Sie sind auf Seite 1von 41

Nominal Productivity Rate Table

Operations Department Earth Works

Max. Low.
Labours Hour Company Company
Productivity Rate productivity per
Activity Type UNIT Rate Standard Standard
(Unit/Man/Hour) day (AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Mechanical Excavation (Large Areas ) m³ 28.5 228 10 0.35 0.25


Mechanical Excavation (Small Areas ) m³ 16 128 10 0.63 0.44
Manual Excavation m³ 0.3 2.4 10 33.33 23.33
Excavation for Kerb Stone (Manual) Lm 1 8 10 10.00 7.00
Excavation for Manholes ( Mechanical ) Nos 3 24 10 3.33 2.33
Excavation for Trenches (Mechanical ) Lm 15 120 10 0.67 0.47
Levelling Works (Single Level) m² 12.5 100 10 0.80 0.56
Levelling Works For Multi Levels (Profiling) m² 7 56 10 1.43 1.00
Levelling for Semi Rock Area m² 7 56 10 1.43 1.00
Road Base m³ 2.5 20 10 4.00 2.80
Levelling of Black Sand under Inter Lock Tiles m² 12.5 100 10 0.80 0.56
Compaction Works m² 100 800 10 0.10 0.07
PCC Shutter Works ( Raft) m² 25 200 10 0.40 0.28
PCC Shutter Works ( Strip Footing ) m² 12.5 100 10 0.80 0.56
PCC Shutter for Single Footing m² 7 56 10 1.43 1.00
PCC Shutter for Tie Beams ( 400mm - 800mm) m² 7 56 10 1.43 1.00
Backfilling Under Suspended Slab ( No Layers Required) m³ 13 104 10 0.77 0.54
Backfilling Under Suspended Slab ( Layers) m³ 6 48 10 1.67 1.17
Back Filling Work for Trenches ( With Backhoe ) Lm 10 80 10 1.00 0.70
Backfilling Works For Manholes Nos 3 24 10 3.33 2.33
Remarks
Nominal Productivity Rate Table
Water Proofing Work

Low.
Max. Company
Labours Company Standard
Productivity Rate Hour
Activity Type UNIT Rate Standard Remarks
(Unit/Man/Hour) (AED/Hour) Labour Rate Labour
Rate
(AED/Unit) (AED/Unit)

Applying Lequid Betumin Water Proofing (Per Coat) m² 36 10 0.28 0.19


Applying Water Proofing Membrane for Vertical ( Hot Fix) m² 7.5 10 1.33 0.93

Applying Water Proofing Membrane for Horizontal ( Hot m² 10 10 1.00 0.70


Fix)
Extruded polystreme insulation laid horizontally m² 10 10 1.00 0.70
Fixing Protection Board for Vertical Surfaces m² 5 10 2.00 1.40
ANGLE FILLET Lm 10 10 1.00 0.70
Foam Concrete m² 10 10 1.00 0.70
Polystyrene Fixing m² 10 10 1.00 0.70
Geotextile m² 10 10 1.00 0.70
ROOF SCREED m² 3.5 10 2.86 2.00
Nominal Productivity Rate Table

Kerb Stone and Interlock

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour) (AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Fixing of Kerb Stone Lm 1 10 10.00 7.00

Fixing Interlock Tiles 1 10 10.00 7.00


Nominal Productivity Rate Table
Operations Department Shuttering works

Plywood & Aluma


Cup Lock Paschal Doka Peri Miva
System Productivity Productivity Productivi Productivi Productivi
Activity Type Scope of Work UNIT Productivity Rate Rate ty Rate ty Rate
ty Rate (Unit/Man
Rate (Unit/Man/ (Unit/Man/ (Unit/Man (Unit/Man
(Unit/Man/ Hour) Hour) /Hour) /Hour)
/Hour)
Hour)

Shutter Fabricating, Fixing,


Single Footing Shutter m² 0.63 0.90
Applying of Oil Shutter

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Strip Footing Shutter m² 0.63 0.91
Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Raft Footing Shutter m² 0.63 0.90
Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Plinth Walls from .8m to 1.5m Applying of Oil Shutter, m² 0.63 0.90 1.25
Height Scaffolding is Erected by
others for casting
Nominal Productivity Rate Table
Operations Department Shuttering works

Plywood & Aluma


Cup Lock Paschal Doka Peri Miva
System Productivity Productivity Productivi Productivi Productivi
Activity Type Scope of Work UNIT Productivity Rate Rate ty Rate ty Rate
ty Rate (Unit/Man
Rate (Unit/Man/ (Unit/Man/ (Unit/Man (Unit/Man
(Unit/Man/ Hour) Hour) /Hour) /Hour)
/Hour)
Hour)

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Tie Beams up to .8m Height m² 0.35 0.50 0.70
Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (Less Than Applying of Oil Shutter,
40X40) from 0.2m to 1m m² 0.25 0.36
Scaffolding is Erected by
Height others for casting

Shutter Fabricating, Fixing,


Column Necks (More Than Applying of Oil Shutter,
40X40) from 0.2m to 1m m² 0.35 0.50
Scaffolding is Erected by
Height others for casting
Nominal Productivity Rate Table
Operations Department Shuttering works

Plywood & Aluma


Cup Lock Paschal Doka Peri Miva
System Productivity Productivity Productivi Productivi Productivi
Activity Type Scope of Work UNIT Productivity Rate Rate ty Rate ty Rate
ty Rate (Unit/Man
Rate (Unit/Man/ (Unit/Man/ (Unit/Man (Unit/Man
(Unit/Man/ Hour) Hour) /Hour) /Hour)
/Hour)
Hour)

Shutter Fabricating, Fixing,


Column Necks (Less Than Applying of Oil Shutter, m² 0.25 0.36
40X40) from 1m to 2m Height Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (More Than Applying of Oil Shutter, m² 0.35 0.50
40X40) from 1m to 2m Height Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (Less Than Applying of Oil Shutter, m² 0.45 0.65
40X40) from 2m to 3m Height Scaffolding is Erected by
others for casting
Nominal Productivity Rate Table
Operations Department Shuttering works

Plywood & Aluma


Cup Lock Paschal Doka Peri Miva
System Productivity Productivity Productivi Productivi Productivi
Activity Type Scope of Work UNIT Productivity Rate Rate ty Rate ty Rate
ty Rate (Unit/Man
Rate (Unit/Man/ (Unit/Man/ (Unit/Man (Unit/Man
(Unit/Man/ Hour) Hour) /Hour) /Hour)
/Hour)
Hour)

Shutter Fabricating, Fixing,


Column Necks (More Than Applying of Oil Shutter, m² 0.45 0.65
40X40) from 2m to 3m Height Scaffolding is Erected by
others for casting
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivit Productivity Productivit Productivit
Activity Type Scope of Work UNIT Productivit Rate y Rate Rate y Rate y Rate
y Rate (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man
(Unit/Man/ Hour) Hour) Hour) Hour) /Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Grouns slab Shutter Shutter, Scaffolding is m² 0.35 0.50
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Steps Shutter Shutter, Scaffolding is m² 0.35 0.50
Erected by others for
casting
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivit Productivity Productivit Productivit
Activity Type Scope of Work UNIT Productivit Rate y Rate Rate y Rate y Rate
y Rate (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man
(Unit/Man/ Hour) Hour) Hour) Hour) /Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Normal Stair Case Shutter Shutter, Scaffolding is m² 0.63 0.90
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Decorative Stair Case Shutter, Scaffolding is m² 0.35 0.50
Erected by others for
casting
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivit Productivity Productivit Productivit
Activity Type Scope of Work UNIT Productivit Rate y Rate Rate y Rate y Rate
y Rate (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man
(Unit/Man/ Hour) Hour) Hour) Hour) /Hour)
Hour)

Shutter Fabricating,
Retaining Walls Shutter (Single Side) Fixing, Applying of Oil
Shutter, Scaffolding is m² 0.63 0.90
up to 3.5m Height Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Retaining Walls Shutter (Single Erected by others for m² 0.63 0.90
Side)More Than 3.5 3m Height casting, plat forms
used to work at
heigher Level is
produced by Others
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivit Productivity Productivit Productivit
Activity Type Scope of Work UNIT Productivit Rate y Rate Rate y Rate y Rate
y Rate (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man
(Unit/Man/ Hour) Hour) Hour) Hour) /Hour)
Hour)

Shutter Fabricating,
Retaining Walls Shutter (Double Side) Fixing, Applying of Oil
Shutter, Scaffolding is m² 0.63 0.90
up to 3.5m Height Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Retaining Walls Shutter (Double)More Erected by others for m² 0.63 0.90
Than 3.5 3m Height casting, plat forms
used to work at
heigher Level is
produced by Others
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivit Productivity Productivit Productivit
Activity Type Scope of Work UNIT Productivit Rate y Rate Rate y Rate y Rate
y Rate (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man/ (Unit/Man
(Unit/Man/ Hour) Hour) Hour) Hour) /Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Columns Shutter (Less Than 40X40) up Erected by others for m² 0.63 0.90
to 3.5m Height casting, plat forms
used to work at
heigher Level is
produced by Others
Nominal Productivity Rate Table

Operations Department Shuttering Works


Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivity Productivity Productivity Productivity
Activity Type Scope of Work UNIT Productivity Rate Rate Rate Rate Rate
Rate (Unit/Man/Ho (Unit/Man/Ho (Unit/Man/Ho (Unit/Man/Ho (Unit/Man/Ho
(Unit/Man/H ur) ur) ur) ur) ur)
our)

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Columns Shutter (More Than 40X40) up Scaffolding is Erected by
m² 0.63 0.90
to 3.5m Height others for casting, plat
forms used to work at
heigher Level is produced
Shutter Fabricating, Fixing,
by Others
Applying of Oil Shutter,
Columns Shutter (Less Than 40X40) More Scaffolding is Erected by
m² 0.63 0.90
Than 3.5m Height others for casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Columns Shutter (More Than 40X40) Scaffolding is Erected by m² 0.63 0.90
More Than 3.5m Height others for casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Walls Shutter up to 3.5m Height Scaffolding is Erected by m² 0.63 0.90
others for casting

Shutter Fabricating, Fixing,


Walls Shutter More Than 3.5m Height Applying of Oil Shutter, m² 0.63 0.90
Scaffolding is Erected by
Shutter Fabricating,
others for casting Fixing,
Drop Beams Shutter up to 3.5m Height Applying of Oil Shutter, m² 0.63 0.90
Scaffolding is Erected by
others for casting
Drop Beams Shutter More Than 3.5m Shutter Fabricating, Fixing,
Applying of Oil Shutter, m² 0.63 0.90
Height
Scaffolding is Erected by
others for
Shutter casting Fixing,
Fabricating,
Applying of Oil Shutter,
Slab shutter up to 3.5m Height ( up to Scaffolding is Erected by m² 0.63 0.90
0.4m Slab Thickness) others for casting

Shutter Fabricating, Fixing,


Slab shutter up to 3.5m Height (More Than Applying of Oil Shutter,
0.4m Slab Scaffolding is Erected by m² 0.31 0.45
Thickness) others for casting

Shutter Fabricating, Fixing,


Slab shutter More Than 3.5m Height ( up Applying of Oil Shutter,
to 0.4m Slab Scaffolding is Erected by m² 0.35 0.50
Thickness) others for casting
Nominal Productivity Rate Table

Operations Department Shuttering Works


Plywood &
Cup Lock Paschal Doka Peri Aluma Miva
System Productivity Productivity Productivity Productivity Productivity
Activity Type Scope of Work UNIT Productivity Rate Rate Rate Rate Rate
Rate (Unit/Man/Ho (Unit/Man/Ho (Unit/Man/Ho (Unit/Man/Ho (Unit/Man/Ho
(Unit/Man/Ho ur) ur) ur) ur) ur)
ur)

Shutter Fabricating,
Fixing, Applying of Oil
Slab shutter More Than 3.5m Height (More Shutter, Scaffolding is
Than 0.4m Slab m² 0.16 0.23
Erected by others for
Thickness) casting

Shutter Fabricating,
Fixing, Applying of Oil
Slab Side Shutter Shutter, Scaffolding is m² 0.63 0.90
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Deshuttering Works m² 3.50 5.04
Erected by others for
casting
Nominal Productivity Rate Table

Operations Department Concrete Works


Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Concrete Pouring for PCC 50 mm (Raft and m³ 0.75 10 13.33 9.33


Strip Footing)
Concrete Pouring for PCC 100 mm (Raft
m³ 1 10 10.00 7.00
and Strip Footing)
Concrete Pouring for PCC 50 mm (With Shap m³ 0.5 10 20.00 14.00
Concrete Pouring for PCC 100 mm (With Sha m³ 0.65 10 15.38 10.77
Concrete Pouring for PCC 50 mm For Single m³ 0.6 10 16.67 11.67
Concrete Pouring for PCC 100 mm For Single m³ 0.9 10 11.11 7.78
Concrete Pouring for PCC 50 mm For Tie Be m³ 0.4 10 25.00 17.50
Concrete Pouring for PCC 100 mm For Tie B m³ 0.6 10 16.67 11.67
Concrete Pouring for Single Footing m³ 2.5 10 4.00 2.80
Concrete Pouring For Strip Footing m³ 3 10 3.33 2.33
Concrete Pouring For Raft Footing m³ 4 10 2.50 1.75
Concrete Pouring For Walls m³ 1.5 10 6.67 4.67
Concrete Pouring For Columns m³ 1.5 10 6.67 4.67
Concrete Pouring For Slabs m³ 3 10 3.33 2.33

Cleaning for Slab or Footing Before Casting m² 50 10 0.20 0.14


Curing For Walls and Columns (Per Once Per m² 100 10 0.10 0.07
Curing for Slabs (Per Once Per Day) m² 100 10 0.10 0.07
Laying and Removing of Hessian Cloth m² 50 10 0.20 0.14

Concrete Logistics m³ 20 10 0.50 0.35


Nominal Productivity Rate Table
Operations Department Steel Fixing Works

Productivity Rate Labours Hour Rate


Activity Type UNIT
(Unit/Man/Hour) (AED/Hour)

Steel Fixing for 8mm Kgs 18 10


Fixing of Rings 8mm Kgs 12 10
Steel Fixing for 10mm Kgs 20 10
Fixing of Rings 10mm Kgs 13 10
Steel Fixing for 12mm Kgs 25 10
Fixing of Rings 12mm Kgs 17 10
Steel Fixing for 14mm Kgs 30 10
Fixing of Rings 14mm Kgs 20 10
Steel Fixing for 16mm Kgs 35 10
Fixing of Rings 16mm Kgs 24 10
Steel Fixing for 20mm Kgs 40 10
Steel Fixing for 25mm Kgs 60 10
Steel Fixing for 32mm Kgs 70 10
Steel Fixing for 40mm Kgs 80 10

Steel Cut and Bend 8mm Kgs 150 10


Steel Cut and Bend 10mm Kgs 175 10
Steel Cut and Bend 12mm Kgs 200 10
Steel Cut and Bend 14mm Kgs 225 10
Steel Cut and Bend 16mm Kgs 250 10
Steel Cut and Bend 20mm Kgs 300 10
Steel Cut and Bend 25mm Kgs 350 10
Rings Steel Fabrication 8m Kgs 50 10
Rings Steel Fabrication 10 Kgs 80 10
Rings Steel Fabrication 12 Kgs 115 10
Rings Steel Fabrication 14 Kgs 155 10
Rings Steel Fabrication 16 Kgs 200 10

Steel Works Logistics Kgs 350 10


Low. Company
Max. Company
Standard Labour
Standard Labour Rate Remarks
Rate
(AED/Unit)
(AED/Unit)

0.56 0.39
0.83 0.58
0.50 0.35
0.77 0.54
0.40 0.28
0.59 0.41
0.33 0.23
0.50 0.35
0.29 0.20
0.42 0.29
0.25 0.18
0.17 0.12
0.14 0.10
0.13 0.09

0.07 0.05
0.06 0.04
0.05 0.04
0.04 0.03
0.04 0.03
0.03 0.02
0.03 0.02
0.20 0.14
0.13 0.09
0.09 0.06
0.06 0.05
0.05 0.04

0.03 0.02
Nominal Productivity Rate Table
Operations Department Tiling Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT productivivty per day Rate Standard Standard
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Floor Tiling (Normal)
20X20 m² 0.7 5.6 10 14.29 10.00
Any Size (Areas Less Than 5 m2) m² 0.35 2.8 10 28.57 20.00
25X25 m² 0.75 6 10 13.33 9.33
30X30 m² 0.8 6.4 10 12.50 8.75
40X40 m² 0.85 6.8 10 11.76 8.24
50X50 m² 0.9 7.2 10 11.11 7.78
60X60 m² 0.95 7.6 10 10.53 7.37
Floor Tiling (45 Degree) 0
20X20 m² 0.55 4.4 10 18.18 12.73
Any Size (Areas Less Than 5 m2) m² 0.3 2.4 10 33.33 23.33
25X25 m² 0.6 4.8 10 16.67 11.67
30X30 m² 0.65 5.2 10 15.38 10.77
40X40 m² 0.7 5.6 10 14.29 10.00
50X50 m² 0.75 6 10 13.33 9.33
60X60 m² 0.8 6.4 10 12.50 8.75
Wall Tiling 0
20X20 m² 0.6 4.8 10 16.67 11.67
Any Size (Areas Less Than 10 m2) m² 0.3 2.4 10 33.33 23.33
25X40 m² 0.65 5.2 10 15.38 10.77
30X45 m² 0.7 5.6 10 14.29 10.00
20X50 m² 0.75 6 10 13.33 9.33
30X60 m² 0.8 6.4 10 12.50 8.75
Wall Tiling (45 Degree) 0
20X20 m² 0.5 4 10 20.00 14.00
Any Size (Areas Less Than 10 m2) m² 0.25 2 10 40.00 28.00
25X40 m² 0.55 4.4 10 18.18 12.73
30X45 m² 0.6 4.8 10 16.67 11.67
20X50 m² 0.65 5.2 10 15.38 10.77
30X60 m² 0.65 5.2 10 15.38 10.77
Remarks

14.28571
Trojan Holding Nominal Productivity Rate Table
Operations Department Tiling Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Skirting Works
20CM Lm 2 10 5.00 3.50
30CM Lm 2.5 10 4.00 2.80
40CM Lm 3 10 3.33 2.33
50CM Lm 3.5 10 2.86 2.00
60CM Lm 4 10 2.50 1.75

Grouting Works m² 5 10 2.00 1.40


Cleaning and Protection Works m² 20 10 0.50 0.35
Logistics Works m² 10 10 1.00 0.70
Nominal Productivity Rate Table
Operations Department Painting Works

Max.
Labours Hour Company Low. Company
Productivity Rate
Activity Type UNIT productivity per day Rate Standard Standard Labour Rate
(Unit/Man/Hour)
(AED/Hour) Labour Rate (AED/Unit)
(AED/Unit)
Ceiling
Primar Application ( Normal Ceiling) m² 20 160 10 0.50 0.35
Grooves Preperation in the Ceiling Lm 5 40 10 2.00 1.40
Grooves Stucoo every coat Lm 5 40 10 2.00 1.40
Putty Application ( Single Coat) m² 10 80 10 1.00 0.70
Putty Application ( Two Coat) m² 5 40 10 2.00 1.40
Sanding for Second Coat Only m² 10 80 10 1.00 0.70
Painting First Coat m² 20 160 10 0.50 0.35
Touchup Beefore Final Coat m² 25 200 10 0.40 0.28
Painting Final Coat m² 16 128 10 0.63 0.44
Internal Walls 0
Primar Application m² 25 200 10 0.40 0.28
Putty Application ( Single Coat) m² 12 96 10 0.83 0.58
Putty Application ( Two Coat) m² 6 48 10 1.67 1.17
Sanding for Second Coat Only m² 12 96 10 0.83 0.58
Touch up Before Final Coat m² 30 240 10 0.33 0.23
Painting First Coat m² 25 200 10 0.40 0.28
Painting Final Coat m² 20 160 10 0.50 0.35
0
External Paint 0
Primar Application m² 40 320 10 0.25 0.18
GRC and Decorative Items (in each coat) Lm 10 80 10 1.00 0.70
Texture Coating (Spray) m² 12.5 100 10 0.80 0.56
Weather Proof Paint Application Per Coat m² 25 200 10 0.40 0.28
0
Scaffolding Works m² 4 32 10 2.50 1.75
Logistics Works m² 10 80 10 1.00 0.70
Remarks

0.4 0.32
Nominal Productivity Rate Table
Operations Department Block Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Solid Block 4",6", 8" (Up to 1.5m Height) m² 0.6 10 16.67 11.67
Solid Block 4",6", 8" (From 1.5m to 3m Height) m² 0.4 10 25.00 17.50
Hollow Block 4",6", 8" (Up to 1.5m Height) m² 0.7 10 14.29 10.00
Hollow Block 4",6", 8" (From 1.5m to 3m Height) m² 0.5 10 20.00 14.00
Light Weight Block with Glue m² 1 10 10.00 7.00

Logistics for Solid Block Works m² 2 10 5.00 3.50


Logistics for Hollow Block m² 4 10 2.50 1.75
Logistics for Light Weight Blocks m² 6 10 1.67 1.17

Block Works Layout with Damp Proof Coarse Lm 2 10 5.00 3.50


Curing for Block Works (Per once Per Day) m² 100 10 0.10 0.07
Nominal Productivity Rate Table
Operations Department Plaster Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Fixing of Mesh Lm 40 10 0.25 0.18


Fixing of Angles Lm 3 10 3.33 2.33

Making of Plastering Points ( Up to 3m Height) m² 10 10 1.00 0.70


Making of Plastering Points ( Above 3m Height) m² 6 10 1.67 1.17

Rush Coat ( Up to 3m Height) m² 15 10 0.67 0.47


Rush Coat ( Above 3m Height) m² 10 10 1.00 0.70

Plaster Filling Continuous ( Up to 3m Height) m² 1 10 10.00 7.00


Plaster Filling Continuous ( Above 3m Height) m² 0.7 10 14.29 10.00
Plaster Filling with Control Joints ( Up to 3m Height) m² 0.75 10 13.33 9.33
Plaster Filling with Control Joints ( Above 3m Height) m² 0.5 10 20.00 14.00
Plaster Filling for External Walls ( Up to 3m Height) m² 0.75 10 13.33 9.33
Plaster Filling for External Walls ( Above 3m Height) m² 0.5 10 20.00 14.00

Plaster Filling For Ceilings ( Up to 3m Height) m² 0.625 10 16.00 11.20


Plaster Filling For Ceilings ( Above 3m Height) m² 0.45 10 22.22 15.56

Plastering of Decorative Items Lm 1 10 10.00 7.00

Logistics Works Related to Plaster m² 10 10 1.00 0.70

Curing for Plaster Works (Per once Per Day) m² 100 10 0.10 0.07
Nominal Productivity Rate Table
Operations Department Survey Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Level Points Pts 15 27.5 1.83 1.28


Total Station Points Pts 8 27.5 3.44 2.41
GPS Points Pts 20 27.5 1.38 0.96

Stoppage time and Site Requirement PCT -35%


Nominal Productivity Rate Table

Operations Department Safety and Scaffolding Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Scaffolding Erection Works m² 4 10 2.50 1.75


Scaffolding dismantalling Works m² 8 10 1.25 0.88
Edge Protection Lm 4 10 2.50 1.75 Including shifting of materials
Nominal Productivity Rate Table
Operations Department Other Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Ceiling Joints Between Hollow Core Lm 10 11 1.10 0.77
Walls Joints Between Panels Lm 15 11 0.73 0.51
Cutting for MEP Works in Block Works Lm 5 11 2.20 1.54
Repairing works in Block Works Lm 10 11 1.10 0.77
Coring Works Nos 3 11 3.67 2.57
Angle Fillet in Roof and Wet Aeas Lm 10 11 1.10 0.77
Fixing of Manholes Cover (Any Size) Nos 0.2 11 55.00 38.50
Nominal Productivity Rate Table
Operations Department Electrical Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Fixing of Sleeves in Walls Nos 3 14 4.67 3.27
Under Ground Conduiting Pts 3 14 4.67 3.27
Conduiting in Slabs Pts 3 14 4.67 3.27
Electrical First Fix in Walls (Block Works) Pts 3 14 4.67 3.27
Electrical First Fix in Walls ( Precast) Pts 2 14 7.00 4.90
Coring works Pts 3 14 4.67 3.27
Conduiting in Slabs ( Topping Works) Pts 2 14 7.00 4.90
DB First Fix Box 0.25 14 56.00 39.20
DB First Fix ( Precast) Box 0.25 14 56.00 39.20
Conduiting works in Corridors ( up to 10 Lm to DB ) Room 1 14 14.00 9.80
Conduiting works in Corridors (more than 10 Lm to DB ) Room 0.5 14 28.00 19.60
Wiring for Lighting Circuit Pts 0.5 14 28.00 19.60
Wiring for Power Circuit Pts 0.5 14 28.00 19.60
Wiring for Data Circuit Pts 0.5 14 28.00 19.60
Wiring from Rooms to DB in corridors (up to 10 Lm to DB ) Room 0.5 14 28.00 19.60
Wiring from Rooms to DB in corridors (More Than 10 Lm to D Room 0.5 14 28.00 19.60
Fixing of Lighting Fixtures Nos 2 14 7.00 4.90
Fixing of Face Plates (switches, Sockets,..etc) Nos 3 14 4.67 3.27
Fixing of Lighting Fixtures with threaded rods Nos 1 14 14.00 9.80
Fixing of Spot Lights Nos 2 14 7.00 4.90
Fixing of Cable Trays Lm 3 14 4.67 3.27
DB Dressing and Termination (16 Circuit Breaker DB) CB 2 14 7.00 4.90
ONU Cable Termination Nos 0.25 14 56.00 39.20
Cables Pulling from external to DB and Between DB`s DB 0.15 14 93.33 65.33
Fixing of Exhaust Fans Nos 0.5 14 28.00 19.60
SMDB Cable Glanding CB 0.25 14 56.00 39.20
Nominal Productivity Rate Table
Operations Department Drainage Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)

Fixing of Sleeves Nos 2 14 7.00 4.90


Installation of Drainage First Fix Under Ground ( In Sand) Pts 1.25 14 11.20 7.84
Installation of Drainage First Fix in Rafts (Inside Concrete) Pts 1 14 14.00 9.80
Installation of Risers in Walls and Shafts Nos 0.5 14 28.00 19.60
Installation of Drainage Second Fix in Wet Areas ( With
Pts 0.75 14 18.67 13.07
Connection to
Risers)
Testing of Pipes Pts 1 14 14.00 9.80
Fixing of Sanitary Wares Nos 0.75 14 18.67 13.07
Fixing of Horizontal Piping under Slab ( With Suspension) Pts 0.5 14 28.00 19.60
Fixing of Pumps Nos 0.1 14 140.00 98.00
Fixing of Roof Cowel Nos 3 14 4.67 3.27
Nominal Productivity Rate Table
Operations Department Water supply Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Fixing of Sleeves and Main Inlet Nos 3 14 4.67 3.27
UnderGround Inlets ( First Fix) Pts 1 14 14.00 9.80
PPR Piping Works Hot and Cols Pts 1 14 14.00 9.80
Insulation Works For Pipes ( For Hot Water Pts 2 14 7.00 4.90
Fixing of Horizontal Piping to Main
Connection (With Suspension Pts 0.25 14 56.00 39.20
Works)
Fixing of Angle Valves Nos 3 14 4.67 3.27
Fixing of Gate Valves with Final Connection Nos 1 14 14.00 9.80
Fixing of Shower, Mixer , ...etc. Pts 1 14 14.00 9.80
Testing of Network Pts 1 14 14.00 9.80
Fixing of Electrical Water Heater Nos 0.25 14 56.00 39.20
Fixing of Solar Heating System System 0.02 14 700.00 490.00
Fixing of Water Tank with Main Connection Nos 0.1 14 140.00 98.00
Nominal Productivity Rate Table
Operations Department AC Works

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Coring in Walls for Main Connection Nos 3 14 4.67 3.27
Fixing of Indoor Units With Copper Pipes Connection Nos 0.5 14 28.00 19.60
Fixing the Copper Pipes Supply and Return Lm 4 14 3.50 2.45
Insulation works for Copper Pipes Lm 4 14 3.50 2.45
Suspension Works For Copper Pipes Lm 4 14 3.50 2.45
Installation of Out Door Unit ( up to 2Tons Unit) Nos 0.5 14 28.00 19.60
Installation of Out Door Unit ( Package up to 20 Tons) Nos 0.03 14 466.67 326.67
Pipes Tray and Protection for on Roof Copper Pipes Lm 1 14 14.00 9.80
Nominal Productivity Rate Table
External MEP Works

Operations Department

Max. Low.
Labours Hour Company Company
Productivity Rate
Activity Type UNIT Rate Standard Standard Remarks
(Unit/Man/Hour)
(AED/Hour) Labour Rate Labour Rate
(AED/Unit) (AED/Unit)
Pipes Laying Between Manholes (UPVC) Lm 3 14 4.67 3.27
Cables Laying in Ground Lm 0.25 14 56.00 39.20
Cables Pulling in Manholes Lm 0.1 14 140.00 98.00

Das könnte Ihnen auch gefallen