GC-32: NEW GATHERING CENTRE FOR SEK


CONSTRUCTION PROGRESS MEASUREMENT SYSTEM (PMS)

LEGEND : ON GOING COMPLETED L3 ACTIVITY Status as of : 12-Apr-19

30.54% 2.86% 33.40% 0.00% 0.00% 0.00%

Current Current
Original L3 Plan L3 Plan Percntage in Last Week Weekly Last Week Weekly
L3 / L4 Activity ID Tank No. Activity L3 / L4 Activity Name Manhour Cummulative Actual Start Actual Finish Cummulativ
Duration Start Finish Overall Cum. Plan Plan Cum. Actual Actual
Plan e Actual

32D990A FAB Fire Water Tank ( 032-D-990A ) - Fabrication


TNKFAB32D990A0001 32D990A FAB Plate Shifting from Contractor Yard for Fabrication Works 30 4-Dec-18 8-Jan-19 1200 0.26% 0.26% 0.00% 0.26% 0.00% 0.00% 0.00%
TNKFAB32D990A0010 32D990A FAB Structural Material Shifting from Contractor Yard for Fabrication Works 10 9-Jan-19 20-Jan-19 400 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%
TNKFAB32D990A0020 32D990A FAB Shifting of flange, fittings, Brought out items and nozzle pipes for Fab works 10 2-Feb-19 12-Feb-19 400 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%
TNKFAB32D990A1000 32D990A FAB Fabrication of Annular Plates 4 8-Dec-18 12-Dec-18 200 0.04% 0.04% 0.00% 0.04% 0.00% 0.00% 0.00%
TNKFAB32D990A1010 32D990A FAB Fabrication of Sump 5 12-Dec-18 18-Dec-18 120 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%
TNKFAB32D990A1020 32D990A FAB Surface preperation and Underside Painting of Annular Plates and Sump 7 13-Dec-18 20-Dec-18 90 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%
TNKFAB32D990A1030 32D990A FAB Fabrication of Bottom Plates 8 13-Dec-18 22-Dec-18 1100 0.24% 0.24% 0.00% 0.24% 0.00% 0.00% 0.00%
TNKFAB32D990A1040 32D990A FAB Surface preperation and Underside Painting of Bottom Plates 12 23-Dec-18 6-Jan-19 320 0.07% 0.07% 0.00% 0.07% 0.00% 0.00% 0.00%
TNKFAB32D990A1050 32D990A FAB Fabrication of Shell Courses S5 & S6 12 23-Dec-18 6-Jan-19 520 0.11% 0.11% 0.00% 0.11% 0.00% 0.00% 0.00%
TNKFAB32D990A1060 32D990A FAB Fabrication of Wind Girder , Top Landing Platform, Stairway and FPS Brackets 11 6-Jan-19 19-Jan-19 990 0.21% 0.21% 0.00% 0.21% 0.00% 0.00% 0.00%
TNKFAB32D990A1070 32D990A FAB Fabrication of Roof Plates and Roof Structure 23 23-Jan-19 18-Feb-19 1860 0.40% 0.40% 0.00% 0.40% 0.00% 0.00% 0.00%
TNKFAB32D990A1080 32D990A FAB Surface preperation and Painting of Roof Structure 14 2-Feb-19 17-Feb-19 1150 0.25% 0.25% 0.00% 0.25% 0.00% 0.00% 0.00%
TNKFAB32D990A1085 32D990A FAB Fabrication of Shell Courses S4 to S1 20 24-Feb-19 20-Mar-19 1040 0.22% 0.22% 0.00% 0.22% 0.00% 0.00% 0.00%
TNKFAB32D990A1090 32D990A FAB Surface preperation and Painting of Roof Plate and Compression ring Underside 10 11-Feb-19 21-Feb-19 440 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%
TNKFAB32D990A1100 32D990A FAB Fabrication of Shell and Roof Appurtances including all Bal Misc Fabrications 26 21-Mar-19 21-Apr-19 1030 0.22% 0.11% 0.05% 0.16% 0.00% 0.00% 0.00%
TNKFAB32D990A1110 32D990A FAB Fabrication of COD 15 22-Apr-19 12-May-19 900 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A ERE Firewater Tank ( 032-D-0990 A ) - Erection & Welding, Annular & Bottom Plate

TNKERE32D990A1000-1 32D990A ERE Annular Laying and Fitup 2 2-Jan-19 3-Jan-19 108 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%

TNKERE32D990A1000-2 32D990A ERE Annular Welding 4 4-Jan-19 7-Jan-19 135 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%

TNKERE32D990A1000-3 32D990A ERE Annular NDT 1 8-Jan-19 9-Jan-19 27 0.01% 0.01% 0.00% 0.01% 0.00% 0.00% 0.00%

TNKERE32D990A1010-1 32D990A ERE Bottom Full Plate Laying and Fitup 3 10-Jan-19 13-Jan-19 216 0.05% 0.05% 0.00% 0.05% 0.00% 0.00% 0.00%

TNKERE32D990A1010-2 32D990A ERE Short Seam and Long Seam Welding 10 11-Jan-19 21-Jan-19 648 0.14% 0.14% 0.00% 0.14% 0.00% 0.00% 0.00%

TNKERE32D990A1010-3 32D990A ERE Sketch Plate Laying and Fitup 3 21-Jan-19 24-Jan-19 216 0.05% 0.05% 0.00% 0.05% 0.00% 0.00% 0.00%

TNKERE32D990A1010-4 32D990A ERE Annular to Sketch Plate Welding 5 24-Jan-19 30-Jan-19 360 0.08% 0.08% 0.00% 0.08% 0.00% 0.00% 0.00%
TNKERE32D990A1020 32D990A ERE Installation of Temperorary Elevators on Tank Annular 2 14-Jan-19 15-Jan-19 60 0.01% 0.01% 0.00% 0.01% 0.00% 0.00% 0.00%
32D990A ERE Firewater Tank ( 032-D-0990 A ) - Erection & Welding, Shell Course-5

TNKERE32D990A1030-1 32D990A ERE Scaffolding Work 3 14-Jan-19 17-Jan-19 100 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%

TNKERE32D990A1040-1 32D990A ERE Shell Erection & Fitup 2 20-Jan-19 21-Jan-19 116 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%

TNKERE32D990A1040-2 32D990A ERE Shell Vertical Welding 4 22-Jan-19 26-Jan-19 160 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%

TNKERE32D990A1040-3 32D990A ERE NDT 1 27-Jan-19 28-Jan-19 14 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A ERE Firewater Tank ( 032-D-0990 A ) - Erection & Welding, Shell Course-6

TNKERE32D990A1030-2 32D990A ERE Scaffolding Work 2 18-Jan-19 20-Jan-19 100 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%

TNKERE32D990A1050-1 32D990A ERE Shell Erection & Fitup 4 28-Jan-19 31-Jan-19 436 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%

TNKERE32D990A1050-2 32D990A ERE Shell Vertical Welding 6 1-Feb-19 8-Feb-19 600 0.13% 0.13% 0.00% 0.13% 0.00% 0.00% 0.00%

TNKERE32D990A1050-3 32D990A ERE NDT 1 9-Feb-19 10-Feb-19 54 0.01% 0.01% 0.00% 0.01% 0.00% 0.00% 0.00%
32D990A ERE Firewater Tank ( 032-D-0990 A )- Erection & Welding, Wind Girder & Compression ring

TNKERE32D990A1060-1 32D990A ERE Wind Girder Erection and Fitup 2 10-Feb-19 11-Feb-19 198 0.04% 0.04% 0.00% 0.04% 0.00% 0.00% 0.00%

TNKERE32D990A1060-2 32D990A ERE Wind Girder Welding 3 12-Feb-19 15-Feb-19 396 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%

TNKERE32D990A1060-3 32D990A ERE Compression ring Erection and Fitup 2 16-Feb-19 17-Feb-19 198 0.04% 0.04% 0.00% 0.04% 0.00% 0.00% 0.00%

TNKERE32D990A1060-4 32D990A ERE Compression ring Welding 3 18-Feb-19 21-Feb-19 396 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%

TNKERE32D990A1060-5 32D990A ERE Compression Ring NDT 1 22-Feb-19 23-Feb-19 132 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%
32D990A ERE Firewater Tank ( 032-D-0990 A )- Erection & Welding, Roof & Structures
TNKERE32D990A1070 32D990A ERE Scaffolding inside the tank for erection and welding of Roof 10 11-Feb-19 21-Feb-19 500 0.11% 0.11% 0.00% 0.11% 0.00% 0.00% 0.00%
TNKERE32D990A1080-1 32D990A ERE Erection and Welding of Central Drum and Roof Chairs 2 23-Feb-19 25-Feb-19 160 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%
TNKERE32D990A1080-2 32D990A ERE Erection and Fitup of Roof Main Truss 3 26-Feb-19 1-Mar-19 240 0.05% 0.05% 0.00% 0.05% 0.00% 0.00% 0.00%
TNKERE32D990A1080-3 32D990A ERE Welding of Roof Main Truss 5 2-Mar-19 7-Mar-19 320 0.07% 0.07% 0.00% 0.07% 0.00% 0.00% 0.00%
TNKERE32D990A1080-4 32D990A ERE Erection and Fitup of Cross Girders, Secondary rafters , Purlins and Roof assembly4 8-Mar-19 12-Mar-19 320 0.07% 0.07% 0.00% 0.07% 0.00% 0.00% 0.00%
TNKERE32D990A1080-5 32D990A ERE Welding of Cross Girders, Secondary rafters , Purlins and Roof assembly 7 13-Mar-19 20-Mar-19 560 0.12% 0.12% 0.00% 0.12% 0.00% 0.00% 0.00%
TNKERE32D990A1090-1 32D990A ERE Erection and Fitup of Roof Plates 6 21-Mar-19 28-Mar-19 1768 0.38% 0.38% 0.00% 0.38% 0.00% 0.00% 0.00%
TNKERE32D990A1090-2 32D990A ERE Welding of Roof Plates 12 29-Mar-19 11-Apr-19 3282 0.71% 0.40% 0.30% 0.71% 0.00% 0.00% 0.00%
TNKERE32D990A1100 32D990A ERE Erection and Welding Top Handrailing along with Landing Platform and Top Stairway 7 22-Apr-19 29-Apr-19 1400 0.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1110 32D990A ERE Paint touchup after Roof erection and Welding works 11 14-Apr-19 25-Apr-19 410 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A ERE Fire Water Tank ( 032-D-0990 A )- Erection & Welding, Shell Course-4
TNKERE32D990A1120 32D990A ERE Installation of hydraulic jacking systems inside the tanks 4 30-Apr-19 4-May-19 900 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-1 32D990A ERE Shell Erection & Fitup 2 5-May-19 7-May-19 316 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-2 32D990A ERE Shell Vertical and Horizontal Welding 7 8-May-19 15-May-19 632 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-3 32D990A ERE NDT 1 16-May-19 17-May-19 105 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A ERE Fire Water Tank ( 032-D-0990 A )- Erection & Welding, Shell Course-3

TNKERE32D990A1130-4 32D990A ERE Shell Erection & Fitup 2 18-May-19 20-May-19 316 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-5 32D990A ERE Shell Vertical and Horizontal Welding 7 21-May-19 30-May-19 632 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-6 32D990A ERE NDT 1 31-May-19 1-Jun-19 105 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A ERE Fire Water Tank ( 032-D-0990 A )- Erection & Welding, Shell Course-2

TNKERE32D990A1130-7 32D990A ERE Shell Erection & Fitup 3 2-Jun-19 6-Jun-19 421 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-8 32D990A ERE Shell Vertical and Horizontal Welding 8 6-Jun-19 16-Jun-19 842 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKERE32D990A1130-9 32D990A ERE NDT 1 17-Jun-19 18-Jun-19 141 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A ERE Firewater Tank ( 032-D-0990 A ) - Erection & Welding, Shell Course-1 and Appurtances
TNKERE32D990A1140 32D990A ERE Installation and Welding of Spiral Staircase on Tank along with Jacking 30 22-May-19 3-Jul-19 660 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1145 32D990A ERE Post Weld Heat Treatment 7 12-May-19 26-May-19 600 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1150 32D990A ERE Erection of shell course S1 3 18-Jun-19 22-Jun-19 240 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1160 32D990A ERE Erection and Welding of all Tank Internal ,Shell Appurtances and Cleanout Doors 10 18-Jun-19 30-Jun-19 1870 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1170 32D990A ERE Erection and Welding of Roof Appurtances including Guage well, Level Radar and9Temp well
23-Jun-19 2-Jul-19 1340 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1190 32D990A ERE Welding of Shell Strake S1 8 3-Jul-19 13-Jul-19 1200 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1200 32D990A ERE Fitup and Welding of Shell to Bottom Plate Outside and Inside 5 13-Jul-19 18-Jul-19 1920 0.41% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1210 32D990A ERE Fitup and Welding of Annular to Sketch Plate 4 18-Jul-19 23-Jul-19 400 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1220 32D990A ERE Vaccum test of Bottom Plates 3 23-Jul-19 27-Jul-19 180 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKERE32D990A1230 32D990A ERE Punch points liquidation prior to hydrotest 7 27-Jul-19 4-Aug-19 1800 0.39% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A HYD Fire Water Tank ( 032-D-990A ) - Hydrotest works
TNKHYD32D990A1000 32D990A HYD Hydrotest 21 4-Aug-19 1-Sep-19 440 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKHYD32D990A1010 32D990A HYD Tank cleaning 2 1-Sep-19 3-Sep-19 240 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKHYD32D990A1020 32D990A HYD Calibration 4 3-Sep-19 8-Sep-19 120 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A PNT Firewater Tank ( 032-D-0990 A ) - External Painting

TNKPNT32D990A1000-1 32D990A PNT Scaffolding 11 22-Aug-19 2-Sep-19 1650 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKPNT32D990A1040-2 32D990A PNT Surface preparation and Blasting 14 2-Sep-19 16-Sep-19 399 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKPNT32D990A1040-3 32D990A PNT Painting - Primer 19 2-Sep-19 21-Sep-19 228 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKPNT32D990A1040-4 32D990A PNT Painting - 2nd coat 7 22-Sep-19 30-Sep-19 228 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKPNT32D990A1040-5 32D990A PNT Painting - Final coat 7 1-Oct-19 9-Oct-19 228 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TNKPNT32D990A1040-6 32D990A PNT Touch up painting 2 10-Oct-19 12-Oct-19 57 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A PNT Firewater Tank ( 032-D-0990 A ) - Internal Painting & Lining

TNKPNT32D990A1000-2 32D990A PNT Scaffolding 11 3-Sep-19 18-Sep-19 1650 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKPNT32D990A1010 32D990A PNT Internal Painting of Tank Shell 14 18-Sep-19 5-Oct-19 790 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKPNT32D990A1020 32D990A PNT Removal of Scaffolding Inside the Tank 4 5-Oct-19 9-Oct-19 600 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKPNT32D990A1030 32D990A PNT Internal Painting of Tank Bottom 13 9-Oct-19 24-Oct-19 1610 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990A HND Fire Water Tank ( 032-D-990A ) - Final Punch Point and Boxup
TNKHND32D990A1000 32D990A HND Final Punch Points / Checklist Clearance 15 22-Oct-19 9-Nov-19 880 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TNKHND32D990A1010 32D990A HND Final Box-up & Handover 5 9-Nov-19 16-Nov-19 300 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990B FAB Fire Water Tank ( 032-D-990B ) - Fabrication
TNKFAB32D990B0001 32D990B FAB Plate Shifting from Contractor Yard for Fabrication Works 31 12-Dec-18 17-Jan-19 1200 0.26% 0.26% 0.00% 0.26% 0.00% 0.00% 0.00%
TNKFAB32D990B0010 32D990B FAB Structural Material Shifting from Contractor Yard for Fabrication Works 10 19-Jan-19 29-Jan-19 400 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%
TNKFAB32D990B0020 32D990B FAB Shifting of flange, fittings, Brought out items and nozzle pipes for Fab works 10 11-Feb-19 21-Feb-19 400 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%
TNKFAB32D990B1000 32D990B FAB Fabrication of Annular Plates 4 20-Dec-18 25-Dec-18 200 0.04% 0.04% 0.00% 0.04% 0.00% 0.00% 0.00%
TNKFAB32D990B1010 32D990B FAB Fabrication of Sump 5 25-Dec-18 31-Dec-18 120 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%
TNKFAB32D990B1020 32D990B FAB Surface preperation and Underside Painting of Annular Plates and Sump 7 26-Dec-18 3-Jan-19 90 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%
TNKFAB32D990B1030 32D990B FAB Fabrication of Bottom Plates 8 26-Dec-18 5-Jan-19 1100 0.24% 0.24% 0.00% 0.24% 0.00% 0.00% 0.00%
TNKFAB32D990B1040 32D990B FAB Surface preperation and Underside Painting of Bottom Plates 12 6-Jan-19 19-Jan-19 320 0.07% 0.07% 0.00% 0.07% 0.00% 0.00% 0.00%
TNKFAB32D990B1050 32D990B FAB Fabrication of Shell Courses S5 & S6 12 6-Jan-19 19-Jan-19 520 0.11% 0.11% 0.00% 0.11% 0.00% 0.00% 0.00%
TNKFAB32D990B1060 32D990B FAB Fabrication of Wind Girder , Top Landing Platform, Stairway and FPS Brackets 12 16-Jan-19 30-Jan-19 990 0.21% 0.21% 0.00% 0.21% 0.00% 0.00% 0.00%
TNKFAB32D990B1070 32D990B FAB Fabrication of Roof Plates and Roof Structure 22 2-Feb-19 28-Feb-19 1860 0.40% 0.40% 0.00% 0.40% 0.00% 0.00% 0.00%
TNKFAB32D990B1080 32D990B FAB Surface preperation and Painting of Roof Structure 14 12-Feb-19 3-Mar-19 1150 0.25% 0.25% 0.00% 0.25% 0.00% 0.00% 0.00%
TNKFAB32D990B1085 32D990B FAB Fabrication of Shell Courses S4 to S1 20 9-Mar-19 1-Apr-19 1040 0.22% 0.22% 0.00% 0.22% 0.00% 0.00% 0.00%
TNKFAB32D990B1090 32D990B FAB Surface preperation and Painting of Roof Plate and Compression ring Underside 11 20-Feb-19 7-Mar-19 440 0.09% 0.09% 0.00% 0.09% 0.00% 0.00% 0.00%
TNKFAB32D990B1100 32D990B FAB Fabrication of Shell and Roof Appurtances including all Bal Misc Fabrications 26 1-Apr-19 2-May-19 1030 0.22% 0.03% 0.05% 0.08% 0.00% 0.00% 0.00%
TNKFAB32D990B1110 32D990B FAB Fabrication of COD 15 2-May-19 30-May-19 900 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32D990B ERE Firewater Tank ( 032-D-0990 B ) - Erection & Welding, Annular & Bottom Plate

TNKERE32D990B1000-1 32D990B ERE Annular Laying and Fitup 2 10-Jan-19 11-Jan-19 108 0.02% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00%

TNKERE32D990B1000-2 32D990B ERE Annular Welding 4 12-Jan-19 15-Jan-19 135 0.03% 0.03% 0.00% 0.03% 0.00% 0.00% 0.00%

TNKERE32D990B1000-3 32D990B ERE Annular NDT 1 16-Jan-19 17-Jan-19 27 0.01% 0.01% 0.00% 0.01% 0.00% 0.00% 0.00%