Centre Line = Sum of Centre Line of Horizontal Wall +


Sum of Centre Line of Vertical Wall

H1= 0.15+3+0.3+4+0.15 (7.6 *3) 22.8


H2= 0.15+3+0.15 (3.3 * 1) 3.3
SUM 26.1 Column Size 300 mm x 300 mm
V1 0.15+4+0.3+6+0.15 10.6*3 31.8
Beam Size 300 mm x 300 mm
C.L.= 26.1 + 31.8 57.9

NO. OF JUNCTION 8
To Get Unprotect Code Follow Link:
Building Estimation http://civiconcepts.com/building-estimation-excel-sheet/#
QUANTITY SHEET
Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity
(m)
(m) (m)
Earthwork in Excavation in
1
Foundation:
Footing (1m x 1m) 12 1.50 1.50 1.50 40.50 cu m
Depth From GL = 1.5 m

2 P.P.C. in Foundation
Footing (1m x 1m) 12 1.3 1.3 0.1 2.03 cu m
Thickness = 0.10

3 Column(300mm x 300mm)
Base(1m x 1m) 12 1.00 1.00 0.15 1.80 cu m
Thickness = 0.15
Stem(0.30 x0.30)
height= 1.25+0.55 = 1.80 m 12 0.30 0.30 1.80 1.94 cu m
Total 3.74 cu m

4 Plinth Beam
Beam (300 mm x 300 mm)
Beam - 1 (3m length) 4 3.00 0.30 0.30 1.08 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.30 2.52 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.30 0.92 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.30 0.62 cu m
Total 5.14 cu m

5 Earth Filling in Plinth


Bed Room (3m x 4m) 1 3.00 4.00 0.45 5.40 cu m
Kitchen + Dining (4m x 4m) 1 4.00 4.00 0.45 7.20 cu m
Drawing (4m x 6m) 1 4.00 6.00 0.45 10.80 cu m
Bath/ W.C. (3m x 2.3m) 1 3.00 2.30 0.45 3.11 cu m
Varandah (3m x 3.4m) 1 3.00 3.40 0.45 4.59 cu m
Total 31.10 cu m

6 Damp Proof Course(DPC)


57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 17.01 sq. m

7 Brick Work in Super Structure


57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 3.00 51.03 cu m

Bath / WC Wall:
W1, L = 1.5 m , B= 0.10 m 1 1.50 0.10 3.00 0.45 cu m
W2, L=0.8 m, B= 0.10 m(2.3-1.5) 1 0.80 0.10 3.00 0.24 cu m
Total 51.72 cu m
Deduction:
Door:
D(1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
D1(1.00 X 2.10 m) 1 1.00 0.30 2.10 0.63 cu m
D2(0.75 X 2.10 m) 2 0.75 0.30 2.10 0.95 cu m
MS (1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
Windows:
W(2.00 X 1.20 m) 1 2.00 0.30 1.20 0.72 cu m
W1(1.50 X 1.20 m) 3 1.50 0.30 1.20 1.62 cu m
W2(1.20 X 1.00 m) 2 1.20 0.30 1.00 0.72 cu m
W3(1.20 X 1.20 m) 2 1.20 0.30 1.20 0.86 cu m
Ventilation:
V(0.90 x 0.60 m) 1 0.90 0.30 0.60 0.16 cu m
V1 (0.60 x 0.60 m) 1 0.60 0.30 0.60 0.11 cu m
Cupboard:
CB(1.50 x 1.80 m) 1 1.50 0.15 1.80 0.41 cu m
CB1 (1.20 x 1.80 m) 1 1.2 0.15 1.80 0.32 cu m
Open:
O (1.20 x 2.10) 2 1.20 0.30 2.10 1.51 cu m
Total 9.52 cu m
Lintel:
Door:
D(1.20 X 2.10 m)(L= 1.20+0.15+0.15) 1 1.50 0.30 0.15 0.07 cu m
D1(1.00 X 2.10 m) 1 1.30 0.30 0.15 0.06 cu m
D2(0.75 X 2.10 m) 2 1.05 0.30 0.15 0.09 cu m
MS (1.20 X 2.10 m) 1 1.50 0.30 0.15 0.07 cu m
Windows:
W(2.00 X 1.20 m) 1 2.30 0.30 0.15 0.10 cu m
W1(1.50 X 1.20 m) 3 1.80 0.30 0.15 0.24 cu m
W2(1.20 X 1.00 m) 2 1.50 0.30 0.15 0.14 cu m
W3(1.20 X 1.20 m) 2 1.50 0.30 0.15 0.14 cu m
Ventilation:
V(0.90 x 0.60 m) 1 1.20 0.30 0.15 0.05 cu m
V1 (0.60 x 0.60 m) 1 0.90 0.30 0.15 0.04 cu m
Open:
O (1.20 x 2.10) 2 1.50 0.30 0.15 0.14 cu m
Total 1.13 cu m

Total Brickwork after deduction Total 41.06 cu m

Beam (300 mm x 300 mm)


Beam - 1 (3m length) 4 3.00 0.30 0.23 0.83 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.23 1.93 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.23 0.70 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.23 0.48 cu m
Total 3.94 cu m

8 Slab
L = 7.9 m
B = 10.9 m
H = 0.10 1 7.90 10.90 0.10 8.61 cu m