11.369 4.263 15.632
Total 49.444 6.876 56.320 13.9 percent 13.872 63.3)5 28. I percent
-
(or 20 and 28 percent, respectively, to construction activities. The use of over the webs on Hilman rollers,
achieve a 100 percent increase in traf moveable knee-braced formwork at which are locked during the concrete
fic capacity). The required increase in tached to the web and cantilever will pour, and then freed to allow the truss
superstructure moment and shear ca allow the exterior compression struts to advance. A staggered pouring se
pacity is smaller for longer span to be installed, the concrete deck to be quence is used in the same way as that
bridges than for shorter span bridges. formed and poured, and the transverse for the deck pour of a composite steel
The SBWM solution works very well prestressing tendons to be installed girder bridge.
in both examples. and stressed.
If traffic is not allowed on the
bridge during widening, construction DESIGN CONSIDERATIONS
CONSTRUCTION will proceed much more rapidly, but
CONSIDERATIONS the traffic will have to be detoured. Longitudinal Flexure
One of the fundamental decisions The erection truss shown in Fig. 17 The bridge has to be designed for
that has to be made during a bridge can be used to widen the bridge di three stages of construction. By keep
widening project is whether to allow rectly from two to four lanes (or from ing the design for each stage of con
traffic on the bridge during construc two to three lanes or from three to struction independent as outlined
tion. This issue also comes into play four lanes as described previously). below, the additional design work is
when widening the bridge by the The truss facilitates the installation of not substantial.
SBWM. the exterior compression struts. It has Stage 1 requires the traditional de
If traffic is allowed on the bridge suspended forms at the ends for the sign of a segmental bridge where the
during widening, detours will not be Stage 2 and Stage 3 concrete deck construction sequence and the time-
required, but construction will proceed pours. The ends of the truss have dependent effects of creep, shrinkage,
more slowly since it will occur adja safety rails as well as extra room for and relaxation are considered. Pre
cent to traffic. Barriers will be re installing and stressing the transverse stressing is proportioned to facilitate
quired to separate the traffic from the prestressing tendons. The truss bears segmental construction and to accom
76 PCI JOURNAL
Fig. 17. Erection truss for bridge widening.
modate the redistribution of stresses. Longitudinal Shear and Torsion to a 0.25 x 0.25 m (0.8 x 0.8 ft) mesh
There should be a reserve of compres size at the location of concentrated
The webs have to be designed for
sion at the top and bottom of the sec loads is also worthwhile).
shear due to dead load, superimposed
tion at all locations under the effects Plane Frame Model A 5.0 m
dead load, and live load, as well as for —
of all service loads, both at the initial (16.4 ft) unit length of the cross sec
torsion due to eccentric live load and
opening of the bridge and after final tion is modeled for each of the three
overturning wind. Stage 3 is the con
long-term losses have occurred. stages of construction. By having the
trolling case in the design for shear
Stage 2 requires the design for the unit length of the cross section corre
and torsion. It is important that the
incremental loads of Stage 2, and can spond to the spacing of compression
Resal effect be considered in the de
be designed elastically because it oc struts, the model can be run both with
sign. (Note that the Resal effect,
curs so far in the future that the time- and without compression struts to
which is explained in books on seg
dependent effects of Stage 1 have little study the enveloping cases. A number
mental box girder design, relates to the
or no effect. Thus, the Stage 2 incre of different depths of cross section
reduction in shear force by the vertical
mental loads and the Stage 2 section with different locations of compres
component of the inclined compres
properties are applied to an elastic sion struts needs to be considered. The
sion flange.) The webs also have to be
analysis of the completed bridge to effects of concentrated wheel loads are
designed for web bending (as dis
allow the prestressing to be propor determined by using influence sur
cussed in the next section). Of course,
tioned so as to have a reserve of com faces as usual.
the top and bottom slabs also have to
pression at the top and bottom of the The individual elements are de
be designed for torsion.
section at all locations. signed based on the results of the finite
Design for shear and torsion can be
Stage 3 requires the design for the element analyses and the plane frame
performed by the traditional approach
incremental loads of Stage 3 and can analyses. These elements include the
or by the strut-and-tie method. It is
be designed in a similar manner to longitudinal beams, the compression
also desirable that the principal
Stage 2. struts, the web reinforcement, and the
stresses be checked to ensure that
Validation of the final design re top slab transverse prestressing.
cracking of the webs does not occur.
quires analysis for all three stages of Longitudinal Beams — The two
construction in a 2D (or even a 3D) triangular-shaped exterior longitudinal
time-dependent computer program Transverse Design T-beams and one rectangular-shaped
with the assumed dates of construction The transverse analysis for Example interior longitudinal T-beam take the
(the assumed dates will need to be re 1 is facilitated by the creation of two load from the deck and transfer it
placed by the actual dates in the analy computer models: through the compression struts to the
sis when widening occurs). There Finite Element Model — One-half web. The longitudinal beams thus re
should be a reserve of compression at of the interior span is modeled for duce the deck spans in the transverse
the top and bottom of the section at all Stage 3 construction. The model in direction, which reduces the overall
locations at any time during the life cludes plate elements for the top slab, amount of prestressing and reinforce
time of the bridge. webs, and bottom slab, along with off ment in the deck. The longitudinal
It is also necessary to check the ulti set beam elements with rigid links for beams are reinforced with flexural and
mate strength design for all three the longitudinal beams and beam ele shear reinforcement.
stages of construction. The ultimate ments for the compression struts. The Compression Struts — The com
strength at Stage 3 is provided by the appropriate end boundary conditions pression struts can consist of either
internal tendons of Stage 1 along with are applied. It has been found that a 324 mm (12.8 in.) diameter steel pipes
the external tendons of Stage 2 and 1.0 x 1.0 m (3.3 x 3.3 ft) mesh size is (as described previously) having a
Stage 3. reasonable (although local refinement wall thickness of 13 mm (0.5 in.), or
November-December 2003 77
C
0)
II
I —
II
C C
I —
I —
I —
ZL__________
(I) (1) U)
C 0 0
o SEGMENT PLAN
U) U) U)
tendon details.
400 x 400mm (15.7 x 15.7 in.) precast angular-shaped interior longitudinal T and bundled with the shear and torsion
concrete elements. They are designed beam and the right web. Influence bars which are also spaced at 150 mm
for the axial forces given by the analy lines have been found to be very use (5.9 in.). The web bending bars are
ses along with the corresponding shear ful in positioning live loads so as to thus placed 900 mm (3.0 ft) on either
forces and bending moments. produce the maximum effects. side of the strut. No additional outer
Web Reinforcement — The web The finite element analyses have face web bending reinforcement is re
reinforcement is designed for longitu shown that the maximum web bending quired for this example.
dinal shear and torsion (as previously occurs at the location of the strut, and Top Slab Transverse Prestressing
described) in addition to web bending. dies out very quickly at any longitudi — Fig. 18 shows the transverse pre
Web bending is due to the unbalanced nal distance away from the strut. It is, stressing tendon layout in plan and
live load being transmitted through the thus, recommended that additional section for the three stages of con
compression struts to the webs. The web bending reinforcement be banded struction. Each tendon consists of four
maximum inner face web bending in locally on either side of the strut in ad strands in a flat duct. There are twelve
the right web occurs when live loads dition to the shear and torsion rein transverse prestressing tendons in each
are placed on both cantilevers, forcement. For this example, this segment. Three tendons are stressed in
whereas the maximum outer face web means that inner face web bending re Stage 1, three in Stage 2, and six in
bending in the right web occurs when quires an additional 13 No. 15M rein Stage 3. The tendon profile is at the
the live loads are placed on the right forcing bars (13 No. 5 bars) at 150 top of the deck near the web for nega
cantilever as well as between the rect mm (5.9 in.) centered about the strut tive moment, and in the middle of the
78 PCI JOURNAL
deck near midspan for both positive
and negative moment. The stresses
and ultimate strength are checked at
the critical locations for all three
stages of construction.
Another prestressing scheme to con
sider is banding the transverse tendons
in plan near the locations of the com
pression struts. In this way, there will
be more transverse tendons near the
compression struts and fewer transverse
tendons away from the compression
struts. This will allow the transverse
prestressing to more closely follow the
results of the finite element analyses.
The transverse prestressing ducts for STAGE 1 — 2 LANES IN YEAR 2003
the Stages 2 and 3 widenings need to
be installed during Stages 1 and 2 con
struction. These plastic ducts need to
be protected against moisture intrusion,
which can lead to freezing and crack
ing of the deck concrete. One sugges
tion is to fill the ducts with grease or
foam and cap the ends. The grease or
foam would be flushed out when
widening occurs. Another suggestion is
to place continuous foam backer rod in
the empty ducts for the entire length of
each tendon and cap the ends. Freezing
water would simply compress the
backer rod and not crack the concrete.
The backer rod would be removed STAGE 2 — 3 LANES IN YEAR 2020
when widening occurs. At any rate,
protection of ducts for the Stages 2 and
3 widenings is very important for the
durability of the structure.
Shear Lag
The AASHTO Segmental Guide
Specifications state that the effective
7
flange width may be determined (1)
by elastic procedures such as the finite
element method, (2) by provisions
given in the Ontario Highway Bridge
Design Code,
8 or (3) by provisions
given in the AASHTO Segmental
Guide Specifications.
STAGE 3 4 LANES IN YEAR 2060
The overall efficiency of the cross
—
November-December 2003 79
drain pipes dump water into an open sense because financing becomes so given here, the additional shear capac
hopper collector pipe. In widening important. Why not pay for easily ex ity required in Stage 1 varies from
from Stages 1 to 3, the size of the panding the capacity of a design-build 18.3 percent for the variable-depth
scuppers and drain pipes increases. bridge when it is required in 20 or 60 bridge having 160 m (525.0 ft) spans
since the volume of water to be years rather than today? (Table 2) to 27.4 percent for the con
drained increases as the deck area in 4. Reduced incremental cost and stant-depth bridge having 60 m (196.9
creases. The Stages I and 2 scuppers schedule — Widening existing bridges ft) spans (Table 3). In the best-case
are abandoned in place by removing to double the traffic capacity is better scenario, the web thickness required
the grating and carefully concreting than building new bridges because the for Stage I and Stage 3 would be the
the remainder of the scupper. construction cost and schedule are same, meaning that only additional
Fig. 19 also shows that the barrier greatly reduced. shear reinforcement would be re
curbs have to be relocated for each 5. Reduced prestressing for can quired. In the worst-case scenario, a
stage of construction. It is suggested tilever construction The amount of larger web thickness is required for
that stainless steel dowels be used to cantilever prestressing required for Stage 3 than for Stage 1, meaning that
attach the barrier curbs to the deck. balanced cantilever construction is re the additional concrete required for the
The dowels can be cut flush with the duced, since a two-lane wide deck is web would have to be supported by
deck at the time of widening, and cantilevered rather than a four-lane additional shear reinforcing and longi
there will not be any corrodable rein wide deck. In other words, a 13.5 m tudinal prestressing. This additional
forcement near the deck surface. (44.3 ft) deck is cantilevered rather concrete, reinforcement, and prestress
than a 21.4 m (70.2 ft) deck. ing is wasted if widening to Stage 3
6. Potential to satisfy FHWA perfor never occurs. [Note that in Example 2,
ADVANTAGES AND When used in the vertical component of the pre
mance objectives —
DISADVANTAGES conjunction with high performance stressing counteracts the demand for
The SBWM is a valid bridge solu concrete, the SBWM has the potential an increased web thickness, while in
tion that has a wide range of applica to satisfy all ten of the FHWA perfor Example 1, an increased web thick
tions, and it should be considered dur 9 for “The Bridge of
mance objectives ness is provided — i.e., 450 versus
ing the planning stages for any project. the Future.” It readily satisfies the re 500 mm (17.7 versus 19.7 in.).]
Consideration requires the careful quirement “easily widened or adapt 4. Provision for future prestressing
evaluation of both its advantages and able to new demands,” and Reference — Although the strands and anchor
disadvantages, and an evaluation of 10 discusses how it can be applied to ages for the transverse internal ten
the possible widening needs of the satisfy other FHWA performance ob dons and longitudinal external ten
bridge in the future. jectives. dons are installed and stressed in
The advantages of the SBWM in Some of the potential disadvantages Stage 2 and Stage 3 as they are re
clude the following: of the method include the following: quired, provision for this future pre
1. Flexibility in widening — The 1. Increased design effort — The stressing has to made in Stage 1. This
final configuration of the bridge at the designer has to design for three stages means that ducts for transverse ten
conclusion of its useful life can be of construction. By keeping the design dons have to be installed and pro
two, three, or four lanes. for each stage of construction indepen tected. This also means that blisters
2. Structurally efficient solution — dent, however, the additional amount for longitudinal tendon deviation and
Examples 1 and 2 demonstrate that an of design work is not substantial. anchorage (as well as all anchorage
increase in superstructure moment and 2. Greater substructure capacity — zone reinforcement) have to be pro
shear capacity of 10 and 14 percent, The foundations and piers have to be vided in Stage 1.
respectively, gives a 50 percent in designed to support the Stage 3 ser 5. Possible need to close bridge dur
crease in traffic capacity (or 20 and 28 vice loads. Balanced cantilever con ing widening — If the erection truss
percent, respectively, gives a 100 per struction requires increased substruc described in this paper is used, the
cent increase in traffic capacity). ture capacity for unbalanced moments, bridge will have to be closed during
3. Low initial cost — With respect so there already is adequate load ca widening. If moveable formwork at
to traditional bid projects, this solution pacity for the Stage 3 service loads tached to the web and cantilever is
will appeal to government agencies (i.e., Examples 1 and 2). Span-by-span used, however, the bridge may not
who are under increasing pressure to construction (and other methods) nor need to be closed.
make their construction budgets go mally require additional substructure
further. This will make sense to tax capacity in Stage 1 to support the
TWO POTENTIAL
payers who will not question why a Stage 3 service loads.
four-lane bridge has been built when 3. Greater shear capacity The APPLICATIONS
hardly enough traffic exists for a two- shear reinforcement has to be provided Two potential applications of the
lane bridge. With regard to design- in Stage 1 to support the Stage 3 ser SBWM are particularly appealing —
build projects, this especially makes vice loads. For the two examples namely, for major long-span river
80 PCI JOURNAL
crossings and for long median-based tively small substructure footprint in ACKNOWLEDGMENTS
expressways. the median.
Suppose that a major long-span river The author would like to express his
crossing needs to be designed and con gratitude to Stantec Consulting and
structed. Present traffic estimates are CONCLUDING REMARKS Alberta Transportation for allowing
that the bridge requires only one lane The strutted box widening method him to design the three-span concrete
in each direction (Stage 1). It will take (SBWM) introduced in this paper al alternate for the North Saskatchewan
a significant budget and construction lows a two-lane segmental bridge to River Bridge in Edmonton, Canada,
effort to build this bridge. The owner be designed and constructed so that it using the strutted box widening
can construct this bridge to have the can be easily widened into a three-lane method, as an independent consultant
lowest initial cost, or can spend or four-lane bridge at any time in the to Stantec Consulting. The author
slightly more to allow the bridge to be future. This is an attractive solution would like to thank Les Hempsey, Reg
widened in the future to have two since widening only needs to be done Quinton, Bill van der Meer, and Ray
lanes in each direction (Stage 3). when and if traffic volumes warrant it. mond Yu of Alberta Transportation,
Long portions of elevated median The author believes that the strutted along with Carl Clayton of Stantec
based expressways can be constructed box widening method should be given Consulting and Ken Rebel, formerly
in congested urban environments serious consideration by government of Earth Tech, for their interest and
where right-of-way acquisition is pro agencies and design-build consortia support. The author would like to
hibitive. The elevated structure can be starting at the planning stage on any thank his colleague Christophe Deni
constructed and widened in the future, project. It is an excellent solution for aud of Stantec Consulting, who did the
as discussed in this paper, or it can be building an economic and efficient bulk of the analysis on the North
constructed directly to its ultimate bridge to handle current traffic vol Saskatchewan River Bridge.
configuration (three or four lanes). umes, while at the same time planning The author also wishes to express
The SBWM allows a very wide ele ahead to build cost-effective and his appreciation to the PCI JOURNAL
vated superstructure [21.7 m (71.2 ft)] schedule-effective bridge widenings to reviewers for their valuable and con
to be constructed while having a rela handle future traffic volumes. structive conunents.
REFERENCES
1. Podolny, W. Jr., and Muller, J. M., Construction and Design of 7. AASHTO, “Guide Specifications for Design and Construction
Prestressed Concrete Segmental Bridges, John Wiley & Sons, of Segmental Concrete Bridges,” Second Edition, American
New York, NY, 1982. Association of State Highway and Transportation Officials,
2. CAN/CSA-S-6, “Design of Highway Bridges,” Canadian Stan Washington, DC, 1999.
dards Association, Toronto, Ontario, Canada, 1988. 8. OHBDC, “Ontario Highway Bridge Design Code,” Third Edi
3. CAN/CSA-S-6, “Canadian Highway Bridge Design Code,” tion, Ontario Ministry of Transportation and Communications,
CSA International, Toronto, Ontario, Canada, 2000. Toronto, Ontario, Canada, 1991.
4. AASHTO, “Standard Specifications for Highway Bridges,” 9. Chase, S. B., “The Bridge of the Future,” HPC Bridge Views,
17th Edition, American Association of State Highway and Issue No. 25, January/February 2003, published jointly by the
Transportation Officials, Washington, DC, 2002. Federal Highway Administration and the National Concrete
5. AASHTO, “AASHTO LRFD Bridge Design Specifications,” Bridge Council.
Second Edition, American Association of State Highway and 10. Shushkewich, K. W., “Design and Construction of Segmental
Transportation Officials, Washington, DC, 1998. Bridges to Accommodate Future Widening Using the Strutted
6. Shushkewich, K. W., “Design of Segmental Bridges for Ther Box Widening Method,” Proceedings of the Third PCIIFHWA
mal Gradient,” PCI JOURNAL, V. 43, No. 4, July-August International Symposium on High Performance Concrete, Or
1998, pp. 120-137. lando, FL, October 19-22, 2003.
November-December 2003 81