ID Task Task Name Duration Start Finish Predecessors 20 Nov '17 27 Nov '17 04 Dec '17 11 Dec '17

Mode W T F S S M T W T F S S M T W T F S S M T W
1 Pembuatan Frame 10 days Thu Wed Design & Chassis
Baja Ringan (Riset) 23/11/17 06/12/17
2 Pemasangan Rem & 3 days Thu Mon 1 Design
Steering(Baja Ringan) 07/12/17 11/12/17

3 Simulasi Electrical 21 days Mon 27/11/17Mon 25/12/17

4 Persiapan + 16 days Mon Mon


Pembuatan Frame 27/11/17 18/12/17
Alumunium (Riset)
5 Pemasangan Rem & 2 days Tue Wed 4
Steering 19/12/17 20/12/17
(Alumunium)
6 Perancangan dan 10 days Mon Fri 08/12/17 Design & Chass
Pembuatan As 27/11/17
Belakang
7 Improvement Ban 10 days Mon Fri 08/12/17 Chassis
(Pemasangan Ban 27/11/17
FDR dan Balancing)
8 Persiapan Engine 4 days Wed Mon Engine & Electrical
Untuk Trial di 29/11/17 04/12/17
Cikarang (Engine
Supra)
9 Improvement Engine 20 days Thu Wed
(Kang Fahmi) 23/11/17 20/12/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MasterPlan UrbanConc
Summary Manual Summary Rollup Progress
Date: Wed 29/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors 20 Nov '17 27 Nov '17 04 Dec '17 11 Dec '17
Mode W T F S S M T W T F S S M T W T F S S M T W
10 Assembly Engine + 5 days Thu Wed 9
Alignment + Electrical 21/12/17 27/12/17

11 TRIAL RISET & 3 days Tue Thu 10


Trouble Repair 26/12/17 28/12/17
12 Trial Body 6 days Mon Mon Body
(Cetakan&Bahan) 27/11/17 04/12/17
13 Pembuatan Cetakan 21 days Tue Tue 12
Body 05/12/17 02/01/18
14 Pemasangan Sekat 2 days Thu Fri 05/01/18
Bawah Cockpit 04/01/18
15 Pemasangan 3 days Thu Mon
Electrical Tahap 1 04/01/18 08/01/18
(Tech Inspection
DMS, ES, DC to DC)
16 Pembuatan Body 7 days Wed 03/01/18Thu 11/01/1813

17 Pemotongan Pintu & 2 days Fri 12/01/18 Mon 16


Kap Belakang 15/01/18
18 Pemasangan 4 days Tue Fri 19/01/18 17
Electrical Tahap 2 16/01/18
(Tech Inspection
Lampu-Lampu,
Wiper, Merapihkan
Kabel)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MasterPlan UrbanConc
Summary Manual Summary Rollup Progress
Date: Wed 29/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors 20 Nov '17 27 Nov '17 04 Dec '17 11 Dec '17
Mode W T F S S M T W T F S S M T W T F S S M T W
19 TRIAL 3 days Mon 22/01/18Wed 24/01/1818

20 Finishing 5 days Thu Wed 19


(Pengecatan,QC,dan 25/01/18 31/01/18
Tech Inspection
Internal)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MasterPlan UrbanConc
Summary Manual Summary Rollup Progress
Date: Wed 29/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
11 Dec '17 18 Dec '17 25 Dec '17 01 Jan '18 08 Jan '18 15 Jan '18 22 Jan '18 29 Jan '18
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Chassis

Design & Chassis

Electrical

Design & Chassis

Design & Chassis

gn & Chassis

ssis

cal

Engine & Electrical

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MasterPlan UrbanConc
Summary Manual Summary Rollup Progress
Date: Wed 29/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
11 Dec '17 18 Dec '17 25 Dec '17 01 Jan '18 08 Jan '18 15 Jan '18 22 Jan '18 29 Jan '18
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Chassis, Engine

All

Body

Scrutting

Engine, Electrical & Scruttening

Body

Body

Engine, Electrical & Scruttening

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MasterPlan UrbanConc
Summary Manual Summary Rollup Progress
Date: Wed 29/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
11 Dec '17 18 Dec '17 25 Dec '17 01 Jan '18 08 Jan '18 15 Jan '18 22 Jan '18 29 Jan '18
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
All

All

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MasterPlan UrbanConc
Summary Manual Summary Rollup Progress
Date: Wed 29/11/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6