Master of Project Academy Material https://masterofproject.

com

Introduction & The Environment in Which Projects Operate

Definition of Project
Project
• Temporary endeavor with a beginning and an end
• Creates a unique product, service or result

Cannot be copied, redistributed or sold. 1


Master of Project Academy Material https://masterofproject.com

Introduction & The Environment in Which Projects Operate

Why are Projects Initiated?


• Market Demand
• Strategic Opportunity/Business Need
• Social Need
• Environmental Consideration
• Customer Request
• Technological Advance
• Legal Requirement

Cannot be copied, redistributed or sold. 2


Master of Project Academy Material https://masterofproject.com

Introduction & The Environment in Which Projects Operate

Example of a Project
• Construction of Golden Gate Bridge.

• Beginning: Jan 5, 1933


• End: April 19, 1937
• Temporary
• Unique

Cannot be copied, redistributed or sold. 3


Master of Project Academy Material https://masterofproject.com

The Role of The Project Manager

Project Manager’s Sphere of Influence

Cannot be copied, redistributed or sold. 4


Master of Project Academy Material https://masterofproject.com

Integration Management

Develop Project Charter


Law of Diminishing Returns
• After a certain point, adding more input will not produce
proportional increase in productivity.
• This might be due to extra coordination for instance.

Cannot be copied, redistributed or sold. 5


Master of Project Academy Material https://masterofproject.com

Integration Management
Develop Project Charter
Law of Diminishing Returns
• E.g. home constructing project
Number of Constructed Average 60
Construction Area per Constructed

Area Constructed Per Day


50
Workers day (m2) Area per
day (m2) 40

4 20 5.00 30

8 36 4.50 20

12 44 3.67 10

16 48 0
3.00
4 8 12 16 20
20 50 2.50 Number of Workers

Cannot be copied, redistributed or sold. 6


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise)
Activity Successors Duration (days)
A F 6
B --- 5
C --- 8
D E,F 4
E G 8
F B,G 7
G H 5
H C 7
Find critical path, and float of activities E and F.

Cannot be copied, redistributed or sold. 7


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
Activity Successors Duration (days)
A F 6
B --- 5
C --- 8
D E,F 4
6d
A F
B 5d END
C 8d END
D
4d E
4d F

Cannot be copied, redistributed or sold. 8


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
Activity Successors Duration (days)
E G 8
F B,G 7
G H 5
H C 7
8d
E G
F
7d B
7d G
5d
G H
H 7d C

Cannot be copied, redistributed or sold. 9


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d

PATH 1 = 4+8+5+7+8 = 32d

Cannot be copied, redistributed or sold. 10


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d

PATH 1 = 4+8+5+7+8 = 32d


PATH 2 = 4+7+5+7+8 = 31d

Cannot be copied, redistributed or sold. 11


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d
PATH 1 = 4+8+5+7+8 = 32d
PATH 2 = 4+7+5+7+8 = 31d
PATH 3 = 6+7+5+7+8 = 33d

Cannot be copied, redistributed or sold. 12


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d

PATH 1 = 4+8+5+7+8 = 32d


PATH 2 = 4+7+5+7+8 = 31d
PATH 3 = 6+7+5+7+8 = 33d
PATH 4 = 6+7+5 = 18d

Cannot be copied, redistributed or sold. 13


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d

PATH 1 = 4+8+5+7+8 = 32d


PATH 2 = 4+7+5+7+8 = 31d PATH 3 is the
PATH 3 = 6+7+5+7+8 = 33d CRITICAL PATH for
PATH 4 = 6+7+5 = 18d this schedule.

Cannot be copied, redistributed or sold. 14


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
• Activities A, F, G, H, and C are on critical path. Any delay on these tasks will
have impact on end date of the project. They have “zero” float.

• Calculation of Float

LATE ES EF EARLY Start/Finish is


Start/Finish is calculated when
calculated when moving from START
moving from LS LF
to END
END to START

Cannot be copied, redistributed or sold. 15


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
• Float of E Activity
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d

EF= 4+8 = 12d

Cannot be copied, redistributed or sold. 16


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
• Float of E Activity
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d

EF= 4+8 = 12d


LF= 33-8-7-5 = 13d

Cannot be copied, redistributed or sold. 17


Master of Project Academy Material https://masterofproject.com

Schedule Management
Develop Schedule
Critical Path Method (Exercise):
• Float of E Activity
4d E
D 4d
8d

START A 6d F 7d
G 5d H 7d C 8d END

7d B 5d
EF= 4+8 = 12d
Activity E can be delayed
LF= 33-8-7-5 = 13d only for 1 DAY without
FLOAT = LF – EF = 13 – 12 = 1d affecting the project duration.

Cannot be copied, redistributed or sold. 18


Master of Project Academy Material https://masterofproject.com

Cost Management
Determine Budget
• Process of aggregating the estimated costs of individual activities
or work packages to establish an authorized cost baseline.
• Determines the cost baseline
• Budget = Total cost of the project
• Budget defines how much money the company should have
available.

Cannot be copied, redistributed or sold. 19


Master of Project Academy Material https://masterofproject.com

Cost Management
Determine Budget
• Project estimate cannot be completed without risk management
activities and the inclusion of reserves.

Contingency Reserves: to address the cost impacts of remaining


risks.

Management Reserves: to address the cost of any unforeseen risks


or changes.

Cannot be copied, redistributed or sold. 20


Master of Project Academy Material https://masterofproject.com

Cost Management
Determine Budget
Management Reserves COST BUDGET
68K $ 1423K $

Contingency Reserves COST BASELINE


105K $ 1355K $

Project Estimates
1250K $

Control Account CA1 CA2


Estimates 850K $ 400K $

Work Package WP1 WP2 WP3


Estimates 100K $ 250K $ 500K $

Activity A1 A2 A3 A4
Estimates 25K $ 25K $ 50K $ 45K $

Cannot be copied, redistributed or sold. 21