To Do List as of Fri 19/10/18

Pembangunan Puskesmas Sidoarjo.mpp

ID Indicators Task Mode Task Name Duration Start Finish Predecessors


Week of 17 September
20 Auto Scheduled Beton foot plat 2 days Tue 18/09/18 Thu 20/09/18 19
Week of 24 September
24 Auto Scheduled Pengecoran sloof 2 days Mon 24/09/18 Wed 26/09/18 23
28 Auto Scheduled Pengecoran kolom 2 days Sat 29/09/18 Tue 02/10/18 26SS+3 days

Week of 01 October
28 Auto Scheduled Pengecoran kolom 2 days Sat 29/09/18 Tue 02/10/18 26SS+3 days
32 Auto Scheduled Pengecoran balok 2 days Sat 06/10/18 Tue 09/10/18 31FF+2 days
Week of 08 October
32 Auto Scheduled Pengecoran balok 2 days Sat 06/10/18 Tue 09/10/18 31FF+2 days
36 Auto Scheduled Pengecoran plat 2 days Tue 09/10/18 Thu 11/10/18 32SS+2 days

Page 1
To Do List as of Fri 19/10/18
Pembangunan Puskesmas Sidoarjo.mpp

Resource Names % Complete Physical % Complete Cost

pekerja[9,49];tukang[0,95];kepala tukang[0,63];beton0%
K300[1 m3];alat bantu;mandor[0,06]
0% Rp2.093.073

pekerja[9,49];tukang[0,95];kepala tukang[0,63];beton0%
K300[1 m3];alat bantu;mandor[0,06]
0% Rp2.093.073
pekerja[20,13];tukang[2,1];kepala tukang[1,34];beton0%
K300[1 m3];alat bantu;mandor[0,13]
0% Rp3.236.163

pekerja[20,13];tukang[2,1];kepala tukang[1,34];beton0%
K300[1 m3];alat bantu;mandor[0,13]
0% Rp3.236.163
pekerja[20,13];tukang[2,1];kepala tukang[1,34];beton0%
K300[1 m3];alat bantu;mandor[0,13]
0% Rp3.236.163

pekerja[20,13];tukang[2,1];kepala tukang[1,34];beton0%
K300[1 m3];alat bantu;mandor[0,13]
0% Rp3.236.163
pekerja[17,64];tukang[1,76];kepala tukang[1,18];beton
0%K300[1 m3];alat bantu;mandor[0,12]
0% Rp2.961.623

Page 2