COLLEGE OF ENGINEERING AND ARCHITECTURE

CIVIL ENGINEERING DEPARTMENT


ON THE JOB TRAINING
Summer 2019

Weekly Accomplishment Report

Name: Mary Kaye Paquibot - 109


Company: UKC Builders, Inc.
Address: Tablon, Cagayan de Oro City

DATE Activities Description Participation Learning Experience Documentation


1 Curing of Curing is the process of Helped in making Curing of concrete samples must begin
samples. maintaining satisfactory and gathering the after placement and finishing and must
moisture content and samples and continue for a time until it reaches its
temperature in freshly cast putting it into the desired strength and durability.
concrete for a definite period curing tank. Uniform temperature should be
of time immediately following maintained throughout the process to
placement. It is intended to avoid thermal shrinkage cracks. The
keep the concrete moist quickly drying surface of concrete Curing tank with Details written on
enough for the hydration of results the interior of the concrete. That concrete cylinder a white board
20-May cement to be continued until will then cause high internal stresses samples
the desired properties are which are responsible for early micro
developed. cracks.

2 Field density A field density test is used Conducted the A field density test is used to measure
test as a field control test for the field density test the amount of compaction achieved
compaction of soil or any along with other during a construction. The most
other pavement layer. The trainees. commonly used method is the sand
test method used in highway replacement method. The basic Excavating the Sand replacement
construction is the sand principle is to measure the in-situ material method
replacement method. This volume of hole from which the material