Duration
Activity Description
(Days)
1-2 Preparatory Works 4
2-3 Excavation Works 5
3-4 Foundation Works 10
4-5 Column Structure Works 10
4-6 Sloof Works 4
6-7 Wall Layering and Frame Works 13
7-9 Dummy 0
5-8 Roof Truss (steel) Works 9
8-9 Roof (Ceiling And Tiles) Works 13
9-10 Sanitary Works and Electrical Installation 16
9-11 Plastering/ Moulding 18
10-11 Floor Works 12
Installation Works ( Lamps, Glass, Doors,
7-12 Windows, Switches, Outlets, Locks, Sanitation 18
and other Accessories)
11-13 Painting Works 7
12-13 Fencing Works 10
13-14 Finishing/ Complementary Works 6
Note:
The path that was highlighted with dark blue show the critical path of
the network diagram.
Scheduling of Project with PERT/CPM
16
9 13
5 8 9 12
18
10
4 5 10 7 6
11 13 14
1 2 3 4
4
10
6 7 12
13 18
LEGEND
Dummy
Critical Path
Activity
Event
Probable Time Estimates
Probability
Z at 90
Expected Path V2 that it will
Path Activity a m b V2 days or
Time Total Path finish in
less
96 days
1-2-3-4-5-8-9-10-11-13-14 1-2 3 4 5 4 0.11
2-3 3 5 6 4 5/6 0.25
3-4 8 10 10 9 2/3 0.11
4-5 7 10 11 9 2/3 0.44
5-8 8 9 11 9 1/6 0.25
91.33 2.28 0.29 61%
8-9 11 13 14 12 5/6 0.25
9-10 15 16 18 16 1/6 0.25
10-11 11 12 13 12 0.11
11-13 6 7 9 7 1/6 0.25
13-14 4 6 7 5 5/6 0.25
1-2-3-4-5-8-9-11-13-14 1-2 3 4 5 4 0.11
2-3 3 5 6 4 5/6 0.25
3-4 8 10 10 9 2/3 0.11
4-5 7 10 11 9 2/3 0.44
5-8 8 9 11 9 1/6 81.17 0.25 2.36 4.59 100%
8-9 11 13 14 12 5/6 0.25
9-11 16 18 20 18 0.44
11-13 6 7 9 7 1/6 0.25
13-14 4 6 7 5 5/6 0.25
Probability
Z at 90
Expected Path V2 that it will
Path Activity a m b V2 days or
Time Total Path finish in
less
96 days
1-2-3-4-6-7-9-10-11-13-14 1_2 3 4 5 4 0.11
2_3 3 5 6 4 5/6 0.25
3_4 8 10 10 9 2/3 0.11
4_6 3 4 6 4 1/6 0.25
6_7 11 13 14 12 5/6 0.25
76.67 1.83 8.36 100%
7_9 0 0 0 0 0.00
9_10 15 16 18 16 1/6 0.25
10_11 11 12 13 12 0.11
11_13 6 7 9 7 1/6 0.25
13_14 4 6 7 5 5/6 0.25
1-2-3-4-6-7-9-11-13-14 1_2 3 4 5 4 0.11
2_3 3 5 6 4 5/6 0.25
3_4 8 10 10 9 2/3 0.11
4_6 3 4 6 4 1/6 0.25
6_7 11 13 14 12 5/6 66.50 0.25 1.92 13.30 100%
7_9 0 0 0 0 0.00
9_11 16 18 20 18 0.44
11_13 6 7 9 7 1/6 0.25
13_14 4 6 7 5 5/6 0.25
1-2-3-4-6-7-12-13-14 1_2 3 4 5 4 0.11
2_3 3 5 6 4 5/6 0.25
3_4 8 10 10 9 2/3 0.11
4_6 3 4 6 4 1/6 0.25
69.33 1.72 13.16 100%
6_7 11 13 14 12 5/6 0.25
7_12 16 18 19 17 5/6 0.25
12_13 9 10 12 10 1/6 0.25
13_14 4 6 7 5 5/6 0.25
Man Power Leveling
Duration
Activity Description No. of Men
(Days)
1-2 Preparatory Works 4 5
2-3 Excavation Works 5 7
3-4 Foundation Works 10 5
4-5 Column Structure Works 10 9
4-6 Sloof Works 4 5
Wall Layering and Frame
6-7 13 9
Works
7-9 Dummy 0 0
5-8 Roof Truss (steel) Works 9 6
Roof (Ceiling And Tiles)
8-9 13 5
Works
Sanitary Works and Electrical
9-10 16 6
Installation
9-11 Plastering/ Moulding 18 4
10-11 Floor Works 12 5
Installation Works (Lamps,
Glass, Doors, Windows,
7-12 Switches, Outlets, Locks, 18 9
Sanitation and other
Accessories)
11-13 Painting Works 7 7
12-13 Fencing Works 10 7
Finishing/ Complementary
13-14 6 4
Works
Calculating Man Power Labor Cost
Note:
The assumed daily rate is is Php. 300.00/ day/ men
From: