1 Earthwork in excavation of foundation for structures including pipe culverts in all types of soil complete as per drawings and Technical Specification Clause 304, 3
2903. cum.
Footing for Portal structure (Main Carriageway) 2 40.99 4.60 2.90 1093.67 1094.00
Footing for Portal structure (Service Road) 2 23.51 4.40 2.70 558.55 559.00
Retaining Wall/ Wing Wall 2 10.00 4.26 1.60 136.18 137.00
2 Cement concrete in foundation/M-15 levelling course including centering and shuttering all complete as drawing and Technical Specifications Sections 21
2200. cum.
Box Cell (Main Carriageway) 2 40.99 4.60 0.10 37.71 38.00
Box Cell (Service Carriageway) 2 23.51 4.40 0.10 20.69 21.00
Retaining Wall/ Wing Wall 2 10.00 4.26 0.10 8.51 9.00
3 Providing and laying filter medium, behind abutments, retaining wall and return wall complete as per drawing and Technical Specifications
Clause 2504. cum.
Vertical outer wall (Main Carriageway) 2 40.99 0.60 3.50 172.17 173.00
Vertical outer wall (Service Road) 2 23.51 0.60 3.50 98.73 99.00
Retaining Wall/ Wing Wall 2 10.00 0.60 3.94 47.24 48.00
4 Back filling behind abutments, wing walls/ retaining and return walls or any other area with selected granular material of approved quality complete as per drawing an
Technical Specification clause 300. cum. Main Carriageway
Filling above box top level (Cushion above box culvert of main
carriageway had already considered (on backfill of RE Wall 0.00
portion) in schedule-B of contract agreement, therefore the
quantity has not been added here. ) 0 40.79 7.92 10.46 0.00
Filling between box top level and GL 0 40.79 4.22 4.20 0.00 0.00
Filling between GL and founding level 2 40.79 4.22 2.80 964.16 965.00
Deduction due to heel 2 40.79 2.20 0.80 -143.59 -144.00
Service Road
Filling above box top level (Cushion above box culvert of main
carriageway had already considered (on backfill of RE Wall 0.00
portion) in schedule-B of contract agreement, therefore the
quantity has not been added here. ) 0 23.31 7.81 1.93 0.00
Filling between box top level and GL 0 23.31 4.11 4.00 0.00 0.00
Filling between GL and founding level 2 23.31 4.11 2.60 497.5636 498
Deduction due to heel 2 23.31 2.20 0.60 -61.53 -62.00
tions
112.32 113
288.58 289
118.48 119
24.33 25
9.75 10
315.64 316.00
129.29 130
0 0
24.9 25
SI. No. Description Unit No. Length Breadth Height
0. MT
00
ause
SI. No. Description Unit No. Length Breadth Height
13 Providing 65mm thick wearing course comprising of 40 mm Bituminous concrete overlaid with 25 mm bitumen mastic layer as per Technical Specifications Sections 500
(Wearing course had already considered in road work of schedule-B of contract agreement, therefore
the quantity has not been added here. ) sqm 0.0 35.0 7.40 0 0.00
0 0
0 0
-1992.2 -1993
0 0
SI.No. Description Unit Quantity Rate
5.02 Cement concrete in foundation/M-15 grade levelling course on Box culvert cum.
and under approach
68.00 slab etc.including
7203.64
centering and shuttering all complete as dra
5.03 Providing and laying filter medium, behind abutments, retaining wall and return
cum.wall complete
320.00
as per drawing 2603.82
and Technical Specifications Clause 2504.
5.04 Back filling behind abutments, wing walls/ retaining and return walls or
any other area with selected granular material of approved quality
complete as per drawing and Technical Specification clause 300.
5.06 M-35 grade Reinforced cement concrete in Box/Portal including cum. 1301.00 8392.17
centering and shuttering but excluding reinforcement, complete as per
drawing and Technical Specifications Sections
1500 ,1700 and 2300.
5.07 HYSD TMT Fe-500 bar reinforcement for culverts, underpass, retaining walls
MT etc. complete as
161.00
per drawings and 73620.24
Technical Specifiations Section 1600.
Amount Rate as per Amount as per PWD
PWD
111034.00
440863.00
749901.00
- 1309.55 -
19,93,419.00 1309.55 17,94,084.00 1794084.00
9826401.00
10667572.00
0.00 23589855.00
SI.No. Description Unit Quantity Rate
5.08 Provision of an Reinforced cement concrete crash barrier at the edges of the road,
Lm approaches 19.00
to bridge structures 4003.10
and medians, constructed with M-40 grad
5.09 Providing weep holes in abutments, wing walls, retaining walls, return wallsNr.etc. complete 531.00
as per drawing and
167.94
Technical
5.1 Painting of culvert no. and span arrangement as per Technical Nr. 2.00 45.33
Specifications Clause 803
5.11 Providing and laying Floor apron complete as per drawing and cum.
Technical Specifications Clause 2500.
5.12 Providing and fixing of Guard post complete as per drawing and Technical Specification
Nr. or as directed by Engineer.
5.13 Providing cement concrete M-15 grade in cut off wall complete as per drawing
cum.
and Technical Specifications Sections 1500 &
5.15 Drainage Spouts complete as per drawings and Technical Nr 4.00 507.95
Specifications
5.16 Expansion Joint Complete as per drawings and Technical Lm 0.00 310.00
Specifications Section 2600
5.16 Providing 65mm thick wearing course comprising of 40 mm Sqm 0.00 1039.00
Bituminous concrete overlaid with 25 mm bitumen mastic layer
Amount Rate as per Amount as per PWD
PWD
76,059.00 4003.10 76,059.00
76059
- -
- -
- -
4773
- 310.00 -
- 1039.00 -
0
161169
SI.No. Description Unit Quantity Rate
5.18 Amount of subgrade not used due to addition of culvert at this location Cum -1993.00 457.15
Total Amount =
Amount Rate as per Amount as per PWD
PWD
23751024.00