DAILY PROGRESS REPORT(september) 2018

labour labour labour labour labour labour labour labour


DATE WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P07 involved well P06 involved WELL P05 involved WELL A2 involved total labour
1-Sep-18 0 sinking in progress 5 no work due to rain because welding is not possible and chance of 0 5
2-Sep-18 0 sinking in progress 5 electicity failure in welding machine 0 5
3-Sep-18 0 sinking in progress 5 fabrication of outer skin plate& making reinforcement cutting and bending 24 29
4-Sep-18 0 sinking in progress 5 fabrication of inner skin plate& making reinforcement cutting and bending 27 32
No work due to water in river so crane shifting is not possible near well
5-Sep-18 0 sinking in progress 4 fabrication of inner skin plate& making reinforcement cutting and bending 33 37
6-Sep-18 0 sinking in progress 4 fabrication of inner skin plate& making reinforcement cutting and bending 36 40
7-Sep-18 0 sinking in progress 4 fabrication of inner skin plate& making reinforcement cutting and bending 35 39
8-Sep-18 0 sinking in progress 4 fabrication of inner skin plate& making reinforcement cutting and bending 36 40
9-Sep-18 0 0 reinforecement cutting and bending AT STEEL YARD 17 No Activity 17
10-Sep-18 0 0 reinforecement cutting and bending AT STEEL YARD 13 fabrication of cutting edge at fabrication yard 20 33
No work due to water flow in river which comes due to
11-Sep-18 0 0 reinforecement cutting and bending AT STEEL YARD 12 fabrication of cutting edge at fabrication yard 20 32
open of gate at kota dam
12-Sep-18 0 0 reinforecement cutting and bending AT STEEL YARD 12 fabrication of cutting edge at fabrication yard 20 32
13-Sep-18 No work due to water flow in river which comes due to open of gate at kota 0 0 reinforecement cutting and bending AT STEEL YARD 3 fabrication of cutting edge at fabrication yard 20 23
14-Sep-18 dam 0 shuttering work 20 fabrication of inner skin plate 10 fabrication of cutting edge at fabrication yard 10 40
15-Sep-18 0 shuttering work 21 fabrication of inner skin plate 10 fabrication of cutting edge at fabrication yard 10 No Activity 41
16-Sep-18 0 shuttering and reinforcement binding 20 fabrication of inner skin plate 19 0 bracket making and cutting edge bending and fabrication work in progress 12 51
17-Sep-18 0 no work due to viswakarma puja 0 no work due to viswakarma puja 0 0 no work due to viswakarma puja 0 0
18-Sep-18 0 no work due to viswakarma puja 19 no work due to viswakarma puja 20 0 bracket making and cutting edge bending and fabrication work in progress 19 58
19-Sep-18 sinking in progress 5 shuttering and reinforcement binding 20 fabrication of cutting edge at site 17 0 bracket making and cutting edge bending and fabrication work in progress 17 59
20-Sep-18 sinking in progress 5 shuttering and reinforcement binding 20 fabrication of cutting edge at site 17 0 bracket making and cutting edge bending and fabrication work in progress 14 56
21-Sep-18 sinking in progress 4 shuttering and reinforcement binding 20 fabrication of cutting edge at site 17 0 bracket making and cutting edge bending and fabrication work in progress 14 55
22-Sep-18 sinking in progress and bar cutting well steining 11 shuttering correction 4 reinforecement binding and fixing & fabrication work 33 0 bracket making and cutting edge bending and fabrication work in progress 14 62
23-Sep-18 sinking in progress 5 20 reinforecement binding and fixing & fabrication work 39 0 bracket making and cutting edge bending and fabrication work in progress 16 80
casting of 5th lift well steining
24-Sep-18 sinking in progress 5 15 reinforecement binding and fixing & fabrication work 39 0 bracket making and cutting edge bending and fabrication work in progress 16 75
25-Sep-18 sinking in progress 5 curing of concete 2 reinforecement binding and fixing & fabrication work 41 No Activity bracket making and cutting edge bending and fabrication work in progress 16 64
26-Sep-18 sinking in progress 5 curing of concete & deshuttering 7 reinforecement binding and fixing & fabrication work 38 cutting edge shift to site both circular part 2 cutting edge fabrication in progress 14 66
27-Sep-18 sinking in progress 5 curing of concete & deshuttering 7 reinforecement binding and fixing & fabrication work 40 0 cutting edge fabrication in progress 14 66
28-Sep-18 no work sinking completed and labour gang not available 0 curing of concete & deshuttering 7 reinforecement binding and fixing & fabrication work 40 0 no work 0 47
29-Sep-18 clean of well steining top 5 sinking in progress . reinforecement binding and fixing & fabrication work 40 0 cutting edge fabrication in progress for intermidiate 14 64
30-Sep-18 no work 0 sinking in progress 5 reinforecement binding and fixing & fabrication work 20 NO activity 0 cutting edge fabrication in progress for intermidiate 14 39
Total 55 248 688 102 194 1287

DAILY PROGRESS REPORT(October) 2018


labour labour labour labour labour labour
DATE WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P07 involved Well P06 involved WELL P05 WELL A2 total labour
01- Oct-18 0 sinking in progress 5 reinforecement binding and fixing & fabrication work 26 DRILLING OF P11 CUTTING edge 7 cutting edge fabrication in progress for intermidiate 14 0 52
02- Oct-18 0 sinking in progress 5 reinforecement binding and fixing & fabrication work 20 DRILLING OF P11 CUTTING edge 18 cutting edge fabrication in progress for intermidiate 14 57
no work sinking completed and labour gang not available
03- Oct-18 0 sinking in progress 5 reinforecement binding and fixing & fabrication work 26 DRILLING OF P11 CUTTING edge 12 cutting edge fabrication in progress for intermidiate 14 57
04- Oct-18 0 sinking in progress 5 reinforecement binding and fixing & fabrication work 23 welding of bent plate at site 15 cutting edge fabrication in progress for intermidiate 10 53
05- Oct-18 Reinforcement making in progress 10 sinking in progress 5 casting in progress 25 setting out of cutting edge on location 14 no work since gang is involved in shuttering making 0 54
06- Oct-18 reinforcement binding in progress 10 sinking in progress 5 sinking prepation in progress (manual sinking ) removal of woodan blocks 10 welding and alignment of cutting edge 16 no work since gang is involved in shuttering making 0 41
07- Oct-18 shuttering work in progress 21 no sinking (sunday) 0 curing work 2 bracket fixing on cutting edge 20 no work since gang is involved in shuttering making 0 43
08- Oct-18 shuttering work in progress 21 sinking in progress 5 curing work 2 bracket fixing on cutting edge 19 no work since gang is involved in shuttering making 0 47
09- Oct-18 reinforecement binding and fixing in progress 21 sinking in progress 5 curing work 2 bracket fixing on cutting edge 20 no work since gang is involved in shuttering making 0 48
10- Oct-18 reinforecement binding and fixing in progress 21 sinking in progress 5 curing work 2 no work due to local land problem 0 no work since gang is involved in shuttering making 0 28
11- Oct-18 casting in progress 25 sinking in progress 5 sinking started 5 bracket fixing on cutting edge 16 no work since gang is involved in shuttering making 0 51
12- Oct-18 casting in progress 25 sinking in progress 5 sinking in progress 13 bracket fixing on cutting edge 19 no work since gang is involved in shuttering making 0 62
13- Oct-18 curing in progress 2 sinking in progress 5 sinking in progress 12 no work due to local land problem 0 bent plate work in progress 10 29
14- Oct-18 curing in progress 2 sinking in progress 5 sinking in progress 12 bracket fixing on cutting edge 15 bent plate welding in progress 10 44
15- Oct-18 curing / BUT SINKING POSSIBLE CRANE NOT AVALABLE 2 sinking in progress 5 sinking in progress 12 outer skin plate fixing 15 bent plate welding in progress 10 44
16- Oct-18 sinking in progress 5 sinking in progress 5 sinking in progress TILL 5 PM 5 outer skin plate fixing 18 bent plate welding in progress 10 43
17- Oct-18 sinking in progress 5 sinking in progress 5 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 16 welding of bent plate and shift cutting edge to site 10 36
18- Oct-18 sinking in progress 5 sinking in progress 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 layout making and placing of cutting edge 7 32
19- Oct-18 no work desherra holiday 0 no work desherra holiday 0 no work desherra holiday 0 no work desherra holiday 0 no work desherra holiday 0 0
20- Oct-18 sinking in progress 5 reinforcement making for 6th lift 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 fixing of cutting edge 5 30
21- Oct-18 sinking in progress 5 reinforcement making for 6th lift 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 fixing of cutting edge and making of hole 5 30
22- Oct-18 sinking in progress 5 reinforcement & Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 fixing of cutting edge and making of hole 5 30
23- Oct-18 sinking in progress 5 reinforcement & Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 fixing of cutting edge and making of hole 8 33
24- Oct-18 sinking in progress 5 Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 fixing of cutting edge and making of hole 10 35
25- Oct-18 sinking in progress 5 Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 outer skin plate fixing 10 welding of stiffner 10 35
26- Oct-18 sinking in progress 5 Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 bracket repairing work and welding work 10 no work 0 25
27- Oct-18 sinking in progress 5 Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 bracket repairing work and welding work 10 welding of cutting edge and bent plate 14 bracket making of size 75*75*8 10 49
28- Oct-18 no sinking 0 Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 skin plate welding work 10 bracket fixing work in progress 9 bracket making of size 75*75*8 10 39
29- Oct-18 sinking in progress 5 Shuttering work at P9 6th lift 10 no progress since SHUTTERING gang is not available 0 skin plate welding work 10 bracket fixing work in progress 9 bracket making of size 75*75*8 10 44
30- Oct-18 sinking in progress 5 Shuttering work at P9 6th lift 14 no progress since SHUTTERING gang is not available 0 skin plate fixing work 19 skin plate cutting work and bracket fixing work 9 cutting edge fabrication work 10 57
31- Oct-18 sinking in progress 5 reinforcement binding work 14 no progress since SHUTTERING gang is not available 0 skin plate fixing work 19 skin plate cutting work and bracket fixing work 9 10 57
Total P8 230 P9 218 P10 197 P11 388 P07 202 50 1285

DAILY PROGRESS REPORT(November) 2018


labour labour labour labour labour labour
DATE WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P07 involved Well P06 involved WELL P05 WELL A2 total labour
01- Nov-18 sinking in progress 5 reinforcement binding in progress 14 no progress since SHUTTERING gang is not available 0 inner skin plate fixing work 19 skin plate cutting work and bracket fixing work 9 cutting edge fabrication work 10 57
02- Nov-18 sinking compeleted 5 reinforcement binding in progress 20 no progress since SHUTTERING gang is not available 0 inner skin plate fixing work 19 no work since gang do not work on friday 0 cutting edge fabrication work 10 54
03- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 10 casting in progress at 6th lift WS 25 reinforcement & shuttering work in progress at WS 1st lift 15 inner skin plate fixing work 19 outer skin plate fixing work in progress 7 cutting edge fabrication work 10 86
04- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 14 casting in progress at 6th lift WS 25 reinforcement & shuttering work in progress at WS 1st lift 10 inner skin plate fixing work 19 outer skin plate fixing work in progress 7 cutting edge fabrication work 10 85
05- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 10 CURING 2 reinforcement & shuttering work in progress at WS 1st lift 12 inner skin plate fixing work 19 outer skin plate fixing work in progress 7 cutting edge fabrication work 7 57
06- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 10 deshuttering work 5 reinforcement & shuttering work in progress at WS 1st lift 12 inner skin plate fixing work 19 outer skin plate fixing work in progress 9 cutting edge fabrication work 3 58
07- Nov-18 diwali holiday 0 diwali holiday 0 diwali holiday 0 diwali holiday 0 diwali holiday 0 diwali holiday 0 0
08- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 9 sinking started 5 no work gang is absent 0 inner skin plate fixing work 19 outer skin plate fixing work in progress 9 cutting edge fabrication work 3 45
09- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 9 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 8 inner skin plate fixing work 18 outer skin plate fixing work in progress 8 cutting edge fabrication work 2 50
10- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 9 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 10 inner skin plate fixing work 19 outer skin plate fixing work in progress 8 no work 0 51
11- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 9 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 8 inner skin plate fixing work 18 outer skin plate fixing work in progress 8 no work 0 48
12- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 9 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 11 inner skin plate fixing work 18 no work 0 no work 0 43
13- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 13 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 15 inner skin plate fixing work 18 outer skin plate fixing work in progress 8 no work 0 59
14- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 15 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 17 inner skin plate fixing work 17 inner skin plate bending and welding work 7 cutting edge fabrication work 5 66
15- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 10 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 15 welding of inner plate 15 inner skin plate bending and welding work 7 cutting edge fabrication work 10 62
16- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 10 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 10 welding of inner plate 15 no work 0 cutting edge fabrication work 10 50
17- Nov-18 casting in progress at 5th lift 25 no sinking since chisel stuk in well 0 reinforcement & shuttering work in progress at WS 1st lift 15 welding of inner plate 15 inner skin plate bending and welding work 10 cutting edge fabrication work 10 75
18- Nov-18 casting in progress at 5th lift 25 no sinking since chisel stuk in well 0 reinforcement & shuttering work in progress at WS 1st lift 14 no work 0 inner skin plate bending and welding work 10 no work 0 49
19- Nov-18 curing and deshuttering 10 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 14 welding of inner plate 10 inner skin plate bending and welding work 8 cutting edge fabrication work 5 52
20- Nov-18 curing and deshuttering 10 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 14 welding of inner plate 10 inner skin plate bending and welding work 8 cutting edge fabrication work 5 52
21- Nov-18 curing and deshuttering 8 SINKING IN PROGRESS 5 reinforcement & shuttering work in progress at WS 1st lift 18 welding of inner plate 17 inner skin plate bending and welding work 10 cutting edge fabrication work 8 cutting edge fabrication work 8 74
22- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 15 SINKING IN PROGRESS 5 casting in progress at 1st lift 25 welding of inner plate 5 inner skin plate bending and welding work 5 cutting edge fabrication work 10 cutting edge fabrication work 8 73
23- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 20 SINKING IN PROGRESS 5 curing work 3 welding of inner plate 6 no work 0 cutting edge fabrication work 10 cutting edge fabrication work 8 52
24- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 18 SINKING IN PROGRESS 5 deshuttering work 8 welding of inner plate 8 inner skin plate bending and welding work 10 cutting edge fabrication work 10 cutting edge fabrication work 8 67
25- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 14 SINKING IN PROGRESS 5 deshuttering work 7 no work 0 inner skin plate bending and welding work 10 cutting edge fabrication work 10 cutting edge fabrication work 8 54
26- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 14 cleaning of top surface 4 SINKING IN PROGRESS 6 welding &reinforcement fxing in progress 12 inner skin plate bending and welding work 8 cutting edge fabrication work 10 cutting edge fabrication work 8 62
27- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 15 no work since worker not available 0 SINKING IN PROGRESS 6 welding &reinforcement fxing in progress 12 inner skin plate bending and welding work 8 cutting edge assemble work 10 cutting edge fabrication work 6 57
28- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 14 SINKING IN PROGRESS 6 reinforcement & shuttering work in progress at WS 2ND lift 15 reinforcement fixing and binding work in well curb 20 inner skin plate bending and welding work 8 cutting edge welding work 10 bracket making and island filling 10 83
29- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 10 SINKING IN PROGRESS 6 reinforcement & shuttering work in progress at WS 2ND lift 15 reinforcement fixing and binding work in well curb 20 inner skin plate bending and welding work 8 cutting edge welding work 10 bracket making and island filling 10 79
30- Nov-18 casting in progress at 6th lift 25 SINKING IN PROGRESS 6 reinforcement & shuttering work in progress at WS 2ND lift 15 reinforcement fixing and binding work in well curb 20 inner skin plate bending and welding work 8 cutting edge welding work 10 bracket making and island filling 10 94

DAILY PROGRESS REPORT(DECEMBER) 2018


labour labour labour labour labour labour labour
DATE WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P07 involved Well P06 involved WELL P05 involved WELL P12 total labour
01- Dec-18 curing work 2 SINKING IN PROGRESS 6 reinforcement & shuttering work in progress at WS 2ND lift 15 reinforcement fixing and binding work in well curb 20 inner skin plate bending and welding work 12 hole drilling and welding 15 bracket making and island filling 6 76
02- Dec-18 deshuttering of 6th lift WS 8 no work 0 reinforcement & shuttering work in progress at WS 2ND lift 15 no work 0 inner skin plate bending and welding work 12 hole drilling and welding 15 bracket making and island filling 6 56
03- Dec-18 deshuttering of 6th lift WS 8 SURFACE CLEANING FOR next casting 6 reinforcement & shuttering work in progress at WS 2ND lift 20 reinforcement fixing and binding work in well curb 25 inner skin plate bending and welding work 12 hole drilling and welding 15 bracket making and island filling 6 92
04- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 25 reinforcement & shuttering work in progress at WS 2ND lift 27 reinforcement fixing and binding work in well curb 23 inner skin plate bending and welding work 12 hole drilling and welding 9 fabrication of cutting edge 7 107
05- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 17 reinforcement & shuttering work in progress at WS 2ND lift 25 reinforcement fixing and binding work in well curb 25 inner skin plate bending and welding work 12 bracket fixing work 11 fabrication of cutting edge 6 100
06- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 23 correction work 27 reinforcement fixing and binding work in well curb 25 inner skin plate bending and welding work 12 bracket fixing work 12 fabrication of cutting edge 5 108
07- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 23 reinforcement & shuttering work in progress at WS 2ND lift 5 reinforcement fixing and binding work in well curb 10 inner skin plate bending and welding work 15 bracket fixing work 12 fabrication of cutting edge 5 74
08- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 25 no work due to election 0 correction work 2 inner skin plate bending and welding work 20 bracket fixing work 11 fabrication of cutting edge 5 67
09- Dec-18 NO WORK 0 NO WORK 0 correction work 5 correction work 3 inner skin plate bending and welding work 20 bracket fixing work 11 fabrication of cutting edge 5 44
10- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 15 casting at 2nd lift WS 25 correction work 2 inner skin plate bending and welding work 10 bracket fixing work 11 fabrication of cutting edge 5 72
11- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 7th lift 17 curing work 2 no work 0 inner and outer skin plate bending and welding work 20 bracket fixing work 11 fabrication of cutting edge 5 59
12- Dec-18 SINKING IN PROGRESS 4 no work 0 deshuttering work 5 casting of well curb 25 reinforcement &inner and outer skin plate bending and welding work 25 bracket fixing work 10 fabrication of cutting edge 6 75
13- Dec-18 0 no work done material not available for casting 0 deshuttering work 11 curing work 2 reinforcement &inner and outer skin plate bending and welding work 25 bracket welding work 11 fabrication of cutting edge 6 55
14- Dec-18 0 cating of WS 7th lift 25 sinking in progress 4 curing work 2 reinforcement &inner and outer skin plate bending and welding work 25 outer skin plate fixing 11 fabrication of cutting edge 5 72
15- Dec-18 0 curing work 2 sinking in progress 4 curing work 2 reinforcement &inner and outer skin plate bending and welding work 25 outer skin plate fixing 11 fabrication of cutting edge 5 49
16- Dec-18 0 deshuttering work 10 reinforcement & shuttering work in progress at WS 3rdlift 15 curing work 2 reinforcement &inner and outer skin plate bending and welding work 25 outer skin plate fixing 11 fabrication of cutting edge 5 68
17- Dec-18 no activity crane are not available 0 reinforcement & shuttering work in progress at WS 8th lift 10 reinforcement & shuttering work in progress at WS 3rdlift 15 sinking started 10 reinforcement &inner and outer skin plate bending and welding work 25 outer skin plate fixing 11 fabrication of cutting edge 5 76
18- Dec-18 0 reinforcement & shuttering work in progress at WS 8th lift 8 reinforcement & shuttering work in progress at WS 3rdlift 15 sinking in progress 10 reinforcement &inner and outer skin plate bending and welding work 25 inner plate cutting 11 cutting edge shifted to site 5 74
19- Dec-18 0 reinforcement & shuttering work in progress at WS 8th lift 8 reinforcement & shuttering work in progress at WS 3rdlift 8 sinking in progress 4 reinforcement &inner and outer skin plate bending and welding work 25 inner plate fitting and welding 11 drilling of hole in cutting edge 5 61
20- Dec-18 0 reinforcement & shuttering work in progress at WS 8th lift 8 reinforcement & shuttering work in progress at WS 3rdlift 8 sinking in progress 4 reinforcement &inner and outer skin plate bending and welding work 25 inner plate fitting and welding 11 drilling of hole in cutting edge 5 61
21- Dec-18 0 reinforcement & shuttering work in progress at WS 8th lift 8 reinforcement & shuttering work in progress at WS 3rdlift 8 sinking in progress 4 reinforcement &inner and outer skin plate bending and welding work 35 inner plate fitting and welding 11 drilling of hole in cutting edge 5 71
22- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 8th lift 25 reinforcement & shuttering work in progress at WS 3rdlift 15 0 casting work in progress 40 inner plate fitting and welding 11 drilling of hole in cutting edge 5 100
23- Dec-18 NO WORK SUNDAY 0 reinforcement & shuttering work in progress at WS 8th lift 25 reinforcement & shuttering work in progress at WS 3rdlift 15 0 praparation of snking of well curb 4 inner plate fitting and welding 11 drilling of hole in cutting edge 5 60
24- Dec-18 SINKING IN PROGRESS 4 reinforcement & shuttering work in progress at WS 8th lift 25 reinforcement & shuttering work in progress at WS 3rdlift 15 0 praparation of snking of well curb 4 inner plate fitting and welding 12 drilling of hole in cutting edge 5 ISA 150*150*16 Fabrication 12 77
NO WORK SHUTTERING GANG NOT AVAILABLE
25- Dec-18 0 casting at 8th lift 25 reinforcement & shuttering work in progress at WS 3rdlift 25 0 sinking in progress 4 inner plate fitting and welding 12 bent plate rectification 5 ISA 150*150*16 Fabrication 12 83
26- Dec-18 no sinking since crane are not available 0 casting at 8th lift 25 reinforcement & shuttering work in progress at WS 3rdlift 25 0 sinking in progress 4 inner plate fitting and welding 12 bent plate rectification 5 ISA 150*150*16 Fabrication 12 83
27- Dec-18 0 deshuttering work 10 reinforcement & shuttering work in progress at WS 3rdlift 30 0 sinking in progress 6 inner plate fitting and welding 12 bent plate rectification 5 ISA 150*150*16 Fabrication 12 75
28- Dec-18 SINKING IN PROGRESS 4 deshuttering work 10 reinforcement & shuttering work in progress at WS 3rdlift 25 shuttering work started 12 sinking completed 4 inner plate fitting and welding 12 bent plate rectification 5 ISA 150*150*16 Fabrication 12 84
29- Dec-18 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 casting at 3RD WS lift 25 reinforcement & shuttering work in progress at WS 1st lift 10 reinforcement & shuttering work in progress at WS 1st lift 20 inner plate fitting and welding 12 no work 0 ISA 150*150*16 Fabrication 8 83
30- Dec-18 NO WORK 0 NO WORK 0 casting at 3RD WS lift 25 reinforcement & shuttering work in progress at WS 1st lift 10 reinforcement & shuttering work in progress at WS 1st lift 20 inner plate fitting and welding 12 no work 0 ISA 150*150*16 Fabrication 8 75
31- Dec-18 SINKING IN PROGRESS 4 no sinking work 0 deshuttering work 10 reinforcement & shuttering work in progress at WS 1st lift 10 reinforcement & shuttering work in progress at WS 1st lift 15 inner plate fitting and welding 12 no work 0 no work 0 51
DAILY PROGRESS REPORT(JANUARY ) 2019
labour labour labour labour labour labour labour labour labour
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P12 involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 WELL P11 involved total labour
01- Jan-19 0 no work 0 no work 0 no work 0 NO WORK 0 0 curing work 2 no work 0 2
02- Jan-19 0 no work 0 inner skin plate welding work 18 shuttering and reinforcement work at S1 WS 21 SINKING IN PROGRESS 4 0 deshuttering work of WS S3 6 shuttering and reinforcement work at WS S1 10 59
03- Jan-19 no work 0 Island making 3 inner skin plate welding work 16 shuttering and reinforcement work at S1 WS 21 SINKING IN PROGRESS 4 0 deshuttering work of WS S3 6 shuttering and reinforcement work at WS S1 10 60
no sinking work CRANE IS NOT
04- Jan-19 0 Island making 3 inner skin plate welding work 16 shuttering and reinforcement work at S1 WS 21 SINKING IN PROGRESS 4 AVAILABLE 0 deshuttering work of WS S3 6 shuttering and reinforcement work at WS S1 10 60
05- Jan-19 0 Island making 3 inner skin plate welding work 16 shuttering and reinforcement work at S1 WS 21 0 0 sinking in progress 4 shuttering and reinforcement work at WS S1 10 54
06- Jan-19 fabrication work of cutting edge 2 Island making 0 outer skin plate fixing and welding 15 casting in progress at WS S1 25 0 0 NO SINKING WORK 0 shuttering and reinforcement work at WS S1 15 57
07- Jan-19 fabrication work of cutting edge 2 Island making 0 outer skin plate fixing and welding 15 casting in progress at WS S1 25 0 0 SINKING IN PROGRESS 4 shuttering and reinforcement work at WS S1 15 61
08- Jan-19 fabrication work of cutting edge 2 Island making 0 outer skin plate fixing and welding 15 CURING WORK 2 0 SINKING IN PROGRESS 4 shuttering and reinforcement work at S4 WS 21 casting in progress at 1st lift WS 25 69
09- Jan-19 fabrication work of cutting edge 4 Island making 0 outer skin plate fixing and welding 15 Deshuttering work 10 0 SINKING IN PROGRESS 4 shuttering and reinforcement work at S4 WS 21 casting in progress at 1st lift WS 25 79
10- Jan-19 fabrication work of cutting edge 4 Island making 0 outer skin plate fixing and welding 15 Deshuttering work 10 0 SINKING IN PROGRESS 4 shuttering and reinforcement work at S4 WS 21 curing work 2 56
no sinking
11- Jan-19 No work fabrication work of cutting edge 4 Island making 0 outer skin plate fixing and welding 15 CURING WORK 1 0 SINKING IN PROGRESS 4 shuttering and reinforcement work at S4 WS 27 deshuttering work 10 61
12- Jan-19 fabrication work of cutting edge 4 Island making 0 outer skin plate fixing and welding 15 SINKING IN PROGRESS 4 0 SINKING IN PROGRESS 4 shuttering and reinforcement work at S4 WS 27 deshuttering work 10 64
13- Jan-19 fabrication work of cutting edge 4 Island making 0 no work 0 SINKING IN PROGRESS 4 0 NO SINKING WORK 0 shuttering and reinforcement work at S4 WS 10 curing work 1 19
14- Jan-19 fabrication work of cutting edge 8 Island making 0 outer skin plate fixing and welding 18 SINKING IN PROGRESS 4 0 SINKING IN PROGRESS 4 0 sinking in progress 4 38
15- Jan-19 fabrication work of cutting edge 8 island making & cutting edge placement 6 skin plate welding & reinforcement work 30 shuttering and reinforcement work at S2 WS 20 0 SINKING IN PROGRESS 4 0 sinking in progress 4 72
16- Jan-19 No work fabrication work of cutting edge 10 island making & cutting edge placement 6 skin plate welding & reinforcement work 30 shuttering and reinforcement work at S2 WS 20 0 SINKING IN PROGRESS 4 0 sinking in progress 4 74
17- Jan-19 fabrication work of cutting edge 10 bracket fixing in progress 15 skin plate welding & reinforcement work 30 shuttering and reinforcement work at S2 WS 31 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 no casting shortage of sand 0 no work 0 94
18- Jan-19 fabrication work of cutting edge 10 bracket fixing in progress 15 skin plate welding & reinforcement work 30 shuttering and reinforcement work at S2 WS 25 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 0 no work 0 88
19- Jan-19 fabrication work of cutting edge 10 bracket fixing in progress 15 skin plate welding & reinforcement work 30 shuttering and reinforcement work at S2 WS 15 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 0 shuttering and reinforcement work at WS S2 10 88
20- Jan-19 fabrication work of cutting edge 10 no work 0 skin plate welding & reinforcement work 30 No work 0 No work 0 no sinking work 0 0 no work 0 40
21- Jan-19 fabrication work of cutting edge 10 outer skin plate fixing in progress 15 skin plate welding & reinforcement work 30 0 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 casting in progress 25 shuttering and reinforcement work at WS S2 25 113
casting delay due to shortage of sand
22- Jan-19 Fabrication of cutting edge 10 fabrication work of cutting edge 10 Plate cutting in process 15 skin plate welding & reinforcement work 30 0 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 CURING WORK 0 shuttering and reinforcement work at WS S2 25 88
23- Jan-19 Fabrication of cutting edge 10 0 Plate cutting in process 15 skin plate welding & reinforcement work 18 Casting in progress at P7 2nd lift 30 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 Deshuttering in progress at P10 4th lift 9 shuttering and reinforcement work at WS S2 25 105
24- Jan-19 Fabrication of cutting edge 10 0 inner skin plate fixing in progress 10 skin plate welding & reinforcement work 26 curing work 2 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 Deshuttering in progress at P10 4th lift 9 shuttering and reinforcement work at WS S2 25 80
25- Jan-19 Fabrication of cutting edge 10 0 inner skin plate fixing in progress 18 skin plate welding & reinforcement work 14 curing work 2 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 sinking in progress 4 shuttering and reinforcement work at WS S2 25 71
26- Jan-19 no work 0 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 0
27- Jan-19 bending of cutting and welding 10 no work 0 inner plate fixing and welding 17 skin plate welding & reinforcement work 15 deshuttering work at p7 2nd lift 8 no work no work 0 shuttering & reinforcement work in progress at 5th lift 14 shuttering and reinforcement work at WS S2 25 79
28- Jan-19 bending of cutting and welding 10 0 inner plate fixing and welding 17 skin plate welding & reinforcement work 18 deshuttering work in progress 8 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 shuttering & reinforcement work in progress at 5th lift 32 casting in progress at 2nd lift 25 108
29- Jan-19 bending of cutting and welding 10 0 inner plate fixing and welding 17 casting in progress at well curb 25 SINKING IN progress 4 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 shuttering & reinforcement work in progress at 5th lift 25 curing work 10 89
30- Jan-19 Gusset plate layout marking 8 0 outer and inner skin plate fixing and welding 18 curing work 1 SINKING IN progress 4 Cleaning of surface and S7 WS 5 SINKING IN PROGRESS 4 shuttering & reinforcement work in progress at 5th lift 25 curing work 2 59
31- Jan-19 fabrication of bracket for casssion 20 0 inner plate fixing and welding 10 curing work & wooden block removing 5 SINKING IN progress 4 Shuttering and reinforcement work S7 15 SINKING IN PROGRESS 4 casting in progress at S5 25 deshuttering work in progress 10 73

DAILY PROGRESS REPORT(february ) 2019


labour labour labour labour labour labour labour labour labour labour
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P12 involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved Total Labour
01- Feb-19 cutting edge fabrication in progress 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 10 sinking in progress 4 shuttering & reinforcement work in progress at 3rd lift 21 Shuttering and reinforcement work S7 18 SINKING IN PROGRESS 4 curing work 1 sinking in progress 4 62
02- Feb-19 cutting edge fabrication in progress 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 11 sinking in progress 4 shuttering & reinforcement work in progress at 3rd lift 25 Shuttering and reinforcement work S7 18 SINKING IN PROGRESS 4 deshuttering work in progress 10 sinking in progress 4 76
03- Feb-19 cutting edge fabrication in progress 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 5 no work 0 shuttering & reinforcement work in progress at 3rd lift 12 no work 0 no work 0 no work 0 0 17
04- Feb-19 cutting edge fabrication in progress 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 5 sinking in progress 4 shuttering & reinforcement work in progress at 3rd lift 25 Shuttering and reinforcement work S7 22 SINKING IN PROGRESS 4 deshuttering work in progress 6 no work 0 66
05- Feb-19 Cutting edge fabrication in progress & bracket making 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 5 0 shuttering & reinforcement work in progress at 3rd lift 25 Shuttering and reinforcement work S7 22 SINKING IN PROGRESS 4 sinking in progress 4 shuttering and reinforcement work S3 5 65
06- Feb-19 Cutting edge fabrication in progress & bracket making 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 6 no work 0 shuttering & reinforcement work in progress at 3rd lift 15 casting work is in progress at S7 25 SINKING IN PROGRESS 4 sinking in progress 4 shuttering and reinforcement work S3 10 64
07- Feb-19 Cutting edge fabrication in progress & bracket making 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 5 shuttering and reinforcement at S1 18 casting in progress at P7 3rd lift 25 curing 2 SINKING IN PROGRESS 4 sinking in progress 4 shuttering and reinforcement work S3 20 78
08- Feb-19 Cutting edge fabrication in progress & bracket making 10 fabrication of bracket for casssion 20 0 inner plate fixing and welding 5 shuttering and reinforcement at S1 10 curing work 1 deshuttering in progress 8 SINKING IN PROGRESS 4 sinking in progress 4 shuttering and reinforcement work S3 20 52
09- Feb-19 Cutting edge fabrication in progress & bracket making 5 fabrication of bracket for casssion 20 0 inner plate fixing and welding 5 shuttering and reinforcement at S1 18 curing work 1 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 sinking in progress 4 shuttering and reinforcement work S3 20 56
10- Feb-19 no work 0 no work 0 0 no work 0 shuttering and reinforcement at S1 10 no work 0 no work 0 no work 0 no work 0 shuttering and reinforcement work S3 10 20
11- Feb-19 Cutting edge fabrication in progress & bracket making 10 fabrication of bracket for casssion & cutting edge fixing 20 0 inner plate fixing and welding 8 shuttering and reinforcement at S1 18 Deshuttering in progress 8 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 Shuttering & reinfrocement work in Progress at S6 10 casting in progress S3 25 77
12- Feb-19 Cutting edge fabrication in progress & bracket making 15 fabrication of bracket for casssion & cutting edge fixing 15 0 inner plate fixing and welding 15 shuttering and reinforcement at S1 18 Deshuttering in progress 8 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 Shuttering & reinfrocement work in Progress at S6 15 curing work 1 65
13- Feb-19 no work 0 bracket fixing work in progress 15 0 inner plate fixing and welding 15 shuttering and reinforcement at S1 18 Sinking in progress 4 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 Shuttering & reinfrocement work in Progress at S6 15 deshuttering work in progress 6 66
14- Feb-19 no work 0 bracket fixing work in progress 15 0 inner plate fixing and welding 15 casting in progress at S1 25 Sinking in progress 4 SINKING IN PROGRESS 4 chiselling work 4 Shuttering & reinfrocement work in Progress at S6 15 deshuttering work in progress 6 73
no work
15- Feb-19 no work 0 bracket fixing work in progress 26 0 inner plate fixing and welding 18 curing work 1 Sinking in progress 3 SINKING IN PROGRESS 4 chiselling work 1 Shuttering & reinfrocement work in Progress at S6 15 sinking in progress 4 46
16- Feb-19 no work 0 bracket fixing work in progress 20 0 inner plate fixing and welding 18 Deshuttering work 15 Sinking in progress 4 SINKING IN PROGRESS 4 shuttering and reinforcement work at S9 21 Casting in progress at S6 25 sinking in progress 4 91
17- Feb-19 no work 0 outer ring fitting work in progress 15 0 inner plate fixing and welding 18 curing work 1 no work 0 no work 0 shuttering and reinforcement work at S9 15 Casting in progress at S6 25 shuttering in progress 4th lift 15 74
18- Feb-19 no work 0 outer ring fitting work in progress 26 0 inner plate fixing and welding 18 sinking in progress 4 Sinking in progress 4 no work 0 shuttering and reinforcement work at S9 25 curing work 1 shuttering in progress 4th lift 18 70
19- Feb-19 no work 0 outer ring fitting work in progress 26 0 inner plate fixing and welding 18 sinking in progress 4 Sinking in progress 4 SINKING IN PROGRESS 4 shuttering and reinforcement work at S9 25 Deshuttering work 6 shuttering in progress 4th lift 18 79
20- Feb-19 no work 0 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 No work 0 Sinking in progress 4 SINKING IN PROGRESS 4 shuttering and reinforcement work at S9 25 Deshuttering work 2 shuttering in progress 4th lift 18 71
21- Feb-19 no work 0 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 No work 0 Sinking in progress 4 No work shuttering gang not available 0 casting in progress at S9 25 Deshuttering work 8 shuttering in progress 4th lift 18 73
22- Feb-19 no work 0 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 Shuttering and reinforcement work at S2 25 Sinking in progress 4 No work shuttering gang not available 0 Curing work 1 Sinking in progress 4 shuttering in progress 4th lift 18 70
23- Feb-19 no work 0 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 Shuttering and reinforcement work at S2 25 Sinking in progress 4 No work shuttering gang not available 0 deshuttering work in progress 7 SINKING IN progress 4 casting in progress at S4 25 83
24- Feb-19 no work 0 Outer skin plate fixing work in progress 26 0 Outer skin plate fixing work in progress 10 Shuttering and reinforcement work at S2 13 no work 0 no work 0 deshuttering work in progress 7 no work 4 curing work 1 35
25- Feb-19 no work 0 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 Shuttering and reinforcement work at S2 25 Sinking in progress 4 shuttering and reinforcement at S8 25 deshuttering work in progress 7 SINKING IN progress 4 deshuttering work in progress 10 93
26- Feb-19 no work 0 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 Shuttering and reinforcement work at S2 25 Sinking in progress 4 shuttering and reinforcement at S8 25 no work crane operator not available 0 SINKING IN progress 4 deshuttering work in progress 10 86
27- Feb-19 BRACKET MAKiNG IN PROGRESS 15 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 casting in progress at S2 25 Sinking in progress 4 shuttering and reinforcement at S8 25 SINKING IN PROGRESS 4 SINKING IN progress 4 deshuttering work in progress 10 90
28- Feb-19 BRACKET MAKiNG IN PROGRESS 15 Outer skin plate fixing work in progress 25 0 Outer skin plate fixing work in progress 18 curing work 1 no work 0 shuttering and reinforcement at S8 25 SINKING IN PROGRESS 4 SINKING IN progress 4 SINKING IN progress 4 56

DAILY PROGRESS REPORT(March ) 2019


labour labour labour labour labour labour labour labour labour labour
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P12 involved Total Labour
01- Mar-19 BRACKET MAKiNG IN PROGRESS 15 inner skin plate fixing work 22 Outer skin plate fixing work in progress 10 curing work & deshuttering work 5 shuttering and reinforcement at S4 15 casting in progress at S8 25 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 No work since gang is not available 0 104
02- Mar-19 BRACKET MAKiNG IN PROGRESS 10 inner skin plate fixing work 23 Outer skin plate fixing work in progress 7 deshuttering work 7 shuttering and reinforcement at S4 26 casting in progress at S8 25 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 SINKING IN PROGRESS 4 No work since gang is not available 0 110
03- Mar-19 No work 0 No work 0 No work 0 No work 0 No work 0 No work 0 No work 0 No work 0 No work 0 No work since gang is not available 0 0
04- Mar-19 BRACKET MAKiNG IN PROGRESS 12 inner skin plate fixing work 20 Reinforcemnt & fabrication work well curb 15 deshuttering work 12 shuttering and reinforcement at S4 16 deshuttering work 7 SINKING IN PROGRESS 4 chissling work 1 No work 0 No work since gang is not available 0 87
05- Mar-19 BRACKET MAKiNG IN PROGRESS 12 inner skin plate fixing work 20 Reinforcemnt & fabrication work well curb 12 SINKING IN PROGRESS 4 shuttering and reinforcement at S4 22 deshuttering work 7 SINKING IN PROGRESS 4 0 shuttering in progress 5th lift 8 No work since gang is not available 0 89
06- Mar-19 BRACKET MAKiNG IN PROGRESS 12 inner skin plate fixing work 20 Reinforcemnt & fabrication work well curb 20 SINKING IN PROGRESS 4 casting in progress at S4 25 deshuttering work 5 SINKING IN PROGRESS 4 0 shuttering in progress 5th lift 15 No work since gang is not available 0 105
07- Mar-19 cutting edge bending work & bracket making in progress 15 inner skin plate fixing work 22 Reinforcemnt & fabrication work well curb 20 SINKING IN PROGRESS 4 casting in progress at S4 25 no work 0 SINKING IN PROGRESS 4 0 shuttering in progress 5th lift 20 No work since gang is not available 0 110
08- Mar-19 cutting edge bending work & bracket making in progress 15 inner skin plate fixing work 22 Reinforcemnt & fabrication work well curb 20 SINKING IN PROGRESS 1 Deshuttering in progress 7 Arrangement for shift correction 0 SINKING IN PROGRESS 4 0 shuttering in progress 5th lift 20 No work since gang is not available 0 89
09- Mar-19 cutting edge bending work & bracket making in progress 15 inner skin plate fixing work 22 Reinforcemnt & fabrication work well curb 20 SINKING IN PROGRESS 2 Deshuttering in progress 7 Arrangement for shift correction 6 SINKING IN PROGRESS 4 No work since worker 0 shuttering in progress 5th lift 20 No work since gang is not available 0 96
10- Mar-19 No work 0 inner skin plate fixing work 12 Reinforcemnt & fabrication work well curb 15 No work 0 No work 0 No work 0 No work 0 gang is not availble 0 shuttering in progress 5th lift 5 No work since gang is not available 0 32
11- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing work 12 Reinforcemnt & fabrication work well curb 15 sinking in progress 4 No work 0 No work 0 SINKING IN PROGRESS 4 shuttering in progress 7th lift 25 casting in progress at S5 25 No work since gang is not available 0 95
12- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing work 12 Reinforcemnt & fabrication work well curb 15 sinking in progress 4 Sinking in progress 4 Arrangement for shift correction 2 SINKING IN PROGRESS 4 shuttering in progress 7th lift 25 CURING 1 No work since gang is not available 0 77
13- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing work 12 Reinforcemnt & fabrication work well curb 15 0 Sinking in progress 4 Arrangement for shift correction 5 SINKING IN PROGRESS 4 shuttering in progress 7th lift 25 deshuttering work 5 No work since gang is not available 0 80
14- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing work 12 Reinforcemnt & fabrication work well curb 20 No work due to gang not avalable 0 Sinking in progress 4 Arrangement for shift correction 6 SINKING IN PROGRESS 4 shuttering in progress 7th lift 15 deshuttering work 10 No work since gang is not available 0 81
15- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing of molude 18 Reinforcemnt & fabrication work well curb 18 shuttering and reinforcement of S3 20 Sinking in progress 4 Arrangement for shift correction 4 SINKING IN PROGRESS 4 CASTING IN PROGRESS AT S7 25 deshuttering work 8 No work since gang is not available 0 111
16- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing of molude 18 Reinforcemnt & fabrication work well curb 18 shuttering and reinforcement of S3 20 Sinking in progress 4 Arrangement for shift correction 4 SINKING IN PROGRESS 4 casting complted at 10 AM 25 deshuttering work 4 No work since gang is not available 0 107
17- Mar-19 cutting edge bending work & bracket making in progress 10 inner skin plate fixing of molude 10 casting in progress at well curb 25 shuttering and reinforcement of S3 10 Sinking in progress 4 Arrangement for shift correction 5 SINKING IN PROGRESS 4 curing work 1 SINKING IN PROGRESS 4 No work since gang is not available 0 73
18- Mar-19 module fabrication work 20 inner skin plate fixing of molude 18 casting complted at 6am 25 shuttering and reinforcement of S3 14 Sinking in progress 4 Arrangement for shift correction 5 SINKING IN PROGRESS 4 deshuttering work 5 SINKING IN PROGRESS 4 No work since gang is not available 0 99
19- Mar-19 module fabrication work 20 inner skin plate fixing of molude 18 sinking preparation 10 shuttering and reinforcement of S3 14 Sinking in progress 4 Sinking in progress 3 SINKING IN PROGRESS 4 deshuttering work 8 SINKING IN PROGRESS 4 No work since gang is not available 0 85
20- Mar-19 module fabrication work 18 module fabrication work 20 Sinking in progress 4 shuttering and reinforcement of S3 14 Sinking in progress 4 no work due crane wire danaged 0 SINKING IN PROGRESS 3 deshuttering work 4 SINKING IN PROGRESS 4 No work since gang is not available 0 71
21- Mar-19 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 No work since gang is not available 0 0
22- Mar-19 module fabrication work 18 welding of cassion 16 no work due to holi 0 shuttering and reinforcement of S3 14 no work due to holi 0 no work due to holi 0 no work due to holi 0 no work due to holi 0 shuttering in progress 6th lift 16 No work since gang is not available 0 64
23- Mar-19 module fabrication work 18 welding of cassion 16 Sinking in progress 4 0 Sinking in progress 4 no work crane break down 0 SINKING IN PROGRESS 2 deshuttering work 3 shuttering in progress 6th lift 16 No work since gang is not available 0 63
24- Mar-19 no work 0 No work 0 Sinking in progress 4 No work casting delay due to admixtures 0 NO WORK 0 NO WORK 0 SINKING IN PROGRESS 3 no work 0 no work 0 No work since gang is not available 0 7
25- Mar-19 module fabrication work 18 welding of cassion 10 shuttering and reinforecment work at S1 14 casting in progress at S3 25 Sinking in progress 4 Sinking in progress 3 SOIL REMOVINGFROM WELL SIDE 0 SINKING IN PROGRESS 4 shuttering in progress 6th lift 14 No work since gang is not available 0 92
26- Mar-19 module fabrication work 18 welding of cassion 16 shuttering and reinforecment work at S1 15 casting in progress at S3 TILL 1PM 25 Sinking in progress 4 Sinking in progress 3 SOIL REMOVINGFROM WELL SIDE 0 SINKING IN PROGRESS 3 shuttering in progress 6th lift 15 No work since gang is not available 0 99
27- Mar-19 module fabrication work 18 cassion surraounding soil excavation work 5 shuttering and reinforecment work at S1 14 curing work 0 Sinking in progress 3 Sinking in progress 3 no work 0 SINKING IN PROGRESS 3 shuttering in progress 6th lift 14 No work since gang is not available 0 60
28- Mar-19 module fabrication work 18 cassion surraounding soil excavation work 4 shuttering and reinforecment work at S1 14 deshuttering work 10 no work 0 Sinking in progress 3 no work 0 SINKING IN PROGRESS 3 shuttering in progress 6th lift 14 No work since gang is not available 0 66
29- Mar-19 module fabrication work 25 cassion surraounding soil excavation work 5 shuttering and reinforecment work at S1 14 no work 0 no work 0 Sinking in progress 3 no work 0 SINKING IN PROGRESS 2 casting in progress at S6 25 No work since gang is not available 0 74
30- Mar-19 module fabrication work 25 cassion surraounding soil excavation work 5 shuttering and reinforecment work at S1 14 no work 0 no work 0 no work 0 surface cleaning work 3 SINKING IN PROGRESS 3 curing work 1 No work since gang is not available 0 51
31- Mar-19 module fabrication work 25 cassion surraounding soil excavation work 5 casting in progress at S1 25 deshuttering work 5 no work 0 no work 0 surface cleaning work 2 SINKING IN PROGRESS 3 curing work 1 GROUND LEVELING WORK 2 68

DAILY PROGRESS REPORT(APRIL ) 2019


labour labour labour labour labour labour labour labour labour labour
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P12 involved Total Labour
01- Apr-19 module fabrication work 25 FLOATING OF CASSION DONE 10 deshuttering work 1 deshuttering work 10 shuttering and reinforcement work at S5 7 Sinking in progress 3 shuttering and reinforcement work at S10 8 SINKING IN PROGRESS 4 deshuttering work at S6 12 LAYOUT OF CUTTING EDGE 2 82
02- Apr-19 module fabrication work 30 reinforcement fixing work in cassion 8 deshuttering work 1 deshuttering work 12 shuttering and reinforcement work at S5 8 Sinking in progress 3 shuttering and reinforcement work at S10 9 SINKING IN PROGRESS 4 deshuttering work at S6 10 cutting edge shifted to site 5 90
03- Apr-19 cutting edge assembly work 30 reinforcement fixing work in cassion 28 Sinking in progress 1 Sinking in progress 4 shuttering and reinforcement work at S5 12 Sinking in progress 3 shuttering and reinforcement work at S10 12 SINKING IN PROGRESS 4 curing work 1 no work 0 95
04- Apr-19 cutting edge assembly work 14 reinforcement fixing work in cassion 8 deshuttering work 5 Sinking in progress 4 shuttering and reinforcement work at S5 7 no work 0 shuttering and reinforcement work at S10 13 SINKING IN PROGRESS 4 no work 0 no work 0 55
05- Apr-19 cutting edge assembly work 14 reinforcement fixing work in cassion 8 deshuttering work 5 Sinking in progress 4 shuttering and reinforcement work at S5 6 no work 0 shuttering and reinforcement work at S10 13 no work shuttering gang not available 0 no work 0 no work 0 50
06- Apr-19 Bracket faxing in progress 18 reinforcement fixing work in cassion 8 Sinking in progress 3 Sinking in progress 4 shuttering and reinforcement work at S5 10 no work 0 shuttering and reinforcement work at S10 18 no work shuttering gang not available 0 SINKING IN PROGRESS 3 cutting edge placing wrok 13 77
07- Apr-19 no work 0 no work 0 no work no work no work 0 no work 0 no work 0 no work shuttering gang not available 0 no work 0 no work 0 0
08- Apr-19 Bracket faxing in progress 18 reinforcement fixing work in cassion 8 Sinking in progress 3 Sinking in progress 4 shuttering and reinforcement work at S5 20 no work 0 casting at S10 23 no work shuttering gang not available 0 SINKING IN PROGRESS 2 cutting edge parts assemblly work 22 100
09- Apr-19 Bracket faxing in progress 18 reinforcement fixing work in cassion 8 Sinking in progress 3 Sinking in progress 4 shuttering and reinforcement work at S5 20 shuttering and reinforecment at S9 10 casting at S10 23 no work shuttering gang not available 0 no work 0 cutting edge parts assemblly work 22 108
10- Apr-19 outer skin welding work 10 reinforcement fixing work in progress & module fabrication 27 Sinking in progress 4 Sinking in progress 4 shuttering and reinforcement work at S5 14 shuttering and reinforecment at S9 6 deshuttering work 4 no work shuttering gang not available 0 SINKING IN PROGRESS 3 cutting edge parts assemblly work 14 86
11- Apr-19 outer skin welding work 17 reinforcement fixing work in progress & module fabrication 32 no work 0 Sinking in progress 4 shuttering and reinforcement work at S5 18 no work 0 deshuttering work 4 no work shuttering gang not available 0 SINKING IN PROGRESS 3 drilling of holes 13 91
12- Apr-19 outer skin welding work 18 reinforcement fixing work in progress & module fabrication 39 no work 0 Sinking in progress 4 casting at s5 25 shuttering and reinforecment at S9 15 deshuttering work 5 no work shuttering gang not available 0 SINKING IN PROGRESS 4 stiiffner welding work 4 114
13- Apr-19 outer skin welding work 28 reinforcement fixing work in progress & module fabrication 45 curing work 0 Sinking in progress 4 curing work 1 shuttering and reinforecment at S9 18 no work 0 no work shuttering gang not available 0 SINKING IN PROGRESS 4 no work 0 100
14- Apr-19 no work 0 no work 0 no work 0 no work 0 curing work 1 no work 0 no work 0 no work shuttering gang not available 0 no work 0 no work 0 1
15- Apr-19 outer skin and inner skin plate welding work 24 reinforcement fixing work in progress & module fabrication 42 curing work 1 Sinking in progress 4 deshuttering work S5 4 shuttering and reinforecment at S9 20 Sinking in progress 2 no work shuttering gang not available 0 SINKING IN PROGRESS 3 no work 0 100
16- Apr-19 outer skin and inner skin plate welding work 18 reinforcement fixing work in progress & module fabrication 39 shuttering and reinforcement work at S2 12 Sinking in progress 4 deshuttering work S5 4 shuttering and reinforecment at S9 8 Sinking in progress 2 no work shuttering gang not available 0 SINKING IN PROGRESS 2 no work 0 89
17- Apr-19 outer skin and inner skin plate welding work 25 reinforcement fixing work in progress & module fabrication 35 shuttering and reinforcement work at S2 14 Sinking in progress 2 deshuttering work S5 4 casting at S9 23 Sinking in progress 2 no work shuttering gang not available 0 SINKING IN PROGRESS 2 no work 0 107
18- Apr-19 outer skin and inner skin plate welding work 27 reinforcement fixing work in progress & module fabrication 24 shuttering and reinforcement work at S2 20 Sinking in progress 2 Sinking in progress 2 casting at S9 25 Sinking in progress 2 no work shuttering gang not available 0 SINKING IN PROGRESS 2 no work 0 104
19- Apr-19 outer skin and inner skin plate welding work 25 reinforcement fixing work in progress & module fabrication 25 shuttering and reinforcement work at S2 14 no work Sinking in progress 2 deshuttering work in progress 3 Sinking in progress 2 no work shuttering gang not available 0 no work 0 no work 0 71
20- Apr-19 outer skin and inner skin plate welding work 40 reinforcement fixing work in progress & module fabrication 27 shuttering and reinforcement work at S2 13 no work 0 Sinking in progress 2 deshuttering work in progress 5 Sinking in progress 2 no work shuttering gang not available 0 no work 0 no work 0 89
21- Apr-19 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work shuttering gang not available 0 no work 0 no work 0 0
22- Apr-19 outer skin and iner skin plate welding work 39 reinforcement fixing work in progress 26 shuttering and reinforcement work at S2 12 no work 0 Sinking in progress 2 deshuttering work in progress 4 Sinking in progress 2 no work shuttering gang not available 0 no work 0 no work 0 85
23- Apr-19 outer skin and iner skin plate welding work 39 reinforcement fixing work in progress 26 shuttering and reinforcement work at S2 12 no work 0 Sinking in progress 2 deshuttering work in progress 10 Sinking in progress 2 no work shuttering gang not available 0 no work 0 no work 0 91
24- Apr-19 outer skin and iner skin plate welding work 30 reinforcement fixing work in progress 10 shuttering and reinforcement work at S2 20 no work 0 Sinking in progress 2 CURING WORK 1 Sinking in progress 2 no work shuttering gang not available 0 no work 0 no work 0 65
25- Apr-19 outer skin and iner skin plate welding work 39 Frame fixing with cassion 26 shuttering and reinforcement work at S2 12 SHUTTERING WORK AT S4 18 Sinking in progress 2 CURING WORK 1 Sinking in progress 2 no work shuttering gang not available 0 no work 0 no work 0 100

NO WORK DONE FROM 26/04/2019 TO 31/05/2019


labour labour labour labour labour labour labour labour labour labour
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P12 involved Total Labour
01- Jun-19 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 0
02- Jun-19 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 0
03- Jun-19 no work 0 no work 0 Casting at S2 well steining 25 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 25
04- Jun-19 no work 0 no work 0 Casting at S2 well steining 25 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 25
05- Jun-19 no work 0 no work 0 Deshuttering work 10 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 10
06- Jun-19 no work 0 no work 0 Deshuttering work 10 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 10
07- Jun-19 no work 0 no work 0 Deshuttering work 7 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 7
08- Jun-19 no work 0 no work 0 sinking in progress 2 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 2
09- Jun-19 no work 0 no work 0 sinking in progress 2 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 2
10- Jun-19 no work 0 no work 0 sinking in progress 2 no work 0 no work 0 no work 0 0 0 no work 0 no work due to material and gand shortage 0 2
11- Jun-19 no work 0 no work 0 sinking in progress 2 Shuttering and reinforcement work at S4 15 no work 0 no work 0 no work 0 0 no work 0 no work due to material and gand shortage 0 17
12- Jun-19 no work 0 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2 0 no work 0 no work due to material and gand shortage 0 17
13- Jun-19 no work 0 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2 0 no work 0 no work due to material and gand shortage 0 17
14- Jun-19 no work 0 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2
no work due to gang 0 no work 0 no work due to material and gand shortage 0 17
15- Jun-19 inner skin plate welding work in progress 10 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2
not available 0 SINKING IN PROGRESS 2 no work due to material and gand shortage 0 29
16- Jun-19 inner skin plate welding work in progress 10 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2 0 SINKING IN PROGRESS 2 no work due to material and gand shortage 0 29
17- Jun-19 inner skin plate welding work in progress 10 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2 0 SINKING IN PROGRESS 2 no work due to material and gand shortage 0 29
18- Jun-19 inner skin plate welding work in progress 10 no work 0 no work 0 Shuttering and reinforcement work at S4 15 no work 0 no work 0 Sinking in progress 2 0 SINKING IN PROGRESS 2 no work due to material and gand shortage 0 29
19- Jun-19 inner skin plate welding work in progress 15 no work 0 no work 0 no work 0 no work 0 no work 0 no work 3 0 no work 0 no work due to material and gand shortage 0 18
20- Jun-19 inner skin plate welding work in progress 18 no work 0 shuttering and reinforcement work at S3 15 Casting in progress at S4 25 shuttering and reinforcement work in progress at S6 15 no work 0 Sinking in progress 3 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 79
21- Jun-19 inner skin plate welding work in progress 15 no work 0 shuttering and reinforcement work at S3 15 Casting in progress at S4 24 shuttering and reinforcement work in progress at S6 15 no work 0 Sinking in progress 3 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 75
22- Jun-19 inner skin plate welding work in progress 15 no work 0 shuttering and reinforcement work at S3 15 Deshuttering work in progress 10 shuttering and reinforcement work in progress at S6 15 no work 0 Sinking in progress 3 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 61
23- Jun-19 inner skin plate welding work in progress 18 no work 0 shuttering and reinforcement work at S3 15 Deshuttering work in progress 10 shuttering and reinforcement work in progress at S6 15 no work 0 Sinking in progress 3 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 64
24- Jun-19 inner skin plate welding work in progress 18 no work 0 shuttering and reinforcement work at S3 18 Sinking in progress 3 shuttering and reinforcement work in progress at S6 15 no work 0 Sinking in progress 3 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 60
25- Jun-19 inner skin plate welding work in progress 18 no work 0 shuttering and reinforcement work at S3 15 Sinking in progress 3 shuttering and reinforcement work in progress at S6 15 no work 0 no work (well sink due to self weight 0 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 54
26- Jun-19 inner skin plate welding work in progress 18 no work 0 shuttering and reinforcement work at S3 14 Sinking in progress 3 shuttering and reinforcement work in progress at S6 15 no work 0 no work (well sink due to self weight 0 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 53
27- Jun-19 inner skin plate welding work in progress 18 no work 0 casting at S3 well steining 25 Sinking in progress 3 shuttering and reinforcement work in progress at S6 15 no work 0 no work (well sink due to self weight 0 0 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 64
28- Jun-19 inner skin plate welding work in progress 18 Shifting of cassion toward A1 side 10 casting at S3 well steining till 8 AM 25 Sinking in progress 3 shuttering and reinforcement work in progress at S6 15 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 15 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 89
29- Jun-19 inner skin plate welding work in progress 18 Shifting of cassion toward A1 side 10 Deshuttering work 6 Sinking in progress 3 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 15 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 55
30- Jun-19 no work 0 no work 0 Deshuttering work 15 no work 0 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 no work 0 no work 0 no work due to material and gand shortage 0 15

DAILY PROGRESS REPORT(JULY ) 2019 0


labour labour labour labour labour labour labour labour labour labour TOTAL
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P12 involved WORKER
01- Jul-19 Outer skin plate welding worl in progress 18 no work 0 sinking started 3 Sinking in progress 3 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 10 SINKING IN PROGRESS 3 no work due to material and gand shortage 0 37
02- Jul-19 Outer skin plate welding worl in progress 18 no work 0 sinking in progress 3 Sinking in progress 3 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 12 Shuttering and reinforcement work in progress at S7 15 no work due to material and gand shortage 0 51
03- Jul-19 Outer skin plate welding worl in progress 18 no work 0 sinking in progress 3 Sinking in progress 3 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 12 Shuttering and reinforcement work in progress at S7 15 no work due to material and gand shortage 0 51
04- Jul-19 Outer skin plate welding worl in progress 18 no work 0 sinking in progress 3 Sinking in progress 3 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 16 Shuttering and reinforcement work in progress at S7 15 no work due to material and gand shortage 0 55
05- Jul-19 Outer skin plate welding worl in progress 18 no work 0 sinking in progress 3 Sinking in progress 3 no work due to unavailability of machanical splices 0 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 15 Shuttering and reinforcement work in progress at S7 15 no work due to material and gand shortage 0 54
06- Jul-19 Outer skin plate welding worl in progress 18 no work 0 sinking in progress 3 Sinking in progress 3 shuttering and reinforcement work in progress at S6 10 no work 0 no work (well sink due to self weight 0 Shuttering and reinforcement work at S8 10 no work 0 no work due to material and gand shortage 0 44
07- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 shuttering and reinforcement work in progress at S6 10 no work 0 no work (well sink due to self weight 0 casting in progress for S8 25 no work 0 no work 0 35
08- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 shuttering and reinforcement work in progress at S6 3 Assembly of section for tilt ad shift correction 5 no work (well sink due to self weight 0 casting in progress for S8 till 7 AM 25 no work 0 drilling hole in cutting edge 10 43
09- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Assembly of section for tilt ad shift correction 10 no work (well sink due to self weight 0 deshuttering work in progress 15 no work 0 drilling hole in cutting edge 15 40
10- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Assembly of section for tilt ad shift correction 5 no work (well sink due to self weight 0 sinking in progress 2 Shuttering and reinforcement work in progress at S7 8 drilling hole in cutting edge 12 27
11- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Assembly of section for tilt ad shift correction 5 no work (well sink due to self weight 0 sinking in progress 2 Shuttering and reinforcement work in progress at S7 8 drilling hole in cutting edge 3 18
12- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 casting in progress at S6 25 Assembly of section for tilt ad shift correction 5 no work (well sink due to self weight 0 sinking in progress 3 Shuttering and reinforcement work in progress at S7 8 drilling hole in cutting edge 3 44
13- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 casting in progress at S6 25 Assembly of section for tilt ad shift correction 5 no work (well sink due to self weight 0 sinking in progress 3 Shuttering and reinforcement work in progress at S7 10 drilling hole in cutting edge 8 51
14- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 Assembly of section for tilt ad shift correction 5 no work (well sink due to self weight 0 no work 0 no work 0 no work 0 5
15- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 curing work 1 sinking in progress 4 no work (well sink due to self weight 0 sinking in progress 3 casting in progress at S7 25 drilling hole in cutting edge 3 36
16- Jul-19 NO WROK DUE WATER LEVEL RISES 0 no work 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 curing work 1 sinking in progress 4 no work (well sink due to self weight 0 sinking in progress 3 curing work 1 inner skin plate cutting in progress 9 18
17- Jul-19 no work no work 0 sinking in progress 3 Cleaning of steinig 1 Deshuttering work in progress 1 sinking in progress 4 no work (well sink due to self weight sinking in progress 3 deshuttering work in progress 5 inner skin plate cutting in progress 8 25
18- Jul-19 no work 0 no work 0 sinking in progress 3 Shuttering and reinforcement work at S5 7 Deshuttering work in progress 5 sinking in progress 3 bottom plugging in progress 25 no work 0 deshuttering work in progress 7 inner skin plate cutting in progress 8 58
19- Jul-19 Floating of cassion 5 no work 0 sinking in progress 3 Shuttering and reinforcement work at S5 7 curing work but no sinking work 5 sinking in progress 3 bottom plugging in progress 25 no work 0 deshuttering work in progress 5 bracket fabrication work in progress 8 61
20- Jul-19 Floating of cassion 5 no work 0 sinking in progress 3 Shuttering and reinforcement work at S5 12 curing work but no sinking work 1 sinking in progress 3 no work 0 no work 0 deshuttering work in progress 5 bracket fabrication work in progress 8 37
21- Jul-19 Floating of cassion 5 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 no work 0 5
22- Jul-19 no work 0 no work sinking in progress 2 Shuttering and reinforcement work at S5 12 curing work but no sinking work 1 sinking in progress 2 no work 0 sinking in progress 2 no work 0 bracket fabrication work in progress 8 27
23- Jul-19 no work 0 no work sinking in progress 2 Shuttering and reinforcement work at S5 12 curing work but no sinking work 1 sinking in progress 2 no work 0 sinking in progress 2 no work 0 bracket fabrication work in progress 8 27
24- Jul-19 no work 0 no work sinking in progress 2 Shuttering and reinforcement work at S5 12 curing work but no sinking work 1 sinking in progress 2 no work 0 sinking in progress 2 no work 0 bracket fabrication work in progress 8 27
25- Jul-19 no work 0 no work sinking in progress 2 Casting at S5 well steining 25 curing work but no sinking work 1 sinking in progress 2 no work 0 sinking in progress 2 no work 0 bracket fabrication work in progress 8 40
26- Jul-19 no work 0 no work sinking in progress 2 Casting at S5 well steining 25 sinking in progress 2 sinking in progress 2 no work 0 sinking in progress 2 no work 0 Skin plate cutting in progress 12 45
27- Jul-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 Skin plate cutting in progress 12 12
28- Jul-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 Skin plate cutting in progress 12 12
29- Jul-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 outer skin plate fixing in progress 20 20
30- Jul-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 outer skin plate fixing in progress 17 17
31- Jul-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Sinking in progress 2 outer skin plate fixing in progress 18 20
labour labour labour labour labour labour labour labour labour labour TOTAL
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P12 involved WORKER
01- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Sinking in progress 2 inner skin plate fixing in progress 17 19
02- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 Sinking in progress 2 inner skin plate fixing in progress 17 19
03- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 Sinking in progress 2 inner skin plate fixing in progress 17 19
04- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 no work 0 inner skin plate fixing in progress 17 17
05- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Shuttering and reinforcement work at S9 10 Sinking in progress 2 inner skin plate fixing in progress 17 29
06- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Shuttering and reinforcement work at S9 10 Sinking in progress 2 inner skin plate fixing in progress 17 29
07- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Shuttering and reinforcement work at S9 10 Sinking in progress 2 inner skin plate fixing in progress 17 29
08- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Shuttering and reinforcement work at S9 10 Sinking in progress 2 inner skin plate fixing in progress 17 29
09- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Shuttering and reinforcement work at S9 10 Sinking in progress 2 inner skin plate fixing in progress 17 29
10- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 Shuttering and reinforcement work at S9 10 Sinking in progress 2 inner skin plate fixing in progress 16 28
11- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 no work 0 0
12- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL
26- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 1 NO WROK DUE WATER LEVEL RISES NO WROK DUE WATER LEVEL RISES 1
27- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 1 NO WROK DUE WATER LEVEL RISES NO WROK DUE WATER LEVEL RISES 1
28- Aug-19 NO WROK DUE WATER LEVEL RISES 0 NO WROK DUE WATER LEVEL RISES 1 NO WROK DUE WATER LEVEL RISES NO WROK DUE WATER LEVEL RISES 1
29- Aug-19 0
30- Aug-19 0
31- Aug-19 0
labour labour labour labour labour labour labour labour labour labour TOTAL
DATE Well P3 Cassion involved Well P4 Cassion involved WELL P05 involved Well P06 involved WELL P07 involved WELL P8 involved WELL P9 involved WELL P10 involved WELL P11 involved WELL P12 involved WORKER
DATE Wrok Description 1283640 to 1283700 1283700 to 1283750 1283750 to 1283800 1283800 to 1238880 1283880 to 1283980 1238980 to 1284000 1284000 to 1284100
01- Jun-19
02- Jun-19 FDD checking betwwn 1283880 to 1283980 1st layer Layer 1
03- Jun-19
04- Jun-19 FDD checking betwwn 1284000 to 1284100 3rd layer Layer 3
05- Jun-19 FDD checking betwwn 1284100 to 1284160 3rd layer
06- Jun-19 FDD checking betwwn 1283880 to 1283980 2ND layer AND 1284000 TO 1284100 4TH LAYER Layer 2 Layer 4
07- Jun-19 FDD checking betwwn 1283800 to 1283880 1ST layer & 2ND Layer Layer 1 & Layer 2
08- Jun-19 FDD checking betwwn 1283800 to 1283880 1ST layer & 3rd Layer Layer 3 Layer 3
09- Jun-19 FDD checking betwwn 1284000 to 1284100 5th layer Layer 1 Layer 5
10- Jun-19 Layer 4
11- Jun-19 Layer 1 Layer 1 Layer 1
12- Jun-19
13- Jun-19
14- Jun-19
15- Jun-19
16- Jun-19
17- Jun-19
18- Jun-19
19- Jun-19
20- Jun-19
21- Jun-19
22- Jun-19
23- Jun-19
24- Jun-19
25- Jun-19
26- Jun-19
27- Jun-19
28- Jun-19
29- Jun-19
30- Jun-19
summary of sinking and construction at P03
Machine & Man Power
RL OF BOTTOM
OF CUTTING SINKING CUMMULATIVE CRANE 1 CRANE 2 LABOUR
DATE work details OGL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
01- Feb-19 cutting edge fabrication in progress 0 0 10 12
02- Feb-19 cutting edge fabrication in progress 0 0 10 12
03- Feb-19 cutting edge fabrication in progress 0 0 10 12
04- Feb-19 cutting edge fabrication in progress 0 0 10 12
05- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 10 12
06- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 10 12
07- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 10 12
08- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 10 12
09- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 5 12
10- Feb-19 no work 0 0 0 0
11- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 10 12
12- Feb-19 Cutting edge fabrication in progress & bracket making 0 0 15 12
13- Feb-19 no work 0 0 0 0
14- Feb-19 no work 0 0 0 0
15- Feb-19 no work 0 0 0 0
16- Feb-19 no work 0 0 0 0
17- Feb-19 no work 0 0 0 0
18- Feb-19 no work 0 0 0 0
19- Feb-19 no work 0 0 0 0
20- Feb-19 no work 0 0 0 0
21- Feb-19 no work 0 0 0 0
22- Feb-19 no work 0 0 0 0
23- Feb-19 no work 0 0 0 0
24- Feb-19 no work 0 0 0 0
25- Feb-19 no work 0 0 0 0
26- Feb-19 no work 0 0 0 0
27- Feb-19 BRACKET MAKiNG IN PROGRESS 0 0 15 12
28- Feb-19 BRACKET MAKiNG IN PROGRESS 0 0 15 12

01- Mar-19 BRACKET MAKiNG IN PROGRESS 0 0 15 12


02- Mar-19 BRACKET MAKiNG IN PROGRESS 0 0 10 12
03- Mar-19 No work 0 0 0 0
04- Mar-19 BRACKET MAKiNG IN PROGRESS 0 0 12 12
05- Mar-19 BRACKET MAKiNG IN PROGRESS 0 0 12 12
06- Mar-19 BRACKET MAKiNG IN PROGRESS 0 0 12 12
07- Mar-19 cutting edge bending work & bracket making in progress 0 0 15 12
08- Mar-19 cutting edge bending work & bracket making in progress 0 0 15 12
09- Mar-19 cutting edge bending work & bracket making in progress 0 0 15 12
10- Mar-19 No work 0 0 0 0
11- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
12- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
13- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
14- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
15- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
16- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
17- Mar-19 cutting edge bending work & bracket making in progress 0 0 10 12
18- Mar-19 module fabrication work 0 0 20 12
19- Mar-19 module fabrication work 0 0 20 12
20- Mar-19 module fabrication work 0 0 18 12
21- Mar-19 no work due to holi 0 0 0 0
22- Mar-19 module fabrication work 0 0 18 12
23- Mar-19 module fabrication work 0 0 18 12
24- Mar-19 no work 0 0 0 0
25- Mar-19 module fabrication work 0 0 18 12
26- Mar-19 module fabrication work 0 0 18 12
27- Mar-19 module fabrication work 0 0 18 12
28- Mar-19 module fabrication work 0 0 18 12
29- Mar-19 module fabrication work 0 0 25 12
30- Mar-19 module fabrication work 0 0 25 12
31- Mar-19 module fabrication work 0 0 25 12

01- Apr-19 module fabrication work 0 0 25 12


02- Apr-19 module fabrication work 0 0 30 12
03- Apr-19 cutting edge assembly work 0 0 30 12
04- Apr-19 cutting edge assembly work 0 0 14 12
05- Apr-19 cutting edge assembly work 0 0 14 12
06- Apr-19 Bracket faxing in progress 0 0 18 12
07- Apr-19 no work 0 0 0 0
08- Apr-19 Bracket faxing in progress 0 0 18 12
09- Apr-19 Bracket faxing in progress 0 0 18 12
10- Apr-19 outer skin welding work 0 0 10 12
11- Apr-19 outer skin welding work 0 0 17 12
12- Apr-19 outer skin welding work 0 0 18 12
13- Apr-19 outer skin welding work 0 0 28 12
14- Apr-19 no work 0 0 0 0
15- Apr-19 outer skin and inner skin plate welding work 0 0 24 12
16- Apr-19 outer skin and inner skin plate welding work 0 0 18 12
17- Apr-19 outer skin and inner skin plate welding work 0 0 25 12
18- Apr-19 outer skin and inner skin plate welding work 0 0 27 12
19- Apr-19 outer skin and inner skin plate welding work 0 0 25 12
20- Apr-19 outer skin and inner skin plate welding work 0 0 40 12
21- Apr-19 no work 0 0 0 0
22- Apr-19 outer skin and iner skin plate welding work 0 0 39 12
23- Apr-19 outer skin and iner skin plate welding work 0 0 39 12
24- Apr-19 outer skin and iner skin plate welding work 0 0 39 12
25- Apr-19 outer skin and iner skin plate welding work 0 0 39 12
26- Apr-19

01- Jun-19 0 0 0 0
02- Jun-19 0 0 0 0
03- Jun-19 0 0 0 0
04- Jun-19 0 0 0 0
05- Jun-19 0 0 0 0
06- Jun-19 0 0 0 0
07- Jun-19 0 0 0 0
08- Jun-19
no work 0 0 0 0
09- Jun-19 0 0 0 0
10- Jun-19 0 0 0 0
11- Jun-19 0 0 0 0
12- Jun-19 0 0 0 0
13- Jun-19 0 0 0 0
14- Jun-19 0 0 0 0
15- Jun-19 inner skin plate welding work in progress 0 0 10 12
16- Jun-19 inner skin plate welding work in progress 0 0 10 12
17- Jun-19 inner skin plate welding work in progress 0 0 10 12
18- Jun-19 inner skin plate welding work in progress 0 0 10 12
19- Jun-19 inner skin plate welding work in progress 0 0 15 12
20- Jun-19 inner skin plate welding work in progress 0 0 18 12
21- Jun-19 inner skin plate welding work in progress 0 0 15 12
22- Jun-19 inner skin plate welding work in progress 0 0 15 12
23- Jun-19 inner skin plate welding work in progress 0 0 18 12
24- Jun-19 inner skin plate welding work in progress 0 0 18 12
25- Jun-19 inner skin plate welding work in progress 0 0 18 12
26- Jun-19 inner skin plate welding work in progress 0 0 18 12
27- Jun-19 inner skin plate welding work in progress 0 0 18 12
28- Jun-19 inner skin plate welding work in progress 0 0 18 12
29- Jun-19 inner skin plate welding work in progress 0 0 18 12
30- Jun-19 no work 0 0 0 0

01- Jul-19 Outer skin plate welding worl in progress 0 0 18 12


02- Jul-19 Outer skin plate welding worl in progress 0 0 18 12
03- Jul-19 Outer skin plate welding worl in progress 0 0 18 12
04- Jul-19 Outer skin plate welding worl in progress 0 0 18 12
05- Jul-19 Outer skin plate welding worl in progress 0 0 18 12
06- Jul-19 Outer skin plate welding worl in progress 0 0 18 12
07- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
08- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
09- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
10- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
11- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
12- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
13- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
14- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
15- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
16- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
17- Jul-19 no work 0 0 0 0
18- Jul-19 no work 0 0 0 0
19- Jul-19 Floating of cassion 0 0 5 12
20- Jul-19 Floating of cassion 0 0 5 12
21- Jul-19 Floating of cassion 0 0 5 12
22- Jul-19 no work 0 0 0 0
23- Jul-19 no work 0 0 0 0
24- Jul-19 no work 0 0 0 0
25- Jul-19 no work 0 0 0 0
26- Jul-19 no work 0 0 0 0
27- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
28- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
29- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
30- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
31- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0

01- Aug-19 NO WROK DUE WATER LEVEL RISES


02- Aug-19 NO WROK DUE WATER LEVEL RISES
03- Aug-19
summary of sinking and construction at P04
Machine & Man Power
RL OF BOTTOM
OF CUTTING SINKING CUMMULATIVE CRANE 1 CRANE 2 LABOUR
DATE work details OGL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
24- Dec-18 ISA 150*150*16 Fabrication 0 0 12 12
25- Dec-18 ISA 150*150*16 Fabrication 0 0 12 12
26- Dec-18 ISA 150*150*16 Fabrication 0 0 12 12
27- Dec-18 ISA 150*150*16 Fabrication 0 0 12 12
28- Dec-18 ISA 150*150*16 Fabrication 0 0 12 12
29- Dec-18 ISA 150*150*16 Fabrication 0 0 8 12
30- Dec-18 NO WORK 0 0 0 0
31- Dec-18 NO WORK 0 0 0 0

01- Jan-19 0 0 0 0
02- Jan-19 0 0 0 0
03- Jan-19 no work 0 0 0 0
04- Jan-19 0 0 0 0
05- Jan-19 0 0 0 0
06- Jan-19 fabrication work of cutting edge 0 0 2 12
07- Jan-19 fabrication work of cutting edge 0 0 2 12
08- Jan-19 fabrication work of cutting edge 0 0 2 12
09- Jan-19 fabrication work of cutting edge 0 0 4 12
10- Jan-19 fabrication work of cutting edge 0 0 4 12
11- Jan-19 fabrication work of cutting edge 0 0 4 12
12- Jan-19 fabrication work of cutting edge 0 0 4 12
13- Jan-19 fabrication work of cutting edge 0 0 4 12
14- Jan-19 fabrication work of cutting edge 0 0 8 12
15- Jan-19 fabrication work of cutting edge 0 0 8 12
16- Jan-19 fabrication work of cutting edge 0 0 10 12
17- Jan-19 fabrication work of cutting edge 0 0 10 12
18- Jan-19 fabrication work of cutting edge 0 0 10 12
19- Jan-19 fabrication work of cutting edge 0 0 10 12
20- Jan-19 fabrication work of cutting edge 0 0 10 12
21- Jan-19 fabrication work of cutting edge 0 0 10 12
22- Jan-19 Fabrication of cutting edge 0 0 10 12
23- Jan-19 Fabrication of cutting edge 0 0 10 12
24- Jan-19 Fabrication of cutting edge 0 0 10 12
25- Jan-19 Fabrication of cutting edge 0 0 10 12
26- Jan-19 no work 0 0 0 0
27- Jan-19 bending of cutting and welding 0 0 10 12
28- Jan-19 bending of cutting and welding 0 0 10 12
29- Jan-19 bending of cutting and welding 0 0 10 12
30- Jan-19 Gusset plate layout marking 0 0 8 12
31- Jan-19 fabrication of bracket for casssion 0 0 20 12
01- Feb-19 fabrication of bracket for casssion 0 0 20 12
02- Feb-19 fabrication of bracket for casssion 0 0 20 12
03- Feb-19 fabrication of bracket for casssion 0 0 20 12
04- Feb-19 fabrication of bracket for casssion 0 0 20 12
05- Feb-19 fabrication of bracket for casssion 0 0 20 12
06- Feb-19 fabrication of bracket for casssion 0 0 20 12
07- Feb-19 fabrication of bracket for casssion 0 0 20 12
08- Feb-19 fabrication of bracket for casssion 0 0 20 12
09- Feb-19 fabrication of bracket for casssion 0 0 20 12
10- Feb-19 no work 0 0 0 0
11- Feb-19 fabrication of bracket for casssion & cutting edge fixing 0 0 20 12
12- Feb-19 fabrication of bracket for casssion & cutting edge fixing 0 0 15 12
13- Feb-19 bracket fixing work in progress 0 0 15 12
14- Feb-19 bracket fixing work in progress 0 0 15 12
15- Feb-19 bracket fixing work in progress 0 0 26 12
16- Feb-19 bracket fixing work in progress 0 0 15 12
17- Feb-19 outer ring fitting work in progress 0 0 15 6
18- Feb-19 outer ring fitting work in progress 0 0 26 12
19- Feb-19 outer ring fitting work in progress 0 0 26 12
20- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
21- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
22- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
23- Feb-19 Outer skin plate fixing work in progress
no sinking during this days 0 0 25 12
24- Feb-19 Outer skin plate fixing work in progress 0 0 26 12
25- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
26- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
27- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
28- Feb-19 Outer skin plate fixing work in progress 0 0 25 12
01- Mar-19 inner skin plate fixing work 0 0 22 12
02- Mar-19 inner skin plate fixing work 0 0 23 12
03- Mar-19 No work 0 0 0 0
04- Mar-19 inner skin plate fixing work 0 0 20 12
05- Mar-19 inner skin plate fixing work 0 0 20 12
06- Mar-19 inner skin plate fixing work 0 0 20 12
07- Mar-19 inner skin plate fixing work 0 0 22 12
08- Mar-19 inner skin plate fixing work 0 0 22 12
09- Mar-19 inner skin plate fixing work 0 0 22 12
10- Mar-19 inner skin plate fixing work 0 0 12 12
11- Mar-19 inner skin plate fixing work 0 0 12 12
12- Mar-19 inner skin plate fixing work 0 0 12 12
13- Mar-19 inner skin plate fixing work 0 0 12 12
14- Mar-19 inner skin plate fixing work 0 0 12 12
15- Mar-19 inner skin plate fixing of molude 0 0 18 12
16- Mar-19 inner skin plate fixing of molude 0 0 18 12
17- Mar-19 inner skin plate fixing of molude 0 0 10 12
18- Mar-19 inner skin plate fixing of molude 0 0 18 12
19- Mar-19 inner skin plate fixing of molude 0 0 18 12
20- Mar-19 module fabrication work 0 0 20 12
21- Mar-19 no work due to holi 0 0 0 0
22- Mar-19 welding of cassion 0 0 16 12
23- Mar-19 welding of cassion 0 0 16 12
24- Mar-19 No work 0 0 0 0
25- Mar-19 welding of cassion 0 0 10 12
26- Mar-19 welding of cassion 0 0 16 12
27- Mar-19 cassion surraounding soil excavation work 12 0 5 12
28- Mar-19 cassion surraounding soil excavation work 12 0 4 12
29- Mar-19 cassion surraounding soil excavation work 12 0 5 12
30- Mar-19 cassion surraounding soil excavation work 12 0 5 12
31- Mar-19 cassion surraounding soil excavation work 12 0 5 12
01- Apr-19 FLOATING OF CASSION DONE 0 0 10 12
02- Apr-19 reinforcement fixing work in cassion 0 0 8 12
03- Apr-19 reinforcement fixing work in cassion 0 0 28 12
04- Apr-19 reinforcement fixing work in cassion 0 0 8 12
05- Apr-19 reinforcement fixing work in cassion 0 0 8 12
06- Apr-19 reinforcement fixing work in cassion 0 0 8 12
07- Apr-19 no work 0 0 0
08- Apr-19 reinforcement fixing work in cassion 0 0 8 12
09- Apr-19 reinforcement fixing work in cassion 0 0 8 12
10- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 27 12
11- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 32 12
12- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 39 12
13- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 45 12
14- Apr-19 no work 0 0 0 0
15- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 42 12
16- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 39 12
17- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 35 12
18- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 24 12
19- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 25 12
20- Apr-19 reinforcement fixing work in progress & module fabrication 0 0 27 12
21- Apr-19 no work 0 0 0 0
22- Apr-19 reinforcement fixing work in progress 0 0 26 12
23- Apr-19 reinforcement fixing work in progress 0 0 26 12
24- Apr-19 reinforcement fixing work in progress 0 0 10 12
25- Apr-19 Frame fixing with cassion 0 0 26 12

01- Jun-19 no work 0 0 0 0


02- Jun-19 no work 0 0 0 0
03- Jun-19 no work 0 0 0 0
04- Jun-19 no work 0 0 0 0
05- Jun-19 no work 0 0 0 0
06- Jun-19 no work 0 0 0 0
07- Jun-19 no work 0 0 0 0
08- Jun-19 no work 0 0 0 0
09- Jun-19 no work 0 0 0 0
10- Jun-19 no work 0 0 0 0
11- Jun-19 no work 0 0 0 0
12- Jun-19 no work 0 0 0 0
13- Jun-19 no work 0 0 0 0
14- Jun-19 no work 0 0 0 0
15- Jun-19 no work 0 0 0 0
16- Jun-19 no work 0 0 0 0
17- Jun-19 no work 0 0 0 0
18- Jun-19 no work 0 0 0 0
19- Jun-19 no work 0 0 0 0
20- Jun-19 no work 0 0 0 0
21- Jun-19 no work 0 0 0 0
22- Jun-19 no work 0 0 0 0
23- Jun-19 no work 0 0 0 0
24- Jun-19 no work 0 0 0 0
25- Jun-19 no work 0 0 0 0
26- Jun-19 no work 0 0 0 0
27- Jun-19 no work 0 0 0 0
28- Jun-19 Shifting of cassion toward A1 side 0 0 10 12
29- Jun-19 Shifting of cassion toward A1 side 0 0 10 12
30- Jun-19 no work 0 0 0 0
01- Jul-19 no work 0 0 0 0
02- Jul-19 no work 0 0 0 0
03- Jul-19 no work 0 0 0 0
04- Jul-19 no work 0 0 0 0
05- Jul-19 no work 0 0 0 0
06- Jul-19 no work 0 0 0 0
07- Jul-19 no work 0 0 0 0
08- Jul-19 no work 0 0 0 0
09- Jul-19 no work 0 0 0 0
10- Jul-19 no work 0 0 0 0
11- Jul-19 no work 0 0 0 0
12- Jul-19 no work 0 0 0 0
13- Jul-19 no work 0 0 0 0
14- Jul-19 no work 0 0 0 0
15- Jul-19 no work 0 0 0 0
16- Jul-19 no work 0 0 0 0
17- Jul-19 no work 0 0 0 0
18- Jul-19 no work 0 0 0 0
19- Jul-19 no work 0 0 0 0
20- Jul-19 no work 0 0 0 0
21- Jul-19 no work 0 0 0 0
22- Jul-19 no work 0 0 0 0
23- Jul-19 no work 0 0 0 0
24- Jul-19 no work 0 0 0 0
25- Jul-19 no work 0 0 0 0
26- Jul-19 no work 0 0 0 0
27- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
28- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
29- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
30- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
31- Jul-19 NO WROK DUE WATER LEVEL RISES 0 0 0 0
01- Aug-19
02- Aug-19
03- Aug-19
04- Aug-19
05- Aug-19
summary of sinking and construction at P05
Machine & Man Power
RL OF BOTTOM
OF CUTTING SINKING CUMMULATIVE CRANE 1 CRANE 2 LABOUR
DATE work details FFL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
21- Nov-18 cutting edge fabrication work 118.987 0 0 8 12
22- Nov-18 cutting edge fabrication work 118.987 0 0 8 12
23- Nov-18 cutting edge fabrication work 118.987 0 0 8 12
24- Nov-18 cutting edge fabrication work 118.987 0 0 8 12
25- Nov-18 cutting edge fabrication work 118.987 0 0 8 12
26- Nov-18 cutting edge fabrication work 118.987 0 0 8 12
27- Nov-18 cutting edge fabrication work 118.987 0 0 6 12
28- Nov-18 bracket making and island filling 118.987 0 0 10 12
29- Nov-18 bracket making and island filling 118.987 0 0 10 12
30- Nov-18 bracket making and island filling 118.987 0 0 10 12
01- Dec-18 bracket making and island filling 118.987 0 0 6 12
02- Dec-18 bracket making and island filling 118.987 0 0 6 12
03- Dec-18 bracket making and island filling 118.987 0 0 6 12
04- Dec-18 fabrication of cutting edge 118.987 0 0 7 12
05- Dec-18 fabrication of cutting edge 118.987 0 0 6 12
06- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
07- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
08- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
09- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
10- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
11- Dec-18 fabrication of cutting edge 118.987 sinking not done this days 0 0 5 12
12- Dec-18 fabrication of cutting edge 118.987 0 0 6 12
13- Dec-18 fabrication of cutting edge 118.987 0 0 6 12
14- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
15- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
16- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
17- Dec-18 fabrication of cutting edge 118.987 0 0 5 12
18- Dec-18 cutting edge shifted to site 118.987 0 0 5 12
19- Dec-18 drilling of hole in cutting edge 118.987 0 0 5 12
20- Dec-18 drilling of hole in cutting edge 118.987 0 0 5 12
21- Dec-18 drilling of hole in cutting edge 118.987 0 0 5 12
22- Dec-18 drilling of hole in cutting edge 118.987 0 0 5 12
23- Dec-18 drilling of hole in cutting edge 118.987 0 0 5 12
24- Dec-18 drilling of hole in cutting edge 118.987 0 0 5 12
25- Dec-18 bent plate rectification 118.987 0 0 5 12
26- Dec-18 bent plate rectification 118.987 0 0 5 12
27- Dec-18 bent plate rectification 118.987 0 0 5 12
28- Dec-18 bent plate rectification 118.987 0 0 5 12
29- Dec-18 no work 118.987 0 0 0 0
30- Dec-18 no work 118.987 0 0 0 0
31- Dec-18 no work 118.987 0 0 0 0
118.987
01- Jan-19 no work 118.987 0 0 0 0
02- Jan-19 no work 118.987 0 0 0 0
03- Jan-19 Island making 118.987 0 0 0 12
04- Jan-19 Island making 118.987 0 0 0 12
05- Jan-19 Island making 118.987 0 0 0 12
06- Jan-19 Island making 118.987 0 0 0 12
07- Jan-19 Island making 118.987 0 0 0 12
08- Jan-19 Island making 118.987 0 0 0 12
09- Jan-19 Island making 118.987 0 0 0 12
10- Jan-19 Island making 118.987 0 0 0 12
11- Jan-19 Island making 118.987 0 0 0 12
12- Jan-19 Island making 118.987 0 0 0 12
13- Jan-19 Island making 118.987 0 0 0 12
14- Jan-19 Island making 118.987 0 0 0 12
15- Jan-19 island making & cutting edge placement 118.987 0 0 6 12
16- Jan-19 island making & cutting edge placement 118.987 0 0 6 12
17- Jan-19 bracket fixing in progress 118.987 0 0 15 12
18- Jan-19 bracket fixing in progress 118.987 0 0 15 12
19- Jan-19 bracket fixing in progress 118.987 0 0 15 12
20- Jan-19 no work 118.987 0 0 0 12
21- Jan-19 outer skin plate fixing in progress 118.987 0 0 15 12
22- Jan-19 Plate cutting in process 118.987 0 0 15 12
23- Jan-19 Plate cutting in process 118.987 0 0 15 12
24- Jan-19 inner skin plate fixing in progress 118.987 0 0 10 12
25- Jan-19 inner skin plate fixing in progress 118.987 0 0 18 12
26- Jan-19 no work 118.987 0 0 0 0
27- Jan-19 inner plate fixing and welding 118.987 0 0 17 12
28- Jan-19 inner plate fixing and welding 118.987 0 0 17 12
29- Jan-19 inner plate fixing and welding 118.987 0 0 17 12
30- Jan-19 outer and inner skin plate fixing and welding 118.987 0 0 18 12
31- Jan-19 inner plate fixing and welding 118.987 0 0 10 12
01- Feb-19 inner plate fixing and welding 118.987 0 0 10 12
02- Feb-19 inner plate fixing and welding 118.987 0 0 11 12
03- Feb-19 inner plate fixing and welding 118.987 0 0 5 12
04- Feb-19 inner plate fixing and welding 118.987 0 0 5 12
05- Feb-19 inner plate fixing and welding 118.987 0 0 5 12
06- Feb-19 inner plate fixing and welding 118.987 0 0 6 12
07- Feb-19 inner plate fixing and welding 118.987 0 0 5 12
08- Feb-19 inner plate fixing and welding 118.987 sinking not done these 0 0 5 12
09- Feb-19
10- Feb-19
inner plate fixing and welding
no work
118.987
118.987
days 0
0
0
0
5
0
12
0
11- Feb-19 inner plate fixing and welding 118.987 0 0 8 12
12- Feb-19 inner plate fixing and welding 118.987 0 0 15 12
13- Feb-19 inner plate fixing and welding 118.987 0 0 15 12
14- Feb-19 inner plate fixing and welding 118.987 0 0 15 12
15- Feb-19 inner plate fixing and welding 118.987 0 0 18 12
16- Feb-19 inner plate fixing and welding 118.987 0 0 18 12
17- Feb-19 inner plate fixing and welding 118.987 0 0 18 12
18- Feb-19 inner plate fixing and welding 118.987 0 0 18 12
19- Feb-19 inner plate fixing and welding 118.987 0 0 18 12
20- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
21- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
22- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
23- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
24- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 10 12
25- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
26- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
27- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
28- Feb-19 Outer skin plate fixing work in progress 118.987 0 0 18 12
01- Mar-19 Outer skin plate fixing work in progress 118.987 0 0 10 12
02- Mar-19 Outer skin plate fixing work in progress 118.987 0 0 7 12
03- Mar-19 No work 118.987 0 0 0 0
04- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 15 12
05- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 12 12
06- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 20 12
07- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 20 12
08- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 20 12
09- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 20 12
10- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 15 12
11- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 15 12
12- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 15 12
13- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 15 12
14- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 20 12
15- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 18 12
16- Mar-19 Reinforcemnt & fabrication work well curb 118.987 0 0 18 12
17- Mar-19 casting in progress at well curb 118.987 0 0 25 12
18- Mar-19 casting complted at 6am 118.987 0 0 25 12
19- Mar-19 sinking preparation 118.987 0 0 10 12
20- Mar-19 Sinking in progress 118.987 118.449 0.538 0.538 sand 12 12 4 12
21- Mar-19 no work due to holi 118.987 0 0 0 0
22- Mar-19 no work due to holi 118.987 0 0 0 0
23- Mar-19 Sinking in progress 118.987 117.137 1.312 1.85 12 12 4 12
24- Mar-19 Sinking in progress 118.987 116.278 0.859 2.709 sand 12 12 4 12
25- Mar-19 shuttering and reinforecment work at S1 118.987 0 0 14 12

sinking not done these days


26- Mar-19 shuttering and reinforecment work at S1 118.987 0 0 15 12
27- Mar-19 shuttering and reinforecment work at S1 118.987 0 0 14 12
28- Mar-19 shuttering and reinforecment work at S1 118.987 0 0 14 12
29- Mar-19 shuttering and reinforecment work at S1 118.987 0 0 14 12
30- Mar-19 shuttering and reinforecment work at S1 118.987 0 0 14 12
31- Mar-19 casting in progress at S1 118.987
sinking not done these days 0 0 25 12
01- Apr-19 deshuttering work 118.987 0 0 1 12
02- Apr-19 deshuttering work 118.987 0 0 1 12
03- Apr-19 Sinking in progress 118.987 0 0 1 12
04- Apr-19 deshuttering work 118.987 0 0 5 12
05- Apr-19 deshuttering work 118.987 0 0 5 12
06- Apr-19 Sinking in progress 118.987 114.828 1.45 4.159 12 12 3 12
07- Apr-19 no work 118.987 114.828 0 4.159 0 0 0 0
08- Apr-19 Sinking in progress 118.987 114.148 0.68 4.839 sand 12 12 3 12
09- Apr-19 Sinking in progress 118.987 113.316 0.832 5.671 12 12 3 12
10- Apr-19 Sinking in progress 118.987 112.868 0.448 6.119 12 12 4 12
11- Apr-19 no work 118.987 0 0 0 0
12- Apr-19 no work 118.987 0 0 0 0
13- Apr-19 curing work 118.987 0 0 1 10
14- Apr-19 no work 118.987 0 0 0 0
15- Apr-19 curing work 118.987 0 0 1 10
16- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 12 12
17- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 14 12
18- Apr-19 shuttering and reinforcement work at S2 118.987 sinking not done these days 0 0 20 12
19- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 14 12
20- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 13 12
21- Apr-19 no work 118.987 0 0 0 0
22- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 12 12
23- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 12 12
24- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 20 12
25- Apr-19 shuttering and reinforcement work at S2 118.987 0 0 12 12

01- Jun-19 no work 118.987 0 0 0 0


02- Jun-19 no work 118.987 0 0 0 0
03- Jun-19 Casting at S2 well steining 118.987 0 0 25 12
04- Jun-19 Casting at S2 well steining 118.987 sinking not done these days 0 0 25 10
05- Jun-19 Deshuttering work 118.987 0 0 10 12
06- Jun-19 Deshuttering work 118.987 0 0 10 12
07- Jun-19 Deshuttering work 118.987 0 0 7 10
08- Jun-19 sinking in progress 118.987 112.103 0.765 6.884 12 12 2 12
09- Jun-19 sinking in progress 118.987 111.443 0.66 7.544 sand and 12 12 2 12
10- Jun-19 sinking in progress 118.987 110.757 0.686 8.23 boulder 12 12 2 12
11- Jun-19 sinking in progress 118.987 110.522 0.235 8.465 12 12 2 12
12- Jun-19 no work 118.987 0 0 0 0
13- Jun-19 no work 118.987 0 0 0 0
14- Jun-19 no work 118.987 0 0 0 0
15- Jun-19 no work 118.987 0 0 0 0
16- Jun-19 no work 118.987 0 0 0 0
17- Jun-19 no work 118.987 0 0 0 0
18- Jun-19 no work 118.987 0 0 0 0
19- Jun-19 no work 118.987 0 0 0 0
20- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 15 12
21- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 15 12
22- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 15 12
23- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 15 12
24- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 18 12
25- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 15 12
26- Jun-19 shuttering and reinforcement work at S3 118.987 0 0 14 12
27- Jun-19 casting at S3 well steining 118.987 0 0 25 12
28- Jun-19 casting at S3 well steining 118.987 0 0 25 10
29- Jun-19 Deshuttering work 118.987 0 0 6 12
30- Jun-19 Deshuttering work 118.987 0 0 15 12
01- Jul-19 sinking started 118.987 110.373 0.149 8.614 2 2 3 12
02- Jul-19 sinking in progress 118.987 110.237 0.136 8.75 12 12 3 12

Clay
03- Jul-19 sinking in progress 118.987 110.037 0.2 8.95 12 12 3 12
Clay
04- Jul-19 sinking in progress 118.987 109.924 0.113 9.063 12 12 3 12
05- Jul-19 sinking in progress 118.987 109.873 0.051 9.114 12 12 3 12
06- Jul-19 sinking in progress 118.987 109.847 0.026 9.14 12 12 3 12
07- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
08- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
09- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
10- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
11- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
12- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
13- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
14- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
15- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
16- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
17- Jul-19 sinking in progress 118.987 109.836 0.011 9.151 12 12 3 12
18- Jul-19 sinking in progress 118.987 109.836 0.000 9.151 12 12 3 12
19- Jul-19 sinking in progress 118.987 109.507 0.329 9.48 12 12 3 12
20- Jul-19 sinking in progress 118.987 109.447 0.060 9.54 12 12 3 12
21- Jul-19 no work 118.987 109.411 0.036 9.576 6 6 3 6
Clay
22- Jul-19 sinking in progress 118.987 109.301 0.110 9.686 12 12 3 12
23- Jul-19 sinking in progress 118.987 109.271 0.030 9.716 12 12 3 12
24- Jul-19 sinking in progress 118.987 109.135 0.136 9.852 12 12 3 12
25- Jul-19 sinking in progress 118.987 108.951 0.184 10.036 12 12 3 12
26- Jul-19 sinking in progress 118.987 108.755 0.196 10.232 12 12 2 12
27- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
28- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
29- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
30- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
31- Jul-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
01- Aug-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
02- Aug-19 NO WROK DUE WATER LEVEL RISES 118.987 0 0 0 0
03- Aug-19
04- Aug-19
05- Aug-19
06- Aug-19
07- Aug-19
08- Aug-19
summary of sinking and construction at P06
Machine & Man Power
RL OF BOTTOM CRANE 1 CRANE 2 LABOUR
OF CUTTING SINKING CUMMULATIVE
DATE work details FFL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs

27- Oct-18 bracket making of size 75*75*8 118.95 0 0 10 12


28- Oct-18 bracket making of size 75*75*8 118.95 0 0 10 12
29- Oct-18 bracket making of size 75*75*8 118.95 0 0 10 12
30- Oct-18 cutting edge fabrication work 118.95 0 0 10 10
31- Oct-18 cutting edge fabrication work 118.95 0 0 10 10
01- Nov-18 cutting edge fabrication work 118.95 0 0 10 10
02- Nov-18 cutting edge fabrication work 118.95 0 0 10 10
03- Nov-18 cutting edge fabrication work 118.95 0 0 10 10
04- Nov-18 cutting edge fabrication work 118.95 0 0 10 10
05- Nov-18 cutting edge fabrication work 118.95 0 0 7 10
06- Nov-18 cutting edge fabrication work 118.95 0 0 7 10
07- Nov-18 diwali holiday 118.95 0 0 0 0
08- Nov-18 cutting edge fabrication work 118.95 0 0 3 12
09- Nov-18 cutting edge fabrication work 118.95 0 0 2 12
10- Nov-18 no work 118.95 0 0 0 12
11- Nov-18 no work 118.95 0 0 0 12
12- Nov-18 no work 118.95 0 0 0 12
13- Nov-18 no work 118.95 NO SINKING WORK 0 0 0 12
14- Nov-18 cutting edge fabrication work 118.95 0 0 5 12
15- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
16- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
17- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
18- Nov-18 no work 118.95 0 0 0 12
19- Nov-18 cutting edge fabrication work 118.95 0 0 5 12
20- Nov-18 cutting edge fabrication work 118.95 0 0 5 12
21- Nov-18 cutting edge fabrication work 118.95 0 0 8 12
22- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
23- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
24- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
25- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
26- Nov-18 cutting edge fabrication work 118.95 0 0 10 12
27- Nov-18 cutting edge assemble work 118.95 0 0 10 12
28- Nov-18 cutting edge welding work 118.95 0 0 10 12
29- Nov-18 cutting edge welding work 118.95 0 0 10 12
30- Nov-18 cutting edge welding work 118.95 0 0 10 12
118.95
01- Dec-18 hole drilling and welding 118.95 0 0 15 12
02- Dec-18 hole drilling and welding 118.95 0 0 15 12
03- Dec-18 hole drilling and welding 118.95 0 0 15 12
04- Dec-18 hole drilling and welding 118.95 0 0 9 12
05- Dec-18 bracket fixing work 118.95 0 0 11 12
06- Dec-18 bracket fixing work 118.95 0 0 12 12
07- Dec-18 bracket fixing work 118.95 0 0 12 12
08- Dec-18 bracket fixing work 118.95 0 0 11 12
09- Dec-18 bracket fixing work 118.95 0 0 11 12
10- Dec-18 bracket fixing work 118.95 0 0 11 12
11- Dec-18 bracket fixing work 118.95 0 0 11 12
12- Dec-18 bracket fixing work 118.95 0 0 10 12
13- Dec-18 bracket welding work 118.95 0 0 11 12
14- Dec-18 outer skin plate fixing 118.95 0 0 11 12
15- Dec-18 outer skin plate fixing 118.95 0 0 11 12
16- Dec-18 outer skin plate fixing 118.95 NO SINKING WORK 0 0 11 12
17- Dec-18 outer skin plate fixing 118.95 0 0 11 12
18- Dec-18 inner plate cutting 118.95 0 0 11 12
19- Dec-18 inner plate fitting and welding 118.95 0 0 11 12
20- Dec-18 inner plate fitting and welding 118.95 0 0 11 12
21- Dec-18 inner plate fitting and welding 118.95 0 0 11 12
22- Dec-18 inner plate fitting and welding 118.95 0 0 11 12
23- Dec-18 inner plate fitting and welding 118.95 0 0 11 12
24- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
25- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
26- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
27- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
28- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
29- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
30- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
31- Dec-18 inner plate fitting and welding 118.95 0 0 12 12
118.95
01- Jan-19 no work 118.95 0 0 0 0
02- Jan-19 inner skin plate welding work 118.95 0 0 18 12
03- Jan-19 inner skin plate welding work 118.95 0 0 16 12
04- Jan-19 inner skin plate welding work 118.95 0 0 16 12
05- Jan-19 inner skin plate welding work 118.95 0 0 16 12
06- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
07- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
08- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
09- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
10- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
11- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
12- Jan-19 outer skin plate fixing and welding 118.95 0 0 15 12
13- Jan-19 no work 118.95 0 0 0 0
14- Jan-19 outer skin plate fixing and welding 118.95 0 0 18 12
15- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
16- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
17- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
18- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
19- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
20- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
21- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
22- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 30 12
23- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 18 12
24- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 26 12
25- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 14 12
26- Jan-19 no work 118.95 0 0 0 0
27- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 15 12
28- Jan-19 skin plate welding & reinforcement work WELL CURB 118.95 0 0 18 12
29- Jan-19 casting in progress at well curb 118.95 0 0 25 12
30- Jan-19 curing work 118.95 0 0 1 12
31- Jan-19 curing work & wooden block removing 118.95 0 0 5 12
01- Feb-19 sinking in progress 118.95 118.349 0.601 0.601 12 12 4 12
02- Feb-19 sinking in progress 118.95 115.998 2.351 2.952 12 12 4 12
Sand
03- Feb-19 no work 118.95 115.998 0 2.952 0 0 0 0
04- Feb-19 sinking in progress 118.95 115.257 0.741 3.693 12 12 4 12
05- Feb-19 118.95 0 0 0 0
06- Feb-19 no work 118.95 0 0 0 0
07- Feb-19 shuttering and reinforcement at S1 118.95 0 0 18 12
08- Feb-19 shuttering and reinforcement at S1 118.95 0 0 10 12
09- Feb-19 shuttering and reinforcement at S1 118.95 0 0 18 12
10- Feb-19 shuttering and reinforcement at S1 118.95 0 0 10 12
11- Feb-19 shuttering and reinforcement at S1 118.95 0 0 18 12
12- Feb-19 shuttering and reinforcement at S1 118.95 0 0 18 12
13- Feb-19 shuttering and reinforcement at S1 118.95 0 0 18 12
14- Feb-19 casting in progress at S1 118.95 0 0 25 12
15- Feb-19 curing work 118.95 0 0 1 12
16- Feb-19 Deshuttering work 118.95 0 0 15 12
17- Feb-19 curing work 118.95 0 0 1 12
18- Feb-19 sinking in progress 118.95 114.353 0.904 4.597 12 12 4 12
19- Feb-19 sinking in progress 118.95 112.763 1.59 6.187 Sand 12 12 4 12
20- Feb-19 No work 118.95 0 0 0 0
21- Feb-19 No work 118.95 0 0 0 0
22- Feb-19 Shuttering and reinforcement work at S2 118.95 0 0 25 12
23- Feb-19 Shuttering and reinforcement work at S2 118.95 0 0 25 12
24- Feb-19 Shuttering and reinforcement work at S2 118.95 0 0 13 12
25- Feb-19 Shuttering and reinforcement work at S2 118.95 0 0 25 12
26- Feb-19 Shuttering and reinforcement work at S2 118.95 no sinking 0 0 25 12
27- Feb-19 casting in progress at S2 118.95 0 0 25 18
28- Feb-19 curing work 118.95 0 0 1 12
01- Mar-19 curing work & deshuttering work 118.95 0 0 5 12
02- Mar-19 deshuttering work 118.95 0 0 7 12
03- Mar-19 No work 118.95 0 0 0 0
04- Mar-19 deshuttering work 118.95 0 0 12 12
05- Mar-19 SINKING IN PROGRESS 118.95 111.732 1.031 7.218 Sand 12 12 4 12
06- Mar-19 SINKING IN PROGRESS 118.95 111.517 0.215 7.433 12 12 4 12
07- Mar-19 SINKING IN PROGRESS 118.95 111.438 0.079 7.512 12 12 4 12
08- Mar-19 SINKING IN PROGRESS 118.95 111.202 0.236 7.748 12 12 1 12
09- Mar-19 SINKING IN PROGRESS 118.95 110.824 0.378 8.126 12 12 2 12
10- Mar-19 No work 118.95 110.824 0 8.126 0 0 0 0
11- Mar-19 sinking in progress 118.95 110.392 0.432 8.558 12 12 4 12
12- Mar-19 sinking in progress 118.95 110.23 0.162 8.72 clay 12 12 4 12
13- Mar-19 118.95 0 0 0 0
14- Mar-19 No work due to gang not avalable 118.95 0 0 0 0
15- Mar-19 shuttering and reinforcement of S3 118.95 0 0 20 12
16- Mar-19 shuttering and reinforcement of S3 118.95 0 0 20 12
17- Mar-19 shuttering and reinforcement of S3 118.95 0 0 10 12
18- Mar-19 shuttering and reinforcement of S3 118.95 0 0 14 12

no sinking
19- Mar-19 shuttering and reinforcement of S3 118.95 0 0 14 12
20- Mar-19 shuttering and reinforcement of S3 118.95 0 0 14 12
21- Mar-19 no work due to holi 118.95 0 0 0 0
22- Mar-19 shuttering and reinforcement of S3 118.95 0 0 14 12
23- Mar-19 118.95 no sinking 0 0 0 0
24- Mar-19 No work casting delay due to admixtures 118.95 0 0 0 0
25- Mar-19 casting in progress at S3 118.95 0 0 25 12
26- Mar-19 casting in progress at S3 TILL 1PM 118.95 0 0 25 12
27- Mar-19 curing work 118.95 0 0 0 12
28- Mar-19 deshuttering work 118.95 0 0 10 12
29- Mar-19 no work 118.95 0 0 0 0
30- Mar-19 no work 118.95 0 0 0 0
31- Mar-19 deshuttering work 118.95 0 0 5 12
01- Apr-19 deshuttering work 118.95 0 0 10 12
02- Apr-19 deshuttering work 118.95 0 0 12 12
03- Apr-19 Sinking in progress 118.95 109.795 0.435 9.155 12 12 4 12
04- Apr-19 Sinking in progress 118.95 109.671 0.124 9.279 12 12 4 12
05- Apr-19 Sinking in progress 118.95 109.538 0.133 9.412 12 12 4 12
06- Apr-19 Sinking in progress 118.95 109.397 0.141 9.553 12 12 4 12
07- Apr-19 no work 118.95 109.397 0 9.553 0 0 0 0
08- Apr-19 Sinking in progress 118.95 109.132 0.265 9.818 12 12 4 12
09- Apr-19 Sinking in progress 118.95 108.977 0.155 9.973 12 12 4 12
10- Apr-19 Sinking in progress 118.95 108.822 0.155 10.128 12 12 4 12
clay
11- Apr-19 Sinking in progress 118.95 108.672 0.15 10.278 12 12 4 12
12- Apr-19 Sinking in progress 118.95 108.476 0.196 10.474 12 12 4 12
13- Apr-19 Sinking in progress 118.95 108.363 0.113 10.587 12 12 4 12
14- Apr-19 no work 118.95 108.363 0 10.587 0 0 0 0
15- Apr-19 Sinking in progress 118.95 107.814 0.549 11.136 12 12 4 12
16- Apr-19 Sinking in progress 118.95 107.592 0.222 11.358 12 12 4 12
17- Apr-19 Sinking in progress 118.95 107.484 0.108 11.466 12 12 2 12
18- Apr-19 Sinking in progress 118.95 107.308 0.176 11.642 12 12 2 12
19- Apr-19 no work 118.95 0 0 0 0
20- Apr-19 no work 118.95 0 0 0 0
21- Apr-19 no work 118.95 0 0 0 0
22- Apr-19 no work 118.95 no sinking 0 0 0 0
23- Apr-19 no work 118.95 0 0 0 0
24- Apr-19 no work 118.95 0 0 0 0
25- Apr-19 SHUTTERING WORK AT S4 118.95 0 0 18 0

01- Jun-19 no work 118.95 0 0 0 0


02- Jun-19 no work 118.95 0 0 0 0
03- Jun-19 no work 118.95 0 0 0 0
04- Jun-19 no work 118.95 0 0 0 0
05- Jun-19 no work 118.95 0 0 0 0
06- Jun-19 no work 118.95 0 0 0 0
07- Jun-19 no work 118.95 0 0 0 0
08- Jun-19 no work 118.95 0 0 0 0
09- Jun-19 no work 118.95 0 0 0 0
10- Jun-19 no work 118.95 0 0 0 0
11- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
12- Jun-19 Shuttering and reinforcement work at S4 118.95 no sinking 0 0 15 12
13- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
14- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
15- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
16- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
17- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
18- Jun-19 Shuttering and reinforcement work at S4 118.95 0 0 15 12
19- Jun-19 no work 118.95 0 0 0 0
20- Jun-19 Casting in progress at S4 118.95 0 0 25 12
21- Jun-19 Casting in progress at S4 118.95 0 0 24 5
22- Jun-19 Deshuttering work in progress 118.95 0 0 10 12
23- Jun-19 Deshuttering work in progress 118.95 0 0 10 12
24- Jun-19 Sinking in progress 118.95 106.821 0.487 12.129 10 10 3 10
25- Jun-19 Sinking in progress 118.95 106.583 0.238 12.367 12 12 3 12
26- Jun-19 Sinking in progress 118.95 106.387 0.196 12.563 12 12 3 12
27- Jun-19 Sinking in progress 118.95 106.247 0.14 12.703 12 12 3 12
28- Jun-19 Sinking in progress 118.95 106.147 0.1 12.803 12 12 3 12
29- Jun-19 Sinking in progress 118.95 105.952 0.195 12.998 clay 12 12 3 12
30- Jun-19 no work 118.95 105.952 0 12.998 0 0 0 0
01- Jul-19 Sinking in progress 118.95 105.666 0.286 13.284 12 12 3 12
02- Jul-19 Sinking in progress 118.95 105.483 0.183 13.467 12 12 3 12
03- Jul-19 Sinking in progress 118.95 105.156 0.327 13.794 12 12 3 12
04- Jul-19 Sinking in progress 118.95 104.948 0.208 14.002 12 12 3 12
05- Jul-19 Sinking in progress 118.95 104.757 0.191 14.193 6 6 3 6
06- Jul-19 Sinking in progress 118.95 104.71 0.047 14.24 12 12 3 12
07- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
08- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
09- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
10- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
11- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
12- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
13- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
14- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
15- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
16- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
17- Jul-19 Cleaning of steinig 118.95 0 0 1 12
18- Jul-19 Shuttering and reinforcement work at S5 118.95 0 0 7 12
19- Jul-19 Shuttering and reinforcement work at S5 118.95
no sinking 0 0 7 12
20- Jul-19 Shuttering and reinforcement work at S5 118.95 0 0 12 12
21- Jul-19 no work 118.95 0 0 0 0
22- Jul-19 Shuttering and reinforcement work at S5 118.95 0 0 12 12
23- Jul-19 Shuttering and reinforcement work at S5 118.95 0 0 12 12
24- Jul-19 Shuttering and reinforcement work at S5 118.95 0 0 12 12
25- Jul-19 Casting at S5 well steining 118.95 0 0 25 12
26- Jul-19 Casting at S5 well steining 118.95 0 0 25 12
27- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
28- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
29- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
30- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0 0 0 0
31- Jul-19 NO WROK DUE WATER LEVEL RISES 118.95 0
01- Aug-19 118.95
02- Aug-19 118.95
03- Aug-19 118.95
04- Aug-19 118.95
05- Aug-19 118.95
06- Aug-19 118.95
07- Aug-19 118.95
08- Aug-19 118.95
09- Aug-19 118.95
10- Aug-19 118.95
11- Aug-19 118.95
12- Aug-19 118.95
13- Aug-19 118.95
14- Aug-19 118.95
15- Aug-19 118.95
16- Aug-19 118.95
17- Aug-19 118.95
18- Aug-19 118.95
19- Aug-19 118.95
20- Aug-19 118.95
21- Aug-19 118.95
22- Aug-19 118.95
23- Aug-19 118.95
Summary of sinking and construction at P07
RL OF
Machine & Man Power
FINISHED BOTTOM OF CRANE 1 CRANE 2 LABOUR
FORMATION CUTTING SINKING DURING CUMMULATIVE
DATE Work Details LEVEL EDGE A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
CASTING OF WELL CURB P10 ()
16-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 12 12
17-Sep-2018 no work due to viswakarma puja 120.29 0 0 0 0
18-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 19 12
19-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 17 12
20-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 14 12
21-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 14 12
22-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 14 12
23-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 16 12
24-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 16 12
25-Sep-2018 bracket and cutting edge bending and fabrication work in progress 120.29 0 0 16 12
26-Sep-2018 cutting edge fabrication in progress 120.29 0 0 14 12
27-Sep-2018 cutting edge fabrication in progress 120.29 0 0 14 12
28-Sep-2018 no work 120.29 0 0 0 0
29-Sep-2018 cutting edge fabrication in progress for intermidiate 120.29 0 0 14 12
30-Sep-2018 cutting edge fabrication in progress for intermidiate 120.29 0 0 14 12

1-Oct-2018 cutting edge fabrication in progress for intermidiate 120.29 0 0 14 12


2-Oct-2018 cutting edge fabrication in progress for intermidiate 119.09 0 0 14 12
3-Oct-2018 cutting edge fabrication in progress for intermidiate 120.29 0 0 14 12
4-Oct-2018 cutting edge fabrication in progress for intermidiate 120.29 0 0 10 12
5-Oct-2018 no work since gang is involved in shuttering making for banganga 120.29 0 0 0 0
6-Oct-2018 no work since gang is involved in shuttering making for banganga 120.29 0 0 0 0
7-Oct-2018 no work since gang is involved in shuttering making for banganga 120.29 0 0 0 0
8-Oct-2018 no work since gang is involved in shuttering making for banganga 120.29 0 0 0 0
9-Oct-2018 no work since gang is involved in shuttering making for banganga 120.29 0 0 0 0
10-Oct-2018 no work since gang is involved in shuttering making for banganga 120.29 0 0 0 0
11-Oct-2018 no work since gang is involved in shuttering making 120.29 0 0 0 0
12-Oct-2018 no work since gang is involved in shuttering making 120.29 0 0 0 0
13-Oct-2018 bent plate work in progress 120.29 0 0 10 12
14-Oct-2018 bent plate welding in progress 120.29 0 0 10 12
15-Oct-2018 bent plate welding in progress 120.29 0 0 10 12
16-Oct-2018 bent plate welding in progress 120.29 0 0 10 12
17-Oct-2018 welding of bent plate and shift cutting edge to site 120.29 0 0 10 12
18-Oct-2018 layout making and placing of cutting edge 120.29 0 0 7 12
19-Oct-2018 no work desherra holiday 120.29 0 0 0 0
20-Oct-2018 fixing of cutting edge 120.29 0 0 5 12
21-Oct-2018 fixing of cutting edge and making of hole 120.29 0 0 5 12
22-Oct-2018 fixing of cutting edge and making of hole 120.29 0 0 5 12
23-Oct-2018 fixing of cutting edge and making of hole 120.29 0 0 8 12
24-Oct-2018 fixing of cutting edge and making of hole 120.29 0 0 10 12
25-Oct-2018 welding of stiffner 120.29 0 0 10 12
26-Oct-2018 no work 120.29 0 0 0 0
27-Oct-2018 welding of cutting edge and bent plate 120.29 0 0 14 12
28-Oct-2018 bracket fixing work in progress 120.29 0 0 9 12
29-Oct-2018 bracket fixing work in progress 120.29 0 0 9 12
30-Oct-2018 skin plate cutting work and bracket fixing work 120.29 0 0 9 12
31-Oct-2018 skin plate cutting work and bracket fixing work 120.29 0 0 9 12
1-Nov-2018 skin plate cutting work and bracket fixing work 120.29 0 0 9 12
2-Nov-2018 no work since gang do not work on friday 120.29 0 0 0 0
3-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 7 12
4-Nov-2018 outer skin plate fixing work in progress 120.29 No sinikng during the days 0 0 7 12
5-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 7 12
6-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 9 12
7-Nov-2018 diwali holiday 120.29 0 0 0 0
8-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 9 12
9-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 8 12
10-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 8 12
11-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 8 12
12-Nov-2018 no work 120.29 0 0 0 0
13-Nov-2018 outer skin plate fixing work in progress 120.29 0 0 8 12
14-Nov-2018 inner skin plate bending and welding work 120.29 0 0 7 12
15-Nov-2018 inner skin plate bending and welding work 120.29 0 0 7 12
16-Nov-2018 no work 120.29 0 0 0 0
17-Nov-2018 inner skin plate bending and welding work 120.29 0 0 10 12
18-Nov-2018 inner skin plate bending and welding work 120.29 0 0 10 12
19-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
20-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
21-Nov-2018 inner skin plate bending and welding work 120.29 0 0 10 12
22-Nov-2018 inner skin plate bending and welding work 120.29 0 0 5 12
23-Nov-2018 no work 120.29 0 0 0 0
24-Nov-2018 inner skin plate bending and welding work 120.29 0 0 10 12
25-Nov-2018 inner skin plate bending and welding work 120.29 0 0 10 12
26-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
27-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
28-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
29-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
30-Nov-2018 inner skin plate bending and welding work 120.29 0 0 8 12
1-Dec-2018 inner skin plate bending and welding work 120.29 0 0 12 12
2-Dec-2018 inner skin plate bending and welding work 120.29 0 0 12 12
3-Dec-2018 inner skin plate bending and welding work 120.29 0 0 12 12
4-Dec-2018 inner skin plate bending and welding work 120.29 0 0 12 12
5-Dec-2018 inner skin plate bending and welding work 120.29 0 0 12 12
6-Dec-2018 inner skin plate bending and welding work 120.29 0 0 12 12
7-Dec-2018 inner skin plate bending and welding work 120.29 0 0 15 12
8-Dec-2018 inner skin plate bending and welding work 120.29 0 0 20 12
9-Dec-2018 inner skin plate bending and welding work 120.29 0 0 20 12
10-Dec-2018 inner skin plate bending and welding work 120.29 0 0 10 12
11-Dec-2018 inner and outer skin plate bending and welding work 120.29 0 0 20 12
12-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
13-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
14-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
15-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
16-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
17-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
18-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
19-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
20-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 25 12
21-Dec-2018 reinforcement &inner and outer skin plate bending and welding work 120.29 0 0 35 12
22-Dec-2018 casting work in progress 120.29 0 0 40 12
23-Dec-2018 praparation of snking of well curb 120.29 0 0 4 12
24-Dec-2018 praparation of snking of well curb 120.29 0 0 4 12
25-Dec-2018 sinking in progress 120.29 119.075 1.215 1.215 6 6 4 6
26-Dec-2018 sinking in progress 120.29 117.869 1.206 2.421 10 10 4 10
natural sand
27-Dec-2018 sinking in progress 120.29 117.647 0.222 2.643 10 10 6 10
28-Dec-2018 sinking completed 120.29 116.347 1.3 3.943 10 10 4 10
29-Dec-2018 reinforcement & shuttering work in progress at WS 1st lift 120.29 0 0 12 12
30-Dec-2018 reinforcement & shuttering work in progress at WS 1st lift 120.29 0 0 12 12
31-Dec-2018 reinforcement & shuttering work in progress at WS 1st lift 120.29 0 0 12 12
120.29
1-Jan-2019 no work 120.29 0 0 0 0
2-Jan-2019 shuttering and reinforcement work at S1 WS 120.29 0 0 21 12
3-Jan-2019 shuttering and reinforcement work at S1 WS 120.29 0 0 21 12
4-Jan-2019 shuttering and reinforcement work at S1 WS 120.29 0 0 21 12
5-Jan-2019 shuttering and reinforcement work at S1 WS 120.29 0 0 21 12
NO SINKING DURING THE DAYS
6-Jan-2019 casting in progress at WS S1 120.29 0 0 25 12
7-Jan-2019 casting in progress at WS S1 120.29 0 0 25 12
8-Jan-2019 CURING WORK 120.29 0 0 2 0
9-Jan-2019 Deshuttering work 120.29 0 0 10 10
10-Jan-2019 Deshuttering work 120.29 0 0 10 10
11-Jan-2019 SINKING IN PROGRESS 120.29 116.117 0.23 4.173 0 0 1 0
12-Jan-2019 SINKING IN PROGRESS 119.09 114.451 0.466 4.639 10 10 4 10
natural sand & soil
13-Jan-2019 SINKING IN PROGRESS 120.29 115.651 1.413 6.052 12 12 4 12
14-Jan-2019 SINKING IN PROGRESS 120.29 113.756 0.482 6.534 12 12 4 12
15-Jan-2019 shuttering and reinforcement work at S2 WS 120.29 0 0 20 12
16-Jan-2019 shuttering and reinforcement work at S2 WS 120.29 0 0 20 12
17-Jan-2019 shuttering and reinforcement work at S2 WS 120.29 0 0 31 12
18-Jan-2019 shuttering and reinforcement work at S2 WS 120.29 0 0 25 12
19-Jan-2019 shuttering and reinforcement work at S2 WS 120.29 0 0 15 12
20-Jan-2019 No work 120.29 0 0 0 0
21-Jan-2019 120.29 0 0 0 0
casting delay due to shortage of sand NO SINKING DURING THE DAYS
22-Jan-2019 120.29 0 0 0 0
23-Jan-2019 Casting in progress at P7 2nd lift 120.29 0 0 30 12
24-Jan-2019 curing work 120.29 0 0 2 12
25-Jan-2019 curing work 120.29 0 0 2 12
26-Jan-2019 no work 120.29 0 0 0 0
27-Jan-2019 deshuttering work at p7 2nd lift 120.29 0 0 8 12
28-Jan-2019 deshuttering work in progress 120.29 0 0 8 12
29-Jan-2019 SINKING IN progress 120.29 112.797 0.959 7.493 12 12 4 12
natural sand & soil
30-Jan-2019 SINKING IN progress 120.29 111.843 0.954 8.447 12 12 4 12
31-Jan-2019 SINKING IN progress 120.29 111.78 0.063 8.51 Clay mixed sand 12 12 4 12
1-Feb-2019 shuttering & reinforcement work in progress at 3rd lift 120.29 0 0 21 12
2-Feb-2019 shuttering & reinforcement work in progress at 3rd lift 120.29 0 0 25 12
3-Feb-2019 shuttering & reinforcement work in progress at 3rd lift 120.29 0 0 12 12
4-Feb-2019 shuttering & reinforcement work in progress at 3rd lift 120.29 0 0 25 12
5-Feb-2019 shuttering & reinforcement work in progress at 3rd lift 120.29 0 0 25 12
6-Feb-2019 shuttering & reinforcement work in progress at 3rd lift 120.29 0 0 15 12
7-Feb-2019 casting in progress at P7 3rd lift 120.29 0 0 25 12
8-Feb-2019 curing work 120.29 0 0 1 12
9-Feb-2019 curing work 120.29 0 0 1 12
10-Feb-2019 no work 120.29 0 0 0 0
11-Feb-2019 Deshuttering in progress 120.29 0 0 8 12
12-Feb-2019 Deshuttering in progress 120.29 NO SINKING DURING THE DAYS 0 0 8 12
13-Feb-2019 Sinking in progress 120.29 111.295 0.485 8.995 12 12 4 12
14-Feb-2019 Sinking in progress 120.29 111.172 0.123 9.118 12 12 4 12
15-Feb-2019 Sinking in progress 120.29 111.07 0.102 9.22 12 12 4 12
16-Feb-2019 Sinking in progress 120.29 110.919 0.151 9.371 12 12 4 12
17-Feb-2019 no work 120.29 110.919 0 9.371 0 0 0 0
18-Feb-2019 Sinking in progress 120.29 110.65 0.269 9.64 12 12 4 12
19-Feb-2019 Sinking in progress 120.29 110.436 0.214 9.854 12 12 4 12
20-Feb-2019 Sinking in progress 120.29 110.15 0.286 10.14 Clay 12 12 4 12
21-Feb-2019 Sinking in progress 120.29 109.895 0.255 10.395 12 12 4 12
22-Feb-2019 Sinking in progress 120.29 109.747 0.148 10.543 12 12 4 12
23-Feb-2019 Sinking in progress 120.29 109.538 0.209 10.752 12 12 4 12
24-Feb-2019 no work 120.29 109.538 0 10.752 0 0 0 0
25-Feb-2019 Sinking in progress 120.29 108.896 0.642 11.394 12 12 4 12
26-Feb-2019 Sinking in progress 120.29 108.549 0.347 11.741 12 12 4 12
27-Feb-2019 Sinking in progress 120.29 108.373 0.176 11.917 12 12 4 12
28-Feb-2019 cleaning by dozzer near by well 120.29 6 6 0 0
1-Mar-2019 shuttering and reinforcement at S4 120.29 0 0 15 12
2-Mar-2019 shuttering and reinforcement at S4 120.29 0 0 26 12
3-Mar-2019 No work 120.29 0 0 0 0
4-Mar-2019 shuttering and reinforcement at S4 120.29 0 0 16 12
5-Mar-2019 shuttering and reinforcement at S4 120.29 0 0 22 12
6-Mar-2019 casting in progress at S4 120.29 0 0 25 12
7-Mar-2019 casting in progress at S4 120.29 0 0 25 12
8-Mar-2019 Deshuttering in progress 120.29 0 0 7 12
9-Mar-2019 Deshuttering in progress 120.29 0 0 7 12
10-Mar-2019 No work 120.29 0 0 0 0
11-Mar-2019 No work 120.29 no sinking 0 0 0 0
12-Mar-2019 Sinking in progress 120.29 107.373 1 12.917 12 12 4 12
13-Mar-2019 Sinking in progress 120.29 107.128 0.245 13.162 12 12 4 12
14-Mar-2019 Sinking in progress 120.29 106.916 0.212 13.374 12 12 4 12
15-Mar-2019 Sinking in progress 120.29 106.732 0.184 13.558 12 12 4 12
16-Mar-2019 Sinking in progress 120.29 106.505 0.227 13.785 12 12 4 12
17-Mar-2019 Sinking in progress 120.29 106.402 0.103 13.888 12 12 4 12
18-Mar-2019 Sinking in progress 120.29 106.3 0.102 13.99 12 12 4 12
19-Mar-2019 Sinking in progress 120.29 106.201 0.099 14.089 12 12 4 12
Clay
20-Mar-2019 Sinking in progress 120.29 106.118 0.083 14.172 12 12 4 12
21-Mar-2019 no work due to holi 120.29 106.118 0.000 14.172 0 0 0 0
22-Mar-2019 no work due to holi 120.29 106.118 0.000 14.172 0 0 0 0
23-Mar-2019 Sinking in progress 120.29 106.018 0.100 14.272 12 12 4 12
24-Mar-2019 NO WORK 120.29 106.018 0.000 14.272 0 0 0 0
25-Mar-2019 Sinking in progress 120.29 105.817 0.201 14.473 12 12 4 12
26-Mar-2019 Sinking in progress 120.29 105.661 0.156 14.629 12 12 4 12
27-Mar-2019 Sinking in progress 120.29 105.585 0.076 14.705 12 12 3 12
28-Mar-2019 120.29 0 0 0 0
29-Mar-2019 120.29 0 0 0 0
30-Mar-2019
no work 120.29 0 0 0 0
31-Mar-2019 120.29 0 0 0 0
1-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 7 12
2-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 8 12
3-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 12 12
4-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 7 12
5-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 6 12
6-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 10 12
7-Apr-2019 no work 120.29 0 0 0 0
8-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 20 12
9-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 20 12
10-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 14 12
11-Apr-2019 shuttering and reinforcement work at S5 120.29 0 0 18 12
12-Apr-2019 casting at s5 120.29 0 0 25 12
13-Apr-2019 curing work 120.29 0 0 1 12
14-Apr-2019 curing work 120.29 0 0 1 12
15-Apr-2019 deshuttering work S5 120.29 0 0 4 12
16-Apr-2019 deshuttering work S5 120.29 0 0 4 12
17-Apr-2019 deshuttering work S5 120.29 NO SINKING WORK 0 0 4 12
18-Apr-2019 Sinking in progress 120.29 105.162 0.423 15.128 12 12 2 12
19-Apr-2019 Sinking in progress 120.29 104.997 0.165 15.293 12 12 2 12
20-Apr-2019 Sinking in progress 120.29 104.719 0.278 15.571 12 12 2 12

CLAY
21-Apr-2019 no work 120.29 104.719 0 15.571 0 0 0 0
CLAY
22-Apr-2019 Sinking in progress 120.29 104.506 0.213 15.784 12 12 2 12
23-Apr-2019 Sinking in progress 120.29 104.263 0.243 16.027 12 12 2 12
24-Apr-2019 Sinking in progress 120.29 103.799 0.464 16.491 12 12 2 12
25-Apr-2019 Sinking in progress 120.29 103.412 0.387 16.878 12 12 2 12

1-Jun-2019 no work 120.29 0 0 0 0


2-Jun-2019 no work 120.29 0 0 0 0
3-Jun-2019 no work 120.29 0 0 0 0
4-Jun-2019 no work 120.29 0 0 0 0
5-Jun-2019 no work 120.29 0 0 0 0
6-Jun-2019 no work 120.29 0 0 0 0
7-Jun-2019 no work 120.29 0 0 0 0
8-Jun-2019 no work 120.29 0 0 0 0
9-Jun-2019 no work 120.29 0 0 0 0
10-Jun-2019 no work 120.29 0 0 0 0
11-Jun-2019 no work 120.29 0 0 0 0
12-Jun-2019 no work 120.29 0 0 0 0
13-Jun-2019 no work 120.29 0 0 0 0
14-Jun-2019 no work 120.29 0 0 0 0
15-Jun-2019 no work 120.29 0 0 0 0
16-Jun-2019 no work 120.29 0 0 0 0
17-Jun-2019 no work 120.29 0 0 0 0
18-Jun-2019 no work 120.29 0 0 0 0
19-Jun-2019 no work 120.29 0 0 0 0
20-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
21-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
22-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
23-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
24-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
25-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
26-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
27-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 15 12
28-Jun-2019 shuttering and reinforcement work in progress at S6 120.29 NO SINKING WORK 0 0 15 12
29-Jun-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
30-Jun-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
1-Jul-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
2-Jul-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
3-Jul-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
4-Jul-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
5-Jul-2019 no work due to unavailability of machanical splices 120.29 0 0 0 0
6-Jul-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 10 12
7-Jul-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 10 12
8-Jul-2019 shuttering and reinforcement work in progress at S6 120.29 0 0 3 0
9-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
10-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
11-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
12-Jul-2019 casting in progress at S6 120.29 0 0 25 0
13-Jul-2019 casting in progress at S6 120.29 0 0 25 0
14-Jul-2019 no work 120.29 0 0 0 0
15-Jul-2019 curing work 120.29 0 0 1 10
16-Jul-2019 curing work 120.29 0 0 1 10
17-Jul-2019 Deshuttering work in progress 120.29 0 0 1 10
18-Jul-2019 Deshuttering work in progress 120.29 0 0 5 12
19-Jul-2019 curing work but no sinking work 120.29 0 0 5 12
20-Jul-2019 curing work but no sinking work 120.29 0 0 1 12
21-Jul-2019 no work 120.29 0 0 0 0
22-Jul-2019 curing work but no sinking work 120.29 0 0 1 12
23-Jul-2019 curing work but no sinking work 120.29 0 0 1 12
24-Jul-2019 curing work but no sinking work 120.29 0 0 1 12
25-Jul-2019 curing work but no sinking work 120.29 0 0 1 12
26-Jul-2019 sinking in progress 120.29 102.843 0.569 17.447 12 12 2 12
27-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
28-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
29-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
30-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
31-Jul-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
1-Aug-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
2-Aug-2019 NO WROK DUE WATER LEVEL RISES 120.29 0 0 0 0
3-Aug-2019
4-Aug-2019
5-Aug-2019
6-Aug-2019
7-Aug-2019
8-Aug-2019
9-Aug-2019
10-Aug-2019
11-Aug-2019
12-Aug-2019
13-Aug-2019
14-Aug-2019
15-Aug-2019 NO WROK DUE WATER LEVEL RISES
16-Aug-2019 NO WROK DUE WATER LEVEL RISES
17-Aug-2019 NO WROK DUE WATER LEVEL RISES
18-Aug-2019 NO WROK DUE WATER LEVEL RISES
19-Aug-2019 NO WROK DUE WATER LEVEL RISES
20-Aug-2019 NO WROK DUE WATER LEVEL RISES
21-Aug-2019 NO WROK DUE WATER LEVEL RISES
22-Aug-2019 NO WROK DUE WATER LEVEL RISES
23-Aug-2019 NO WROK DUE WATER LEVEL RISES
24-Aug-2019 NO WROK DUE WATER LEVEL RISES
25-Aug-2019 NO WROK DUE WATER LEVEL RISES
26-Aug-2019
27-Aug-2019
28-Aug-2019
Summary of sinking and construction at P8
Machine & Man Power
RL OF BOTTOM CRANE 1 CRANE 2 LABOUR
OF CUTTING SINKING CUMMULATIVE
DATE work details OGL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
CASTING OF WELL CURB P8 (11/05/18)

15/05/18 sinking in progess 121.033 119.588 1.445 1.445 12 0 16 12


16/05/18 sinking in progess 121.033 119.028 0.56 2.005 13 0 15 13
17/05/18 sinking in progess 121.033 118.57 0.458 2.463 12 0 16 12
18/05/18 sinking in progess 121.033 118.25 0.32 2.783 14 0 16 14
19/05/18 sinking in progess 121.033 117.457 0.793 3.576 15 0 16 15
20/05/18 sinking in progess 121.033 117.457 0 3.576 5 0 14 5
21/05/18 sinking in progess 121.033 117.032 0.425 4.001 sand 15 0 14 15

CASTING OF 1ST LIFT WELL STEINIG (09/06/18)


13/06/18 sinking in progess 121.033 115.982 1.05 5.051 15 0 5 15
14/06/18 sinking in progess 121.033 115.08 0.902 5.953 16 0 5 16
15/06/18 sinking in progess 121.033 114.404 0.676 6.629 16 0 5 16
16/06/18 sinking in progess 121.033 114.383 0.021 6.65 coarse sand 12 0 5 12

CASTING OF 2nd LIFT WELL STEINIG (24/06/18)


28/06/18 sinking in progess 121.033 113.851 0.532 7.182 16 0 5 16
29/06/18 sinking in progess 121.033 113.610 0.241 7.423 16 0 5 16
30/06/18 sinking in progess 121.033 113.099 0.511 7.934 16 0 5 16
1/7/2018 sinking in progess 121.033 112.886 0.213 8.147 16 16 5 16
2/7/2018 sinking in progess 121.033 112.691 0.195 8.342 16 10 6 16
3/7/2018 sinking in progess 121.033 112.236 0.455 8.797 clay and sand 10 16 6 10

CASTING OF 3rd LIFT WELL STEINIG (07/07/18)


10/7/2018 sinking in progess 121.033 112.136 0.1 8.897 16 16 4 16
11/7/2018 sinking in progess 121.033 112.011 0.125 9.022 16 16 5 16
12/7/2018 sinking in progess 121.033 111.951 0.06 9.082 16 16 5 16
13/07/18 sinking in progess 121.033 111.891 0.06 9.142 16 16 5 16
14/07/18 sinking in progess 121.033 111.677 0.214 9.356 16 16 5 16
15/07/18 sinking in progess 121.033 111.648 0.029 9.385 16 16 5 16
16/07/18 sinking in progess 121.033 111.574 0.074 9.459 16 16 5 16
17/07/18 sinking in progess 121.033 111.526 0.048 9.507 16 16 5 16
18/07/18 sinking in progess 121.033 111.456 0.07 9.577 16 16 5 16
19/07/18 sinking in progess 121.033 111.432 0.024 9.601 hard clay & 16 16 5 16
20/07/18 sinking in progess 121.033 111.409 0.023 9.624 loose boulders 16 16 5 16

sinking stop due to water in river from 21/07/18 to 31/07/18


1/8/2018 sinking in progess 121.033 111.402 0.007 9.631 16 16 5 16
3/8/2018 sinking in progess 121.033 111.39 0.012 9.643 16 16 5 16
4/8/2018 sinking in progess 121.033 111.38 0.01 9.653 16 16 5 16
5/8/2018 sinking in progess 121.033 111.364 0.016 9.669 16 16 5 16
6/8/2018 sinking in progess 121.033 111.346 0.018 9.687 16 16 5 16
11/8/2018 sinking in progess 121.033 111.339 0.007 9.694 hard clay & 16 16 5 16
12/8/2018 sinking in progess 121.033 111.322 0.017 9.711 loose boulder 16 16 5 16
13/8/2018 sinking in progess 121.033 111.127 0.195 9.906 16 16 5 15
14/08/2018 sinking in progess 121.033 110.844 0.283 10.189 16 16 5 16
16/08/2018 sinking in progess 121.033 110.724 0.12 10.309 16 16 5 16
18/08/2018 sinking in progess 121.033 110.646 0.078 10.387 16 16 5 16
21/08/2018 sinking in progess 121.033 110.597 0.049 10.436 16 16 5 16
22/08/2018 sinking in progess 121.033 110.431 0.166 10.602 hard clay 12 12 5 12

sinking stop due to water in river from 23/08/18 to 18/09/18 (water come from upstream dam at kota )
19- Sep-18 sinking in progess 121.033 110.358 0.073 10.675 12 12 5 12
20- Sep-18 sinking in progess 121.033 110.316 0.042 10.717 16 16 5 16
21- Sep-18 sinking in progess 121.033 110.134 0.182 10.899 16 16 5 16
22- Sep-18 sinking in progess 121.033 110.065 0.069 10.968 12 12 5 12
23- Sep-18 sinking in progess 121.033 110.035 0.03 10.998 hard clay 8 8 5 8
24- Sep-18 sinking in progess 121.033 110.009 0.026 11.024 8 8 5 8
25- Sep-18 sinking in progess 121.033 109.691 0.318 11.342 12 12 4 12
26- Sep-18 sinking in progess 121.033 109.564 0.127 11.469 12 12 5 12
27- Sep-18 sinking in progess 121.033 109.25 0.314 11.783 16 16 5 16
28- Sep-18 NO work since labour not available 121.033 0 0 0 0
29- Sep-18 Clean of well steining top 121.033 0 0 5 10
30- Sep-18 121.033 0 0 0 0
01- Oct-18 121.033 0 0 0 0
02- Oct-18 NO work since labour not available 121.033 0 0 0 0
03- Oct-18 121.033 0 0 0 0
04- Oct-18 121.033 0 0 0 0
05- Oct-18 Reinforcement making in progress 121.033 0 0 10 12

No sinking
06- Oct-18 reinforcement binding in progress 121.033 0 0 10 12
07- Oct-18 reinforcement binding in progress 121.033
No sinking 0 0 21 12
08- Oct-18 reinforcement binding in progress 121.033 0 0 21 12
09- Oct-18 reinforecement binding and fixing in progress 121.033 0 0 21 12
10- Oct-18 reinforecement binding and fixing in progress 121.033 0 0 21 12
11- Oct-18 casting in progress 121.033 0 0 25 12
12- Oct-18 casting in progress 121.033 0 0 25 7
13- Oct-18 curing in progress 121.033 0 0 2 0
14- Oct-18 curing in progress 121.033 0 0 2 0
15- Oct-18 curing in progress 121.033 0 0 2 0
16- Oct-18 sinking in progess 121.033 108.918 0.332 12.115 6 6 5 6
17- Oct-18 sinking in progess 121.033 108.696 0.222 12.337 12 12 5 12
18- Oct-18 sinking in progess 121.033 108.547 0.149 12.486 12 12 5 12
19- Oct-18 dusshera holiday 121.033 108.547 0 12.486 0 0 0 0
20- Oct-18 sinking in progess 121.033 108.502 0.045 12.531 12 12 5 12
21- Oct-18 sinking in progess 121.033 108.075 0.427 12.958 12 12 5 12
22- Oct-18 sinking in progess 121.033 108.018 0.057 13.015 12 12 5 12
23- Oct-18 sinking in progess 121.033 107.882 0.136 13.151 12 12 5 12
24- Oct-18 sinking in progess 121.033 107.653 0.229 13.38 12 12 5 12
25- Oct-18 sinking in progess 121.033 107.45 0.203 13.583 hard clay 12 12 5 12
26- Oct-18 sinking in progess 121.033 107.035 0.415 13.998 12 12 5 12
27- Oct-18 sinking in progess 121.033 106.66 0.375 14.373 12 12 5 12
28- Oct-18 NO sinking 121.033 106.66 0 14.373 0 0 0 0
29- Oct-18 sinking in progess 121.033 106.235 0.425 14.798 12 12 5 12
30- Oct-18 sinking in progess 121.033 105.981 0.254 15.052 12 12 5 12
31- Oct-18 sinking in progess 121.033 105.845 0.136 15.188 12 12 5 12

01- Nov-18 sinking in progess 121.033 105.534 0.311 15.499 12 12 5 12


02- Nov-18 sinking in progess 121.033 105.316 0.218 15.717 12 12 5 12
03- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 10 12
04- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 14 12
05- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 10 12
06- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 10 12
07- Nov-18 diwali holiday 121.033 0 0 0 0
08- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 9 12
09- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 9 12
10- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 9 12
11- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 9 12
12- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 9 12
13- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 13 12
14- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 15 12
15- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 10 10
16- Nov-18 reinforcement & shuttering work in progress at WS 5th lift 121.033 0 0 10 10
17- Nov-18 casting in progress at 5th lift 121.033 0 0 25 12
18- Nov-18 casting in progress at 5th lift 121.033 NO SINKING DURING THE DAYS 0 0 25 12
19- Nov-18 curing and deshuttering 121.033 0 0 10 10
20- Nov-18 curing and deshuttering 121.033 0 0 10 10
21- Nov-18 curing and deshuttering 121.033 0 0 8 10
22- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 8 10
23- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 20 10
24- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 18 10
25- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 14 10
26- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 14 10
27- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 15 10
28- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 14 10
29- Nov-18 reinforcement & shuttering work in progress at WS 6th lift 121.033 0 0 10 10
30- Nov-18 casting in progress at 6th lift 121.033 0 0 25 20
01- Dec-18 curing work 121.033 0 0 2 0
02- Dec-18 deshuttering of 6th lift WS 121.033 0 0 8 12
03- Dec-18 deshuttering of 6th lift WS 121.033 0 0 8 12
04- Dec-18 sinking in progess 121.033 104.489 0.827 16.544 12 12 4 12
05- Dec-18 sinking in progess 121.033 104.413 0.076 16.62 12 12 4 12
06- Dec-18 sinking in progess 121.033 104.288 0.125 16.745 12 12 4 12
07- Dec-18 sinking in progess 121.033 104.243 0.045 16.79 12 12 4 12
08- Dec-18 sinking in progess 121.033 104.172 0.071 16.861 hard clay 12 12 4 12
09- Dec-18 NO WORK 121.033 104.172 0 16.861 0 0 0 0
10- Dec-18 sinking in progess 121.033 104.172 0 16.861 12 12 4 12
11- Dec-18 sinking in progess 121.033 104.046 0.126 16.987 12 12 4 12
12- Dec-18 sinking in progess 121.033 103.983 0.063 17.05 12 12 4 12
13- Dec-18 121.033 0 0 0 0
14- Dec-18 121.033 0 0 0 0
15- Dec-18 121.033 0 0 0 0
16- Dec-18 121.033 0 0 0 0
no activity crane are not available no sinking during the day
17- Dec-18 no activity crane are not available 121.033 no sinking during the day 0 0 0 0
18- Dec-18 121.033 0 0 0 0
19- Dec-18 121.033 0 0 0 0
20- Dec-18 121.033 0 0 0 0
21- Dec-18 121.033 0 0 0 0
22- Dec-18 sinking in progess 121.033 103.746 0.237 17.287 12 12 6 12
23- Dec-18 NO WORK 121.033 no sinking during the day 0 0 0 0
24- Dec-18 sinking in progess 121.033 103.398 0.348 17.635 12 12 6 12
25- Dec-18 121.033 0 0 0 0
26- Dec-18 no sinking since crane are not available 121.033 no sinking during the day 0 0 0 0
27- Dec-18 121.033 0 0 0 0
28- Dec-18 sinking in progess 121.033 103.239 0.159 17.794 12 12 4 12
29- Dec-18 sinking in progess 121.033 103.13 0.109 17.903 12 12 4 12
hard clay
30- Dec-18 NO WORK 121.033 103.13 0 17.903 0 0 0 0
31- Dec-18 sinking in progess 121.033 103.047 0.083 17.986 12 12 0 12

01- Jan-19 NO WORK 121.033 103.047 0 17.986 0 0 0 0


02- Jan-19 sinking in progess 121.033 102.863 0.184 18.17 12 12 4 12
hard clay
03- Jan-19 sinking in progess 121.033 102.745 0.118 18.288 12 12 4 12
04- Jan-19 sinking in progess 121.033 102.693 0.052 18.34 12 12 4 12
05- Jan-19 121.033 0 0 0 0
06- Jan-19 121.033 0 0 0 0
07- Jan-19 121.033 0 0 0 0
08- Jan-19 121.033 0 0 0 0
09- Jan-19 121.033 0 0 0 0
10- Jan-19 121.033 0 0 0 0
no sinking due to shortage of crane NO SINKING DURING THE DAYS
11- Jan-19 121.033 0 0 0 0
12- Jan-19 121.033 0 0 0 0
13- Jan-19 121.033 0 0 0 0
14- Jan-19 121.033 0 0 0 0
15- Jan-19 121.033 0 0 0 0
16- Jan-19 121.033 0 0 0 0
17- Jan-19 sinking in progess 121.033 102.152 0.541 18.881 12 12 4 12
18- Jan-19 sinking in progess 121.033 102.076 0.076 18.957 12 12 4 12
19- Jan-19 sinking in progess 121.033 101.866 0.21 19.167 12 12 4 12
20- Jan-19 No work 121.033 101.866 0 19.167 0 0 0 0
21- Jan-19 sinking in progess 121.033 101.618 0.248 19.415 12 12 4 12
22- Jan-19 sinking in progess 121.033 101.481 0.137 19.552 12 12 4 12
23- Jan-19 sinking in progess 121.033 101.386 0.095 19.647 hard clay 12 12 4 12
24- Jan-19 sinking in progess 121.033 101.248 0.138 19.785 12 12 4 12
25- Jan-19 sinking in progess 121.033 101.107 0.141 19.926 12 12 4 12
26- Jan-19 no work 121.033 101.107 0 19.926 0 0 0 0
27- Jan-19 no work 121.033 101.107 0 19.926 0 0 0 0
28- Jan-19 sinking in progess 121.033 100.902 0.205 20.131 12 12 4 12
29- Jan-19 sinking in progess 121.033 100.882 0.02 20.151 12 12 4 12
30- Jan-19 Cleaning of surface and S7 WS 121.033 0 0 5 12
31- Jan-19 Shuttering and reinforcement work S7 121.033 0 0 15 12
01- Feb-19 Shuttering and reinforcement work S7 121.033 0 0 18 12
02- Feb-19 Shuttering and reinforcement work S7 121.033 0 0 18 12
03- Feb-19 no work 121.033 0 0 0 0
no sinikng during the days
04- Feb-19 Shuttering and reinforcement work S7 121.033 0 0 22 12
05- Feb-19 Shuttering and reinforcement work S7 121.033 0 0 22 12
06- Feb-19 casting work is in progress at S7 121.033 0 0 25 15
07- Feb-19 curing 121.033 0 0 2 12
08- Feb-19 deshuttering in progress 121.033 0 0 8 12
09- Feb-19 SINKING IN PROGRESS 121.033 100.426 0.456 20.607 12 12 4 12
10- Feb-19 no work 121.033 100.426 0 20.607 0 0 0 0
11- Feb-19 SINKING IN PROGRESS 121.033 100.297 0.129 20.736 12 12 4 12
12- Feb-19 SINKING IN PROGRESS 121.033 100.238 0.059 20.795 12 12 4 12
clay
13- Feb-19 SINKING IN PROGRESS 121.033 100.196 0.042 20.837 12 12 4 12
14- Feb-19 SINKING IN PROGRESS 121.033 100.126 0.07 20.907 12 12 4 12
15- Feb-19 SINKING IN PROGRESS 121.033 100.036 0.09 20.997 12 12 4 12
16- Feb-19 SINKING IN PROGRESS 121.033 98.613 1.423 22.42 12 12 4 12
17- Feb-19 no work 121.033 0 0 0 0
no sinikng during the days
18- Feb-19 no work since crane not available 121.033 0 0 0 0
19- Feb-19 SINKING IN PROGRESS 121.033 98.607 0.006 22.426 12 12 4 12
clay
20- Feb-19 SINKING IN PROGRESS 121.033 98.605 0.002 22.428 12 12 4 12
21- Feb-19 No work shuttering gang not available 121.033 0 0 0 0
22- Feb-19 No work shuttering gang not available 121.033 0 0 0 0
23- Feb-19 No work shuttering gang not available 121.033 0 0 0 0
24- Feb-19 no work 121.033 0 0 0 0
25- Feb-19 shuttering and reinforcement at S8 121.033 0 0 25 12
26- Feb-19 shuttering and reinforcement at S8 121.033 0 0 25 12
27- Feb-19 shuttering and reinforcement at S8 121.033 0 0 25 12
28- Feb-19 shuttering and reinforcement at S8 121.033 0 0 25 12
01- Mar-19 casting in progress at S8 121.033 0 0 25 12
02- Mar-19 casting in progress at S8 121.033 0 0 25 12
03- Mar-19 No work 121.033 0 0 0 0
04- Mar-19 deshuttering work 121.033 0 0 7 12
05- Mar-19 deshuttering work 121.033 0 0 7 12
06- Mar-19 deshuttering work 121.033 0 0 5 12
07- Mar-19 no work 121.033 0 0 0 0
08- Mar-19 Arrangement for shift correction 121.033 0 0 0 12
09- Mar-19 Arrangement for shift correction 121.033 0 0 6 0
10- Mar-19 No work 121.033 0 0 0 0
11- Mar-19 No work 121.033 0 0 0 12
12- Mar-19 Arrangement for shift correction 121.033 0 0 2 12
13- Mar-19 Arrangement for shift correction 121.033 0 0 5 12
14- Mar-19 Arrangement for shift correction 121.033 0 0 6 12
15- Mar-19 Arrangement for shift correction 121.033 0 0 4 12
16- Mar-19 Arrangement for shift correction 121.033 0 0 4 12
17- Mar-19 Arrangement for shift correction 121.033 0 0 5 12
18- Mar-19 Arrangement for shift correction 121.033 98.359 0.246 22.674 12 0 3 12
clay
19- Mar-19 Sinking in progress 121.033 98.343 0.016 22.69 12 0 3 12
20- Mar-19 no work due crane wire danaged 121.033 0 0 0 0
21- Mar-19 no work due to holi 121.033 0 0 0 0
22- Mar-19 no work due to holi 121.033 0 0 0 0
23- Mar-19 no work crane break down 121.033 0 0 0 0
24- Mar-19 NO WORK 121.033 0 0 0 0
25- Mar-19 Sinking in progress 121.033 98.27 0.073 22.763 12 12 4 12
26- Mar-19 Sinking in progress 121.033 98.15 0.12 22.883 12 12 4 12
27- Mar-19 Sinking in progress 121.033 98.09 0.06 22.943 clay 12 12 4 12
28- Mar-19 Sinking in progress 121.033 98.008 0.082 23.025 12 12 4 12
29- Mar-19 Sinking in progress 121.033 97.821 0.187 23.212 12 12 4 12
30- Mar-19 no work 121.033 0 0 0 0
31- Mar-19 no work 121.033 0 0 0 0
01- Apr-19 Sinking in progress 121.033 97.538 0.283 23.495 12 12 3 12
02- Apr-19 Sinking in progress 121.033 97.456 0.082 23.577 clay 12 12 3 12
03- Apr-19 Sinking in progress 121.033 96.511 0.945 24.522 12 12 3 12
04- Apr-19 no work 121.033 0 0 0 0
05- Apr-19 no work 121.033 0 0 0 0
06- Apr-19 no work 121.033 0 0 0 0
07- Apr-19 no work 121.033 0 0 0 0
08- Apr-19 no work 121.033 0 0 0 0
09- Apr-19 shuttering and reinforecment at S9 121.033 0 0 10 12
10- Apr-19 shuttering and reinforecment at S9 121.033 0 0 6 12
11- Apr-19 no work 121.033 0 0 0 0
12- Apr-19 shuttering and reinforecment at S9 121.033 0 0 15 12
13- Apr-19 shuttering and reinforecment at S9 121.033 0 0 18 12
14- Apr-19 no work 121.033 0 0 0 0
15- Apr-19 shuttering and reinforecment at S9 121.033 0 0 20 12
16- Apr-19 shuttering and reinforecment at S9 121.033 0 0 8 12
17- Apr-19 casting at S9 121.033 0 0 23 12
18- Apr-19 casting at S9 121.033 0 0 25 12
19- Apr-19 deshuttering work in progress 121.033 0 0 3 12
20- Apr-19 deshuttering work in progress 121.033 0 0 5 12
21- Apr-19 no work 121.033 0 0 0 0
22- Apr-19 deshuttering work in progress 121.033 0 0 4 12
23- Apr-19 curing 121.033 0 0 1 10
24- Apr-19 curing 121.033 0 0 1 10

01- Jun-19 no work 121.033 0 0 0 0


02- Jun-19 no work 121.033 0 0 0 0
03- Jun-19 no work 121.033 0 0 0 0
04- Jun-19 no work 121.033 0 0 0 0
05- Jun-19 no work 121.033 0 0 0 0
06- Jun-19 no work 121.033 0 0 0 0
07- Jun-19 no work 121.033 0 0 0 0
08- Jun-19 no work 121.033 0 0 0 0
09- Jun-19 no work 121.033 0 0 0 0
10- Jun-19 no work 121.033 0 0 0 0
11- Jun-19 no work 121.033 0 0 0 0
12- Jun-19 no work 121.033 0 0 0 0
13- Jun-19 no work 121.033 0 0 0 0
14- Jun-19 no work 121.033 0 0 0 0
15- Jun-19 no work 121.033 0 0 0 0
16- Jun-19 no work 121.033 0 0 0 0
17- Jun-19 no work 121.033 0 0 0 0
18- Jun-19 no work 121.033 0 0 0 0
19- Jun-19 no work 121.033 0 0 0 0
20- Jun-19 no work 121.033 0 0 0 0
21- Jun-19 no work 121.033 0 0 0 0
22- Jun-19 no work 121.033 0 0 0 0
23- Jun-19 no work 121.033 0 0 0 0
24- Jun-19 no work 121.033 0 0 0 0
25- Jun-19 no work 121.033 0 0 0 0
26- Jun-19 no work 121.033 0 0 0 0
27- Jun-19 no work 121.033 0 0 0 0
28- Jun-19 no work 121.033 0 0 0 0
29- Jun-19 no work 121.033 0 0 0 0
30- Jun-19 no work 121.033 0 0 0 0
01- Jul-19 no work 121.033 0 0 0 0
02- Jul-19 no work 121.033 0 0 0 0
03- Jul-19 no work 121.033 0 0 0 0
04- Jul-19 no work 121.033 0 0 0 0
05- Jul-19 no work 121.033 0 0 0 0
06- Jul-19 no work 121.033 0 0 0 0
07- Jul-19 no work 121.033 0 0 0 0
08- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 5 10
09- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 10 10
10- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 5 10
11- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 5 10
12- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 5 10
13- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 5 10
14- Jul-19 Assembly of section for tilt ad shift correction 121.033 0 0 5 10
15- Jul-19 sinking in progress 121.033 96.363 0.148 24.67 12 12 4 12
16- Jul-19 sinking in progress 121.033 96.358 0.005 24.675 12 12 4 12
17- Jul-19 sinking in progress 121.033 96.358 0 24.675 12 12 4 12
18- Jul-19 sinking in progress 121.033 96.358 0 24.675 12 12 3 12
19- Jul-19 sinking in progress 121.033 96.358 0 24.675 12 12 3 12
20- Jul-19 sinking in progress 121.033 96.166 0.192 24.867 12 12 3 12
clay
21- Jul-19 no work 121.033 96.166 0 24.867 0 0 0 0
22- Jul-19 sinking in progress 121.033 96.073 0.093 24.96 12 12 2 12
23- Jul-19 sinking in progress 121.033 95.901 0.172 25.132 12 12 2 12
24- Jul-19 sinking in progress 121.033 95.702 0.199 25.331 12 12 2 12
25- Jul-19 sinking in progress 121.033 95.547 0.155 25.486 12 12 2 12
26- Jul-19 sinking in progress 121.033 95.437 0.11 25.596 12 12 2 12
27- Jul-19 NO WROK DUE WATER LEVEL RISES 121.033 0 0 0 0
28- Jul-19 NO WROK DUE WATER LEVEL RISES 121.033 0 0 0 0
29- Jul-19 NO WROK DUE WATER LEVEL RISES 121.033 0 0 0 0
30- Jul-19 NO WROK DUE WATER LEVEL RISES 121.033 0 0 0 0
31- Jul-19 NO WROK DUE WATER LEVEL RISES 121.033 0 0 0 0
01- Aug-19
02- Aug-19
03- Aug-19
04- Aug-19
05- Aug-19
summary of sinking and construction at P9
RL OF Machine & Man Power
BOTTOM
CRANE 1 CRANE 2 LABOUR
OF SINKING CUMMULA
CUTTING DURING TIVE STRATA
DATE work details OGL EDGE A DAY SINKING crane 1 hrs crane 2 hrs heads hrs
CASTING OF WELL CURB P9 (29/06/18)
3/7/2018 SINKING IN PROGRESS 123.397 123.397 0.125 0.125 12 12 8 4
4/7/2018 SINKING IN PROGRESS 123.397 122.302 0.97 1.095 13 13 6 16
course sand
5/7/2018 SINKING IN PROGRESS 123.397 119.772 2.53 3.625 12 12 8 16
6/7/2018 SINKING IN PROGRESS 123.397 119.172 0.6 4.225 14 14 8 15
CASTING OF 1ST LIFT WELL STEINIG (21/07/18)
28/07/18 SINKING IN PROGRESS 123.397 117.962 1.21 5.435 16 16 5 16
course sand
30/07/18 SINKING IN PROGRESS 123.397 117.824 0.138 5.573 16 16 5 16
CASTING OF 2nd LIFT WELL STEINIG (04/08/18)
7/8/2018 SINKING IN PROGRESS 123.397 116.866 0.958 6.531 15 15 5 15
course sand
8/8/2018 SINKING IN PROGRESS 123.397 115.107 1.759 8.29 16 16 5 16

CASTING OF 3rd LIFT WELL STEINIG (14/08/18)


17/08/18 SINKING IN PROGRESS 123.397 114.867 0.24 8.53 14 14 5 14
course sand
18/08/18 SINKING IN PROGRESS 123.397 112.347 2.52 11.05 16 16 4 16
CASTING OF 4th LIFT WELL STEINIG (27/08/18)
30/08/18 SINKING IN PROGRESS 123.397 111.386 0.961 12.011 12 12 5 12
course sand
31/08/18 SINKING IN PROGRESS 123.397 111.089 0.297 12.308 14 14 5 14
01/09/2018 SINKING IN PROGRESS 123.397 111.017 0.072 12.38 14 14 5 14
02/09/2018 SINKING IN PROGRESS 123.397 110.946 0.071 12.451 8 8 5 8
03/09/2018 SINKING IN PROGRESS 123.397 110.926 0.02 12.471 12 12 5 12
04/09/2018 SINKING IN PROGRESS 123.397 110.918 0.008 12.479 hard clay & 9 9 4 9
05/09/2018 SINKING IN PROGRESS 123.397 110.904 0.014 12.493 loose boulder 8 8 4 8
06/09/2018 SINKING IN PROGRESS 123.397 110.889 0.015 12.508 12 12 4 12
07/09/2018 SINKING IN PROGRESS 123.397 110.825 0.064 12.572 12 12 4 12
08/09/2018 SINKING IN PROGRESS 123.397 110.456 0.369 12.941 12 12 4 12
CASTING OF 5th LIFT WELL STEINIG (23/09/18)
29-Sep-2018 SINKING IN PROGRESS 123.397 110.133 0.323 13.264 stiff clay 12 12 5 12
30-Sep-2018 NO WORK 0 0 0 0
1-Oct-2018 SINKING IN PROGRESS 123.397 109.82 0.313 13.577 12 12 5 12
2-Oct-2018 SINKING IN PROGRESS 123.397 109.683 0.137 13.714 12 12 5 12
stiff clay & one
3-Oct-2018 SINKING IN PROGRESS 123.397 109.527 0.156 13.87 12 12 5 12
big boulder on
4-Oct-2018 SINKING IN PROGRESS 123.397 109.417 0.11 13.98 03/10 12 12 5 12
5-Oct-2018 SINKING IN PROGRESS 123.397 109.304 0.113 14.093 12 12 5 12
6-Oct-2018 SINKING IN PROGRESS 123.397 109.097 0.207 14.3 12 12 5 12
7-Oct-2018 no sinking (sunday)
8-Oct-2018 SINKING IN PROGRESS 123.397 108.878 0.219 14.519 12 12 5 12
9-Oct-2018 SINKING IN PROGRESS 123.397 108.641 0.237 14.756 12 12 5 12
10-Oct-2018 SINKING IN PROGRESS 123.397 108.468 0.173 14.929 12 12 5 12
11-Oct-2018 SINKING IN PROGRESS 123.397 108.12 0.348 15.277 12 12 5 12
12-Oct-2018 SINKING IN PROGRESS 123.397 107.917 0.203 15.48 12 12 5 12
13-Oct-2018 SINKING IN PROGRESS 123.397 107.709 0.208 15.688 clay layer 12 12 5 12
14-Oct-2018 SINKING IN PROGRESS 123.397 107.467 0.242 15.93 12 12 5 12
15-Oct-2018 SINKING IN PROGRESS 123.397 107.44 0.027 15.957 12 12 5 12
16-Oct-2018 SINKING IN PROGRESS 123.397 107.229 0.211 16.168 12 12 5 12
17-Oct-2018 SINKING IN PROGRESS 123.397 106.963 0.266 16.434 12 12 5 12
18-Oct-2018 SINKING IN PROGRESS 123.397 106.787 0.176 16.61
19-Oct-2018 no work desherra holiday 123.397 0 0 0 0
20-Oct-2018 reinforcement making for 6th lift 123.397 12 12 10 12
21-Oct-2018 reinforcement making for 6th lift 123.397 12 12 10 12
22-Oct-2018 reinforcement & Shuttering work at P9 6th lift 123.397 12 12 10 12
23-Oct-2018 reinforcement & Shuttering work at P9 6th lift 123.397 12 12 10 12
24-Oct-2018 Shuttering work at P9 6th lift 123.397 12 12 10 12

no skining during the days


25-Oct-2018 Shuttering work at P9 6th lift 123.397 12 12 10 12
26-Oct-2018 Shuttering work at P9 6th lift 123.397 12 12 10 12
27-Oct-2018 Shuttering work at P9 6th lift 123.397 12 12 10 12
28-Oct-2018 Shuttering work at P9 6th lift 123.397 12 12 10 12
29-Oct-2018 Shuttering work at P9 6th lift 123.397 no skining during the days 12 12 10 12
30-Oct-2018 Shuttering work at P9 6th lift 123.397 12 12 10 12
31-Oct-2018 reinforcement binding work 123.397 0 0 14 12
1-Nov-2018 reinforcement binding in progress 123.397 0 0 14 10
2-Nov-2018 reinforcement binding in progress 123.397 0 0 20 12
3-Nov-2018 casting in progress at 6th lift WS 123.397 0 0 25 12
4-Nov-2018 casting in progress at 6th lift WS 123.397 0 0 25 12
5-Nov-2018 CURING 123.397 0 0 2 0
6-Nov-2018 deshuttering work 123.397 0 0 5 12
7-Nov-2018 diwali holiday 123.397 0 0 0 0
8-Nov-2018 sinking started 123.397 106.362 0.425 17.035 12 12 5 12
9-Nov-2018 SINKING IN PROGRESS 123.397 106.169 0.193 17.228 12 12 5 12
10-Nov-2018 SINKING IN PROGRESS 123.397 106.022 0.147 17.375 12 12 5 12
11-Nov-2018 SINKING IN PROGRESS 123.397 105.936 0.086 17.461 12 12 5 12
12-Nov-2018 SINKING IN PROGRESS 123.397 105.851 0.085 17.546 12 12 5 12
13-Nov-2018 SINKING IN PROGRESS 123.397 105.648 0.203 17.749 12 12 5 12
14-Nov-2018 SINKING IN PROGRESS 123.397 105.36 0.288 18.037 12 12 5 12
15-Nov-2018 SINKING IN PROGRESS 123.397 105.177 0.183 18.22 12 12 5 12
16-Nov-2018 SINKING IN PROGRESS 123.397 104.992 0.185 18.405 12 12 5 12
17-Nov-2018 no sinking since chisel stuk in well 123.397 104.992 0.000 18.405 0 0 0 0
18-Nov-2018 no sinking since chisel stuk in well 123.397 104.992 0.000 18.405 0 0 0 0
19-Nov-2018 SINKING IN PROGRESS 123.397 104.713 0.279 18.684 12 12 5 12
20-Nov-2018 SINKING IN PROGRESS 123.397 104.572 0.141 18.825 12 12 5 12
21-Nov-2018 SINKING IN PROGRESS 123.397 104.387 0.185 19.01 hard clay layer 12 12 5 12
22-Nov-2018 SINKING IN PROGRESS 123.397 104.165 0.222 19.232 12 12 5 12
23-Nov-2018 SINKING IN PROGRESS 123.397 104.108 0.057 19.289 12 12 5 12
24-Nov-2018 SINKING IN PROGRESS 123.397 104.081 0.027 19.316 12 12 5 12
25-Nov-2018 cleaning of top surface 123.397 104.081 0.000 19.316 12 12 5 12
26-Nov-2018 cleaning of top surface 123.397 104.081 0.000 19.316 0 0 4 0
27-Nov-2018 no work since worker not available 123.397 104.081 0.000 19.316 0 0 0 0
28-Nov-2018 SINKING IN PROGRESS 123.397 103.898 0.183 19.499 12 12 4 12
29-Nov-2018 SINKING IN PROGRESS 123.397 103.797 0.101 19.6 12 12 4 12
30-Nov-2018 SINKING IN PROGRESS 123.397 103.707 0.090 19.69 12 12 4 12
1-Dec-2018 SINKING IN PROGRESS 123.397 103.411 0.296 19.986 12 12 4 12
2-Dec-2018 SINKING IN PROGRESS 123.397 103.255 0.156 20.142 0 0 0 0
3-Dec-2018 no work 123.397 103.255 0 20.142 0 0 6 0
4-Dec-2018 SINKING IN PROGRESS 123.397 103.089 0.166 20.308 0 0 25 12
5-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 7th lift 0 0 17 12
6-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 7th lift 0 0 23 12
7-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 7th lift 0 0 25 12
8-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 7th lift 0 0 25 12
9-Dec-2018 NO WORK 123.397 0 0 0 0
10-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 7th lift 0 0 15 12
11-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 7th lift 0 0 17 12
12-Dec-2018 no work 123.397 0 0 0 0
13-Dec-2018 no work done material not available for casting123.397 0 0 0 0
14-Dec-2018 casting of WS 7th lift 123.397 0 0 25 12
15-Dec-2018 curing work 123.397 0 0 2 0
16-Dec-2018 deshuttering work 123.397 0 0 10 12
no skining during the days
17-Dec-2018 surface cleaming and coller fitting 123.397 0 0 10 12
18-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 8 12
19-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 8 12
20-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 8 12
21-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 8 12
22-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 25 12
23-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 25 12
24-Dec-2018 reinforcement & shuttering work in progress at 123.397
WS 8th lift 0 0 25 12
25-Dec-2018 casting at 8th lift 123.397 0 0 25 12
26-Dec-2018 casting at 8th lift 123.397 0 0 25 12
27-Dec-2018 deshuttering work 123.397 0 0 10 12
28-Dec-2018 deshuttering work 123.397 0 0 10 12
29-Dec-2018 SINKING IN PROGRESS 123.397 102.814 0.275 20.583 6 6 4 6
30-Dec-2018 NO WORK 123.397 0 0 0 0
no skining during the days
31-Dec-2018 no sinking work 123.397 0 0 0 0

1-Jan-2019 123.397 0 0 0 0
2-Jan-2019 123.397 0 0 0 0
3-Jan-2019 no sinking work CRANE IS NOT 123.397 0 0 0 0
AVAILABLE no skining during the days
4-Jan-2019 123.397 0 0 0 0
5-Jan-2019 123.397 0 0 0 0
6-Jan-2019 123.397 0 0 0 0
7-Jan-2019 SINKING IN PROGRESS 123.397 102.543 0.271 20.854 12 12 4 12
8-Jan-2019 SINKING IN PROGRESS 123.397 102.488 0.055 20.909 12 12 4 12
9-Jan-2019 SINKING IN PROGRESS 123.397 102.400 0.088 20.997 12 12 4 12
10-Jan-2019 SINKING IN PROGRESS 123.397 102.275 0.125 21.122 12 12 4 12
11-Jan-2019 SINKING IN PROGRESS 123.397 102.096 0.179 21.301 12 12 4 12
12-Jan-2019 SINKING IN PROGRESS 123.397 101.744 0.352 21.653 12 12 4 12
13-Jan-2019 no sinking work 123.397 101.744 0 21.653 0 0 0 0
14-Jan-2019 SINKING IN PROGRESS 123.397 101.382 0.362 22.015 10 10 4 10
15-Jan-2019 SINKING IN PROGRESS 123.397 101.270 0.112 22.127 12 12 4 12
16-Jan-2019 SINKING IN PROGRESS 123.397 101.229 0.041 22.168 12 12 4 12
17-Jan-2019 SINKING IN PROGRESS 123.397 101.131 0.098 22.266 12 12 4 12
18-Jan-2019 SINKING IN PROGRESS 123.397 100.932 0.199 22.465 12 12 4 12
19-Jan-2019 SINKING IN PROGRESS 123.397 100.830 0.102 22.567 12 12 4 12
20-Jan-2019 no sinking work 123.397 100.830 0 22.567 0 0 0 0
21-Jan-2019 SINKING IN PROGRESS 123.397 100.773 0.057 22.624 12 12 4 12
22-Jan-2019 SINKING IN PROGRESS 123.397 100.526 0.247 22.871 12 12 4 12
23-Jan-2019 SINKING IN PROGRESS 123.397 100.403 0.123 22.994 12 12 4 12
24-Jan-2019 SINKING IN PROGRESS 123.397 100.297 0.106 23.1 12 12 4 12
25-Jan-2019 SINKING IN PROGRESS 123.397 100.245 0.052 23.152 12 12 4 12
clay layer
26-Jan-2019 no work 123.397 100.245 0 23.152 0 0 0 0
27-Jan-2019 no work 123.397 100.245 0 23.152 0 0 0 0
28-Jan-2019 SINKING IN PROGRESS 123.397 100.135 0.11 23.262 12 12 4 12
29-Jan-2019 SINKING IN PROGRESS 123.397 100.102 0.033 23.295 12 12 4 12
30-Jan-2019 SINKING IN PROGRESS 123.397 100.053 0.049 23.344 12 12 4 12
31-Jan-2019 SINKING IN PROGRESS 123.397 100.001 0.052 23.396 12 12 4 12
1-Feb-2019 SINKING IN PROGRESS 123.397 99.925 0.076 23.472 12 12 4 12
2-Feb-2019 SINKING IN PROGRESS 123.397 99.856 0.069 23.541 12 12 4 12
3-Feb-2019 no work 123.397 99.856 0 23.541 0 0 0 0
4-Feb-2019 SINKING IN PROGRESS 123.397 99.691 0.165 23.706 12 12 4 12
5-Feb-2019 SINKING IN PROGRESS 123.397 99.594 0.097 23.803 12 12 4 12
6-Feb-2019 SINKING IN PROGRESS 123.397 99.498 0.096 23.899 12 12 4 12
7-Feb-2019 SINKING IN PROGRESS 123.397 99.377 0.121 24.02 12 12 4 12
8-Feb-2019 SINKING IN PROGRESS 123.397 99.265 0.112 24.132 12 12 4 12
9-Feb-2019 SINKING IN PROGRESS 123.397 99.143 0.122 24.254 12 12 4 12
10-Feb-2019 no work 123.397 99.143 0 24.254 0 0 0 0
11-Feb-2019 SINKING IN PROGRESS 123.397 98.971 0.172 24.426 12 12 4 12
12-Feb-2019 SINKING IN PROGRESS 123.397 98.858 0.113 24.539 12 12 4 12
13-Feb-2019 SINKING IN PROGRESS 123.397 98.796 0.062 24.601 12 12 4 12
14-Feb-2019 chiselling work 123.397 12 12 4 12
15-Feb-2019 chiselling work 123.397 12 12 4 12
16-Feb-2019 shuttering and reinforcement work at S9 123.397 0 0 21 12
17-Feb-2019 shuttering and reinforcement work at S9 123.397 0 0 15 12
18-Feb-2019 shuttering and reinforcement work at S9 123.397 0 0 25 12
19-Feb-2019 shuttering and reinforcement work at S9 123.397 0 0 25 12
20-Feb-2019 shuttering and reinforcement work at S9 123.397 0 0 25 12
21-Feb-2019 casting in progress at S9 123.397 0 0 25 12
22-Feb-2019 Curing work 123.397 0 0 1 12
23-Feb-2019 deshuttering work in progress 123.397 0 0 7 12
24-Feb-2019 deshuttering work in progress 123.397 0 0 7 12
25-Feb-2019 deshuttering work in progress 123.397 0 0 7 12
26-Feb-2019 no work 123.397 0 0 0 0
27-Feb-2019 SINKING IN PROGRESS 123.397 98.201 0.595 25.196 12 12 4 12
28-Feb-2019 SINKING IN PROGRESS 123.397 98.15 0.051 25.247 12 12 4 12
1-Mar-2019 SINKING IN PROGRESS 123.397 98.065 0.085 25.332 12 12 4 12
2-Mar-2019 SINKING IN PROGRESS 123.397 98.016 0.049 25.381 12 12 4 12
3-Mar-2019 No work 123.397 98.016 0.000 25.381 0 0 0 0
4-Mar-2019 SINKING IN PROGRESS 123.397 97.875 0.141 25.522 12 12 4 12
5-Mar-2019 SINKING IN PROGRESS 123.397 97.75 0.125 25.647 12 12 4 12
6-Mar-2019 SINKING IN PROGRESS 123.397 97.593 0.157 25.804 12 12 4 12
7-Mar-2019 SINKING IN PROGRESS 123.397 96.389 1.204 27.008 12 12 4 12
8-Mar-2019 SINKING IN PROGRESS 123.397 96.152 0.237 27.245 12 12 4 12
9-Mar-2019 SINKING IN PROGRESS 123.397 95.962 0.190 27.435 12 12 4 12
10-Mar-2019 No work 123.397 95.962 0.000 27.435 0 0 0 0
11-Mar-2019 SINKING IN PROGRESS 123.397 95.776 0.186 27.621 12 12 4 12
clay
12-Mar-2019 SINKING IN PROGRESS 123.397 95.523 0.253 27.874 12 12 4 12
13-Mar-2019 SINKING IN PROGRESS 123.397 95.322 0.201 28.075 12 12 4 12
14-Mar-2019 SINKING IN PROGRESS 123.397 95.092 0.230 28.305 12 12 4 12
15-Mar-2019 SINKING IN PROGRESS 123.397 94.602 0.490 28.795 12 12 4 12
16-Mar-2019 SINKING IN PROGRESS 123.397 94.115 0.487 29.282 6 6 4 6
17-Mar-2019 SINKING IN PROGRESS 123.397 93.965 0.150 29.432 12 12 4 12
18-Mar-2019 SINKING IN PROGRESS 123.397 93.636 0.329 29.761 12 12 4 12
19-Mar-2019 SINKING IN PROGRESS 123.397 93.568 0.068 29.829 12 12 4 12
20-Mar-2019 SINKING IN PROGRESS 123.397 93.501 0.067 29.896 12 12 4 12
21-Mar-2019 no work due to holi 123.397 93.501 0.000 29.896 0 0 0 0
22-Mar-2019 no work due to holi 123.397 93.501 0.000 29.896 0 0 0 0
23-Mar-2019 SINKING IN PROGRESS 123.397 93.11 0.391 30.287 12 12 4 12
24-Mar-2019 SINKING IN PROGRESS 123.397 93.002 0.108 30.395 12 12 4 12
25-Mar-2019 SOIL REMOVINGFROM WELL SIDE 123.397 0 0 0 0
26-Mar-2019 SOIL REMOVINGFROM WELL SIDE 123.397 0 0 0 0
27-Mar-2019 no work 123.397 0 0 0 0
28-Mar-2019 no work 123.397 0 0 0 0
29-Mar-2019 no work 123.397 0 0 0 0
30-Mar-2019 surface cleaning work 123.397 0 0 0 0
31-Mar-2019 surface cleaning work 123.397 0 0 0 0
1-Apr-2019 shuttering and reinforcement work at S10 123.397 0 0 8 12
2-Apr-2019 shuttering and reinforcement work at S10 123.397 0 0 9 12
3-Apr-2019 shuttering and reinforcement work at S10 123.397 0 0 12 12
4-Apr-2019 shuttering and reinforcement work at S10 123.397 0 0 13 12
5-Apr-2019 shuttering and reinforcement work at S10 123.397 0 0 13 12
6-Apr-2019 shuttering and reinforcement work at S10 123.397 0 0 18 12
7-Apr-2019 no work 123.397 0 0 0 12
8-Apr-2019 casting at S10 123.397 0 0 23 12
9-Apr-2019 casting at S10 123.397 0 0 23 12
10-Apr-2019 deshuttering work 123.397 0 0 4 12
11-Apr-2019 deshuttering work 123.397 0 0 4 12
12-Apr-2019 deshuttering work 123.397 0 0 5 12
13-Apr-2019 no work 123.397 0 0 0 0
14-Apr-2019 no work 123.397 0 0 0 0
15-Apr-2019 Sinking in progress 123.397 92.475 0.527 30.922 12 12 2 12
16-Apr-2019 Sinking in progress 123.397 92.352 0.123 31.045 12 12 2 12
17-Apr-2019 Sinking in progress 123.397 92.302 0.05 31.095 12 12 2 12
18-Apr-2019 Sinking in progress 123.397 92.258 0.044 31.139 12 12 2 12

CLAY
19-Apr-2019 Sinking in progress 123.397 92.232 0.026 31.165 12 12 2 12
20-Apr-2019 Sinking in progress 123.397 92.221 0.011 31.176 CLAY 12 12 2 12
21-Apr-2019 no work 123.397 92.221 0 31.176 0 0 0 0
22-Apr-2019 Sinking in progress 123.397 92.133 0.088 31.264 12 12 2 12
23-Apr-2019 Sinking in progress 123.397 92.006 0.127 31.391 12 12 2 12
24-Apr-2019 Sinking in progress 123.397 91.946 0.06 31.451 12 12 2 12
25-Apr-2019 Sinking in progress 123.397 91.937 0.009 31.46 12 12 2 12
26-Apr-2019 to 31-May-2019
1-Jun-2019 0 0 0 0
2-Jun-2019 0 0 0 0
3-Jun-2019 0 0 0 0
4-Jun-2019 0 0 0 0
5-Jun-2019 0 0 0 0
6-Jun-2019 no work 0 0 0 0
7-Jun-2019 0 0 0 0
8-Jun-2019 0 0 0 0
9-Jun-2019 0 0 0 0
10-Jun-2019 0 0 0 0
11-Jun-2019 0 0 0 0
12-Jun-2019 Sinking in progress 123.397 91.138 0.799 32.259 12 12 2 12
13-Jun-2019 Sinking in progress 123.397 91.066 0.072 32.331 12 12 2 12
14-Jun-2019 Sinking in progress 123.397 90.977 0.089 32.42 12 12 2 12
15-Jun-2019 Sinking in progress 123.397 90.9 0.077 32.497 12 12 2 12
16-Jun-2019 Sinking in progress 123.397 90.863 0.037 32.534 12 12 2 12
17-Jun-2019 Sinking in progress 123.397 90.786 0.077 32.611 12 12 2 12
18-Jun-2019 Sinking in progress 123.397 90.703 0.083 32.694 12 12 2 12
19-Jun-2019 no work 123.397 90.703 0 32.694 12 12 3 12
20-Jun-2019 Sinking in progress 123.397 90.663 0.04 32.734 12 12 3 12
21-Jun-2019 Sinking in progress 123.397 90.603 0.06 32.794 12 12 3 12
22-Jun-2019 Sinking in progress 123.397 90.561 0.042 32.836 12 12 3 12
23-Jun-2019 Sinking in progress 123.397 90.54 0.021 32.857 12 12 3 12
24-Jun-2019 Sinking in progress 123.397 90.531 0.009 32.866 12 12 3 12
25-Jun-2019 123.397 90.52 0.011 32.877 0 0 0 0
26-Jun-2019 123.397 90.505 0.015 32.892 0 0 0 0
27-Jun-2019 123.397 90.486 0.019 32.911 0 0 0 0
well sunk due to self weight
28-Jun-2019 123.397 90.468 0.018 32.929 0 0 0 0
29-Jun-2019 123.397 90.457 0.011 32.94 0 0 0 0
CLAY
30-Jun-2019 123.397 90.457 0 32.94 0 0 0 0
1-Jul-2019 no work (well sink due to self weight 123.397 90.44 0.017 32.957 0 0 0 0
2-Jul-2019 no work (well sink due to self weight 123.397 90.425 0.015 32.972 0 0 0 0
3-Jul-2019 no work (well sink due to self weight 123.397 90.421 0.004 32.976 0 0 0 0
4-Jul-2019 no work (well sink due to self weight 123.397 90.42 0.001 32.977 0 0 0 0
5-Jul-2019 no work (well sink due to self weight 123.397 90.412 0.008 32.985 0 0 0 0
6-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
7-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
8-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
9-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
10-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
11-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
12-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
13-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
14-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
15-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
16-Jul-2019 no work (well sink due to self weight 123.397 90.412 0 32.985 0 0 0 0
17-Jul-2019 no work (well sink due to self weight 123.397 90.395 0.017 33.002 0 0 0 0
18-Jul-2019 bottom plugging in progress 123.397 24 0 25 24
19-Jul-2019 bottom plugging in progress 123.397 24 0 25 24
20-Jul-2019 no work 123.397 0 0 0 0
21-Jul-2019 no work 123.397 0 0 0 0
22-Jul-2019 no work 123.397 0 0 0 0
23-Jul-2019 no work 123.397 0 0 0 0
24-Jul-2019 no work 123.397 0 0 0 0
25-Jul-2019 no work 123.397 0 0 0 0
26-Jul-2019 no work 123.397 0 0 0 0
27-Jul-2019 NO WROK DUE WATER LEVEL RISES 123.397 0 0 0 0
28-Jul-2019 NO WROK DUE WATER LEVEL RISES 123.397 0 0 0 0
29-Jul-2019 NO WROK DUE WATER LEVEL RISES 123.397 0 0 0 0
30-Jul-2019 NO WROK DUE WATER LEVEL RISES 123.397 0 0 0 0
31-Jul-2019 NO WROK DUE WATER LEVEL RISES 123.397 0 0 0 0
1-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
2-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
3-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
4-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
5-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
6-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
7-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
8-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
9-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
10-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
11-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
12-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
13-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
14-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
15-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
16-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
17-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
18-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
19-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
20-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
21-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
22-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
23-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
24-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
25-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
26-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
27-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
28-Aug-2019 NO WROK DUE WATER LEVEL RISES 123.397
29-Aug-2019 123.397
30-Aug-2019 123.397
31-Aug-2019
1-Sep-2019
2-Sep-2019
3-Sep-2019
summary of sinking and construction at P10
Machine & Man Power
RL OF CRANE 1 CRANE 2 LABOUR
BOTTOM OF SINKING CUMMULATI
CUTTING DURING A VE SINKING
DATE work details OGL EDGE DAY STRATA crane 1 hrs crane 2 hrs heads hrs
1-Sep-18 no work due to rain because welding is not possible and 124.677 0 0 0
2-Sep-18 chance of electicity failure in welding machine 124.677 0 0 0
3-Sep-18 fabrication of outer skin plate& making reinforcement 124.677 0 0 24 12
4-Sep-18 fabrication of outer skin plate& making reinforcement 124.677 0 0 27 12
5-Sep-18 fabrication of outer skin plate& making reinforcement 124.677 0 0 33 12
6-Sep-18 fabrication of outer skin plate& making reinforcement 124.677 0 0 36 12
7-Sep-18 fabrication of outer skin plate& making reinforcement 124.677 0 0 35 12
8-Sep-18 fabrication of outer skin plate& making reinforcement 124.677 0 0 36 12
9-Sep-18 reinforecement cutting and bending AT STEEL YARD 124.677 0 0 17 12
10-Sep-18 reinforecement cutting and bending AT STEEL YARD 124.677 0 0 13 12
11-Sep-18 reinforecement cutting and bending AT STEEL YARD 124.677 0 0 12 12
12-Sep-18 reinforecement cutting and bending AT STEEL YARD 124.677 0 0 12 12
13-Sep-18 reinforecement cutting and bending AT STEEL YARD 124.677 0 0 3 12
14-Sep-18 fabrication of inner skin plate 124.677 0 0 10 12
15-Sep-18 fabrication of inner skin plate 124.677 0 0 10 12
16-Sep-18 fabrication of inner skin plate 124.677 0 0 19 12
17-Sep-18 124.677 0 0 0 0
18-Sep-18 no work due to viswakarma puja 124.677 0 0 0 0
19-Sep-18 fabrication of cutting edge at site 124.677 0 0 17 12
20-Sep-18 fabrication of cutting edge at site 124.677 0 0 17 12
21-Sep-18 fabrication of cutting edge at site 124.677 No sinking during the days 0 0 17 12
22-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 33 12
23-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 39 12
24-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 39 12
25-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 41 12
26-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 38 12
27-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 40 12
28-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 40 12
29-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 40 12
30-Sep-18 reinforecement binding and fixing & fabrication work 124.677 0 0 20 12
124.677 0
1-Oct-18 reinforecement binding and fixing & fabrication work 124.677 0 0 26 12
2-Oct-18 reinforecement binding and fixing & fabrication work 124.677 0 0 20 12
3-Oct-18 reinforecement binding and fixing & fabrication work 124.677 0 0 26 12
4-Oct-18 reinforecement binding and fixing & fabrication work 124.677 0 0 23 12
5-Oct-18 casting in progress well curb 25
6-Oct-18 sinking prepation in progress (manual sinking ) 124.677 0 0 10 12
7-Oct-18 curing work 124.677 0 0 2 0
8-Oct-18 curing work 124.677 0 0 2 0
9-Oct-18 curing work 124.677 0 0 2 0
10-Oct-18 curing work 124.677 0 0 2 0
11-Oct-18 sinking started 124.677 124.387 0.29 0.29 12 12 5 12
12-Oct-18 sinking in progress 124.677 124.376 0.301 0.591 12 12 13 12
13-Oct-18 sinking in progress 124.677 124.623 0.054 0.645 12 12 13 12
14-Oct-18 sinking in progress 124.677 123.705 0.972 1.617
natural soil 12 12 12 12
15-Oct-18 sinking in progress 124.677 124.047 0.63 2.247 8 8 12 8
16-Oct-18 sinking in progress 124.677 123.732 0.945 3.192 8 8 5 8
17-Oct-18 124.677 0 0 0 0
18-Oct-18 124.677 0 0 0 0
19-Oct-18 124.677 0 0 0 0
20-Oct-18 124.677 0 0 0 0
21-Oct-18 124.677 0 0 0 0
22-Oct-18 124.677 0 0 0 0
23-Oct-18 124.677 0 0 0 0
24-Oct-18 124.677 0 0 0 0
25-Oct-18 NO WORK SHUTTERING GANG IS NOT PRESENT 124.677 0 0 0 0
26-Oct-18 124.677 0 0 0 0
27-Oct-18 124.677 0 0 0 0
28-Oct-18 124.677 0 0 0 0
29-Oct-18 124.677 0 0 0 0
30-Oct-18 124.677 0 0 0 0
31-Oct-18 124.677 0 0 0 0
1-Nov-18 124.677 0 0 0 0
2-Nov-18 124.677 0 0 0 0
3-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 15 12
4-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 10 12

NO SINKING
5-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 12 12
6-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 NO SINKING 0 0 12 12
7-Nov-18 diwali holiday 124.677 0 0 0 0
8-Nov-18 NO WORK SHUTTERING GANG IS NOT PRESENT 124.677 0 0 0 0
9-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 8 12
10-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 10 12
11-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 8 12
12-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 11 12
13-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 15 12
14-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 15 12
15-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 15 12
16-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 10 12
17-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 14 12
18-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 14 12
19-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 14 12
20-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 14 12
21-Nov-18 reinforcement & shuttering work in progress at WS 1st lift 124.677 0 0 18 12
22-Nov-18 casting in progress at 1st lift 124.677 0 0 21 20
23-Nov-18 curing work 124.677 0 0 3 0
24-Nov-18 deshuttering work 124.677 0 0 8 12
25-Nov-18 deshuttering work 124.677 0 0 7 12
26-Nov-18 SINKING IN PROGRESS 124.677 121.185 0.300 3.492 12 12 6 12
27-Nov-18 SINKING IN PROGRESS 124.677 119.087 2.088 5.58 natural soil & sand mix 12 12 6 12
28-Nov-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 15 12
29-Nov-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 15 12
30-Nov-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 15 12
1-Dec-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 15 12
2-Dec-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 15 12
3-Dec-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 20 12
4-Dec-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 27 12
5-Dec-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 25 12
6-Dec-18 correction work 124.677 no sinking 0 0 27 12
7-Dec-18 reinforcement & shuttering work in progress at WS 2ND lift 124.677 0 0 5 12
8-Dec-18 no work due to election 124.677 0 0 0 0
9-Dec-18 correction work 124.677 0 0 5 12
10-Dec-18 casting at 2nd lift WS 124.677 0 0 25 12
11-Dec-18 curing work 124.677 0 0 2 0
12-Dec-18 deshuttering work 124.677 0 0 5 12
13-Dec-18 deshuttering work 124.677 0 0 11 12
14-Dec-18 sinking in progress 124.677 117.973 1.124 6.704 12 12 4 12
15-Dec-18 sinking in progress 124.677 116.462 1.511 8.215 natural soil & sand mix 12 12 4 12
16-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 25 12
17-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 25 12
18-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 25 12
19-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 8 12
20-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 8 12
21-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 8 12
22-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 15 12
23-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 15 12
24-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 15 12
25-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 no sinking during the days 0 0 25 12
26-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 25 12
27-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 30 12
28-Dec-18 reinforcement & shuttering work in progress at WS 3rdlift 124.677 0 0 25 12
29-Dec-18 casting at 3RD WS lift 124.677 0 0 25 12
30-Dec-18 casting at 3RD WS lift 124.677 0 0 25 12
31-Dec-18 deshuttering work 124.677 0 0 10 12
1-Jan-19 curing work 124.677 0 0 6 12
2-Jan-19 deshuttering work of WS S3 124.677 0 0 6 12
3-Jan-19 deshuttering work of WS S3 124.677 0 0 6 12
4-Jan-19 deshuttering work of WS S3 124.677 116.12 0.342 8.557 12 12 4 12
5-Jan-19 sinking in progress 124.677 115.036 1.084 9.641 natural soil & 12 12 4 12
6-Jan-19 NO SINKING WORK 124.677 115.036 0 9.641 sand mix 0 0 0 0
7-Jan-19 SINKING IN PROGRESS 124.677 113.778 1.258 10.899 12 12 4 12
8-Jan-19 shuttering and reinforcement work at S4 WS 124.677 0 0 21 12
9-Jan-19 shuttering and reinforcement work at S4 WS 124.677 0 0 21 12
10-Jan-19 shuttering and reinforcement work at S4 WS 124.677 0 0 21 12
11-Jan-19 shuttering and reinforcement work at S4 WS 124.677 0 0 27 12
12-Jan-19 shuttering and reinforcement work at S4 WS 124.677 0 0 27 12
13-Jan-19 shuttering and reinforcement work at S4 WS 124.677 0 0 10 6
14-Jan-19 124.677 0 0 0 0

no sinking during the days


no casting shortage of sand
15-Jan-19 124.677 0 0 0 0
16-Jan-19 124.677 no sinking during the days 0 0 0 0
17-Jan-19 no casting shortage of sand 124.677 0 0 0 0
18-Jan-19 124.677 0 0 0 0
19-Jan-19 124.677 0 0 0 0
20-Jan-19 124.677 0 0 0 0
21-Jan-19 casting in progress S4 124.677 0 0 25 12
22-Jan-19 CURING WORK 124.677 0 0 0 0
23-Jan-19 Deshuttering in progress at P10 4th lift 124.677 0 0 9 12
24-Jan-19 Deshuttering in progress at P10 4th lift 124.677 0 0 9 12
25-Jan-19 sinking in progress 124.677 112.114 1.664 12.563 12 12 4 12
26-Jan-19 no work 124.677 112.114 0 12.563 0 0 0 0
27-Jan-19 sinking in progress 124.677 110.815 1.299 13.862 Sand 12 12 14 12
28-Jan-19 shuttering & reinforcement work in progress at 5th lift 124.677 0 0 32 12
29-Jan-19 shuttering & reinforcement work in progress at 5th lift 124.677 0 0 25 12
30-Jan-19 shuttering & reinforcement work in progress at 5th lift 124.677 0 0 25 12
31-Jan-19 casting in progress at S5 124.677 0 0 25 12
1-Feb-19 curing work 124.677 0 0 1 12
2-Feb-19 deshuttering work in progress 124.677 0 0 10 12
3-Feb-19 no work 124.677 0 0 0 0
4-Feb-19 deshuttering work in progress 124.677 no sinking during the days 0 0 6 12
5-Feb-19 sinking in progress 124.677 109.654 1.161 15.023 12 12 4 12
6-Feb-19 sinking in progress 124.677 108.849 0.805 15.828 Sand 12 12 4 12
7-Feb-19 sinking in progress 124.677 108.699 0.15 15.978 12 12 4 12
8-Feb-19 sinking in progress 124.677 108.473 0.226 16.204 12 12 4 12
9-Feb-19 sinking in progress 124.677 108.298 0.175 16.379 Clay 12 12 4 12
10-Feb-19 no work 124.677 0 0 0 0
11-Feb-19 Shuttering & reinfrocement work in Progress at S6 124.677 0 0 10 12
12-Feb-19 Shuttering & reinfrocement work in Progress at S6 124.677 0 0 15 12
13-Feb-19 Shuttering & reinfrocement work in Progress at S6 124.677 0 0 15 12
14-Feb-19 Shuttering & reinfrocement work in Progress at S6 124.677 0 0 15 12
15-Feb-19 Shuttering & reinfrocement work in Progress at S6 124.677 0 0 15 12
16-Feb-19 Casting in progress at S6 124.677 0 0 25 12
17-Feb-19 Casting in progress at S6 124.677 0 0 25 12
18-Feb-19 curing work 124.677 0 0 1 12
19-Feb-19 Deshuttering work 124.677 0 0 6 12
20-Feb-19 Deshuttering work 124.677 0 0 2 12
21-Feb-19 Deshuttering work 124.677 no sinking during the days 0 0 8 12
22-Feb-19 sinking in progress 124.677 107.805 0.493 16.872 12 12 4 12
23-Feb-19 sinking in progress 124.677 107.76 0.045 16.917 12 12 4 12
24-Feb-19 no work 124.677 107.76 0 16.917 0 0 0 0
25-Feb-19 sinking in progress 124.677 107.518 0.242 17.159 12 12 4 12
26-Feb-19 sinking in progress 124.677 107.231 0.287 17.446 Clay 12 12 4 12
27-Feb-19 sinking in progress 124.677 106.885 0.346 17.792 12 12 4 12
28-Feb-19 sinking in progress 124.677 106.568 0.317 18.109 12 12 4 12
1-Mar-19 SINKING IN PROGRESS 124.677 106.157 0.411 18.52 12 12 4 12
2-Mar-19 SINKING IN PROGRESS 124.677 105.797 0.36 18.88 12 12 4 12
3-Mar-19 No work 124.677 0 0 0 0
4-Mar-19 chissling work 124.677 12 0 1 12
5-Mar-19 124.677 0 0 0 0
6-Mar-19 124.677 0 0 0 0
7-Mar-19 124.677 0 0 0 0
8-Mar-19 124.677 0 0 0 0
9-Mar-19 No work since worker gang is not 124.677 0 0 0 0
10-Mar-19 availble 124.677 0 0 0 0
11-Mar-19 shuttering in progress 7th lift 124.677 0 0 25 12
12-Mar-19 shuttering in progress 7th lift 124.677 0 0 25 12
13-Mar-19 shuttering in progress 7th lift 124.677 0 0 25 12
14-Mar-19 shuttering in progress 7th lift 124.677 0 0 15 12
15-Mar-19 CASTING IN PROGRESS AT S7 124.677 0 0 25 12
16-Mar-19 casting complted at 10 AM 124.677 0 0 25 12
17-Mar-19 curing work 124.677 0 0 1 12
18-Mar-19 deshuttering work 124.677 0 0 5 12
19-Mar-19 deshuttering work 124.677 0 0 8 12
20-Mar-19 deshuttering work 124.677 0 0 8 12
21-Mar-19 no work due to holi 124.677 0 0 0 0
22-Mar-19 no work due to holi 124.677 0 0 0 0
23-Mar-19 deshuttering work 124.677 10 10 3 10
24-Mar-19 no work 124.677 no sinking during the days 0 0 0 0
25-Mar-19 SINKING IN PROGRESS 124.677 104.949 0.848 19.728 12 12 4 12
26-Mar-19 SINKING IN PROGRESS 124.677 104.923 0.026 19.754 12 12 3 12

Clay
27-Mar-19 SINKING IN PROGRESS 124.677 104.827 0.096 19.850 12 12 3 12
28-Mar-19 SINKING IN PROGRESS 124.677 104.762 0.065 19.915 12 12 3 12
29-Mar-19 SINKING IN PROGRESS 124.677 104.703 0.059 19.974 12 12 2 12
30-Mar-19 SINKING IN PROGRESS 124.677 104.244 0.459 20.433 Clay 12 12 2 12
31-Mar-19 SINKING IN PROGRESS 124.677 103.732 0.512 20.945 6 6 3 6
1-Apr-19 SINKING IN PROGRESS 124.677 103.587 0.145 21.090 12 12 4 12
2-Apr-19 SINKING IN PROGRESS 124.677 103.367 0.220 21.310 12 12 4 12
3-Apr-19 SINKING IN PROGRESS 124.677 103.025 0.342 21.652 12 12 4 12
4-Apr-19 SINKING IN PROGRESS 124.677 102.794 0.231 21.883 12 12 4
5-Apr-19 no work 124.677 0 0 0 0
6-Apr-19 no work 124.677 0 0 0 0
7-Apr-19 no work 124.677 0 0 0 0
8-Apr-19 no work 124.677 0 0 0 0
9-Apr-19 no work 124.677 0 0 0 0
10-Apr-19 no work 124.677 0 0 0 0
11-Apr-19 no work 124.677 0 0 0 0
12-Apr-19 no work 124.677 0 0 0 0
13-Apr-19 no work 124.677 0 0 0 0
14-Apr-19 no work 124.677 0 0 0 0
15-Apr-19 no work 124.677 0 0 0 0
no sinking during the days
16-Apr-19 no work 124.677 0 0 0 0
17-Apr-19 no work 124.677 0 0 0 0
18-Apr-19 no work 124.677 0 0 0 0
19-Apr-19 no work 124.677 0 0 0 0
20-Apr-19 no work 124.677 0 0 0 0
21-Apr-19 no work 124.677 0 0 0 0
22-Apr-19 no work 124.677 0 0 0 0
23-Apr-19 no work 124.677 0 0 0 0
24-Apr-19 no work 124.677 0 0 0 0
25-Apr-19 no work 124.677 0 0 0 0
26-Apr-19 no work 124.677 0 0 0 0

1-Jun-19 no work due to gang not available 124.677 0 0 0 0


2-Jun-19 no work due to gang not available 124.677 0 0 0 0
3-Jun-19 no work due to gang not available 124.677 0 0 0 0
4-Jun-19 no work due to gang not available 124.677 0 0 0 0
5-Jun-19 no work due to gang not available 124.677 0 0 0 0
6-Jun-19 no work due to gang not available 124.677 0 0 0 0
7-Jun-19 no work due to gang not available 124.677 0 0 0 0
8-Jun-19 no work due to gang not available 124.677 0 0 0 0
9-Jun-19 no work due to gang not available 124.677 0 0 0 0
10-Jun-19 no work due to gang not available 124.677 0 0 0 0
11-Jun-19 no work due to gang not available 124.677 0 0 0 0
12-Jun-19 no work due to gang not available 124.677 0 0 0 0
13-Jun-19 no work due to gang not available 124.677 0 0 0 0
14-Jun-19 no work due to gang not available 124.677 0 0 0 0
15-Jun-19 no work due to gang not available 124.677 0 0 0 0
16-Jun-19 no work due to gang not available 124.677 0 0 0 0
17-Jun-19 no work due to gang not available 124.677 0 0 0 0
18-Jun-19 no work due to gang not available 124.677 0 0 0 0
19-Jun-19 no work due to gang not available 124.677 0 0 0 0
20-Jun-19 no work due to gang not available 124.677 no sinking during the days 0 0 0 0
21-Jun-19 no work due to gang not available 124.677 0 0 0 0
22-Jun-19 no work due to gang not available 124.677 0 0 0 0
23-Jun-19 no work due to gang not available 124.677 0 0 0 0
24-Jun-19 no work due to gang not available 124.677 0 0 0 0
25-Jun-19 no work due to gang not available 124.677 0 0 0 0
26-Jun-19 no work due to gang not available 124.677 0 0 0 0
27-Jun-19 no work due to gang not available 124.677 0 0 0 0
28-Jun-19 Shuttering and reinforcement work at S8 124.677 0 0 15 12
29-Jun-19 Shuttering and reinforcement work at S8 124.677 0 0 15 12
30-Jun-19 no work 124.677 0 0 0 0
1-Jul-19 Shuttering and reinforcement work at S8 124.677 0 0 10 12
2-Jul-19 Shuttering and reinforcement work at S8 124.677 0 0 12 12
3-Jul-19 Shuttering and reinforcement work at S8 124.677 0 0 12 12
4-Jul-19 Shuttering and reinforcement work at S8 124.677 0 0 16 12
5-Jul-19 Shuttering and reinforcement work at S8 124.677 0 0 15 12
6-Jul-19 Shuttering and reinforcement work at S8 124.677 0 0 10 12
7-Jul-19 casting in progress for S8 124.677 0 0 25 12
8-Jul-19 casting in progress for S8 till 7 AM 124.677 0 0 25 12
9-Jul-19 deshuttering work in progress 124.677 0 0 15 12
10-Jul-19 sinking in progress 124.677 102.555 22.122 12 12 2 12
11-Jul-19 sinking in progress 124.677 102.404 0.151 22.273 12 12 2 12
12-Jul-19 sinking in progress 124.677 102.288 0.116 22.389 12 12 3 12
13-Jul-19 sinking in progress 124.677 102.15 0.138 22.527 12 12 3 12
clay layer
14-Jul-19 no work 124.677 102.15 0 22.527 0 0 0 0
15-Jul-19 sinking in progress 124.677 101.68 0.47 22.997 12 12 3 12
16-Jul-19 sinking in progress 124.677 101.477 0.203 23.2 12 12 3 12
17-Jul-19 sinking in progress 124.677 101.387 0.09 23.29 12 12 3 12
18-Jul-19 no work 124.677 0 0 0 0
19-Jul-19 no work 124.677 0 0 0 0
20-Jul-19 no work 124.677 0 0 0 0
21-Jul-19 no work 124.677 0 0 0 0
22-Jul-19 sinking in progress 124.677 101.164 0.223 23.513 12 12 2 12
23-Jul-19 sinking in progress 124.677 101.057 0.107 23.62 12 12 2 12
clay layer
24-Jul-19 sinking in progress 124.677 100.946 0.111 23.731 12 12 2 12
25-Jul-19 sinking in progress 124.677 100.805 0.141 23.872 12 12 2 12
26-Jul-19 no work 124.677 0 0 0 0
27-Jul-19 NO WROK DUE WATER LEVEL RISES 124.677 0 0 0 0
28-Jul-19 NO WROK DUE WATER LEVEL RISES 124.677 0 0 0 0
29-Jul-19 NO WROK DUE WATER LEVEL RISES 124.677 0 0 0 0
30-Jul-19 NO WROK DUE WATER LEVEL RISES 124.677 0 0 0 0
31-Jul-19 NO WROK DUE WATER LEVEL RISES 124.677 0 0 0 0
1-Aug-19 NO WROK DUE WATER LEVEL RISES 124.677 0 0 0 0
2-Aug-19 no work 124.677 0 0 0 0
3-Aug-19 no work 124.677 0 0 0 0
4-Aug-19 no work 124.677 0 0 0 0
5-Aug-19 Shuttering and reinforcement work at S9 124.677 12 12 10 12
6-Aug-19 Shuttering and reinforcement work at S9 124.677 12 12 10 12
7-Aug-19 Shuttering and reinforcement work at S9 124.677 12 12 10 12
8-Aug-19 Shuttering and reinforcement work at S9 124.677 12 12 10 12
9-Aug-19 Shuttering and reinforcement work at S9 124.677 12 12 10 12
10-Aug-19 Shuttering and reinforcement work at S9 124.677 12 12 10 12
11-Aug-19 no work 124.677 0 0 0 0
12-Aug-19 Shuttering and reinforcement work at S9 124.677 6 6 10 6
13-Aug-19 Shuttering and reinforcement work at S9 124.677 6 6 10 6
14-Aug-19 casting in progress for S9 124.677 12 12 20 12
15-Aug-19 casting in progress for S9 till 7 AM 124.677 7 7 20 7
16-Aug-19 124.677 0 0 0 0
17-Aug-19 124.677 0 0 0 0
18-Aug-19 124.677 0 0 0 0
19-Aug-19 124.677 0 0 0 0
no work since water rise in river
20-Aug-19 124.677 0 0 0 0
21-Aug-19 124.677 0 0 0 0
22-Aug-19 124.677 0 0 0 0
23-Aug-19 124.677 0 0 0 0
24-Aug-19 Deshuttering work in progress 124.677 12 12 5 12
25-Aug-19 124.677
26-Aug-19 124.677
27-Aug-19 124.677
Summary of sinking and construction at P11
Machine & Man Power
RL OF BOTTOM
OF CUTTING SINKING CUMMULATIVE CRANE 1 CRANE 2 LABOUR
DATE WORK DETAILS OGL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
10-Sep-2018 fabrication of cutting edge at fabrication yard 126.155 0 0 20 12
11-Sep-2018 fabrication of cutting edge at fabrication yard 126.155 0 0 20 12
12-Sep-2018 fabrication of cutting edge at fabrication yard 126.155 0 0 20 12
13-Sep-2018 fabrication of cutting edge at fabrication yard 126.155 0 0 20 12
14-Sep-2018 fabrication of cutting edge at fabrication yard 126.155 0 0 10 12
15-Sep-2018 fabrication of cutting edge at fabrication yard 126.155 0 0 10 12
16-Sep-2018 126.155 0 0 0 0
17-Sep-2018 126.155 0 0 0 0
18-Sep-2018 126.155 0 0 0 0
19-Sep-2018 126.155 0 0 0 0
20-Sep-2018 126.155 no sinkng during the day 0 0 0 0
21-Sep-2018 No Activity 126.155 0 0 0 0
22-Sep-2018 126.155 0 0 0 0
23-Sep-2018 126.155 0 0 0 0
24-Sep-2018 126.155 0 0 0 0
25-Sep-2018 126.155 0 0 0 0
26-Sep-2018 cutting edge shift to site both circular part 126.155 0 0 4 12
27-Sep-2018 126.155 0 0 0 0
28-Sep-2018 126.155 0 0 0 0
29-Sep-2018 NO activity 126.155 0 0 0 0
30-Sep-2018 126.155 0 0 0 0

1-Oct-2018 DRILLING OF P11 CUTTING edge 126.155 0 0 7 12


2-Oct-2018 DRILLING OF P11 CUTTING edge 126.155 0 0 18 12
3-Oct-2018 DRILLING OF P11 CUTTING edge 126.155 0 0 12 12
4-Oct-2018 welding of bent plate at site 126.155 0 0 15 12
5-Oct-2018 setting out of cutting edge on location 126.155 0 0 14 12
6-Oct-2018 welding and alignment of cutting edge 126.155 0 0 16 12
7-Oct-2018 bracket fixing on cutting edge 126.155 0 0 20 12
8-Oct-2018 bracket fixing on cutting edge 126.155 0 0 19 12
9-Oct-2018 bracket fixing on cutting edge 126.155 0 0 20 12
10-Oct-2018 no work due to local land problem 126.155 0 0 0 0
11-Oct-2018 bracket fixing on cutting edge 126.155 0 0 16 12
12-Oct-2018 bracket fixing on cutting edge 126.155 0 0 19 12
13-Oct-2018 no work due to local land problem 126.155 0 0 0 0
14-Oct-2018 bracket fixing on cutting edge 126.155 0 0 15 12
15-Oct-2018 outer skin plate fixing 126.155 0 0 15 12
16-Oct-2018 outer skin plate fixing 126.155 no sinkng during the day 0 0 18 12
17-Oct-2018 outer skin plate fixing 126.155 0 0 16 12
18-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
19-Oct-2018 no work desherra holiday 126.155 0 0 0 0
20-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
21-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
22-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
23-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
24-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
25-Oct-2018 outer skin plate fixing 126.155 0 0 10 12
26-Oct-2018 bracket repairing work and welding work 126.155 0 0 10 12
27-Oct-2018 bracket repairing work and welding work 126.155 0 0 10 12
28-Oct-2018 skin plate welding work 126.155 0 0 10 12
29-Oct-2018 skin plate welding work 126.155 0 0 10 12
30-Oct-2018 skin plate fixing work 126.155 0 0 19 12
31-Oct-2018 skin plate fixing work 126.155 0 0 19 12

1-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12


2-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
3-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
4-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
5-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
6-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
7-Nov-2018 diwali holiday 126.155 0 0 0 0
8-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
9-Nov-2018 inner skin plate fixing work 126.155 0 0 18 12
10-Nov-2018 inner skin plate fixing work 126.155 0 0 19 12
11-Nov-2018 inner skin plate fixing work 126.155 0 0 18 12
12-Nov-2018 inner skin plate fixing work 126.155 0 0 18 12
13-Nov-2018 inner skin plate fixing work 126.155 0 0 18 12
14-Nov-2018 inner skin plate fixing work 126.155 0 0 17 12
15-Nov-2018 welding of inner plate 126.155 0 0 15 12
16-Nov-2018 welding of inner plate 126.155 0 0 15 12
17-Nov-2018 welding of inner plate 126.155 0 0 15 12
18-Nov-2018 no work 126.155 0 0 0 12
19-Nov-2018 welding of inner plate 126.155 0 0 10 12
20-Nov-2018 welding of inner plate 126.155 0 0 10 12
21-Nov-2018 welding of inner plate 126.155 0 0 17 12
22-Nov-2018 welding of inner plate 126.155 0 0 5 12
23-Nov-2018 welding of inner plate 126.155 0 0 6 12
24-Nov-2018 welding of inner plate 126.155
no sinkng during the day 0 0 8 12
25-Nov-2018 no work 126.155 0 0 0 12
26-Nov-2018 welding &reinforcement fxing in progress 126.155 0 0 12 12
no sinkng during the day

27-Nov-2018 welding &reinforcement fxing in progress 126.155 0 0 12 12


28-Nov-2018 reinforcement fixing and binding work in well curb 126.155 0 0 20 12
29-Nov-2018 reinforcement fixing and binding work in well curb 126.155 0 0 20 12
30-Nov-2018 reinforcement fixing and binding work in well curb 126.155 0 0 20 12
1-Dec-2018 reinforcement fixing and binding work in well curb 126.155 0 0 20 12
2-Dec-2018 no work 126.155 0 0 0 0
3-Dec-2018 reinforcement fixing and binding work in well curb 126.155 0 0 25 12
4-Dec-2018 reinforcement fixing and binding work in well curb 126.155 0 0 23 12
5-Dec-2018 reinforcement fixing and binding work in well curb 126.155 0 0 25 12
6-Dec-2018 reinforcement fixing and binding work in well curb 126.155 0 0 25 12
7-Dec-2018 reinforcement fixing and binding work in well curb 126.155 0 0 10 12
8-Dec-2018 correction work 126.155 0 0 2 12
9-Dec-2018 correction work 126.155 0 0 3 12
10-Dec-2018 correction work 126.155 0 0 2 12
11-Dec-2018 no work 126.155 0 0 0 0
12-Dec-2018 casting of well curb 126.155 0 0 45 12
13-Dec-2018 curing work 126.155 0 0 4 0
14-Dec-2018 curing work 126.155 0 0 2 0
15-Dec-2018 curing work 126.155 0 0 2 12
16-Dec-2018 curing work 126.155 0 0 2 12
17-Dec-2018 sinking started 126.155 125.835 0.32 0.32 12 12 10 12
18-Dec-2018 sinking in progress 126.155 125.356 0.479 0.799 12 12 10 12
19-Dec-2018 sinking in progress 126.155 124.665 0.691 1.49 natural soil 12 12 4 12
20-Dec-2018 sinking in progress 126.155 123.935 0.73 2.22 12 12 4 12
21-Dec-2018 sinking in progress 126.155 122.725 1.21 3.43 12 12 4 12
22-Dec-2018 126.155 0 0 0 0
23-Dec-2018 126.155 0 0 0 0
24-Dec-2018 126.155 0 0 0 0
NO WORK
25-Dec-2018 126.155 0 0 0 0
26-Dec-2018 126.155 0 0 0 0
no sinkng during the day
27-Dec-2018 126.155 0 0 0 0
28-Dec-2018 shuttering work started 126.155 0 0 17 12
29-Dec-2018 reinforcement & shuttering work in progress at WS 1st lift 126.155 0 0 15 12
30-Dec-2018 reinforcement & shuttering work in progress at WS 1st lift 126.155 0 0 17 12
31-Dec-2018 reinforcement & shuttering work in progress at WS 1st lift 126.155 0 0 0 12

1-Jan-2019 no work 126.155 0 0 0 0


2-Jan-2019 shuttering and reinforcement work at WS S1 126.155 0 0 10 12
3-Jan-2019 shuttering and reinforcement work at WS S1 126.155 0 0 10 12
4-Jan-2019 shuttering and reinforcement work at WS S1 126.155 0 0 10 12
5-Jan-2019 shuttering and reinforcement work at WS S1 126.155 0 0 10 12
6-Jan-2019 shuttering and reinforcement work at WS S1 126.155 0 0 15 12
7-Jan-2019 shuttering and reinforcement work at WS S1 126.155 no sinkng during the day 0 0 15 12
8-Jan-2019 casting in progress at 1st lift WS 126.155 0 0 25 12
9-Jan-2019 casting in progress at 1st lift WS 126.155 0 0 25 12
10-Jan-2019 curing work 126.155 0 0 2 12
11-Jan-2019 deshuttering work 126.155 0 0 10 12
12-Jan-2019 deshuttering work 126.155 0 0 10 12
13-Jan-2019 curing work 126.155 0 0 1 0
14-Jan-2019 sinking in progress 126.155 122.409 0.316 3.746 10 10 4 10
15-Jan-2019 sinking in progress 126.155 121.28 1.129 4.875 natural soil 12 12 4 12
16-Jan-2019 sinking in progress 126.155 120.457 0.823 5.698 12 12 4 12
17-Jan-2019 no work 126.155 0 0 0 0
18-Jan-2019 no work 126.155 0 0 0 0
19-Jan-2019 shuttering and reinforcement work at WS S2 126.155 0 0 10 12
20-Jan-2019 no work 126.155 0 0 0 0
21-Jan-2019 shuttering and reinforcement work at WS S2 126.155 0 0 25 12
22-Jan-2019 shuttering and reinforcement work at WS S2 126.155 0 0 25 12
23-Jan-2019 shuttering and reinforcement work at WS S2 126.155 0 0 25 12
24-Jan-2019 shuttering and reinforcement work at WS S2 126.155 no sinkng during the day 0 0 25 12
25-Jan-2019 shuttering and reinforcement work at WS S2 126.155 0 0 25 12
26-Jan-2019 no work 126.155 0 0 0 0
27-Jan-2019 shuttering and reinforcement work at WS S2 126.155 0 0 25 12
28-Jan-2019 casting in progress at 2nd lift 126.155 0 0 25 12
29-Jan-2019 curing work 126.155 0 0 10 12
30-Jan-2019 curing work 126.155 0 0 2 12
31-Jan-2019 deshuttering work in progress 126.155 0 0 10 12
1-Feb-2019 sinking in progress 126.155 117.895 2.562 8.26 12 12 4 12
2-Feb-2019 sinking in progress 126.155 117.35 0.545 8.805 sand 12 12 4 12
3-Feb-2019 126.155 0 0 0 0
4-Feb-2019 no work 126.155 0 0 0 0
5-Feb-2019 shuttering and reinforcement work S3 126.155 0 0 5 12
6-Feb-2019 shuttering and reinforcement work S3 126.155 0 0 10 12
7-Feb-2019 shuttering and reinforcement work S3 126.155 0 0 20 12
8-Feb-2019 shuttering and reinforcement work S3 126.155 0 0 20 12
no sinkng during the day
9-Feb-2019 shuttering and reinforcement work S3 126.155 0 0 20 12
10-Feb-2019 shuttering and reinforcement work S3 126.155 0 0 10 12
11-Feb-2019 casting in progress S3 126.155 0 0 25 12
12-Feb-2019 curing work 126.155 0 0 1 12
13-Feb-2019 deshuttering work in progress 126.155 0 0 6 12
14-Feb-2019 deshuttering work in progress 126.155 0 0 6 12
15-Feb-2019 sinking in progress 126.155 116.716 0.634 9.439 12 12 4 12
16-Feb-2019 sinking in progress 126.155 114.565 2.151 11.59 sand 12 12 4 12
17-Feb-2019 shuttering in progress 4th lift 126.155 0 0 15 12

no sinkng during the day


18-Feb-2019 shuttering in progress 4th lift 126.155 0 0 18 12
19-Feb-2019 shuttering in progress 4th lift 126.155 0 0 18 12
20-Feb-2019 shuttering in progress 4th lift 126.155 0 0 18 12
21-Feb-2019 shuttering in progress 4th lift 126.155 0 0 18 12
22-Feb-2019 shuttering in progress 4th lift 126.155 no sinkng during the day 0 0 18 12
23-Feb-2019 casting in progress at S4 126.155 0 0 25 12
24-Feb-2019 curing work 126.155 0 0 1 12
25-Feb-2019 deshuttering work in progress 126.155 0 0 10 12
26-Feb-2019 deshuttering work in progress 126.155 0 0 10 12
27-Feb-2019 deshuttering work in progress 126.155 0 0 10 12
28-Feb-2019 sinking in progress 126.155 114.076 0.489 12.079 12 12 4 12
1-Mar-2019 SINKING IN PROGRESS 126.155 112.944 1.132 13.211 12 12 4 12
2-Mar-2019 SINKING IN PROGRESS 126.155 112.236 0.708 13.919 sand 0 12 4 12
3-Mar-2019 No work 126.155 0 0 0 0
4-Mar-2019 No work 126.155 0 0 0 0
5-Mar-2019 shuttering in progress 5th lift 126.155 0 0 8 12
6-Mar-2019 shuttering in progress 5th lift 126.155 0 0 15 12
7-Mar-2019 shuttering in progress 5th lift 126.155 0 0 20 12
8-Mar-2019 shuttering in progress 5th lift 126.155 0 0 20 12
9-Mar-2019 shuttering in progress 5th lift 126.155 0 0 20 12
no sinkng during the day
10-Mar-2019 shuttering in progress 5th lift 126.155 0 0 5 12
11-Mar-2019 casting in progress at S5 126.155 0 0 25 12
12-Mar-2019 CURING 126.155 0 0 1 12
13-Mar-2019 deshuttering work 126.155 0 0 5 12
14-Mar-2019 deshuttering work 126.155 0 0 10 12
15-Mar-2019 deshuttering work 126.155 0 0 8 12
16-Mar-2019 deshuttering work 126.155 0 0 4 12
17-Mar-2019 SINKING IN PROGRESS 126.155 110.523 1.713 15.632 12 12 4 12
18-Mar-2019 SINKING IN PROGRESS 126.155 109.959 0.564 16.196 sand 12 12 4 12
19-Mar-2019 SINKING IN PROGRESS 126.155 109.712 0.247 16.443 12 12 4 12
clay
20-Mar-2019 SINKING IN PROGRESS 126.155 109.583 0.129 16.572 12 12 4 12
21-Mar-2019 no work due to holi 126.155 0 0 0 0
22-Mar-2019 shuttering in progress 6th lift 126.155 0 0 16 12
23-Mar-2019 shuttering in progress 6th lift 126.155 0 0 16 12
24-Mar-2019 no work 126.155 0 0 0 0
25-Mar-2019 shuttering in progress 6th lift 126.155 0 0 14 12
26-Mar-2019 shuttering in progress 6th lift 126.155 0 0 15 12
27-Mar-2019 shuttering in progress 6th lift 126.155 0 0 14 12
28-Mar-2019 shuttering in progress 6th lift 126.155 0 0 14 12
no sinkng during the day
29-Mar-2019 casting in progress at S6 126.155 0 0 25 12
30-Mar-2019 curing work 126.155 0 0 1 10
31-Mar-2019 curing work 126.155 0 0 1 10
1-Apr-2019 deshuttering work at S6 126.155 0 0 12 12
2-Apr-2019 deshuttering work at S6 126.155 0 0 10 12
3-Apr-2019 curing work 126.155 0 0 1 10
4-Apr-2019 no work 126.155 0 0 0 0
5-Apr-2019 no work 126.155 0 0 0 0
6-Apr-2019 SINKING IN PROGRESS 126.155 109.4 0.183 16.755 12 12 3 12
7-Apr-2019 no work 126.155 0 0 0 0
8-Apr-2019 SINKING IN PROGRESS 126.155 109.364 0.036 16.791 12 12 2 12
9-Apr-2019 no work 126.155 0 0 0 0
10-Apr-2019 SINKING IN PROGRESS 126.155 109.319 0.045 16.836 12 12 3 12
11-Apr-2019 SINKING IN PROGRESS 126.155 109.286 0.033 16.869 12 12 3 12
12-Apr-2019 SINKING IN PROGRESS 126.155 109.22 0.066 16.935 clay 12 12 4 12
13-Apr-2019 SINKING IN PROGRESS 126.155 109.144 0.076 17.011 12 12 4 12
14-Apr-2019 no work 126.155 109.144 0 17.011 0 0 0 0
15-Apr-2019 SINKING IN PROGRESS 126.155 108.939 0.205 17.216 12 12 3 12
16-Apr-2019 SINKING IN PROGRESS 126.155 108.824 0.115 17.331 12 12 2 12
17-Apr-2019 SINKING IN PROGRESS 126.155 108.724 0.1 17.431 12 12 2 12
18-Apr-2019 SINKING IN PROGRESS 126.155 108.629 0.095 17.526 12 12 2 12
19-Apr-2019 no work 126.155 0 0 0 0
20-Apr-2019 no work 126.155 0 0 0 0
21-Apr-2019 no work 126.155 0 0 0 0
22-Apr-2019 no work 126.155 0 0 0 0
23-Apr-2019 no work 126.155 0 0 0 0
24-Apr-2019 no work 126.155 0 0 0 0
25-Apr-2019 no work 126.155 0 0 0 0

1-Jun-2019 no work 126.155 0 0 0 0


2-Jun-2019 no work 126.155 0 0 0 0
3-Jun-2019 no work 126.155 0 0 0 0
4-Jun-2019 no work 126.155 0 0 0 0
5-Jun-2019 no work 126.155 0 0 0 0
6-Jun-2019 no work 126.155 0 0 0 0
7-Jun-2019 no work 126.155 0 0 0 0
8-Jun-2019 no work 126.155 0 0 0 0
9-Jun-2019 no work 126.155 0 0 0 0
10-Jun-2019 no work 126.155 0 0 0 0
11-Jun-2019 no work 126.155 0 0 0 0
12-Jun-2019 no work 126.155 0 0 0 0
13-Jun-2019 no work 126.155 0 0 0 0
14-Jun-2019 no work 126.155 0 0 0 0
15-Jun-2019 SINKING IN PROGRESS 126.155 108.043 0.586 18.112 12 12 2 12
16-Jun-2019 SINKING IN PROGRESS 126.155 108.009 0.034 18.146 12 12 2 12

clay
17-Jun-2019 SINKING IN PROGRESS 126.155 107.993 0.016 18.162 12 12 2 12
18-Jun-2019 SINKING IN PROGRESS 126.155 107.905 0.088 18.25 12 12 2 12
19-Jun-2019 no work 126.155 107.905 0 18.25 0 0 0 0
20-Jun-2019 SINKING IN PROGRESS 126.155 107.792 0.113 18.363 12 12 3 12
21-Jun-2019 SINKING IN PROGRESS 126.155 107.732 0.060 18.423 12 12 3 12
22-Jun-2019 SINKING IN PROGRESS 126.155 107.634 0.098 18.521 12 12 3 12
23-Jun-2019 SINKING IN PROGRESS 126.155 107.553 0.081 18.602 12 12 3 12
clay
24-Jun-2019 SINKING IN PROGRESS 126.155 107.417 0.136 18.738 12 12 3 12
25-Jun-2019 SINKING IN PROGRESS 126.155 107.3 0.117 18.855 12 12 3 12
26-Jun-2019 SINKING IN PROGRESS 126.155 107.189 0.111 18.966 12 12 3 12
27-Jun-2019 SINKING IN PROGRESS 126.155 107.048 0.141 19.107 12 12 3 12
28-Jun-2019 SINKING IN PROGRESS 126.155 106.893 0.155 19.262 12 12 3 12
29-Jun-2019 SINKING IN PROGRESS 126.155 106.769 0.124 19.386 12 12 3 12
30-Jun-2019 no work 126.155 106.769 0.000 19.386 0 0 0 0

1-Jul-2019 SINKING IN PROGRESS 126.155 106.663 0.106 19.492 12 12 3 12


2-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 15 12
3-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 15 12
4-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 15 12
5-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 15 12
6-Jul-2019 no work 126.155 0 0 0 0
7-Jul-2019 no work 126.155 0 0 0 0
8-Jul-2019 no work 126.155 0 0 0 0
9-Jul-2019 no work 126.155 0 0 0 0
10-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 8 12
11-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 8 12
12-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 8 12
13-Jul-2019 Shuttering and reinforcement work in progress at S7 126.155 0 0 10 12
14-Jul-2019 no work 126.155 0 0 0 0
15-Jul-2019 casting in progress at S7 126.155 0 0 25 12
16-Jul-2019 curing work 126.155 No sinking this days 0 0 1 12
17-Jul-2019 deshuttering work in progress 126.155 0 0 5 12
18-Jul-2019 deshuttering work in progress 126.155 0 0 7 12
19-Jul-2019 deshuttering work in progress 126.155 0 0 5 12
20-Jul-2019 deshuttering work in progress 126.155 0 0 5 12
21-Jul-2019 no work 126.155 0 0 0 12
22-Jul-2019 no work 126.155 0 0 0 12
23-Jul-2019 no work 126.155 0 0 0 12
24-Jul-2019 no work 126.155 0 0 0 12
25-Jul-2019 no work 126.155 0 0 0 0
26-Jul-2019 no work 126.155 0 0 0 0
27-Jul-2019 no work 126.155 0 0 0 0
28-Jul-2019 no work 126.155 0 0 0 0
29-Jul-2019 no work 126.155 0 0 0 0
30-Jul-2019 no work 126.155 0 0 0 0
31-Jul-2019 Sinking in progress 126.155 106.185 0.478 19.97 12 12 2 12

1-Aug-2019 Sinking in progress 126.155 106.107 0.078 20.048 12 12 2 12


2-Aug-2019 Sinking in progress 126.155 106.015 0.092 20.14 12 12 2 12
3-Aug-2019 Sinking in progress 126.155 105.835 0.18 20.32 12 12 2 12
4-Aug-2019 no work 126.155 105.835 0 20.32 0 0 0 0
5-Aug-2019 Sinking in progress 126.155 105.624 0.211 20.531 12 12 2 12
6-Aug-2019 Sinking in progress 126.155 105.543 0.081 20.612 12 12 2 12
clay
7-Aug-2019 Sinking in progress 126.155 105.499 0.044 20.656 12 12 2 12
8-Aug-2019 Sinking in progress 126.155 105.459 0.04 20.696 12 12 2 12
9-Aug-2019 Sinking in progress 126.155 105.406 0.053 20.749 12 12 2 12
10-Aug-2019 Sinking in progress 126.155 105.333 0.073 20.822 12 12 2 12
11-Aug-2019 no work 126.155 105.333 0 20.822 0 0 0 0
12-Aug-2019 Sinking in progress 126.155 105.105 0.228 21.05 12 12 2 12
13-Aug-2019 Sinking in progress 126.155 105.095 0.01 21.06 12 12 2 12
14-Aug-2019 Sinking in progress 126.155 105.08 0.015 21.075 12 12 2 12
15-Aug-2019 126.155 0 0 0 0
16-Aug-2019 126.155 0 0 0 0
17-Aug-2019 126.155 0 0 0 0
18-Aug-2019 no work since water rise in river 126.155 No sinking this days 0 0 0 0
19-Aug-2019 126.155 0 0 0 0
20-Aug-2019 126.155 0 0 0 0
21-Aug-2019 126.155 0 0 0 0
22-Aug-2019 Sinking in progress 126.155 105.072 0.008 21.083 12 12 2 12
23-Aug-2019 Sinking in progress 126.155 105.04 0.032 21.115 12 12 2 12
24-Aug-2019 Sinking in progress 126.155 105.04 0 21.115 clay 12 12 2 12
25-Aug-2019 no work 126.155 105.04 0 21.115
26-Aug-2019 Sinking in progress 126.155 105.04 0 21.115
27-Aug-2019 surface cleaning in progress for next lift 126.155
28-Aug-2019
29-Aug-2019
30-Aug-2019
31-Aug-2019
Summary of sinking and construction at P12
Machine & Man Power
RL OF BOTTOM
OF CUTTING SINKING CUMMULATIVE CRANE 1 CRANE 2 LABOUR
DATE WORK DETAILS OGL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
24- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 12 12
25- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 12 12
26- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 12 12
27- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 12 12
28- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 12 12
29- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 8 12
30- Dec-18 ISA 150*150*16 Fabrication 128.043 0 0 8 12
31- Dec-18 no work 128.043 0 0 0 0

01- Jan-19 128.043 0 0 0 0


02- Jan-19 128.043 0 0 0 0
03- Jan-19 no work 128.043 0 0 0 0
04- Jan-19 128.043 0 0 0 0
05- Jan-19 128.043 0 0 0 0
06- Jan-19 fabrication work of cutting edge 128.043 0 0 2 12
07- Jan-19 fabrication work of cutting edge 128.043 0 0 2 12
08- Jan-19 fabrication work of cutting edge 128.043 0 0 2 12
09- Jan-19 fabrication work of cutting edge 128.043 0 0 4 12
10- Jan-19 fabrication work of cutting edge 128.043 0 0 4 12
11- Jan-19 fabrication work of cutting edge 128.043 0 0 4 12
12- Jan-19 fabrication work of cutting edge 128.043 0 0 4 12
13- Jan-19 fabrication work of cutting edge 128.043 0 0 4 12
14- Jan-19 fabrication work of cutting edge 128.043 0 0 8 12
15- Jan-19 fabrication work of cutting edge 128.043 0 0 8 12
16- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
17- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
18- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
19- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
20- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
21- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
22- Jan-19 fabrication work of cutting edge 128.043 0 0 10 12
23- Jan-19 128.043 0 0 0 0
24- Jan-19 128.043 0 0 0 0
25- Jan-19 128.043 0 0 0 0
26- Jan-19 128.043 0 0 0 0
27- Jan-19 no work 128.043 0 0 0 0
28- Jan-19 128.043 0 0 0 0
29- Jan-19 128.043 0 0 0 0
30- Jan-19 128.043 0 0 0 0
31- Jan-19 128.043 0 0 0 0

01- Feb-19 128.043 0 0 0 0


02- Feb-19 128.043 0 0 0 0
03- Feb-19 128.043 0 0 0 0
04- Feb-19 128.043 0 0 0 0
05- Feb-19 128.043 0 0 0 0
06- Feb-19 128.043 0 0 0 0
07- Feb-19 128.043 0 0 0 0
08- Feb-19 128.043 0 0 0 0
09- Feb-19 128.043 0 0 0 0
10- Feb-19 128.043 0 0 0 0
11- Feb-19 128.043 0 0 0 0
12- Feb-19 128.043 0 0 0 0
13- Feb-19 128.043 0 0 0 0
14- Feb-19 128.043 0 0 0 0
no work
15- Feb-19 128.043 0 0 0 0
16- Feb-19 128.043 0 0 0 0
17- Feb-19 128.043 0 0 0 0
18- Feb-19 128.043 0 0 0 0
19- Feb-19 128.043 0 0 0 0
20- Feb-19 128.043 0 0 0 0
21- Feb-19 128.043 0 0 0 0
22- Feb-19 128.043 0 0 0 0
23- Feb-19 128.043 0 0 0 0
24- Feb-19 128.043 0 0 0 0
25- Feb-19 128.043 0 0 0 0
26- Feb-19 128.043 0 0 0 0
27- Feb-19 128.043 0 0 0 0
28- Feb-19 128.043 0 0 0 0

01- Mar-19 No work since gang is not available 128.043 0 0 0 0


02- Mar-19 No work since gang is not available 128.043 0 0 0 0
03- Mar-19 No work since gang is not available 128.043 0 0 0 0
04- Mar-19 No work since gang is not available 128.043 0 0 0 0
05- Mar-19 No work since gang is not available 128.043 0 0 0 0
06- Mar-19 No work since gang is not available 128.043 0 0 0 0
07- Mar-19 No work since gang is not available 128.043 0 0 0 0
08- Mar-19 No work since gang is not available 128.043 0 0 0 0
09- Mar-19 No work since gang is not available 128.043 0 0 0 0
10- Mar-19 No work since gang is not available 128.043 0 0 0 0
11- Mar-19 No work since gang is not available 128.043 0 0 0 0
12- Mar-19 No work since gang is not available 128.043 0 0 0 0
13- Mar-19 No work since gang is not available 128.043 0 0 0 0
14- Mar-19 No work since gang is not available 128.043 0 0 0 0
15- Mar-19 No work since gang is not available 128.043 0 0 0 0
16- Mar-19 No work since gang is not available 128.043 0 0 0 0
17- Mar-19 No work since gang is not available 128.043 0 0 0 0
18- Mar-19 No work since gang is not available 128.043 0 0 0 0
19- Mar-19 No work since gang is not available 128.043 0 0 0 0
20- Mar-19 No work since gang is not available 128.043 0 0 0 0
21- Mar-19 No work since gang is not available 128.043 0 0 0 0
22- Mar-19 No work since gang is not available 128.043 0 0 0 0
23- Mar-19 No work since gang is not available 128.043 0 0 0 0
24- Mar-19 No work since gang is not available 128.043 0 0 0 0
25- Mar-19 No work since gang is not available 128.043 0 0 0 0
26- Mar-19 No work since gang is not available 128.043 0 0 0 0
27- Mar-19 No work since gang is not available 128.043 0 0 0 0
28- Mar-19 No work since gang is not available 128.043 0 0 0 0
29- Mar-19 No work since gang is not available 128.043 0 0 0 0
30- Mar-19 No work since gang is not available 128.043 0 0 0 0
31- Mar-19 GROUND LEVELING WORK 128.043 0 0 2 0

01- Apr-19 LAYOUT OF CUTTING EDGE 128.043 0 0 2 12


02- Apr-19 cutting edge shifted to site 128.043 0 0 5 12
03- Apr-19 no work 128.043 0 0 0 0
04- Apr-19 no work 128.043 0 0 0 0
05- Apr-19 no work 128.043 0 0 0 0
06- Apr-19 cutting edge placing wrok 128.043 0 0 13 12
07- Apr-19 no work 128.043 0 0 0 0
08- Apr-19 cutting edge parts assemblly work 128.043 0 0 22 12
09- Apr-19 cutting edge parts assemblly work 128.043 0 0 22 12
10- Apr-19 cutting edge parts assemblly work 128.043 0 0 14 12
11- Apr-19 drilling of holes 128.043 0 0 13 12
12- Apr-19 stiiffner welding work 128.043 0 0 4 12
13- Apr-19 no work 128.043 0 0 0 0
14- Apr-19 no work 128.043 0 0 0 0
15- Apr-19 no work 128.043 0 0 0 0
16- Apr-19 no work 128.043 0 0 0 0
17- Apr-19 no work 128.043 0 0 0 0
18- Apr-19 no work 128.043 0 0 0 0
19- Apr-19 no work 128.043 0 0 0 0
20- Apr-19 no work 128.043 0 0 0 0
21- Apr-19 no work 128.043 0 0 0 0
22- Apr-19 no work 128.043 0 0 0 0
23- Apr-19 no work 128.043 0 0 0 0
24- Apr-19 no work 128.043 0 0 0 0
25- Apr-19 no work 128.043 0 0 0 0

01- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0


02- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
03- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
04- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
05- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
06- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
07- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
08- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
09- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
10- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
11- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
12- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
13- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
14- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
15- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
16- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
17- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
18- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
19- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
20- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
21- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
22- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
23- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
24- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
25- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
26- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
27- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
28- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
29- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0
30- Jun-19 no work due to material and gand shortage 128.043 0 0 0 0

01- Jul-19 no work due to material and gand shortage 128.043 0 0 0 0


02- Jul-19 no work due to material and gand shortage 128.043 0 0 0 0
03- Jul-19 no work due to material and gand shortage 128.043 0 0 0 0
04- Jul-19 no work due to material and gand shortage 128.043 0 0 0 0
05- Jul-19 no work due to material and gand shortage 128.043 0 0 0 0
06- Jul-19 no work due to material and gand shortage 128.043 0 0 0 0
07- Jul-19 no work 128.043 0 0 0 0
08- Jul-19 drilling hole in cutting edge 128.043 0 0 10 12
09- Jul-19 drilling hole in cutting edge 128.043 0 0 15 12
10- Jul-19 drilling hole in cutting edge 128.043 0 0 12 12
11- Jul-19 drilling hole in cutting edge 128.043 0 0 3 12
12- Jul-19 drilling hole in cutting edge 128.043 0 0 3 12
13- Jul-19 drilling hole in cutting edge 128.043 0 0 8 12
14- Jul-19 no work 128.043 0 0 0 0
15- Jul-19 drilling hole in cutting edge 128.043 0 0 3 12
16- Jul-19 inner skin plate cutting in progress 128.043 0 0 9 12
17- Jul-19 inner skin plate cutting in progress 128.043 0 0 8 12
18- Jul-19 inner skin plate cutting in progress 128.043 0 0 8 12
19- Jul-19 bracket fabrication work in progress 128.043 0 0 8 12
20- Jul-19 bracket fabrication work in progress 128.043 0 0 8 12
21- Jul-19 no work 128.043 0 0 0 0
22- Jul-19 bracket fabrication work in progress 128.043 0 0 8 12
23- Jul-19 bracket fabrication work in progress 128.043 0 0 8 12
24- Jul-19 bracket fabrication work in progress 128.043 0 0 8 12
25- Jul-19 bracket fabrication work in progress 128.043 0 0 8 12
26- Jul-19 Skin plate cutting in progress 128.043 0 0 12 12
27- Jul-19 Skin plate cutting in progress 128.043 0 0 12 12
28- Jul-19 Skin plate cutting in progress 128.043 0 0 12 12
29- Jul-19 outer skin plate fixing in progress 128.043 0 0 20 12
30- Jul-19 outer skin plate fixing in progress 128.043 0 0 17 12
31- Jul-19 outer skin plate fixing in progress 128.043 0 0 18 12

01- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12


02- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
03- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
04- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 0
05- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
06- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
07- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
08- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
09- Aug-19 inner skin plate fixing in progress 128.043 0 0 17 12
10- Aug-19 inner skin plate fixing in progress 128.043 0 0 16 12
11- Aug-19 no work 128.043 0 0 0 0
12- Aug-19 outer skin and inner skin plate fitting welding 128.043 0 0 10 12
13- Aug-19 128.043
14- Aug-19 128.043
15- Aug-19 128.043
16- Aug-19 128.043
17- Aug-19 128.043
18- Aug-19 128.043
19- Aug-19 128.043
20- Aug-19 128.043
21- Aug-19 Cleaning of well curb 128.043
22- Aug-19 Inner Skin plate fixing work in progress 128.043
23- Aug-19 Inner Skin plate fixing work in progress 128.043
24- Aug-19 Inner Skin plate fixing work in progress 128.043
25- Aug-19 128.043
26- Aug-19 128.043
27- Aug-19 128.043
28- Aug-19 128.043
29- Aug-19 128.043
30- Aug-19 128.043
31- Aug-19 128.043
Summary of sinking and construction at P13
Machine & Man Power
RL OF BOTTOM
OF CUTTING SINKING CUMMULATIVE CRANE 1 CRANE 2 LABOUR
DATE WORK DETAILS OGL EDGE DURING A DAY SINKING STRATA crane 1 hrs crane 2 hrs heads hrs
Material record as per work programme January 2019
steel bar required and available (MT) Concrete
work programme ACTIVITY ACTIVITY Total 25 mm 16mm 12mm Quantity Cement(PPC) Sand 10mm 20mm Admixture
(name of structure ) START FINISH Day Required Available Required Available Required Available Required Available Required Available Required Available Required Available Required Available
1890 195 154 154 1310
P12 WELL CURB 1/1/2019 9/1/2019 9 6.78 1.838 3.794 266.892
1890 195 154 154 1310
P10 S9 20/1/19 29/1/19 10 6.78 1.838 3.794 266.892
1890 195 154 154 1310
P7 S9
1/1/2019 16/1/19 16 6.78 1.838 3.794 266.892
1890 195 154 154 1310
P8 S8
16/1/19 25/1/19 10 6.78 1.838 3.794 266.892
1890 195 154 154 1310
P10 S7
1/1/2019 23/1/19 23 6.78 1.838 3.794 266.892
1890 195 154 154 1310
P11 S5
6.78 1.838 3.794 266.892
1890 195 154 154 1310
P11 S6
1/1/2019 11/01/19 11 6.78 1.838 3.794 266.892

Total 47.46 0 12.866 0 26.558 0 1868.244 13230 8293 1365 500 1078 800 1078 800 9170 1750

25 mm 16mm 12mm ISA 75*75*8 ISA 150*150*16


Required Available Required Available Required Available Required Available Required Available
0 6.584 0 59.935 5.3 18.224 27.976

Structural steel (plate and angle )


Summary of chambal on 25/08/19
Balance height
LEVEL
Well ht of WS up upto which NUMNER OF Ht of
Total ht curb Ht of well to which casting not WELL STEINING CASTING well HT OF Number
Element FDL NEW FDL BOWC TOWC of well Ht. steining casting done done EACH 2.65M DONE BALANCE cap TOWC BOPC TOPC PC Ht of PIER of lift
A1 89.088 134.088 136.588 45 4 41 0 45 16 0 16 2.5 136.588 151.791 152.791 1 15.203
P1 92.25 126.75 129.000 34.5 4 30.5 0 34.5 12 0 12 2.25 129.000 149.441 152.791 3.35 20.441 4
P2 89.575 118.575 120.825 29 4 25 0 29 10 0 10 2.25 120.825 149.441 152.791 3.35 28.616 5
P3 89.575 118.575 120.825 29 4 25 0 29 10 0 10 2.25 120.825 149.441 152.791 3.35 28.616 5
P4 89.575 118.575 120.825 29 4 25 0 29 10 0 10 2.25 120.825 149.441 152.791 3.35 28.616 5
P5 89.575 118.575 120.825 29 4 25 11.95 17.05 10 3 7 2.25 120.825 149.441 152.791 3.35 28.616 5
P6 89.575 118.575 120.825 29 4 25 17.25 11.75 10 5 5 2.25 120.825 149.441 152.791 3.35 28.616 5
P7 93.508 119.508 121.758 26 4 22 19.9 6.1 9 6 3 2.25 121.758 149.441 152.791 3.35 27.683 5
P8 93.623 92.773 120.623 122.873 27.85 4 23.85 27.85 0 9 9 0 2.25 122.873 149.441 152.791 3.35 26.568 5
P9 93.026 90.395 121.026 123.276 30.631 4 26.631 30.5 0.131 10 10 0 2.25 123.276 149.441 152.791 3.35 26.165 5
P10 93.997 121.997 124.247 28 4 24 27.85 0.15 9 9 0 2.25 124.247 149.441 152.791 3.35 25.194 5
P11 93.098 122.098 124.348 29 4 25 22.55 6.45 10 7 3 2.25 124.348 149.441 152.791 3.35 25.093 5
P12 92.25 124.25 126.500 32 4 28 0 32 11 0 11 2.25 126.500 149.441 152.791 3.35 22.941 4
P13 92.338 134.338 136.588 42 4 38 0 42 15 0 15 2.25 136.588 149.441 152.791 3.35 12.853 3
A2 86.5 137.5 140.000 51 4 47 0 51 18 0 18 2.5 140.000 151.791 152.791 1 11.791 2

BOWC BOTTOM OF WELL CAP NOTE : NUMBER OF STEINING IS NEAREST TO INTEGER


TOWC TOP OF WELL CAP
HT HEIGHT
BOPC BOTTOM OF PIER CAP
TOPC TOP OF PIER CAP
FDL FOUNDING LEVEL
PC PIER CAP
Sinking Summary
Element Founding level Cutting edge level Balance sinking TOTAL SINKING NOS OF DAYS AVG. SINKING Date update on
A1 89.088
P1 92.25
P2 89.575
P3 89.575
P4 89.575
P5 89.575 108.755 19.18 10.232 27 378.963 25/8
P6 89.575 104.71 15.135 14.24 40 356.000 25/8
P7 93.508 102.843 9.335 17.447 42 415.405 25/8
P8 92.773 95.437 2.664 25.596 123 208.098 25/8
P9 90.526 90.395 -0.131 33.002 136 242.662 25/8
P10 93.997 100.805 6.808 23.872 50 477.440 25/8
P11 93.098 105.04 11.942 21.115 46 459.022 25/8
P12 92.25
P13 92.338
A2 86.5

ON DATE 20/12/18
CASSION WATER LEVEL WATER DEPTH BED LEVEL REQUIRED DEPTHCASSION IN M
P2 118.736 9.5 109.236 5.2
P3 118.736 9.3 109.436 5.2
P4 118.736 8.5 110.236 5.2

Sinking Summary (24.07.19) w.r.t scour level


Element Founding level cutting edge level scour level Remark Height below and belowSL
P5 89.575 108.755 107.782 unsafe 0.973
P6 89.575 104.71 107.782 safe -3.072
P7 93.508 103.412 107.782 safe -4.37
P8 92.773 95.702 107.782 safe -12.08
P9 90.526 90.395 107.782 safe -17.387
P10 93.997 100.946 107.782 safe -6.836
P11 93.098 106.663 107.782 safe -1.119
P12 WELL CURB FABRICATION IN PROGRESS
P4 FLOATING DONE
P3 FLOATING DONE

FDL comparison of chambal existing and purposed bridge


FDL OF FDL OF
EXISTING PREPOSED DIFFRENCE
WELL NO BRIDGE BRIDGE IN FDL New FDL Remark
A1 96.96 89.088 7.872
P1 97.896 92.25 5.646
P2 89.906 89.575 0.331
P3 87.811 89.575 -1.764
P4 90.991 89.575 1.416
P5 91.045 89.575 1.47
P6 90.444 89.575 0.869
P7 91.328 93.508 -2.18
P8 91.175 93.623 -2.448 92.773 800 mm extra casting
P9 90.906 90.395 0.511 90.526 One extra lift of 2.5m
P10 90.444 93.997 -3.553
P11 89.373 93.098 -3.725
P12 91.131 92.25 -1.119
P13 101.648 92.338 9.31
A2 99.029 86.5 12.529
WELL FOUNDATION CHAMBAL
WELL NO. OGL IN GAD
A1 135.961 136.18 0.219
P1 128.251 128.736 0.485
P2 109.8 116.24 6.44
P3 109.2 116.212 7.012
P4 110.1 119.971 9.871
P5 118.987 120.330 1.343
P6 118.950 120.689 1.739
P7 120.290 121.758 1.468
P8 121.033 122.873 1.840
P9 123.397 123.276 -0.121
P10 124.677 124.247 -0.430
P11 126.155 124.348 -1.807
P12 128.043 129.200 1.157
P13 135.010 137.898 2.888
A2 140.265 137.898 -2.367