Beruflich Dokumente
Kultur Dokumente
Objective function. The objective function of the SIP where t = 2, … , P and Hd is the total time required for trans-
model is constructed as the maximization of a profit func- portation of a block to destination d.
tion, defined as the total expected NPV minus penalties
for deviations from planned production targets and pen- Application at the LabMag iron ore deposit
alties for not mining the blocks adjacent to a mined block The formulation is applied at the LabMag deposit in
(Ramazan and Dimitrakopoulos, 2005, 2013; Benndorf and order to create a mine production schedule that considers
Dimitrakopoulos, 2013), as well as truck operating costs. multi-element grade uncertainty as well as equipment and
This objective function includes four distinct terms: tailings disposal requirements.
Maximize Obj = Stochastic orebody models at LabMag. Geological vari-
ability and uncertainty is represented here by 10 stochastic
(3a)
conditional simulations of the deposit (Spleit and Dimitrako-
poulos, 2016). Each realization consists of a joint simulation
(3b) of the seven correlated layer thicknesses as well as the joint
simulation of four correlated ore characteristics in each layer
using the joint direct block simulation method (Boucher and
(3c) Dimitrakopoulos, 2009). Each model consists of 13,400 blocks,
measuring 100 × 100 × 15 m (328 × 328 × 49 ft).
The two primary waste types for the LabMag deposit are
(3d) overburden (OB) and Menihek Shale (MS). The OB over-
lies the entire deposit and is minimal (the underlying rock
The first term is the primary term and represents the NPV of is commonly exposed at surface). The MS layer is present
all blocks mined in the optimization. The second term rep- on the northeast side of the deposit, overlies the iron layers
resents the trucking operating cost, which is minimized. The and dips parallel to them at approximately 6 degrees (Fig. 1).
third term acts to penalize deviations from target concen-
trate tonnes and the target silica grade and weight recovery. Implementation. The SIP model was implemented in Vi-
The variables for the deviations are determined by the op- sual C++ using the ILOG CPLEX API. The initial attempts
timization process, based on the corresponding constraints to solve the full orebody model for all 10 periods proved
that are set. The fourth term is a penalty for not mining that it was unsolvable in a reasonable amount of time, as the
adjacent blocks. It is desirable to mine blocks in groups in optimization had made little progress after several days of
order to generate a practical schedule. There is a trade-off running on a 64-bit Dell Precision M6500 Intel I7 quad-core
between the penalty terms, determined by the relative size at 1.73 GHz with 16 GB of RAM. The initial 13,400 blocks
of the penalties. considered are the blocks contained within an ultimate pit
derived using the nested Lerchs-Grossman algorithm. As
Constraints. Constraints are applied to ensure equip- only the first 10 years are scheduled within the optimization
ment accessibility, processing capacity, geotechnical aspects, and the LabMag ultimate pit contains more than 25 years
and blending requirements, which are detailed in Benndorf of ore at the planned capacity, the precise pit limit need not
and Dimitrakopoulos (2013). In addition, constraints are in- be discussed further. To reduce the number of blocks, a new
cluded here to control the schedule sequence and the num- pit was designed that takes as many blocks as possible but
ber of haul trucks in each period. avoids the MS waste layer. As the optimization targets the
first 10 years and tries to minimize trucking hours as well
Sequencing constraints. In order to accommodate in-pit
tailings disposal, the strategy here is to expose the ultimate
pit floor as quickly as possible. In order to accomplish this, Figure 1
mining on each bench is set to start from the shallow side of LabMag typical cross-section.
the deposit. In addition to the standard block predecessors
needed to maintain geotechnical slope constraint, the block
cross-dip, toward where the deposit daylights at surface, is
set to be mined in the same or an earlier period.
Figure 3 Figure 4
Stochastic schedule mine designs: end-of-period (a) 5, (b) 10 Deterministic schedule mine designs: end-of-period (a) 5,
and (c) 15. (b) 10 and (c) 15.
Figure 5 Figure 6
Conventional and stochastic schedules: Comparison of truck Product tonnes in (a) conventional schedule and (b)
productivity. stochastic schedule.
(a)