Beruflich Dokumente
Kultur Dokumente
b. Maintenance
• The Contractor shall maintain the Plant in accordance with the Maintenance Schedule
(contained as an annex to this agreement). The Maintenance Schedule will show the
minimum maintenance required and minimum frequency for each item per annum.
• The Contractor shall carry out a minimum of [two] maintenance inspections per year.
This shall include the assessment of the condition of the Plant including (but not limited
to) the following:
Condition of the generation equipment and supporting structures.
Functional check and condition of the security systems.
Visible damage and defects including functional check of safety equipment.
Inspection of the medium voltage components (up to the grid metering point).
• The Contractor shall, as a minimum, maintain Plant components in order to comply with
their warranty conditions.
• The Contractor shall remove snow and other accretions (dust and dirt) from the
modules as required.
• The Contractor shall keep the Site free from undesirable growth of plants and shrubs, to
achieve the best possible energy yields. Green areas shall be mowed and waste
materials removed. Dust shall be kept to a minimum to reduce soiling. Vehicles and
machines will be used such that they do not damage plant components.
• The Principal shall pay the cost of electricity and water required for maintenance
purposes (within the boundaries of the Plant)—and not expressly covered by another
clause within this agreement.
• The Contractor shall maintain the Plant so that the degradation of the Performance
Ratio is not more than [1%] per year, and shall inform the Principal if this limit is likely to
be exceeded.
• The Contractor shall perform specialised cleaning as required, on a site-specific basis to
avoid seasonal dust and dirt accumulation.
• All maintenance work that may affect the energy generation of the Plant will be carried
out, as far as reasonably possible, during low-irradiation periods.
h. Commercial Operation
• The Contractor will check and verify the accounts with the energy supplier and energy
off-taker in accordance with the Power Purchase Agreement.
• The Contractor shall check invoices that have been received by the Principal from third
parties—in the course of the operation, maintenance and repair of the Plant—for
plausibility and accuracy.
k. Security
[Depending on the requirements of the Principal, the Contractor may be made responsible
for the security arrangements for the Plant. If so, the requirements for monitoring and
maintaining the security system—and the costs of providing these services—should be
contained in the agreement]
• Security to be provided and monitored 365 days/year for 24 hours/day.
c. Guaranteed Availability
• The Contractor is to ensure that the Measured Average Availability in each generation
period equals or exceeds Guaranteed Average Availability figures in the following
manner:
Guaranteed Average Availability for each [twelve] month Generation Period of
this agreement will be in excess of: 97%
• The Measured Average Availability shall be calculated according to the following
formula:
Measured Average Availability = Grid-connected available hours / possible
available hours * 100%.
Grid-connected available hours are the number of hours that the inverters are
connected to the grid and available for export of power. In effect, it also means
the number of daylight hours (which are to be defined) during which the Plant is
able to convert irradiation into energy. Importantly, availability outside daylight
generation hours is not to count towards the grid connected availability hours.
Possible available hours need to be defined (taking leap years into account). It
should exclude hours allowed due to a) defined periods of planned maintenance
(e.g. [x] hours per year in winter months, [x] hours per year in summer months)
and b) hours when the Plant was not available as a result of Force Majeure
events.
• If the Measured Average Availability for a generation period is less than the relevant
Guaranteed Average Availability for a generation period, the Contractor shall pay an
Availability Contractual Penalty [rate of penalty and calculation to be agreed].
d. Liability
It is important to specify the equations for calculation of the liability due to low availability
and the maximum cap on liability besides outlining the method and timing for the
Contractor to reimburse the Principal. These reimbursements may take the form of financial
payments to compensate for the generation losses, or reductions in the remuneration to
the Contractor (under the O&M agreement) in the subsequent term.
• Liability should be limited to the loss of earnings of the Principal, taking into account any
payments that are made by the insurance cover or other warranties on the Plant.
5. Remuneration
The cost and remuneration of the O&M contract will be broken down into:
• Fixed Remuneration
Paid by the Principal based on an annual fixed lump sum per kWp of installed
nominal capacity (as defined in the EPC contract).
• Reimbursement of expenditure and remuneration for other services not included in the
fixed remuneration, and invoiced separately at agreed prices:
Spare parts and components that are approved in advance by the Principal and are
required for maintenance and repair. This will not include parts that are subject to
warranty claims, or minor repairs of value less than [x].
Services and ancillary costs that are approved in advance by the Principal and are
required for maintenance and repair. This will not include services that are due to
parts that are subject to warranty claims, or minor repairs of value less than [x] that
are to be corrected during semiannual inspections.
• Agreement is to be made on the invoicing dates/frequency and payment terms for the
Principal.
• Agreement is to be made on the indexation of the remuneration over the term of the
agreement. Often this is linked to a consumer price index, power purchase or tariff
increase or inflation index.
8. Insurance
The contract should also have a section outlining the insurance responsibilities of the
Contractor for the operations and maintenance activities. This insurance should cover
damage to the plant as well as provide cover for employees conducting the maintenance.
It is also normal for the Contractor to arrange and pay insurance for the full site. The
agreement should contain full details and remuneration requirements, while the annex to
the contract should include the insurance documentation.