Beruflich Dokumente
Kultur Dokumente
JUNCTION DESIGN
Junction Design
in Rock – A State of
the Art Review
Seth Pollak, Senior Engineer, Arup and Hannes Figure 1: Relationship between the
Lagger, Associate Director, Arup review the additional roof settlement and the
intersection angle of tunnels for the
challenges involved in designing and main tunnel (after Hsiao, 2008)
linear tunnel has been replaced by one of in removable block size on either side of the
Δδm/δm0 (%)
complex geometries and intersections as junction. Typically, a value of one adit
engineers struggle to create excavations diameter is applied as a rule of thumb, 40
that fulfill the requirements. This is never based on the fact that the majority of stress
truer than in urban areas where new distribution occurs within this zone. The
projects must be threaded around existing prudent engineer would then verify the 20
utilities, foundations, and other tunnels. The empirical recommendation using a
resulting stress distributions and ground kinematic block analysis such as a 3D
deformations can be difficult to predict, wedge visualization program in order to 0
even with the aid of a full 3D model. The translate joint orientations into wedge 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
application of current analytical design tools volumes and shapes which could be σcm/P0
to the temporary support of junctions is encountered in the junction area. Aside
mainly limited to homogeneous and from the size of the zone of influence, the
isotropic materials – such as soils or drawbacks of the empirical approach are specific factors (such as in situ stress, angle
massive, elastic rock. Few design tools are that no guidance is provided on rock of intersection, etc.) can be accounted for
currently available in the industry to deal reinforcement size or type, no estimate of without sacrificing time.
with discontinuous or weak rock masses, deformation is made, and no extent of A step in the right direction has recently
where stress distributions result in shearing yielding zone is established - all factors been provided by Hsiao et al. (2008) who
and dilation in the rock mass around the which are vital for the stability, construction have presented estimates of crown
excavation. This article aims to address and successful delivery of a tunnel junction. deformation for both the adit and main
where the industry is in terms of a rational The question of rock reinforcement type is tunnel (given as Δδ/δo, where Δδ is the
approach for temporary support design for of interest in terms of performance in additional deformation measured after
junctions in discontinuous rock masses, and design and construction. For example, in an junction formation and δo is the
highlights some recent projects where age where time is money, preference has deformation outside the influence of the
junctions have been successfully designed been given by many contractors to the use junction) for various junction situations. The
and build, with data collected to verify the of friction bolts wherever possible. The results presented are based on 75 different
performance in various types of rock. question of friction bolt performance to numerical model runs, carried out in
that of a fully grouted dowel around a FLAC3D (Itasca Consulting Group) for
Current Junction Design Methodologies junction cannot be answered by application different combinations of depths, rock mass
in Rock of the simplified empirical method quality, lateral stress ratios, and intersection
The most common approach to junction presented by the Q-chart. Although the angle.
design in rock tunnels is through application junction zone may represent an overall small The Δδ/δo ratio is given as a function of
of the empirical Q system (Barton, 1974). portion of the project, using dowels or two key factors: the in situ rock mass
Where an adjustment needs to be made for other reinforcement types still require the strength to stress ratio (σcm/Po) and the
a tunnel intersection, the joint number contractor to have the appropriate intersection angle (30°, 60°, and 90°). The
value (Jn) is multiplied by 3, effectively equipment on site and requires a change in former parameter addresses the probable
reducing the final Q value by 1/3. Intuitively, the usual mining cycle. yield zone size while the latter considers
the method makes sense as the creation of The ideal solution for the designer is to be different geometrical effects, both
additional free faces increases the likelihood able to carry out a more rational design, highlighted as shortcomings of the
of a removable block. However, several one where analytical and numerical empirical design method. Results are
important unknowns exist. One unknown is methods may be applied and more site tabulated and can be applied in the same
24 TUNNELLING JOURNAL
TJ_1012_024_029.qxd:Feature 20/10/12 16:39 Page 25
JUNCTION DESIGN
TUNNELLING JOURNAL 25
TJ_1012_024_029.qxd:Feature 20/10/12 16:39 Page 26
JUNCTION DESIGN
26 TUNNELLING JOURNAL
TJ_1012_024_029.qxd:Feature 20/10/12 16:39 Page 27
JUNCTION DESIGN
Figure 5: Total displacements obtained from Midas GTS model of the XRL 821
junction area
Adit
sections were analysed in 2D. As the
approach by Hsiao et al. is based on the ratio Increase thickness
of shotcrete 0.5D
of additional crown settlement after junction Install heavier
around adit for
support in cavern 4.5m
formation to the typical deformation away and re-run
potential wedge
confinement
from the junction, it was determined that the and adopt
2D work undertaken previously could be
utilized to provide the “δo” input, and that
the same models could effectively be re-run
with reduced rock strength/stiffness Monitoring of ground displacements several feet above the excavation design
properties in order to induce the additional during construction in the cavern and line. Real time continuous monitoring
deformation, Δδ, estimated by the method around the junction penetrations was provided results which could be correlated
(Pollak et al., 2010). The proposed analysis effectively measured using multiple point against each blast carried out as the
requires some degree of trial and error to borehole extensometers (MPBX) installed junctions were developed. A typical layout
match the crown displacements, but once from surface in arrays across the cavern of the MPBX above the penetration location
this is done the temporary support can be section. The lowest anchor points were only is shown in Figure 6.
assessed for overstress due to the extra
strain. Based on Figure 2, it was expected
Table 1: Summary of junction behavior in the 34th Street Station Cavern, 7 Line
that the perpendicular junction formations
Ext. Project, New York.
would result in an additional 15-20% crown
displacement in the cavern. Localized
thickening of the shotcrete was required, but
axial and shear forces in the grouted 32mm
diameter rock reinforcement was considered
acceptable. The process is presented in the
following flowchart:
TUNNELLING JOURNAL 27
TJ_1012_024_029.qxd:Feature 20/10/12 16:39 Page 28
JUNCTION DESIGN
Conclusion
It is now possible to carry out temporary
support design of rock tunnel junctions by
applying greater analytical and numerical
Three such intersections were monitored. results are shown in Table 1. tools than ever before, without sacrificing
All three were of the same size and located From Table 1, it can be seen that the time and resources, or relying on empirical
in rock masses having similar quality. Of the measured ratio of Δδm/δmo, where δmo simplifications. The state of the art methods
three instrumented junctions, good results was obtained from the MPBX above the presented here provide a good starting
were obtained from two, the third MPBX main cavern crown prior to junction point to incorporate fundamental, site
being damaged due to overbreak. The formation, agrees well with the 15-20% specific rock mass parameters which are
omitted in the traditional empirical
approaches. From that point forward, a
rational, tailored support design can be
Adit T3 and the interlocking chamber at north end of the 34th
developed to suit each junction geometry
Street Station Cavern, New York City
and characteristics.
REFERENCES
28 TUNNELLING JOURNAL