Beruflich Dokumente
Kultur Dokumente
ENERGOPROJEKT ENTEL
ENGINEER
CONTRACTOR
Authority
Authority
Date
20.03.2017
CONTENTS
1. INTRODUCTION
2. ACTIVITY
3. TERMINOLOGY
4. SIGNIFICANT HAZARDS IDENTIFIED
5. ROLES & RESPONSIBILITY
6. SEQUENCE OF ACTIVITIES
7. REQUIREMENTS
7.1. PLANS /RECORDS AND JOB INSTRUCTIONS (DOCUMENTATIONS)
7.2. TRAININGS
7.3. ON SITE RISK ASSESSMENT
7.4. PPE (PERSONAL PROTECTIVE EQUIPMENT)
7.5. EQUIPMENT AND TOOLS REQUIRED
7.6. ADDITIONAL REQUIREMENTS
8. EMERGENCY PROCEDURES
9. REFERENCES
10. ATTACHMENTS
Employer: Contractor:
132/11KV GARDEN TOWER
(GRDNTOWR) S/S
1) INTRODUCTION
Purpose of this method statement is to provide safe working practices at work
place in line with the approved Health safety and Environment Plan of Contractor
and Client.
2) ACTIVITY
The following activities are planned
Demarcation of work area and placement of Signage for the movement of men,
material and Mobile Machineries
Excavation of approximately 50 x 60 M area using Mechanical Excavator up to the
Raft formation level as per the approved drawing
Loading and Transportation of Excavated earth to Municipality Designated Dumping
area
Road base layers shall be filled with approved road base fill materials up to bottom of
the blinding as per the specified thickness in approved drawings compaction will be
done using Vibrated Road roller as per the specification
Filled density compaction tests and Plate load tests shall be carrying out as per the
specification
Buried Earth grid trench as per the Earth grid Installation layout drawing
Excavation formation levels for main building and OWT shall be followed in line with
approved structural foundation drawing
This method statement is only for the main building area below raft building and only
approved structural road base materials shall be used by following approved
structural drawing and DEWA Specification.
3) TERMINOLOGY
O/E: Owner / Engineer
PPE: Personal Protective Equipment
HSE: Health safety and Environment
Client / Engineer: Meraas/DEWA
Consultant: ENERGO
Main Contractor: SIEMENS
Civil Sub Contractor: IAS LOOTAH CONTRACTING
RFC : Released for Construction drawing
HAZARDS
Underground Services
Loose soil and excavated Side wall collapse –Men / Material falling into pit /Edge
Protection
Mobile vehicle /Equipment movement related accident
Employer: Contractor:
132/11KV GARDEN TOWER
(GRDNTOWR) S/S
Toolbox talks to be given to the workmen by concerned supervisor about the hazards
and the precautions to be taken.
Plant equipment’s and its operators are should be competent and required valid third
party competency and fitness certificates to perform any activity at site
Work shall be carried out only in full time presentence of main contractor and IAS
lootah’s DEWA / EPA approved Civil engineers and safety officers
Hard Barricading and Signage’s shall be provided wherever required
Worker Area to be cordoned off and activity based warning signs to be displayed.
All Mobile Equipment must have valid test certificate.
Walk ways / Gangways to be kept free.
Use of PPEs like heavy duty hand gloves, safety shoes, and hard hat...
Gate level established at site shall be inspected and verified by independent third
party surveyor agency and certificate shall be submitted.
DEWA ITP Procedures must be followed at site during execution of works
Shoring and dewatering system shall be installed for OWT area and separate Method
Statement shall be prepared and submitted for EPA Approval
SAFETY OFFICER
ENGINEER
SUPERVISOR / FOREMAN
WORKMEN
6) SEQUENCE OF ACTIVITIES
See Annex-1
7) REQUIREMENTS
Safety helmets, safety shoe, goggles, gloves and coverall, Dust Mask
7.5 EQUIPMENTS AND TOOLS REQUIRED
MACHINERY AND SKILLED MANPOWER
See Annex-2
7.6 ADDITIONAL REQUIREMENTS
First aid facilities with trained first aider and fire fighter shall be made available.
8) EMERGENCY AND RESCUE PROCEDURES
IN CASE OF MAJOR INJURIES
IN CASE OF FIRE
Never try to extinguish a fire if you are not a train fire fighter.
Sound the alarm and notify the emergency controller at site.
Report to the designated Assembly point and follow the evacuation procedures
9) REFERENCES
10) ATTACHMENTS
ANNEX-1
SEQUENCE OF ACTIVITIES
Employer: Contractor:
132/11KV GARDEN TOWER
(GRDNTOWR) S/S
Mark the area to be excavated with the presence of Client, Consultant & Main contractor.
The excavation of cutting shall be carried out in accordance with the relevant approved
drawings and to the levels, widths, heights show thereon in respect to approved gate level
The side slopes of cutting & Embankments shall be as per the approved drawing.
While carrying out Deep Excavation at Oil/Water tank area, necessary slopes will be laid.
Also during excavation if we reach water table level, water will be removed locally by approved
dewatering system and shoring will be done if required.
After Completion of the excavation, level it properly & compact the natural soil minimum of
95% MDD compaction requires.
Finish level shall be recorded in accordance to survey practice and jointly check in the
presence of Engineer.
Fill approved Road base materials of 250 cm thickness with required layer of filling as per
the approved drawing. Also, compact the soil surface to obtain minimum of 98% MDD
compaction requires.
After the completion of the Compaction same will be offered for inspection for the consultant
representative.
Excavation side slopes shall be protected from collapse, hard barrication shall be provided
ANNEX-2
Employer: Contractor:
132/11KV GARDEN TOWER
(GRDNTOWR) S/S
EQUIPMENT
Excavator - 1No
Roller - 1No
Shovel - 1No
MANPOWER
Surveyor - 1No
Operator - 3 Nos
Driver -11Nos