TECHNICAL SPECIFICATION
FOR
GETCO/E/04TS CT6/R2/Mar 08
1
GETCO/E/04TS CT6/R2/Mar 08
1. All the drawings, i.e. elevation, side view, plan, cross sectional view etc., in
AutoCAD format and manuals in PDF format, for offered item shall be submitted.
Also the hard copies as per specification shall be submitted.
2. The bidder shall submit Quality Assurance Plan with the technical bid.
3. The bidder shall have to submit all the required type test reports for the offered
item. In absence of this, the evaluation shall be carried out accordingly as non-
submission of type test reports.
4. The bidder must fill up all the points of GTP for offered item/s. Instead of
indicating “refer drawing, or as per IS/IEC”, the exact value/s must be filled in.
5. All the points other than GTP, which are asked to confirm in technical
specifications must be submitted separately with the bid.
7. Please note that the evaluation will be carried out on the strength of content of
bid only. No further correspondence will be made.
8. The bidder shall bring out all the technical deviation/s only at the specified
annexure.
2
GETCO/E/04TS CT6/R2/Mar 08
4) The bidder should clearly indicate the quantity and Single Value
Contract executed during last FIVE (5) years, for the offered
equipment. Bidder should have executed one single contract
during last five years for the quantity equivalent to tender / bid.
The details are to be submitted in following format,
3
GETCO/E/04TS CT6/R2/Mar 08
SECTION - I
1.0 SCOPE:
1.1 This section covers the design, manufacture, assembly, testing at the
manufacturer’s, supply and delivery of outdoor, Live/Dead tank type, oil
impregnated paper, single phase Current Transformer, along with
supporting structure as detailed in the enclosed schedule of requirement for
relaying and metering services in three phase solidly ground system.
1.2 The bidder shall give assurance for trouble free and maintenance free performance for a
period of 60 (sixty) months from the date of receipt at store, during which period, the CTs
shall be repaired/reconditioned/replaced free of cost immediately in case of any trouble.
Therefore, the bidder shall ensure that sealing of Instrument Transformer is properly
achieved.
1.3 It is not the intent to specify completely herein all details of the design and construction
of equipments. However, the equipment shall conform in all respects to high standards of
engineering, design and workmanship and shall be capable of performing in continuous
commercial operation up to the guarantee, who will interpret in a manner the meanings of
drawings and specification and shall have the power to reject any work or material which
in his judgment is not in accordance therewith. The equipment offered shall be complete
with all components necessary for its effective and trouble free operation. Such
components shall be deemed to be within the scope of Bidder’s supply, irrespective of
whether these are specifically brought out in this specification and/or the commercial
order or not.
2.0 STANDARDS:
2.1 Unless otherwise specified elsewhere in this specification, the rating as well as
performance and testing of the current transformers shall conform but not limited to the
latest revisions and amendments available at the time of placement of order of all the
relevant standards as listed hereunder.
4
GETCO/E/04TS CT6/R2/Mar 08
2.2 Equipment meeting with the requirement of other authoritative Standards, which ensure
equal or better performance than the standards mentioned above, shall also be considered.
When the equipments offered by the Bidder conforms to other standards, salient points of
difference between standard adopted and the standards specified in this specification shall
be clearly brought out in the relevant schedule. Four copies of such standards with
authentic translation in English shall be furnished along with the bid.
3.2 The equipment offered shall be suitable for continuous operation at their full rated
capacity under the above conditions.
3.3 Since the sub-station may be near the sea-shore and/or in an industrial area, the
equipment offered shall be suitable for heavily polluted atmosphere.
The current transformers covered in this specification shall meet the technical
requirements listed hereunder.
SR. SPECIFICATION
ITEM
NO. 400 KV CT
5
GETCO/E/04TS CT6/R2/Mar 08
4.1.1 The insulation of the current transformers shall be so designed that the internal insulation
shall have higher electrical withstand capability than the external insulation. The
designed dielectric withstands values of external and internal insulations shall be clearly
brought out in the guaranteed technical particulars. The dielectric withstand values
specified in this specification are mean for fully assembled current transformers.
6
GETCO/E/04TS CT6/R2/Mar 08
4.1.2.1 The details of location and type of joint, if provided on the porcelain, shall be furnished
by the Bidder along with the offer. The housing shall be made of homogeneous, vitreous
porcelain of high mechanical and dielectric strength, glazing of porcelains shall be of
uniform brown or dark brown colour with a smooth surface arranged to shed away rain
water or condensed water particles. (fog). The profile of porcelain shall be aerodynamic
type as per IEC-815.
4.1.2.2 Details of attachment of metallic flanges to the porcelain shall be brought out in the bid.
4.1.3 The metal tanks shall have bare minimum number of welded joints so as to minimise
possible locations of oil leakage. The metal tanks shall be made out of mild steel/stainless
steel/aluminium alloy, depending on the requirement. Welding in horizontal plane is to be
avoided as welding at this location may give way due to vibrations during transport
resulting in oil leakage. Supplier has to obtain specific approval from purchaser for any
horizontal welding used in the bottom tank.
4.1.4.1 All ferrous parts of CTs including lifting hooks and adjustable arcing horns shall be hot
dip galvanized. Before filling with oil or compound all ferrous parts shall be completely
cleaned and free from dust scale and greases and all external rough surface on castings
shall be filled by metal disposition. The interior of current transformer tank shall be
cleaned of all scale and rust by sand blasting or other approved method.
4.1.4.2 Except for nuts, bolts of washer all the surfaces shall be hot dip galvanized.
4.1.4.3 All external MS surfaces shall be thoroughly cleaned and hot dip galvanized as per
relevant IS .Any damage to galvanized surfaces during transport and erection shall be
made good by thoroughly cleaning the damaged portion and by applying the full number
of coats of zinc rich paints.
4.1.5.1 The quantity of insulating oil for first filling and the complete specification of the oil shall
be stated in tender. The oil shall comply in all respects with the provisions of the latest
edition of IS :335 or IEC Publication No.296 (as amended upto date) The oil shall have
the following main characteristics or equivalent.( The requirement indicated is
determined in accordance with the test methods adopted by IS:335).
7
GETCO/E/04TS CT6/R2/Mar 08
Deg.Min.
5 Flash point 140 Deg. C IS :1448 (P-21) 1970 or equivalent
Pensky marten authoritative standard.
(closed) Min.
6 Pour point Max - 10 Deg. C IS :1448 (P-10) 1970 or equivalent
authoritative standard.
7 Neutralization 0.03 Mg/KOH/g IS :335 - 1972 Appendix -A or
value (Total equivalent authoritative standard.
acidity) Max.
8 Corrosive Non-corrosive. IS :335 -1972 Appendix -A or
sulphar (in equivalent authoritative standard.
terms of
classification of
copper strip
9 Electric strength
(break down
voltage) Min.
a) New 30KV (rms) If the above IS :6792 -1972 or equivalent
untreated oil value is not attained, the oil authoritative standard.
shall be treated
b) After 50 KV (rms)
treatment
10 Dielectric 0.002 IS :6262 -1971 or equivalent
dissipation factor authoritative standard.
(tan δ) at 90 Deg.
C Max.
11 Specific
resistance
(Resistivity)
a) At 90 Deg. C IS :6103-1971 or equivalent
Min. 35 x 1212 Ohm/cm authoritative standard.
b) At 27 Deg. C
Min.
1500 x 1012 oh.
12 Oxidation
stability
a) Neutralization
value after 0.40 mg/KOH/g IS :335 -1972 Appendix -C or
oxidation max. equivalent authoritative standard.
b) Total sludge
after oxidation 0.10 percent by weight
Max.
13 Ageing
characteristic
after accelerated
ageing
a) Specific
resistance
(Resistivity)
i) At 27 Deg. C 2.5 x 1012 Ohm/cm IS-6103 -1971
8
GETCO/E/04TS CT6/R2/Mar 08
Min.
ii) At 90 Deg. C 2.5 x 1012 Ohm/cm
Min.
4.1.6.1 The supplier shall ensure that the sealing of current transformer is properly achieved. In
this connection the arrangement provided by the supplier at various locations including
the following ones shall be described, supported by sectional drawings.
4.1.6.2 Nuts and bolts or screws used for fixation of the interfacing porcelain bushings for taking
out terminals shall be provided on flanges cemented to the bushings and not on the
porcelain.
4.1.6.3 For gasket joints, wherever used, Nitrile Butyl rubberNBR/Viton shall be used. No
CORK gaskets shall be used. All gaskets/O rings shall be fixed in a
machine groove. The gaskets shall be securely fitted for perfect sealing.
4.1.8 Earthing:
Metal tank of the current transformer shall be provided with two separate earthing
terminals for bolted connection to 50 x 8 mm MS flat to be provided for connection to
station earth-mat.
4.1.9 Current transformer shall be provided with suitable lifting arrangement, to lift the entire
unit. The lifting arrangement shall be clearly shown in the general arrangement drawing.
Lifting arrangement (lifting eye) shall be positioned in such a way as to avoid any
9
GETCO/E/04TS CT6/R2/Mar 08
damage to the porcelain housing or the tanks during lifting for installation/transport.
Necessary string guides shall be offered which shall be of removable type.
The current transformer shall be provided with non-corrosive, legible name plate with the
information specified in relevant standards, duly engraved/punched on it.
All Current Transformer shall be provided with Boltless type terminal connectors suitable
to receive 4" IPS (114.3 OD) aluminium pipes or bundled ACSR conductors. Clamps
shall be designed adequately to take care of any bimetallic effect. The temperature at the
clamp shall not exceed 80 ºC corona rings shall be provided at the breaker terminals. The
terminal pad shall have protective covers which shall be removed before interconnections.
The ratings of Terminal connectors shall be equal or higher than that of the current
transformer.
4.1.12 Enamel, if used for conductor insulation, shall be either polyvinyl acetate type or amide
type and shall meet the requirements of IS:4800. Polyester enamel shall not be used.
Double cotton cover, if used, shall be suitably covered to ensure that it does not come in
contact with oil.
4.1.13 The temperature rise on any part of equipment shall not exceed the maximum temperature
rise specified below under the conditions specified in test clauses. The permissible
temperature rise indicated is for a maximum ambient temperature of 50°C.
TEMP. RISE
AT A MAX.
SR. NATURE OF THE PART OR OF THE TEMP. AMBIENT AIR
NO. LIQUID (°C) TEMP. NOT
EXCEEDING
50°C
1 Contacts in air, silver faced copper, copper alloy 105 55
or aluminium alloy (see note (i) and (ii))
10
GETCO/E/04TS CT6/R2/Mar 08
Notes: 1)When applying the temperature rise of 55°C, care should be taken to ensure that no
damage is caused to the surrounding insulating materials.
2) The quality of the silver facing shall be such that a layer of silver remains at the
point of contact after the mechanical endurance test. Otherwise, the contacts shall be
regarded as “bare”.
3) The values of temperature and temperature rise are valid whether or not the
conductor connected to the terminals is silver-faced.
4) The temperature shall not reach a value where the elasticity of the material is
impaired. For pure copper, this implies a temperature limit of 75°C.
4.2 CURRENT TRANSFORMER (CT) DESIGN:
4.2.1 The C.T. shall be of dead tank or Live Tank design and shall be so constructed that it
can be easily transported to site within the allowable transport limitation and in horizontal
position if the transport limitations so demand.
4.2.2 For compensation of variation in the oil volume due to ambient variation, nitrogen
cushion or stainless steel bellows or nitrogen cushion shall be used. Rubber diaphragms
shall not be permitted for this purpose.
11
GETCO/E/04TS CT6/R2/Mar 08
4.2.3 The C.T. secondary terminals shall be brought out in a weatherproof terminal box. The
terminal box shall be provided with removable gland plate and gland/s suitable for 1100
volts grade, PVC insulated, PVC sheathed multi core 6 sq. mm. or 10 sq. mm. stranded
copper or aluminium conductor cable. The terminal box shall be dust and vermin proof
and shall comply with IP55 degree of protection standards & type test report
shall be submitted with technical bid. Suitable arrangement shall be made for
drying of air inside the secondary terminal box. The dimensions of the terminal box and
its openings shall adequate to enable easy access and working space with use of normal
tools.
4.2.4 Polarity shall be indelibly marked on each primary and secondary terminal, Facility shall
be provided for short-circuiting and grounding of the C.T. secondary terminals inside the
terminal box.
4.2.5 The C.T. shall be provided with a rating plate with dimensions and markings as per
IS:2705. The markings shall be punched and not painted.
4.2.6 The current transformer shall be vacuum filled with oil after processing and thereafter
hermetically sealed to eliminate breathing and to prevent air moisture from entering the
tanks. Oil filling and/or oil sampling cocks, if provided to facilitate factory processing,
should be permanently sealed before dispatching the C.T. The method adopted for
hermetic sealing shall be described in the offer.
4.2.7 The castings of base, cooler etc. shall be die cast and tested before assembly to detect
cracks and voids if any.
4.2.8 The instrument security factor of metering core shall be low enough and not greater than
5. This shall be demonstrated on all the ratios of the metering core, in accordance with
procedure specified in IEC-185 or IS:2705. In case the instrument security factor of 5 or
less is not possible to be achieved on higher ratios, auxiliary CTs ratio 1/1 and 0.5
accuracy class shall be deemed to be included in the Bidder’s scope of supply. This shall
also be specifically brought out by the Bidder in his offer.
4.2.9.1 Primary winding shall be made out of high conductivity copper or aluminum, Conductors
used for the primary winding shall be rigid or housed in rigid metallic shell. Unavoidable
joints in the primary winding shall be welded type. The details of such welded joints shall
be indicated in the drawings submitted with the offer. For primary winding current
density shall not exceed 1.65 A/sq. mm for copper and 1.05 A/Sq.mm for aluminum.. if
made out of solid conductor .If the primary conductor is made out of tubular conductor
(pipe), the joints in the bend portion shall be allowed. The welding type quality and extent
shall be as per relevant ISS or other equivalent standard.
4.2.9.2 The design density for short circuit current as well as conductivity of the metal used for
primary winding shall meet the requirement of IS:2705. The Bidder shall in his offer
furnish detailed calculations for selection of winding cross-sections.
12
GETCO/E/04TS CT6/R2/Mar 08
4.2.10.1 Suitably insulated copper of electrolytic grade shall be used for secondary windings.
Type of insulation used shall be described in the offer. For multi ratio design, suitable
tappings shall be provided on the secondary winding.
4.2.11 The exciting current of the CT shall be as low as possible. The Bidder shall furnish along
with his offer the magnetisation curve/s for all the core/s.
A duplicate set of secondary terminals connected through a suitable link shall be provided
in the terminal box. One set shall be connected to the terminal secondary leads while the
other one shall be connected to external cable leads. This type of arrangement is essential
to prevent undue pressure to internal leads and failure of studs while connecting the
external cable leads to the secondary terminals, as both the terminals will be independent
for their connections.
Each primary terminal shall be made out of two rods of suitable dia. The primary
terminals shall be of heavily tinned electrolytic copper or aluminium alloy of 99.9%
conductivity. The minimum thickness of tinning shall be 15 microns. The current density
in the primary terminal rods shall not be exceed 1.75A/Sq. mm (under normal operating
condition current of approxi. 2400 Amps)
Secondary terminal studs shall be provided with at least three nuts and adequate plain and
spring washers for fixing the leads. The studs, nuts and washers shall be of tinned copper
of 99.9% purity and conductivity. The minimum out side diameter of the studs shall be
6mm. The length of at least 20 mm shall be available on the studs for inserting the leads.
The horizontal spacing between centers of the adjacent studs shall be at least 1.5 times the
outside circum dia of the nuts. Secondary terminals shall be brought out through
composite epoxy block with single gasket. Terminal blocks shall be provided for dummy
terminals.
4.2.14 The current transformer shall be provided with suitable test tap for measurement of
capacitance, tan delta as well as partial discharges, in factory as well as at site. Provision
shall be made of a screw on cap for solid and secured earthing of the test tap connection,
when not in use. A suitable caution plate shall be provided duly fixed on the cover of the
secondary terminal box indicating the purpose of the test tap and necessity terminal box
indicating the purpose of the test tap and necessity of its solid earthing as per prescribed
method before energising the C.T.
4.3.1 The porcelain hollow insulator used for the instrument transformer shall be
homogenous, free from lamination cavities and other flaws or imperfection that might
affect the mechanical or dielectric qualities. The hollow insulator shall conform to
the latest edition of IS: 5621. The puncture strengths of the hollow insulator shall
be entirely free from external and internal corona. The total creepage distance of the
hollow insulator shall be suitable for heavily polluted atmosphere i.e. the total
creepage distance shall be 6125 mm (minimum). The hollow insulator shall have
ample insulation, mechanical strength and rigidity for the conditions under with they will
13
GETCO/E/04TS CT6/R2/Mar 08
be used and shall be designed to prevent accumulation of explosive gases and provide
adequate oil circulation to remove internal heat. There shall be no undue stressing of any
part of the bushings due to temperature changes and adequate means shall be provided to
accommodate conductor expansion.
4.3.2 The hollow insulator shall be so designed that when operating at highest system
voltage specified, there will be no electric discharge between the conductors, and hollow
insulator. No corrosion or injury shall be causes to conductor insulation or supports by
the formation of substances produced by chemical action. The insulation of hollow
insulator shall be co-ordinated with that of the instrument transformer such that the
flashover, if any, will occur only externally to the Instrument Transformer. The hollow
insulator shall not cause radio interference when operated at rated voltage. The
specification of the bushing shall be stated in the tender.
4.3.3 The outer surface of metal tank shall be Hot Dip Galvanized, whereas, the
inner portion shall be painted with oil resistive, insoluble paint. The
GETCO reserves right for stage inspection during manufacturing process of
tank / CT. The galvanizing shall be as per applicable standard IS:2629 and
the minimum thickness of zinc coating shall be 610 gr/sqmt.
5.0 TESTS:
5.1 TYPE TESTS:
All the equipment offered shall be fully type tested as per relevant standard (latest
edition) as specified from accredited laboratory (accredited based on ISO/IEC
Guide 25 / 17025 or EN 45001 by the National accredition body of the country
where laboratory is located), as per IEC / IS / technical specification. The Bidder
shall furnish the type test reports for the CT/PT of the type and Design offered by
him along with the offer. The type test reports shall not be older than FIVE
years and shall be valid up to expiry of validity of offer.
Following type tests reports shall be submitted for CT.
1. Lightning Impulse voltage withstand test
2. High voltage power frequency wet withstand test on CT
3. Multiple Chopped lightning impulse test (according to IEC-
60044 -1 clause:9.1)
The current transformer shall be subjected to fast transient test, as per
following method, to access performance of CT in service to withstand the
high frequency over voltage generated due to closing & opening of
isolators.
Oil samples will be taken before and 3 days after the test. Gas analysis must
not show appreciable rate of increase in various gases related with the results
of the analysis performed before test.
14
GETCO/E/04TS CT6/R2/Mar 08
Total sum of crest values of current through secondaries must not exceed 5%
of the crest value to total current to earth.
CT must withstand dielectric tests after this test to pass the test.
However the purchaser reserves the right to demand repetition of some or all
the type tests in the presence of purchaser's representative. For this purpose
the Bidder may quote unit rates for carrying out each type test. This will
not be considered for Evaluation.
IMPORTANT NOTE: In case of non-submission of some of the type test reports, the bidder shall
confirm the submission of same before commencement of supply, without affecting delivery
schedule, from NABL accredited laboratory, free of cost. In absence of this confirmation, the
offer will be evaluated as non submission of type test report.
5.2.1 All acceptance and routine tests as stipulated in the relevant standards shall be carried out
by the bidder in presence of purchaser’s representative.
15
GETCO/E/04TS CT6/R2/Mar 08
10. Thermal coefficient test (On any one unit from offered lot)
11. Measurement of IR value by 5 kV motorized megger
12. Tests on Oil for CT:
a)BDV test ] On randomly selected unit of
b)Tan Delta test ] very first lot offered for
c)Water PPm test ] inspection and to be
d)Resistivity at 90 Deg Cel ] conducted after HV test only.
e)DGA test Copy of test report, received
from the power oil
manufacturer, to be submitted.
(NOTE: If the supplier of oil is changed during execution of order, same test
shall be repeated for the oil of new supplier.
All the tests reports and oscillograms shall be submitted and got approved from the purchaser
before dispatching the equipment.
6.0 INSPECTION:
i) The purchaser shall have access at all times to the works and all other places of
manufacture, where the instrument transformers are being manufactured and the
supplier shall provide purchaser representative all facilities for unrestricted
inspection of the works, raw materials, manufacture of all the accessories and for
conducting necessary testes as detailed herein.
ii) The successful bidder shall submit the stage wise inspection program.
Stages of inspection and owners participation would be defined and
tied up at the time of award of contract..
iii) No material shall be dispatched from its point of manufacture unless the material
has been satisfactorily inspected and tested.
iv) The acceptance of any quantity of the equipments shall in no way relieve the
successful Bidder of his responsibility for meeting all the requirements of this
specification and shall not prevent subsequent rejection if such equipments are
later found to be defective.
16
GETCO/E/04TS CT6/R2/Mar 08
i) Statement giving list of important raw materials, names of sub-suppliers for the
raw material, list of standards according to which the raw material in presence of
Bidder’s representative, copies of test certificates.
ii) Information and copies of test certificates as in (i) above in respect of bought out
items.
iv) Level of automation achieved and list of areas where manual processing exists.
vii) List of testing equipment available with the Bidder for final testing of equipment
specified and test plant limitation, if any, vis-a-vis type, special, acceptance and
routine tests specified in the relevant standards. These limitations shall be very
clearly brought out in schedule of deviations from specified test equipments.
viii) The following testing equipments shall be available for testing
at bidders works.
1) Partial Discharge test set up (preferably Robinsons)
2) Tan delta and capacitance test set up (Tettex or Dobble)
3) Minimum Sensitivity of high voltage laboratory-2.5pC for PD
measurement. This is to be demonstrated before test.
All test set up shall be calibrated at NABL accredited laboratory and
report shall be submitted with inspection report.
ix) Bidder shall have ISO certification.
7.2 The successful Bidder shall within commencement period, submit following information
to the Purchaser.
i) List of raw material as well as bought out accessories and the names of sub-
suppliers selected from the lists furnished along with offer.
ii) Type test certificates of the raw material and bought out accessories.
iii) Quality Assurance Plan (QAP) with hold points for purchaser’s inspection. The
quality assurance plan and hold points shall be discussed between the Purchaser
and Supplier before the QAP is finalised. The bidder shall submit the field Quality
Plan also.
7.3 The successful Bidder shall submit the routine test certificates of bought out items and
form raw material at the time of routine testing of the fully assembled equipment.
8.0 DOCUMENTATION:
17
GETCO/E/04TS CT6/R2/Mar 08
8.2 All drawings shall conform to international standards Specification (ISO) ‘A’ series of
drawing sheet/Indian Standards Specification IS11065. All drawings shall be in ink and
suitable for microfilming. All dimensions and data shall be in S.I. Units.
Drawing incorporating the following particulars shall be submitted by the bidder
with the bid, in hard as well as in AutoCAD format.
The Bidder shall furnish four sets of following drawings along with his offer.
8.4 The successful Bidder shall submit three sets of final versions of all the above drawings
for Purchaser’s approval. The Purchaser shall communicate his comments/approval on
the drawings to the supplier within reasonable time. After receipt of purchaser’s approval,
the supplier shall submit AutoCad format of the approved drawings.
8.5 The manufacturing of the equipment shall be strictly in accordance with the approved
drawings and no deviation shall be permitted without the written approval of the
Purchaser. All manufacturing and fabrication work in connection with the equipment
prior to the approval of the drawing shall be at the Supplier’s risk.
8.6 Twenty (20) copies of nicely printed and bound volumes of operation, maintenance and
erection manuals in English language, for each type and rating of equipment supplied
shall be submitted by the Supplier for distribution, prior to the dispatch of the equipment.
The manual shall contain all the drawings and information required for erection,
operation and maintenance of the instrument transformer. The manual shall also contain a
set of all the approved drawings, type test reports etc.
8.7 Approval of drawings/work by Purchaser shall not relieve the supplier of his
responsibility and liability for ensuring correctness and correct interpretation of the latest
revision of applicable standards, rules and codes of practices. The equipment shall
18
GETCO/E/04TS CT6/R2/Mar 08
confirm in all respects to high standards of engineering, design, workmanship and latest
revisions of relevant standards at the time of ordering and purchaser shall have the power
to reject any work or material which in his judgment is not in full accordance therewith.
9.3 Each consignment shall be accompanied by a detailed packing list containing the
following information:
9.4 The Supplier shall ensure that the packing list and bill of material are approved by the
purchaser before dispatch.
Any fittings, accessories or apparatus which may not have been specifically mentioned in
these specifications, but which are usual or necessary for the equipment of similar plant
shall be deemed to be included in the order and shall be supplied by the supplier without
extra charges. All plant and equipment shall be complete in all details whether such
details are mentioned in the specification or not.
19
GETCO/E/04TS CT6/R2/Mar 08
ANNEXURE – I
(CURRENT TRANSFORMERS)
SYSTEM PARTICULARS
[A] Electrical System Data:
a) System Voltage (KV rms) 400
b) Max. Voltage (KV rms) 420
c) Lighting impulse withstand voltage (dry & wet) (Kvp) 1425
d) Power Frequency withstand voltage (wet) (KV rms) 630
e) Switching surge withstand voltage (wet) (Kvp) 1050
f) Min. Corona extinction voltage at 50 Hz A.C. system 320
dry Condition (KV rms)
g) Radio interference voltage at one MHz for phase to 1000
earth voltage
h) Short Circuit level (KA) for 3 seconds 40
30 on
2000/1 tap,
2000- 2000-
Bus Diff. 60 on
1 4 1000- N.A. Ps 1000- 10/5/2.5 ---
Check 1000/1 tap,
500/1 500
120 on
500/1 tap
Bus Diff. -- Do -- Do -
2 5 N.A. Ps -- Do -- -- Do -- ---
Main -- -
-- Do 5 or
3 3 Metering 40 0.5 N.A. -- Do -- N.A.
-- less
30 on
2000/1 tap,
Transformer 4000/
-- Do 60 on
4 1 back up/line N.A. Ps 2000/ -- Do -- ---
-- 1000/1 tap,
prot main-I 1000
120 on
500/1 tap
Trans. Diff/
-- Do
5 2 line protn. N.A. Ps -- Do - -- Do -- -- Do -- ---
--
main-II
20
GETCO/E/04TS CT6/R2/Mar 08
30 on
2000/1 tap,
2000- 2000-
60 on
1 4 Bus Diff. 1000- N.A. PS 1000- 10/5/2.5 ---
1000/1 tap,
500/1 500
120 on
500/1 tap
-- Do 5 or
2 3 Metering 15 0.5 N.A. -- Do -- N.A.
-- less
30 on
2000/1 tap,
4 Transformer 4000/
-- Do 60 on
1 back up/line N.A. PS 2000/ -- Do -- ---
3 -- 1000/1 tap,
prot main-I 1000
120 on
500/1 tap
5 Trans. Diff/
-- Do
2 line protn. N.A. PS -- Do - -- Do -- -- Do -- ---
4 --
main-II
21
GETCO/E/04TS CT6/R2/Mar 08
30 on
2000/1 tap,
2000- 2000-
Bus / Tie 60 on
1 4 1000- N.A. PS 1000- 10/5/2.5 ---
Diff. Protn - I 1000/1 tap,
500/1 500
120 on
500/1 tap
Bus / Tie
-- Do -- Do -
2 5 Diff. Protn - N.A. PS -- Do -- -- Do -- ---
-- -
II
-- Do 5 or
3 3 Metering 15 0.5 N.A. -- Do -- N.A.
-- less
30 on
2000/1 tap,
Transformer 4000/
-- Do 60 on
4 1 back up/line N.A. PS 2000/ -- Do -- ---
-- 1000/1 tap,
prot main-I 1000
120 on
500/1 tap
Trans. Diff/
-- Do
5 2 line protn. N.A. Ps -- Do - -- Do -- -- Do -- ---
--
main-II
22
GETCO/E/04TS CT6/R2/Mar 08
ANNEXURE – II
(CURRENT TRANSFORMERS)
The test circuit for the measurement of partial discharge (PD) shall be in
accordance with sub clause 4.2 of IEC : 270-1968. The PD test shall be
carried out after all tests are completed. The applied voltage shall be raised
to rated voltage of the CT and shall be maintained for a period greater than
or equal to 10 seconds. The voltage shall then be reduced to measuring
voltage of
420 KV
1.1 X ----------- rms Phase to ground and maintained for a period greater
√¯ 3
than or equal to 1 minute. The PD level shall not exceed 10 pico columbs.
23
GETCO/E/04TS CT6/R2/Mar 08
24
GETCO/E/04TS CT6/R2/Mar 08
30.1 TANK:
i) Thickness of
a) Flange
b) Top plate
ii) Thickness of Press Board
provided inside tank
30.2 GASKET:
i) Material
ii) Thickness
30.4 SECONDARY
TERMINALS:
i) Material of composite
secondary mould (FRP /
EPOXY)
ii) Dummy leads provided?
(YES / NO)
iii) Terminal connector block
a) Make
b) Size
c) Rating
28.5 INSULATOR:
i) Make
ii) Sealant used
25
GETCO/E/04TS CT6/R2/Mar 08
Note : a) The details against each point of GTP are required to be submitted along with
the bid, otherwise, bid is liable for rejection.
Signature :
Name :
Status :
26
GETCO/E/04TS CT6/R2/Mar 08
Annexure - C
List of documents attached with technical bid:
Bidder shall invariably attach the following documents and clearly marked and duly
flagged in technical bid. In absence of these documents offer will be evaluated as a non
submission.
DATE:
PLACE:
27