Three Storey Residential Building Project Schedule

SKMP BUILDERS

Project Start Date 1/29/2018 (Monday) Display Week 11 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18
9 Apr 2018 16 Apr 2018 23 Apr 2018 30 Apr 2018 7 May 2018 14 May 2018 21 May 2018 28 May 2018
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
% WORK
WBS TASK COST % OF COST PREDECESSOR START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 SITE SETUP - -
0.1 MOBILIZATION 15,000 0.1363586159 N/A Mon 1/29/18 Tue 1/30/18 2 0% 2
0.1 SITE CLEARING AND GRABBING 10,000 0.2272643598 MOBILIZATION Wed 1/31/18 Thu 2/01/18 2 0% 2
0.1 SETTING UP TEMPORARY FACILITIES 150,000 1.5908505187 SITE CLEARING AND GRABBING Fri 2/02/18 Fri 2/02/18 1 0% 1
STAKE OUT AND SETTING UP TEMPORARY
0.1 45,000 1.9999263663 SITE CLEARING AND GRABBING Thu 2/01/18 Fri 2/02/18 2 0% 2
FENCING
SUBTOTAL 220,000

2 EARTHWORKS - -
2.1 EXCAVATION 149485 3.3588308794 STAKE OUT AND SETTING UP TEMPORARY FENCING Mon 2/05/18 Sun 2/11/18 7 0% 5

2.2 SHORING 10000 3.4497366233 EXCAVATION Mon 2/12/18 Wed 2/14/18 3 0% 3


2.3 BACKFILLING AND COMPACTION 24600 3.6733647534 SHORING Thu 2/15/18 Mon 2/19/18 5 0% 3
2.4 HAULING OF EXCESS DEBRIS/CLEARING 90000 4.4915164487 BACKFILLING AND COMPACTION Tue 2/20/18 Tue 2/20/18 1 0% 1
2.5 SOIL POISONING 25000 4.7187808085 HAULING OF EXCESS DEBRIS/CLEARING Tue 2/20/18 Tue 2/20/18 1 0% 1
2.6 GRAVEL BEDDING 21000 4.9096828708 SOIL POISONING Wed 2/21/18 Fri 2/23/18 3 3

SUBTOTAL 320,085

3 FOUNDATION WORK - -
REINFORCING STEEL BAR INSTALLATION FOR
3.1 168000 6.4368993687 GRAVEL BEDDING Mon 2/26/18 Fri 3/02/18 5 0% 5
FOOTING AND COLUMN( FROM FDN)
3.2 Shuttering .concrete pouring of footing 67750 7.0527857838 REINFORCING STEEL BAR INSTALLATION FOR FOOTING AND COLUMN( FROM FDN) Mon 3/05/18 Mon 3/05/18 1 0% 1
SUBTOTAL 235750

4 REINFORCING STEEL BAR WORKS - -


4.1 SETTING UP REBAR FOR COLUMN 600200 12.5089485342 REINFORCING STEEL BAR INSTALLATION FOR FOOTING AND COLUMN( FROM FDN) Tue 3/06/18 Mon 3/19/18 14 0% 10

4.2 SETTING UP REBAR FOR BEAMS AND GIRDERS 685938 18.7445189518 SETTING UP REBAR FOR COLUMN Fri 3/09/18 Fri 3/23/18 15 0% 11

4.3 SETTING UP REBAR FOR SLAB 428711 22.6417481902 SETTING UP REBAR FOR BEAMS AND GIRDERS Wed 3/14/18 Fri 3/23/18 10 0% 8
DURATION( DAYS) PERCENTAGE COMPLETED (%)
2 0.1363586159
4 0.2272643598
S CURVE
5 1.5908505187
7 1.9999263663 120
12 3.3588308794
15 3.4497366233 100
18 3.6733647534
19 4.4915164487 80
20 4.7187808085
23 4.9096828708 60
28 6.4368993687
29 7.0527857838 40
39 12.5089485342
50 18.7445189518
20
58 22.6417481902
64 24.1286025378
0
72 25.429600092 0 20 40 60 80 100 120 140 160
80 26.3588840593
90 30.099437248
100 35.7102670311
115 44.1744383502
122 46.9958287899
127 50.5361529871
142 79.0229223379
152 85.0088837638
162 90.3176514865
177 100.0000008182
URVE

00 120 140 160 180 200