Sie sind auf Seite 1von 7

Provision of Well Testing Services

Bunga Mas International Company


Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

SCHEDULE NO.3
APPENDIX NO 1

REMUNERATION AND ESTIMATE OF


DRILL STEM TEST SERVICES

1. CONTRACTOR REMUNERATION

For performing the services SERVICES in accordance with the terms of this CONTRACT, it is
agreed that the remuneration payable to the CONTRACTOR shall be based on the services
SERVICES rendered and shall be calculated by the charges and conditions set forth below
and supported by discounted charges as given in CONTRACTOR’s Pricing Schedule attached.

2. PRICING CONDITIONS

2.1 Only those charges listed in this schedule will be allowed unless COMPANY gives
written instruction to the contrary. Any additional equipment/services shall be based
on applying a standardized ________ percent (%), "blanket" discount to the attached
CONTRACTOR’s price list.

2.2 All charges are in US Dollars unless stated otherwise.


2.3 Drill Stem Testing Service is contracted on an Exclusive Rental basis Formatted: Font: Bold
2.32.4CONTRACTOR is also required to submit rental prices of DST equipment on a Call Out
Basis..
2.42.5One Mobilization and One Demobilization charge each will apply when equipment
moves from CONTRACTOR’s Base to fieldWORKSITE, and from field WORKSITE to
CONTRACTOR’s base.
2.52.6At the end of Well Testing campaign, the equipment will be demobilized to
CONTRACTOR’s base (lump sum demobilization charge)

1. MOBILISATION/DEMOBILISATION FEE

The lump sum Mobilization/Demobilization Fee is the total compensation to the


CONTRACTOR for the mobilization of the CONTRACTOR’s EquipmentEQUIPMENT, specified
in Schedule 2, Appendix 1 – CONTRACTOR’s Equipment and Materials, Base to and from
COMPANY's Point of Delivery during the CONTRACT PeriodTERM. The fee is due and
payable each time the CONTRACTOR’s Equipment EQUIPMENT is called out except for any
trips required for the redress of the subsurface testing tools. It is the total compensation to
the CONTRACTOR for the:

• Repair and or maintenance of the CONTRACTOR’s Equipment EQUIPMENT prior to


the commencement of the services
• Trucking costs for the CONTRACTOR’s Equipment EQUIPMENT from CONTRACTOR’s
Base to the first well location and from the last well location to CONTRACTOR’s Base.
and from the Delivery Point

Remuneration of Drill Stem Services - Page 1 of 7


Provision of Well Testing Services
Bunga Mas International Company
Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

• Compensation during time required to mobilize and demobilize CONTRACTOR’s


Equipment EQUIPMENT and Personnel from the CONTRACTOR’s base and the
COMPANY’s Point of Delivery to the well location.
 No Mobilization nor Demobilization charge is applicable if/when equipment and
personnel are moved inter-well.

The COMPANY must pay the CONTRACTOR for providing the Services SERVICES at the
following rates:

DRILL STEM Testing Equipment Mobilization Fee: US$ / mob

DRILL STEM Testing Equipment Demobilization Fee: US$ / demob

4. CONTRACTOR'S EQUIPMENT RATES

4.1 DRILL STEM Equipment Standby Rate

The Standby Rate for the DRILL Drill STEM Stem TEST Test Equipment equipment will
commence when the equipment arrived on WORKSITE(s) and is fully operational and ready
for serviceSERVICE.

Standby Rate will end the day the CONTRACTOR’s Equipment EQUIPMENT leaves from the
final WORKSITE(s) for demobilization to the CONTRACTOR's local base of operation.

Item Equipment Description Qty Unit Cost Item Total Cost Formatted Table
US$/DAY US$/DAY
Surface Test Tree/ Flowhead, 3,000 psi
4.1.0 1
WP
Tester Valve Assemblies, all items for 5"
4.1.1 2
OD test tools,
4.1.2 Circulating Valves, multi setting, 2
Reversing Valve, annular pressure
4.1.3 2
operated
4.1.4 Safety Valves , downhole 1
4.1.45 Gauge carriers, for up to four recorders. 1
4.1.56 Slip joints 5" OD 2
Retrievable Packers, for 7” 26 ppf
4.1.67 2
casing,
4.1.78 Hydraulic Jars, full bore 2
X-overs for CONTRACTOR's tools to test 2
4.1.89
tubing and drill collars sets
4.1.190 Maintenance Equipment & Spares 1
4.1.101 Electronic Memory recorders, EMR 4

Remuneration of Drill Stem Services - Page 2 of 7


Provision of Well Testing Services
Bunga Mas International Company
Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

4.1.112 Computer for EMR processing 2


4.1.123 Miscellaneous Tools Package 1
9 5/8”, Retrievable Packer (Optional) Commented [d1]: Need to add shock absorber

[NOTE: based on the comments, it Formatted: Font: Font color: Black, (Asian) Korean, Highlight
seems that shock absorber will be
4.1.134 required for the utilization of 9 5/8” 2
retrievable packer, such shock absorber
must also be included in this list, if it is
not an integral part of the retrievable
packer]
4.1.14 7”, Retrievable Packer (Optional) 2
Gauge carriers, for up to four recorders
4.1.155 1
(Optional)
Electronic Memory recorders, EMR
4.1.161 4
(Optional)
4.1.172 Computer for EMR processing (Optional) 2
Two (2) Drop-Bar actuated Production Formatted: Font: 10 pt
4.1.18 2
Valve (Optional) Formatted: Left

Table 4.1 DRILL STEM Equipment Standby Rate / DAY Formatted: Font: 10 pt
Formatted Table

4.2 DRILL STEM Equipment Operating Rate

The Operating Rate for the Drill Stem Testing Equipment equipment will commence when
the Equipment equipment is used to perform DRILL STEM TEST Operations. Only one Rate
should apply.

Operating rates for all downhole components does not commence until tools go below the
rotary table and operating rates cease when tools are above the rotary table. If any
downhole components are deemed Lost in Hole, operational and standby charges will cease
upon declaration of items Lost in Hole.

Item Equipment Description Qty Unit Cost Item Total Cost Formatted Table
US$/DAY US$/DAY
Surface Test Tree/ Flowhead, 3,000 psi
4.2.0 1
WP
Tester Valve Assemblies, all items for 5"
4.2.1 2
OD test tools,
4.2.2 Circulating Valves, multi setting, 2
Reversing Valve, annular pressure
4.2.3 2
operated
4.2.4 Safety Valves , downhole 1
4.2.45 Gauge carriers, for up to four recorders. 1
4.2.56 Slip joints 5" OD 2
Retrievable Packers, for 7” 26 ppf
4.2.67 2
casing,
4.2.78 Hydraulic Jars, full bore 2

Remuneration of Drill Stem Services - Page 3 of 7


Provision of Well Testing Services
Bunga Mas International Company
Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

X-overs for CONTRACTOR's tools to test


tubing and drill collars ; from Surface 2
4.2.89
Test Tree (Flowhead) to 2 7/8” EUE sets
Tubing
4.2.910 Maintenance Equipment & Spares 1
4.2.101 Electronic Memory recorders, EMR 4
4.2.112 Computer for EMR processing 2
4.2.123 Miscellaneous Tools Package 1
9 5/8”, Retrievable Packer (Optional) Commented [d2]: Need to add shock absorber

[NOTE: based on the comments, it


seems that shock absorber will be
4.2.134 required for the utilization of 9 5/8” 2
retrievable packer, such shock absorber
must also be included in this list, if it is
not an integral part of the retrievable
packer]
4.2.14 7”, Retrievable Packer (Optional) 2
Gauge carriers, for up to four recorders
4.2.155 12
(Optional)
Electronic Memory recorders, EMR
4.2.166 4 Formatted: English (United States)
(Optional)
4.2.17 Computer for EMR processing (Optional) 2
Two (2) Drop-Bar actuated Production
4.1.18 2
Valve (Optional)
4.2.17 Computer for EMR processing (Optional) 2 Formatted: English (United States)
Formatted Table
Table 4.1 DRILL STEM Equipment Operating Rate / DAY

The COMPANY reserves the right to reduce the quantity for each item to suit requirements. The
daily rate will be adjusted based on the quantity shipped. The CONTRACTOR shall provide
additional back up equipment, as required, but there will be no additional compensation to the
CONTRACTOR.

5. CONTRACTOR'S PERSONNEL RATES

DRILL STEM Testing Personnel

Item Description Qty Maximum Personnel Rate


US$/day /each
DRILL STEM Testing Personnel:
5.1.i DST Specialist 1
5.2.i DST Operator 1
5.3.i Memory Gauge Engineer 1

The CONTRACTOR shall provide the day rate for each position as per the attached price list and
shall specify the day rate that is applicable for this AgreementCONTRACT. The totals for each
rate will be calculated based on the COMPANY specified number of people. This quantity is

Remuneration of Drill Stem Services - Page 4 of 7


Provision of Well Testing Services
Bunga Mas International Company
Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

sufficient to perform the services in this AgreementCONTRACT. It If the CONTRACTOR requires


additional personnel to perform the testing services there will be no additional compensation
due to the CONTRACTOR.

If the COMPANY approves an increase in the CONTRACTOR’s Personnel, to perform additional


services, the compensation to the Contactor CONTRACTOR will be at the valid price list rate less
the average discount rate from above table. (Total CONTRACTOR’s Personnel Cost based on
Tender Rate divided by the Total CONTRACTOR’s Personnel Cost from the Price Book).

6. EQUIPMENT ASSET VALUE

The Equipment Asset value is the CONTRACTOR's declared asset value as stipulated by
Indonesian Customs declaration for each item of subsurface or subsurface testing equipment
that is lost in the hole or damaged beyond repair. Indonesian Customs documentation must be
presented verifying declared value on all equipment Lost In Hole. If equipment was
manufactured in Indonesia a manufacturing invoice must be presented verifying the declared
value.

Item Description Declared Asset Value


6.1.1 Surface Test Tree Assembly, 3,000 psi WP,
6.2.1 Tester Valve Assemblies, all items for 5" OD test tools,
6.2.2 Circulating Valves, multi setting,
6.2.3 Reversing Valve, annular pressure operated
6.2.4 Gauge carriers, for up to four recorders.
6.2.5 Slip joints 5" OD
6.2.6 Retrievable Packers, for 7” 23 ppf casing,
6.2.7 Safety Joints, full bore,
6.2.8 Hydraulic Jars, full bore
6.2.9 X-overs for CONTRACTOR's tools (as specified above)
6.2.10 Maintenance Equipment & Spares
6.2.11 Electronic Memory recorders, EMR,
6.2.12 Computers, with software
6.2.13 Miscellaneous Tools

7. OPTIONAL EQUIPMENT VALUE

The Optional Equipment Value is the CONTRACTOR’S Optional Equipment Value in order to
purchase or utilizing assets whenever required by COMPANY. The Optional Equipment shall refer
to price list below :

Item COMPANY Specifications Declared Value US$ Formatted: Font: 10 pt

1. 9 5/8”, 40 ppf Retrievable Packer Formatted: Font: 10 pt


 CONTRACTOR to specify and quote for packer
and other hardware to allow DST testing in 9
5/8” 40ppf, if requested.
 Plus one backup packer

Remuneration of Drill Stem Services - Page 5 of 7


Provision of Well Testing Services
Bunga Mas International Company
Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

2. 7”, 26 ppf Retrievable Packer Formatted: Font: 10 pt


 CONTRACTOR to specify and quote for packer
and other hardware to allow DST testing in 7”
26ppf, if requested.
 Plus one backup packer
23. One Two (21) gauge carriers, Formatted: Font: 10 pt
 full bore, with capacity for up to four Formatted: Font: 10 pt
recorders.
Formatted: Font: 10 pt
 Complete with 2 7/8” EUE Cross-over top and
bottom
43. Four (4) Electronic memory recorders, Formatted: Font: 10 pt
 EMR, with a minimum of 1,000,000 data
points Max Temp 270 oF, Press 7,500 Psi

54. One (1) Field Computer, Formatted Table


 with capability to program and read the EMR Formatted: Font: 10 pt
complete with software to analyze and
transfer the data, to compact disc, at the
Sites.
 Plus one backup field computer

Formatted: Font: 10 pt, Not Bold


Formatted: Font color: Blue
Two (2) Drop-Bar actuated Production Valve / Flow
port ( to connect rathole and tubing) after dropping
the Drop Bar to perforate guns Formatted: Font: 10 pt, Font color: Blue

8. TOTAL DRILL STEM VALUE CALCULATIONS

The following estimated days and scope of service for each phase are estimated for the total
value calculation only and do not represent any commitment by the COMPANY. The cost of any
additional equipment, called out, will be at the rate specified in item 2.1 but is not itemized in
the total contract value calculation. CONTRACTOR is also requested to provide similar value Formatted: Font: Bold, Font color: Auto, (Asian) Korean
calculations for Optional Call-out Basis. Formatted: Font: Bold, English (United States)

DRILL STEM Testing Program Total Value

Unit Cost Item Total Cost


Item Description Qty Units Formatted Table
US$/DAY US$/DAY
7.1.1 Mob/Demob

Mobilization Fee 1 Lumpsum


Demobilization Fee 1 Lumpsum
Each
Each
NA
A. Mobilization/Demobilization Charges Total US$

Remuneration of Drill Stem Services - Page 6 of 7


Provision of Well Testing Services
Bunga Mas International Company
Attachment 12- Schedule 3 Appendix 1- Remuneration of Drill Stem Services

7.1.2 DRILL STEM TEST


Equipment

Standby Rate 10100*


Operating Rate 3210** Commented [d3]: 55 days, assumed
Formatted: Left
*estimated standby time
Formatted: Font: 9 pt
**4 days/well, 8 wells Days Formatted: Font: 9 pt, Bold
[NOTE: proposed to Days Formatted: Font: 7 pt
incorporate the comments
regarding estimated Formatted: Left, Indent: Left: 0", Add space between
paragraphs of the same style
utilization days for the
drill stem test equipment Formatted: Left
in this list] Formatted: Font: 9 pt
B. Total Rental Charges US $ Formatted: Left, Indent: Left: 0", Add space between
paragraphs of the same style
7.1.3 CONTRACTOR’s Personnel
Formatted: Font: 9 pt, Bold, Not Highlight

DST Specialist (1) Formatted: Font: 9 pt


DST Operator (1) 1032 Days Formatted: Font: Bold, Highlight
Memory Gauge Eng (1) 1032 Days Formatted: Space Before: 0 pt, After: 0 pt, Don't keep with
10 32 Days next
Formatted: Font: Bold
C. Total Personnel Charges US$
7.1.4 Additional Services
COMPANY Estimate
Less CONTRACTOR
Discount
D. Total Miscellaneous Charges US$
(A+B+C+D) = Total Value US$

Total Drill Stem Testing Services Program Value US$_______________

Remuneration of Drill Stem Services - Page 7 of 7