Beruflich Dokumente
Kultur Dokumente
S and T must be completed before U can be started. T and U cannot begin until S has been completed.
1 S S T 3 T
U S
T 3 4 U 1 2 U S
2 T 4 U
U and V cannot begin until both S and T have been U cannot begin until both S and T have been completed;
completed. V cannot begin until T has been completed.
S U
1 S U 4 S U 1 3 5 S U
T 3 V Dummy
T V
2 5 T V 2 4 6 T V
An Easy Example
Activity Relationships
Activity Relationship
AOA AON
S T V
1 2 4 5 S T V
Dummy
U
3 U
3 Plan Promotion C 1 3
4 Locate Officials D 3 2 A2 C3 D2 G4
5 Send RSVP E 3 10
Invitations
6 Sign Player F 2,3 4 START
E10 I3 J2
Contracts
7 Purchase Balls and G 4 4
Trophies
10 Tournament J 8,9 2
Early finish EF The earliest time an activity can be completed if it is started LF = LS (successor) (min) (3)
at its early start time
LS = LF - t (4)
Late start LS The latest time an activity can begin without delaying the
completion of the project
TS = LF - EF (5)
Late finish LF The latest time an activity can be completed if it is started at
its latest start time or TS = LS - ES (6)
Early Start Gantt Chart for Tennis Resource Leveled Schedule for
Tournament Tennis Tournament
ID Activity Days Day of Project Schedule ID Activity Days Day of Project Schedule
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A Negotiate for 2 A Negotiate for 2
Location Location
B Contact Seeded 8 B Contact Seeded 8
Players Players
C Plan Promotion 3 C Plan Promotion 3
D Locate Officials 2 D Locate Officials 2
E Send RSVP 10 E Send RSVP 10
Invitations Invitations
F Sign Player 4 F Sign Player 4
Contracts Contracts
G Purchase Balls 4 G Purchase Balls 4
and Trophies and Trophies
H Negotiate 1 H Negotiate 1
Catering Catering
I Prepare Location 3 I Prepare Location 3
J Tournament 2 J Tournament 2
Personnel Required 2 2 2 2 2 3 3 3 3 3 3 2 1 1 1 2 1 1 1 1 Personnel Required 2 2 2 2 2 2 2 2 2 2 2 2 2 3 2 2 2 2 1 1
Critical Path Activities Critical Path Activities
Activities with Slack 2006 - Shuguang Liu Activities with Slack 2006 - Shuguang Liu
Incorporating Uncertainty in Activity Formulas for Beta Distribution of
Times Activity Duration
F(D) Expected Duration
P(D<A) = .01
_ A + 4M + B
D=
6
P(D>B) = .01
Variance
2
B − A
V =
6
TIME
A M D B
µ = 20 188/36 = 5.2 = σ
2
24 Days
Indirect Cost
Cost
Direct Cost
D* D Activity Duration (Days)
(0,0)
Duration of Project
C 3 2 10 13 15 25 25 -2
14 21 21 -4
D 2 1 11 17
13 17 17 -6
E 10 6 20 40 12 13 13 -8
F 4 3 8 15
Project Paths Normal Duration After Crashing Activity
Duration
G 4 3 9 10
A-C-D-G-I-J 16
H 1 1 10 10 A-C-E-I-J 20
I 3 2 8 10 A-C-E-H-J 18
A-C-F-H-J 12
J 2 1 12 20 B-F-H-J 15
Total 115 2006 - Shuguang Liu 2006 - Shuguang Liu
Cost
Budgeted Cost own experience.
BCWS (Baseline)
! Are Gantt charts still viable project management
Schedule
Variance
tools? Explain.
BCWP ! Explain why the PERT estimate of expected project
ATWP
Days
! What purpose does a project history report serve?
Value Time
Completed Variance ! Discuss the differences among time variance, cost
Interactive Exercise
! Preparea work breakdown structure (WBS) for a
homecoming dance.