CONTRACT : 921BGCEPS
I have checked with BGC regarding the rahabilitation schedule for this
Industrial water Pump (6600-P-02B)
REVISION RECORD
CHECKED APPROVED
REV DESCRIPTION DATE ORIG.
CONST.
ENG LEAD
BGC WG
CONTENTS
Requirements: REQUIRED
YES NO
OPERATIONS (ISOLATIONS) Y
SPECIAL TOOLS/CRANES Y
SCAFFOLDING N
WORK PERMIT Y
LIVE SYSTEM N
TEMPORARY SUPPORT Y
PAINTERS Y
WELDING
N
Technical Safety
Cert Engineer
WORKPACK QA CHECK LIST
Engineering
HSE
QA
0033-9500-WGEL-
WORKPACK
S002-ISGP-G00000- REV: 01R
NUMBER: BA-5794-00064
WORKPACK CONTENTS CHECK
Drawings, Documents and Drawing Register
a – Drawings included as per Drawing Register
NOTE:
1.0 If not applicable, the relevant party should insert a N/A into the correct box;
2.0 Each party should sign the relevant box with their initials;
3.0 Existing drawing marked for repair is attached;
4.0 Risk Assessment Detail study / demolition methodology shall be addressed by the
demolition CONTRACTOR prior to commencement of work as advised by BGC
15/4/2018.
After evaluation of the inputs from the Field Inspection, Decision Sheets were prepared, and
it has been concluded that the following equipment foundations at the Umm Qasr Storage
Terminal require repairs:
Foundation drawings and photographs of the existing drawings taken during the Field
Inspection referenced in Section 2.
Demolition and Repairs works shall be carried out in accordance with the Project
Specification for Concrete Repair and Concrete Works Specification referenced in Section 2
Piping Demolition scopes are excluded from this work pack. Reference of associated
demolition work pack for piping as included in below table.
Warning
Live process equipment, piping, structures and other facilities may be present
in and around the worksite during the repair work. The contractor shall take all
reasonable precautions to identify and protect these facilities from damage
during the repair work and ensure the safety of personnel and equipment on
site. The contractor is the responsible to get Permit to Work to perform the
work
The at site.
scope of work consists of:
Before starting the repair works CONTRACTOR shall ensure that Industrial Water Pump
shall be removed from foundation or isolated
CONTRACTOR shall follow the sequence of concrete demolished and repair works for
Industrial Water Pump foundations as directed and approved by BGC.
CONTRACTOR shall remove and clean the dust from foundation and from surrounding
area prior to start the repair works
Equipment’s to be used for the repair shall be reviewed by BGC operation team for
acceptance.
All the existing pipe support foundations close to this equipment foundation shall be
demolished and reinstated to avoid any obstruction during the repair works, temporary
pipe supports shall be arranged by the contractor for the pipes with prior approval from
the company.
All materials including anchor bolts, grouting, concrete back fill etc. must be approved
prior to execution of work by BGC supervision staff.
The demolished & loose concrete shall be carted away to the approved dumping area.
Any underground services found present shall be properly protected.
Before re-instatement of the grade slab if any the sub base shall be properly compacted
as per the specification referenced in Section 2.
Marking out the areas to be repaired on sides of foundation. Carrying out deep skin
repair to the sides of foundation as shown in attached drawings in section -2 and as per
concrete Repair and Concrete Works Specifications referenced in Section 2.
Carrying out replacement of cracked grout around base plates of Pumps as per concrete
Repair and Concrete Works Specifications referenced in Section 2.
CONTRACTOR shall ensure that top of concrete should be chipped before doing the
grout works as shown in attached drawings in section 2and as per Concrete Repair and
Concrete Works Specification referenced in section 2.
Providing 25mm thick isolation joint all around pump foundations with joint filler and
sealant as per Concrete Repair and Concrete Works Specifications referenced in Section
2.
Reinstatement of thick grade slab with structural concrete (28 N/mm2 28day cylinder
strength) and reinforcement (ASTM A615 Grade 60) in accordance with concrete Repair
and Concrete Works Specifications referenced in Section 2.
Preparing post-repair documentation: drawings with details of repair works carried out
markups, photographs and test reports as specified in Concrete Repair Specifications.
Updating Bill of Quantities, based on the actual quantum of repair works carried out.
Refer any site queries with this Work Pack to Project Manager by e-mail to
barry.bradley1@woodgroup.com, with a copy being cc’d to DCC on
WG_BGC.DCC@woodgroup.com All TQs are to be accompanied by a standard Query
Form.
Upon scope completion, the Work pack close-out checklist will be completed and
signed-off to confirm Work pack completion and closure.
1.4 Definitions:
Company/ Principal /
Owner Basrah Gas Company (BGC).
Project Management and Engineering Consultant appointed by
Engineer COMPANY to perform services on the contract – WOOD.
The contractor performing the construction work described
Contractor under the CONTRACT with the COMPANY.
The party, which manufactures and/ or supplies, equipment
Manufacturer/
and services to perform the duties as specified by COMPANY
Supplier/ Vendor
in the scope of supply.
Abbreviations
Table 1.1 illustrates the abbreviations and terms used in this document, alongside their
description.
Table 1.1 – Abbreviations
TBC To Be Confirm
UQ Umm Qasr
0011-9500-WGEL-G000-ISGP-
Concrete Works Specifications 02A
G00000-CX-7880-00002
Completely Damaged
Surface
Entire foundation
face got broken
Damaged Damaged
Damaged/Broken foundation face foundation face
foundation face
6600-P-2B
Page 1 of 5
6600-P-2B
Page 2 of 5
SOUTH VIEW
6600-P-02B
6600-P-2B
Page 4 of 5
EAST VIEW
6600-P-02B
N
6600-P-2B
Page 5 of 5
WEST VIEW
6600-P-02B
Wood Doc No: 9500-WGEL-S002-ISGP-G00000-BA-5794-00064 Repair Work Pack-UQST Refrigerated
Storage System – Civil Construction Repair Work Pack for Foundation of Industrial Water Pump 6600-P-2B
1 Revision 01R
AS ATTACHED
AS ATTACHED
Certification
Scope of work is not complete until all Construction and Completions check / test sheets are
Signed-off and approved by the worksite management. Certification included in this
work pack is as ATTACHED.
Red line
Document Number Document Title Rev mark-up
Req
DETAIL OF FOUNDATION
B7300-167C-2 02 YES
(6600-P-2B)