PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -

CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROAD JUNCTION -03A CONSTRUCTION TARGET
INTERNAL TARGET PROGRAMME OF WORKS PROGRAMME
Activity ID Activity Name Original Start Finish 2014 2015 2016 2017
Duration
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J AS
CONTRACT 2 : ORBITAL HIGHWAY:
HIGHWAY CONSTRUCTION PROGRAM NEW DESOGN DATE 371 18-Aug-15 02-Nov-16
DESIGN 185 26-Sep-15 30-Apr-16
CONSTRUCTION 371 18-Aug-15 02-Nov-16
JUNCTION 12 & NORTH OF DUKHAN ROAD 371 18-Aug-15 02-Nov-16
JUNCTION 3A- (Sta.59+500 to 61+200- 1700 M) 371 18-Aug-15 02-Nov-16
JUNCTION 3A-STRUCTURES 371 18-Aug-15 02-Nov-16
SUMMARY AND MILESTONES 388 12-Oct-15 02-Nov-16
BRIDGE 23/BR/3AA and 23/BR/3AB MAIN
M BRIDGE 371 18-Aug-15 02-Nov-16
PHASE 1 210 18-Aug-15 21-Apr-16
TRAFFIC DIVERSION 45 18-Aug-15 11-Oct-15
SITE PREPARATION 24 12-Oct-15 08-Nov-15
ABUTMENT 52 09-Nov-15 07-Jan-16
PIERS 93 15-Nov-15 02-Mar-16
DECK WORKS 61 24-Jan-16 04-Apr-16
SHORING 20 24-Jan-16 16-Feb-16
SPAN 1 32 11-Feb-16 19-Mar-16
SPAN 2 41 17-Feb-16 04-Apr-16
MSE WALL EAST SIDE 69 09-Jan-16 29-Mar-16
APPROACH SLAB & PARAPET WALL
WA 20 30-Mar-16 21-Apr-16
TRAFFIC DIVERSION ON ORBITAL HIGHWAY 31 23-Feb-16 29-Mar-16
Phase 2 137 30-Mar-16 08-Sep-16
Site Preparation 10 30-Mar-16 10-Apr-16
ABUTMENT 54 25-Apr-16 26-Jun-16
PIERS 03 55 11-Apr-16 13-Jun-16
DECK WORKS 67 29-May-16 17-Aug-16
MSE WALL 54 23-Jun-16 28-Aug-16
APPROACH SLAB & PARAPET WALL
WA 15 23-Aug-16 08-Sep-16
ROAD WORKS ON CROSS ROADS 31 04-Sep-16 12-Oct-16
IRRIGATION AND LANDSCAPING WORKS
W 90 18-Jul-16 02-Nov-16
BRIDGE 23/BR/06 RAMP BRIDGE 274 09-Nov-15 01-Oct-16
PHASE 1 218 09-Nov-15 24-Jul-16
SITE INSTALLATION & PREPARATION
PREPARAT WORKS 18 09-Nov-15 29-Nov-15

Remaining Level of Effort Remaining Work Summary Rev Date Checked Approved
Actual Level of Effort Critical Remaining Work C3 22‐02‐15    
Page 1 of 2
Actual Work Milestone
PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -
CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROAD JUNCTION -03A CONSTRUCTION TARGET
INTERNAL TARGET PROGRAMME OF WORKS PROGRAMME
Activity ID Activity Name Original Start Finish 2014 2015 2016 2017
Duration
J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J AS
PIERS 40 03-Dec-15 18-Jan-16
ABUTMENTS & MSE WALLS 90 15-Dec-15 29-Mar-16
DECK WORKS 175 29-Dec-15 24-Jul-16
SPAN 1 69 29-Dec-15 19-Mar-16
MISCELLANEOUS WORKS 97 30-Mar-16 24-Jul-16
CASTING OF BACK WALL 7 13-Mar-16 20-Mar-16
TRAFFIC DIVERSION 9 20-Mar-16 29-Mar-16
PHASE 2 153 30-Mar-16 01-Oct-16
SITE INSTALLATION & PREPARATION
PREPARAT WORKS 10 30-Mar-16 10-Apr-16
ABUTMENT AND MSE WALL 83 11-Apr-16 19-Jul-16
ABUTMENT 2 34 11-Apr-16 19-May-16
MSE WALL 2 61 20-May-16 19-Jul-16
DECK WORKS 59 30-Apr-16 10-Jul-16
ROAD AND UTILITY WORKS 38 20-Jul-16 01-Sep-16
IRRIGATION AND LANDSCAPING WORKS 60 20-Jul-16 01-Oct-16

Remaining Level of Effort Remaining Work Summary Rev Date Checked Approved
Actual Level of Effort Critical Remaining Work C3 22‐02‐15    
Page 2 of 2
Actual Work Milestone

Das könnte Ihnen auch gefallen