A project has the activities and activity times (days) listed below.
Determine die probability that
the project will require less than 15 days from start to finish.
Solution
path mean=25 path std deviation=sqrt(1.31^2+2.70^2+1^2)=3.1632 z=(15-25)/3.1632=-3.16 probability that project will require less thann 15 days =p(x<15)=p(z<-3.16)=0.00079