A.B.N.  55  086    922  312 Pre-­Commissioning  Form
Contractor  Name: ATLAS PRECISION ENVIRONMENT CORP.
Site  Contact: MARC CUCIO Contact  Phone: 09175662947
Site  Contact  during  Warranty: MARC CUCIO Phone: 09175662947
Job  Name: IBM-BDO DATA CENTER
Site  Address: PASEO DE ROXAS COR. GIL PUYAT, BRGY. BEL AIR, MAKATI CITY

Chiller  Location: CHILLER ROOM - LOWER DECK Chiller  Serial#


(To  be  used  in  the  event  of  delays  during  commissioning  due  
Purchase  Order  #: to  incomplete  Pre-­Commissioning  Works,  or  on  site  delays)

This  is  to  confirm  that  the  following  checks  have,  or  will  be  completed  by  (date):

Our  preferred  date  for  the  commissioning  services  of  an  authorised  service  partner  is:
While  every  effort  will  be  made  to  comply  with  this  date,  Smardt  reserves  the  right  to  advise  alternative  dates.  
Minimum  seven  days  notice  is  required,  to  assist  with  scheduling  and  coordination  activities.

General   YES NO N/A NOTES


Chiller  system  mounted  on  a  level  surface  (+/-­  3mm  per  metre)    

Refrigerant  pressure  present  and  no  signs  of  refrigerant  leaks      


Unit  has  no  signs  of  damage

All  insulation  in  sound  condition  (not  damaged  by  rigging  equipment)  
Adequate  service  clearance  available,  as  per  Smardt  requirements  

Electrical  /  Controls   YES NO N/A NOTES


Power  wiring  installed  and  in  accordance  with  chiller  nameplate    
All  interlock  wiring  complete  and  in  accordance  with  Smardt  wiring  schematic      

Control  (BMS)  system  fully  operational,  allowing  for  automatic  control  

Evaporator   YES NO N/A NOTES


Chilled  water  piping  complete,  pressure  tested  and  connected  to  chiller      

Chilled  water  circuit  filled  with  water  and  fully  vented.      

Pumps  installed  and  rotation  checked  


Chilled  Water  bypass  valve  installed  and  operational      
System  flushed  of  debris  and  strainers  clean.    
Flow  switch  installed  and  cutting  out  at  50%  PD  or  70%  of  Flow  (L/S)  
Chilled  water  piping  adequately  supported  externally  from  chiller  unit  

Binder  valves  (or  similar)  fitted,  flows  checked  and  validated  


Evaporator  Design  Flows Evaporator  Actual  Flows

Litres/Sec @ Pressure Drop (kpa) Litres/Sec @ Pressure Drop (kpa)

Note:  Please  refer  to  the  chiller  specification  sheet  for  design  flow  specifications.  
Smardt  Pre-­Commissioning  Form   Page 1 of 2 SCF0001.1202  
Water  Cooled  Condenser  (if  applicable)     YES NO N/A NOTES
Condenser  water  piping  complete  and  connected  to  chiller  

Condenser  water  circuit  filled  with  water  and  fully  vented.  


Pumps  installed  and  rotation  checked  

Condenser  water  by-­pass  valves  installed  and  operational  


System  flushed  of  debris  and  strainers  clean  (including  tower)      

Flow  switch  installed  and  functional      

Condenser  water  piping  adequately  supported  externally  from  chiller  unit    

Binder  valves  (or  similar)  fitted,  to  validate  flows      


Condenser  Design  Flows Condenser  Actual  Flows

Litres/Sec @ Pressure Drop (kpa) Litres/Sec @ Pressure Drop (kpa)

Note:  Please  refer  to  the  chiller  specification  sheet  for  design  flow  specifications.  

Special  Requirements    
Please  take  the  time  to  identify  and  note  any  special  requirements  that  may  be  required,  such  as:    
-­  Special  Directions  to  access  the  site  or  parking  arrangements  
-­  Site  Induction  Required  
-­  Certifications  Required  

Site  Notes:

Any  delays  experienced  by  the  authorised  service  provider  due  to  the  system  not  being  in  the  state  
indicated  by  this  form,  and  therefore  not  being  ready  when  the  service  provider  attends  site  -­  shall  be  
chargeable  and  the  purchase  order  that  has  been  provided  above  will  be  utilised  to  cover  all  out  of  
pocket  expenses  (if  applicable),  till  such  time  as  the  system  is  fully  pre-­  commissioned.    
   
The  authorised  service  provider  is  under  no  obligation  to  remain  on  site  until  pre-­commissioning  work  
is  completed,  but  if  desired  a  purchase  order  may  be  provided  to  the  service  provider  for  such  time  
spent  on  site  due  to  delays  due  to  the  system  not  being  fully  ready  to  be  commissioned.      
   
It  is  the  installing  contractor's  responsibility  to  have  the  necessary  tools,  flow  metering  device  or    calibrated  
gauges  available  -­  for  the  commissioning  agent  to  validate  upon  arriving  on  site.  
-­     Scheduling   of   Commissioning   will   only   occur   once   a   copy   of   this   completed   form   is   received   by   Smardt.  
Please   complete   this   form   and   either   email   or   fax   it   to   the   attention   of   the   Service   Administrator   at     Smardt.  
Email:  service.admin@powerpax.com.au  or  facsimile  +61  (3)  9761  6707  
-­  Please  make  allowances  for  a  minimum  of  7  days  from  receipt  of  this  form  by  Smardt  till  the  Date  of  
Commissioning,  to  allow  time  for  the  coordination  of  Smardt's  Service  Partners.

-­  The  Warranty  Period  commences  for  12  months  from  the  date  of  Commissioning,  or  18  months  from  
date  of  shipment,  whichever  occurs  first,  and  is  not  related  to  the  contractors  Defects  Liability  Period.
I  hereby  certify  that  the  information  contained  on  this  form  is  correct  and  has  been  verified:

Completed By (Name): Company Name:

Date Form Completed: Mobile Number: Fax Number: NA

Smardt  Pre-­Commissioning  Form   Page 2 of 2 SCF0001.1202  