Analysis And Construction of ROB
ACKNOWLEDGEMENT
I would like to express our sense of gratitude from the apex of heart to helpful supervisor Mr.
Rajinder Singh [Executive Engineer,PWD(B&R),Mukerian],Mr. Karanbir Singh [Sub.
Divisional Engineer,PWD(B&R)],Mr.Amarjit Singh,[Junior Engineer,PWD(B&R),Mukerian].
The supervision and support that they gave truly help the progression and smoothness of the
project work. The co-operation is much indeed appreciated.
The project during semester would be nothing without the guidance , support and imagination
from these people.
Besides, this project work makes us realized the value of working together in a team and as a
new experience in working environment ,which challenges us every minute.
Not to forget, great appreciation goes to the rest of Department of Civil Engineering’s faculty
that gives me opportunity to work in practical environment to expand my knowledge . The whole
program really brought us together to appreciate the true value of friendship and respect for each
other.
Last but not least , I would thankful to my parents who provide me required help and guidance
that I needed.
GURPREET SINGH
2|Page 100610180016
Analysis And Construction of ROB
REPORT INDEX
3|Page 100610180016
Analysis And Construction of ROB
4|Page 100610180016
Analysis And Construction of ROB
TO MUKERIAN SIDE:
TO GURDASPUR
SIDE:
5|Page 100610180016
Analysis And Construction of ROB
6|Page 100610180016
Analysis And Construction of ROB
Details Of Project
7|Page 100610180016
Analysis And Construction of ROB
Profile Of Company
1. Deepak Builder Pvt.Ltd is one of the leading construction companies in Punjab today.
2. The Deepak Bulidcon Group is a brainchild of Mr. Deepak Singal, who established it in
the year 1987, with focus on the construction and development of luxury apartments in
Ludhiana.
3. The Deepak Buildcon Group constructs with a conscience luxury integrated with superior
quality and understated grandeur. The spirit of creativity and perfection of the
organization is reflected in its endeavors to achieve excellence, a quality perfected in
serving the nation for the past two decades with "Company Turnover more than 600
Million INR".
4. The Group is known for its design ingenuity, superior quality , professionalism and on-
time delivery, Today the Deepak Buildcon Group, manned by highly qualified
professionals and equipped with latest technology, has expanded into the creation of
world-class commercial offices , retail complexes , office cum retail projects and hotels.
5. From arch and bowstring girder bridges to balanced cantilever, prestressed concrete and
latest cable-stayed bridges, Deepak's capabilities cover the entire spectrum of
technological advances in bridge engineering.
6. Besides designing and building bridges, Deepak has achieved perfection in the techniques
of launching, underwater concreting development of supporting equipment like
pneumatic caissons, winches, cables, grouting machinery etc., and building of enabling
structures.
8|Page 100610180016
Analysis And Construction of ROB
4. Diameter of piles: 1m
9|Page 100610180016
Analysis And Construction of ROB
10 | P a g e 100610180016
Analysis And Construction of ROB
11 | P a g e 100610180016
Analysis And Construction of ROB
transit or rotate about fixed axis so that concrete maintain all those properties required
for good strength before placement of concrete.
iv. JCB :
This type of equipment is generally used for the excavation and filling of the
ground. At site , it is generally used at “rewall” portion.
v. Roller:
This type of equipment is generally used for the compaction of the soil so as
to obtain optimum density of soil. At site, it is used at the “rewall” portion.
12 | P a g e 100610180016
Analysis And Construction of ROB
13 | P a g e 100610180016
Analysis And Construction of ROB
14 | P a g e 100610180016
Analysis And Construction of ROB
x. Concrete pipeline:
This is a medium through which concrete is transport to the non-
reachable places by transit mixer. At site, concrete pipeline is used for concreting the
beams, deck slab.
15 | P a g e 100610180016
Analysis And Construction of ROB
This Railway Over Bridge is constructed on railway LC NO. B-110 at Mukerian to Gurdaspur
road . The purpose of construction of such ROB is to safely bye-pass the highway traffic over
the railway line without interrupting highway traffic . Construction of ROB involve in two
portions which is written as following :
I. Stilt portion: In this portion, major portion of construction is done by RCC and
minor or negligible portion of construction is done by solid or soil. Following are the
processes or construction is done under this head :
a.) Alignment
b.) Piles
d.) Pier
f.) Pedestal
g.) Bearing
i. Stilt portion of Mukerian side: Total length of approach 350.400m, which include
160m stilt portion having average width of 10.00m comprising of 9m carriageway and 0.50m
wide crash barrier on both sides as shown in GAD in gradient of 1:30 with summit curve at the
junction with horizontal portion adjacent to railway bridge.
ii. Stilt portion of Gurdaspur side: Total length of approach 371.700m, which include
160m stilt portion having average width of 10.00m comprising of 9m carriageway and 0.50m
wide crash barrier on both sides as shown in GAD in gradient of 1:30 with summit curve at the
junction with horizontal portion adjacent to railway bridge.
Some important information about stilted portion according to knowledge obtained at site:
16 | P a g e 100610180016
Analysis And Construction of ROB
a.) Alignment: It is the process of align the component bridge as per design drawing. The
b.) Pile: It is the long slender member that carrying and transfer the load of the structure to the
ground located at some depth below the ground level and earth surrounding the pile.
The piles used at site is Bored cast-in-situ having diameter of each pile is 1m and sinking of the
pile into the ground is 20m approx. Grade of concrete used in pile is M45 and Grade of steel
used is Fe415 and Fe500. The clear cover used is 75mm The piles are used at site in group as
following:
c.) Pile cap: It is the structural element of ROB that tie a group of piles together and used to
transmit forces from pier to the pile foundation. The grade of concrete used for pile
cap is M35. The grade of steel used is Fe500. The clear cover used is 75mm. The dimensions of
pile cap written as following:
d.) Pier : It is the intermediate vertical load bearing member of ROB which has transfer the load
to the pile cap from the pier cap. The grade of concrete used for pier is M45. The grade
of steel used is Fe500. The clear cover used is 50mm.The diameter of pier is 1.8m. The height of
each pier is variable generally more near railway span and less near the rewall portion of the
ROB. The picture of pier is shown below:
17 | P a g e 100610180016
Analysis And Construction of ROB
e.) Pier cap: It is the structural element used to support the beams or girders. It is used to transm-
it the load from beams to the pier. The pier cap is provided some jack locations so
as to lift up the beams for the purpose of maintenance of the bearing. The dimensions of the pier
cap is 7000mm×2000mm and the height of pier cap is 1200mm. The clear cover to the pier cap is
40mm.Grade of concrete used for the pier cap M45. Grade of steel used is Fe500. The lap length
of the bars is 76×d.Where d= diameter of lapping bar.
f.) Pedestal & Seismic stopper: Pedestal is the structural member of the bridge whose length is
not exceeds the three times the least laterial dimensions. The
dimensions of the pedestal are 850mm×800mm. It is provide base for the girder. . The pier cap is
provided with the traverse stopper and longitudinal stopper so as to maintain the beams or girder
in its proper position during seismic load. The dimension of traverse stopper is 800mm×550mm
and dimension of longitudinal stopper is 800mm×1400mm. Grade of concrete used for pedestal
and Seismic stopper is M45. Grade of steel used for both is Fe500.
18 | P a g e 100610180016
Analysis And Construction of ROB
g.) Bearing: It is the provision made in the ROB to allow the span to certain displacement
due to the temperature changes. The type of bearing provided is POT/PTFE. The structure shall
also be checked for reduce value of coefficient of friction(i.e. 0.01) at movable bearing as higher
coefficient of friction may not realized during initial period of loading. Use of mortar pad
bearing shall not be permitted.
h.) RCC girder: It is the tension member of the ROB used to transfer the loads from the deck slab
to the pier cap through the bearing and pedestal. The grade of concrete used for
19 | P a g e 100610180016
Analysis And Construction of ROB
girder is M45 and grade of the steel is Fe500.Other dimensions are shown in above two pictures.
i.) Deck slab: It is the horizontal member of ROB which construct the most important part of the
superstructure and providing a platform to the highway traffic. The slab have dim-
ensions shown in figure. Total length of deck slab is 10000mm having center to center beam
distance is 2500mm. The length of cantilever portion is 2500mm on both sides. At beams, total
depth of deck slab is 300mm and at middle of the beams is 220 and at outer end of cantilever,
depth of slab is 200mm.So the average depth of deck slab is 240mm. The grade of concrete used
for deck slab is M45 and grade of the steel is Fe500. The deck slab is two-way slab. The clear
cover of the deck slab is 40mm.
a. Expansion joint : The expansion joint must be durable , specified size and replaceable. It
must
be provided over the full width of the superstructure including kerb, footpaths
and crash barrier. Following are the same additional essential features:
i. The expansion joint of 50mm is provided in deck slab for design movement.
20 | P a g e 100610180016
Analysis And Construction of ROB
i. For hardened concrete, the surface shall be thoroughly cleaned to remove debris
and laitance and made rough so that ¼ the size of aggregate is expose without
structurally damaging the concrete.
ii. For partially hardened concrete, the surface shall be cleaned by wire brush
followed by an air jet the old surface shall be soaked with water without leaving
puddles, immediately before starting concreting to prevent absorption of water
from new concrete. The new concrete shall be thoroughly compacted is region of
the joint.
21 | P a g e 100610180016
Analysis And Construction of ROB
II. Solid fill embankment portion : In this portion, major portion of construction is
is done solid or soil and minor or negligible portion
of construction is done by RCC . Following are the processes or construction is done
under this head :
22 | P a g e 100610180016
Analysis And Construction of ROB
wall/RCC wall and having 10.00m with comprising of 9.00m wide carriageway and
0.50m wide crash barrier on both sides as shown in GAD in gradient of 1:30 with valley
curve at the bottom. The crust as per specification will be extended to a length of 50m
beyond solid fill for regarding of the existing carriageway with the solid fill portion.
ii. Solid fill portion of Gurdaspur side: Length of solid fill is 211.70m in reinforced earth
wall/RCC wall and having 10.00m with comprising of 9.00m wide carriageway and
0.50m wide crash barrier on both sides as shown in GAD in gradient of 1:30 with valley
curve at the bottom. The crust as per specification will be extended to a length of 50m
beyond solid fill for regarding of the existing carriageway with the solid fill portion.
Some important information about stilted portion according to knowledge obtained at site:
a.) Alignment: It is the process of align the component bridge as per design drawing. The
b.) Pad : After the excavation, PCC of M10 is laid so as to provide hard base for the pad. The pad
is made of RCC provide a solid base for erecting the panel and providing the stability.
Grade of concrete used is M15. Width of pad is 500mm and thickness is 200mm.
c.) Panel cast: The panels are cast at mixing-batching unit. Commonly used panel are
i. F-panel
ii. S-panel
23 | P a g e 100610180016
Analysis And Construction of ROB
iii. P-panel
iv. Q-panel
v. R-panel
vi. HB-panel
vii. HT-panel
Mould size of all above panels are written in table shown below:
1. F- panel 1.480×1.480×0.180
2. S- panel 1.480×1.750×0.180
3. P- panel 0.500×1.480×0.180
4. Q- panel 1×1.480×0.180
5. R- panel 1.250×1.480×0.180
i. Lifting hooks: These are the hooks used to lift the panel and place it in proper position.
The diameter of bars is 12mm. Size of the lifting hooks is
220mm×220mm×50mm.
ii. Geo-grid hooks: These are the hooks used to attach geo-grid. The diameter of geo-grid
bar is 10mm. Size of these hooks is 135mm×120mm×40mm.
24 | P a g e 100610180016
Analysis And Construction of ROB
d.) Erection of panel: The cast-in-situ panel bring to site of construction and erected upon pad in
its position by using the Hydra crane so as to built up the “rewall portion”
of solid fill embankment portion. Erection of panels is continue till the deck slab and as per
design.
e.) Filling: After erection of the panel, filling of the “rewall portion” of solid filled embankment
25 | P a g e 100610180016
Analysis And Construction of ROB
is done with the help of sandy soil. The bulk density of sandy soil used id varies from
0 to 18 kg/m³ and cohesion according to test perform is 0.01-0.02. The filling of “rewall portion”
is done with the help of JCB and Dump truck.
f.) Compaction: It is the process of rearrangement of the soil particles so as to achieve maximum
dry density and optimum water content. At site, compaction of the sandy soil is
mostly done with the help of vibrating type roller.
g.) Geo-grid: Multiple layer of geo-grid have been placed horizontally within the filling and fold-
ed at sides to form facing to geo-grid hooks of panel with the help of steel bar. It
has moderately high modulus and low elongation to break, stiffer approach fill was created
which could distribute traffic loads over a wider area and thus provide stability to erected panel
and also provide outward displacement of 0.165mm to 0.170mm.
The filter media in the form of the coarse aggregate is used near erecting panel so that moisture
of the soil is drain down and drain through the drainage hole provided at the regular interval in
erecting panel.
h.) Geotextile: It is the polymer cloth type material provided at the junction or joints of the
26 | P a g e 100610180016
Analysis And Construction of ROB
panels so as to prevent water leakage from the joints of the erecting panel. The
binding material used to bind the geotextile to the joint is fevicol.
i.) PCC : Plain concrete cement of grade M10 is used before the frictional slab have been laid out
j.) Frictional slab & Crash barrier: The frictional slab is sometimes also refer as the sidewalk.
27 | P a g e 100610180016
Analysis And Construction of ROB
Grade of steel used is Fe500.Hight of crash barrier above the frictional slab is 850mm and width
is 500mm of which 275mm is horizontal and 225mm inclined upto 350mm height from slab. The
75φ PVC pipe for carrying electric cables for illumination of ROB provided at height 200mm
from slab. The electric pole of 8000 high from road surface.
28 | P a g e 100610180016
Analysis And Construction of ROB
SUPERVISION OF SUBSTRUCTURE
29 | P a g e 100610180016
Analysis And Construction of ROB
Pile Foundation
Introduction : Piles are long slender members that carry and transfer the load of the structure
to the ground located at some depth below the ground and the earth surrounding the piles.
Bored cast in-situ friction RCC piles of diameter 1000 mm. M45 grade of concrete was used
at our site.Average depth of the piles was 20 m.
Steel quantity:-
Clear cover = 75 mm
Diameter of the bar used for pile rings = 10mm (External) & 18mm(Internal)
30 | P a g e 100610180016
Analysis And Construction of ROB
Vertical bars:
Diameter = 20 mm
Length of one single bar from top to bottom of the pile = 20.3m
Total weight of steel used in one pile = d21× L1/162 + d22× L2/162 + d23× L3/162
= 1854.62 kg
For pile group having 4 piles total weight of steel = 4×1854.62 = 7418.48 kg
For pile group having 6 piles total weight of steel = 6×1854.62 = 11127.72 kg
31 | P a g e 100610180016
Analysis And Construction of ROB
Pile Cap
Structural elements that tie a group of piles together. Used to transmit forces from piers to the
pile foundations. At my site I studied the construction of the pile cap for the fixed pier P3.
Abutment(A1&A2) , Free pier(P1,P2,P4,P7,P8,P10,P11) and pier having expansion joint
(P5,P6) have 4 group of piles while fixed pier (P3&P9) have 6 group of piles. It was
constructed to connect 6 piles. Concrete mix of M35 was used in the pile cap. Total of 60.5
m³ of concrete was used in this pile cap. Clear cover to reinforcement is 75mm. Height of the
pile cap was 1.5 m.
32 | P a g e 100610180016
Analysis And Construction of ROB
= 40.5 m²
Concrete quantity:
= 60.75 m3
33 | P a g e 100610180016
Analysis And Construction of ROB
Pier
Steel quantity:-
Clear cover = 50 mm
Diameter of the bar used for pier rings = 12mm@100mmc/c & 12mm@200mmc/c (External)
Vertical bars(L-type):
Diameter = 20 mm
Length of one single bar from top to bottom of the pier = 6m approx
34 | P a g e 100610180016
Analysis And Construction of ROB
Total weight of steel used in one pier = d21× L1/162 + d22× L2/162 + d23× L3/162
= 951 kg
35 | P a g e 100610180016
Analysis And Construction of ROB
Pier Cap
Elevation of the pier cap:
All dimensions in mm
Concrete quantity
36 | P a g e 100610180016
Analysis And Construction of ROB
37 | P a g e 100610180016
Analysis And Construction of ROB
RCC I-Girder
Cross section of the I-girder:
38 | P a g e 100610180016
Analysis And Construction of ROB
7) Curing:- For next 20 days at least. Using Hessian cloth for curing.
40 | P a g e 100610180016
Analysis And Construction of ROB
Following are the test performed in laboratory as per Indian standard specification:-
41 | P a g e 100610180016
Analysis And Construction of ROB
Chemical Analysis:
1. 1 10 6.95
2. 1 25 6.85
42 | P a g e 100610180016
Analysis And Construction of ROB
1. 2 10 6.98
2. 2 25 7.16
43 | P a g e 100610180016
Analysis And Construction of ROB
Following percentages will govern the price adjustment for entire contract:-
1. Labour 17
2. Cement 16
3. Steel 17
4. Bitumen 6
7. Other material 32
8. Total 100
Where VL = Increase or decrease in cost of work during the month under consideration
R = Value of work
Lo = Consumer price index for industrial worker (Base year 2004-05 = 100) for
Li = Consumer price index for industrial worker (Base year 2004-05 = 100) for
44 | P a g e 100610180016
Analysis And Construction of ROB
Where Vc = Increase or decrease in cost of work during the month under consideration
R = Value of work
Co = All india wholesale price index worker (Base year 2004-05 = 100) for 28
iii. Adjustment of steel component:- Adjustment of cost of steel is done by the following
formula:-
Vs = 0.85 × Ps/100 × R × (Si-So)/So
Where Vs = Increase or decrease in cost of work during the month under consideration
due to changes in rates for steel.
R = Value of work
So = All india wholesale price index worker (Base year 2004-05 = 100) for 28
days preceding the date of opening of Technical bid as published Ministry
industrial development, Government of india.
Si = All india wholesale price index worker (Base year 2004-05 = 100) for the
month under consideration as Published by Ministry industrial development,
Government of india.
Ps = Percentage of steel component of the work.
45 | P a g e 100610180016
Analysis And Construction of ROB
R = Value of work
Fo = The official retail price of High speed Diesel (HSD) at the existing
46 | P a g e 100610180016
Analysis And Construction of ROB
Where Vp = Increase or decrease in cost of work during the month under consideration
R = Value of work.
Po = All india wholesale price index worker (Base year 2004-05 = 100) for Construction
Machinery for 28 days preceding the date of opening of Technical bid as published
47 | P a g e 100610180016
Analysis And Construction of ROB
Remedy: First off all, aggregates were washed before using them. It would increase the
rate of bond formation between the aggregates and cement. Also if use a higher grade of cement,
I will help in early achievement of strength.
2) While placing the concrete by transit mixers through concrete pipeline, concrete pipeline
is block due to remaining concrete in previous use.
Remedy: Hessian cloth was used to retain water for longer period. Continuous curing
was also done.
Safety requirements:
4) Safety manual.
5) Banners.
48 | P a g e 100610180016
Analysis And Construction of ROB
Bibliography