Sie sind auf Seite 1von 3

PROGRESS REPORT

Job No. : N/19/06/004


Subject : Container ER1
Client : PT. KA Properti Manajemen
Project : Muaraenim Div. III Persinyalan & Telekomunikasi (190033)
Dimension/Type : L8,058 x W2,438 x H3,091 mm
Quantity : 1 (one) unit
Issue Date : July 12, 2019
Week 2nd on July 2019
8 - 12 July 2019
PROGRESS WEEKLY 12/07/2019

PROJECT KAPM - CONTAINER ER-1


PT. BASUKIGRAHA FABRIKATAMA
(WEEK 2nd)
Period : 8 - 12 July 2019

Jul-19 Progress
No Process name Bobot (%) WEEK I WEEK II WEEK III WEEK IV WEEK V (%)
1 2 3 4 5 8 9 10 11 12 13 15 16 17 18 19 22 23 24 25 26 29 30 31
Baseframe FAbrication
1 FABRIKASI BASEFRAME 9,15% 1,83% 1,83% 1,83% 1,83% 1,83%

2 NDT BASE FRAME 0,85% 0,85%

3 FABRIKASI DAN PEMASANGAN OMEGA FLOOR 1,95% 0,65% 0,65% 0,65%

4 PEMASANGAN PLAT LANTAI 10,07% 2,52% 2,52% 2,52% 2,52%

5 PAINTING BASEFRAME 11,74% 5,87% 5,87%

General Assy
6 PEMASANGAN Z BAR U BAR 3,27% 3,27%

7 DINDING PARTISI SANDWICH 10,19% 2,55% 2,55% 2,55% 2,55%

8 ROOF 3,61% 1,81% 1,81%

9 ACCESORIES (PINTU DAN VYNIL DLL) 10,84% 2,71% 2,71% 2,71% 2,71%

10 PAINTING WALL 12,01% 12,01%

11 PEMASANGAN DUDUKAN AC DAN PENGECETAN 0,20% 0,07% 0,07% 0,07%

12 FABRIKASI SPREADER BAR, LIFTING LUG dan PAINTING 4,63% 1,16% 1,16% 1,16% 1,16%

Mecahical & Electrical Process


13 FABRIKASI CONDUIT DAN CABLE TRAY 2,34% 2,34%

14 PEMASANGAN CABLE TRAY & CONDUIT 2,64% 1,32% 1,32%

15 PEMASANGAN LAMPU & SMOKE DETECTOR 4,69% 1,56% 1,56% 1,56%

16 PEMASANGAN SWITCH,RECEPTACLE AND SOCKET 1,23% 0,61%


0,0061
17 WIRING CABLE 1,37% 0,46% 0,46% 0,46%

18 PEMASANGAN AC 5,23% 1,74% 1,74% 1,74%

19 INSTALATION PDB & FIRE EXT 4,01% 1,34% 1,34% 1,34%

Total 100,00% `
Per Day 1,83% 1,83% 2,48% 2,48% 3,33% 2,52% 2,52% 4,85% 3,74% 7,09% 5,87% 5,82% 2,55% 3,87% 5,43% 3,44% 6,69% 3,78% 3,16% 4,91% 16,24% 4,24% 1,34%
Progress Plan
Accumulated 1,83% 3,66% 6,14% 8,62% 11,94% 14,46% 16,98% 21,83% 25,57% 32,67% 38,54% 44,36% 46,90% 50,77% 56,20% 59,64% 66,33% 70,11% 73,28% 78,18% 94,43% 98,66% 100,00%

2,25% 3,69% 5,35% 8,54% 9,89% 14,43% 19,59% 23,84% 25,60% 35,35%
Daily Realization
Progress Actual
0,4% 0,0% -0,8% -0,1% -2,1% 0,0% 2,6% 2,0% 0,0% 2,7%
Deviation

Note :

1. Deviasi/ selisih tanggal 5 Juli minggu ke 1, dikarenakan issue quality


untuk finishing after welding (leveling & Sparter remove ) Prepared By Acknowledge By Approved By
Prod. Spv M/E. Spv Prod.Manager Project Manager

( Didi s ) ( Ahmad J. ) ( JUMADI ) ( Mardiansyah )


PROGRESS WEEKLY 12/07/2019

PROJECT KAPM - CONTAINER ER-1


PT. BASUKIGRAHA FABRIKATAMA
(WEEK 2nd)
Period : 8 - 12 July 2019

Building Process Mechanical & Electrical Process


Fabrication Process Cable tray Process Painting
Process (Primer Coat) Baseframe

Accessories Process

Assy & Weld Suppot Outdor AC Lifting lug Assy

Das könnte Ihnen auch gefallen