Juli, 2019

No Uraian Project Jumlah Titik


8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
34 Assessment Jembatan Bentang 14m Sumatera Selatan PT. MSA (PM: Herman, Lead Surveyor: Pak Pupud )
Observasi visual (PM, Simon) 1
Hammer Test (Zidan, Saeful) 40
Pulse Echo Test (Zidan, Simon) 4
Concrete Coredrill & Crushing Test (Zidan, Simon, Saeful) 6
Carbonation Test (Zidan) 6
Rebar scan Test (Zidan, saeful) 10
Perbaikan kondisi setelah pengujian (Saeful, Simon, Zidan) 1
Borelog, 2 titik @30 m (Subkon) 60

35 Assessment Jembatan Kalimantan Selatan PT. BIB (PM: Tasrim, Lead Surveyor: - )
Pengukuraan lendutan dengan LVDT & Total Station (Dodi, Hendi) 1

35 Assessment WTP PT. AETRA, Pulogadung (PM: ?, Lead Surveyor: ? )


Observasi visual & Infrared (PM) 1
Leveling & Re-measurement (Dodi, Simon) & (Hendi, Adit) 1
Hammer Test (Saeful, Fahmi) 130
UPVT (Zidan, Simon) 39
Concrete Coredrill & Crushing Test (Fahmi, Hendi, Zidan) 3
Carbonation Test (Fahmi, Hendi, Zidan) 39
Chemical Content (Zidan, Simon) 13
Brinell (Zidan, Simon) 26
Rebar scan Test (Dodi, Fahmi) 39
Halfcell (Dodi, Fahmi) 39
Perbaikan kondisi setelah pengujian 1

36 Assessment Bungker RSCM (PM: ?, Lead Surveyor: - )


Observasi visual & Mapping Defect (PM) 1
Pengukuran Verticality (Dodi, Simon) 1
Hammer Test (Fahmi, Saeful) 30
UPVT (Fahmi, Saeful) 30
Pulse Echo (Dodi, Zidan) 5
Rebar scan Test (Dodi, Zidan) 30
Halfcell (Dodi, Zidan) 5
Perbaikan kondisi setelah pengujian 1

37 UPVT PT. GAMMA (PM: Panji, Lead Surveyor: Fahmi )


UPVT (Fahmi, Panji) 20
Agustus, 2019
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31