Sie sind auf Seite 1von 15

Geometry Control of Precast

Segmental Concrete Bridges


Brice F. Bender, PE
Senior Consultant
Special Concrete Bridges
Henningson, Durham and
Richardson, Inc.
Omaha, Nebraska

H. Hubert Janssen, PE
Senior Consultant
Special Concrete Bridges
Henningson, Durham and
Richardson, Inc.
Omaha, Nebraska

G eometry control needs to be ac-


counted for from conceptual de-
sign through production and final erec-
bridges erected in cantilever since
many bridges have been and are being
built in this manner.
tion of segmental concrete bridges, If
this control is not adequately provided, Time of Control
the project will be unsatisfactory. Con-
versely, if suitable geometry control is Contrary to some thinking, geometry
established in the beginning and control should not wait until construc-
maintained throughout the project, ex- tion starts. Waiting until production or
cellent results will be achieved. erection begins is a serious oversight
Gegmetry control is required and will cause problems and delays.
whether the segmental bridge is precast Rather than starting control in the con-
or cast in place and erected in can- struction phase, the process should
tilever. It is required whether the begin in the conceptual design phase
bridge is on tangent or curved, flat or and be carried through design, detailing,
on vertical curve. Control is also re- the casting curve, production plan, shop
quired in other types of erection, but drawings, form and manufacturing plant
each varies in some way. This discus- design, production of segments, curing,
sion will concern precast segmental storage, erection of segments, and
post-tensioning.
NOTE: This paper is based on a presentation Of course, the actual geometry con-
given at the Segmental Concrete Bridge Confer-
ence in Kansas City, Missouri, March 9-10, 1982. trol as described later is accomplished
The Conference was sponsored by the Associated in the production and erection phases.
Reinforcing Bar Producers—CBS!, Federal High- Nonetheless, the designer should keep
way Administration, Portland Cement Association,
Post-Tensioning Institute, and Prestressed Con- geometry control in mind when de-
crete Institute. veloping the structural concept, se-

72
Very close and constant control is necessary to
obtain a completely satisfactory segmental concrete
bridge. This control must be established and
maintained in production and during erection of
segments. Methods and amount of control are
discussed.

lecting the most likely erection method, casting curves which will become part
developing details to facilitate the con- of the plans.
trol, and preparing the casting curve. Some might say that this is not neces-
Then the contractor must keep the sary because the contractor might want
control aspect in mind while preparing to change the erection scheme, the size
the production plan and the shop of segments, post-tensioning or some
drawings. other item which would alter these
The contractor must certainly discuss casting curves. However, it is highly
the amount of control and methods to desirable to include this information in
achieve it with the form designer. Con- the plans because it will inform possi-
trol during production and erection are ble bidders and will direct attention to,
usually understood, but one must not the importance and need of geometry
overlook the curing and storage of seg- control. Moreover, most bidders do not
ments. have the staff, capability or desire to re-
Changes in geometric measurements vise the plans.
can occur if just the newly cast seg- It has been noted that with complete,
ment is steam cured, so it is recom- detailed plans, the contractor usually
mended that both the new and the old uses most of the design and sometimes
segment be so cured. This amounts to all of it. Also, it must be remembered
two time periods of curing for each that these complete plans include ten-
segment and while usually not needed don layouts for all permanent post-
for strength, maintaining the higher tensioning, adequate temporary post-
moist temperature does aid in geometry tensioning used during erection, and
control. Likewise, if segments are not the sequence of tensioning, as this
set level on a firm storage pad with could alter the geometry in certain
bearings under the webs, warping can cases.
occur. With these well conceived and de-
The designer must maintain a con- tailed plans, all contractors can prepare
cern for geometry control throughout accurate bids. They will be forewarned
the design and detailing phases. Also, of the need for geometry control in
the designer must select a likely the construction phase, and if they
method of erection, especially in cases should choose to change some item,
where erection loads will occur on the they will know what is required in their
cantilevers, and compute accurate submittal. In preparing bids, the em-

PCI JOURNALJJuIy-August 1982 73


Q
ABUT PIER SPLICE PIER ABUT
II I i I ^

SELFWEIGHT & ' CANTILEVER T^NDONS

ROTATION & EN SPAN CONTINUITY TENDONS

13 1

CORRECTIONS

C
BRIDGE AS ERECTED

SUPERIMPOSED 'DEAD LOADS &I CREEP

1PROFILE
GRADE

Fig. 1. Various steps in correcting erection deflections.

phasis on control in the plans and spe- creep and shrinkage are included in the
cial provisions will inform the form casting curve. These, combined with
manufacturers of the care they must the structure geometry, provide the in-
take to provide an adequate casting formation for each segment shop
machine. drawing.
The successful contractor can im- With adequate forms installed in a
mediately begin the work by ordering complete manufacturing area, and with
the form, preparing the production approved shop drawings in hand, the
schedule, and preparing shop drawings. production of segments can begin.
With the casting curve and other items Anyone who is familiar with segmental
on the plans, shop drawings can be precast concrete bridges knows that
started with no other computations if the segments must be match cast. This
the design plans are used. The is elementary, but most important.
geometry control functions of dead load Likewise, all prudent engineers will
deflection, post-tensioning camber, realize that a box girder constructed on

74
OUTSIDE
FORMWORK

SOFFIT

CARRIAGE —`I L— ADJUSTMENT JACK

Fig. 2. Formwork (Short-line method).

INSIDE FORMWORK

BULKHEAD

NEW OLD
SEGMENT JSEGMENT

SOFFIT

CARRIAGE

Fig. 3. Step 1 (Short-line method).

Fig. 4. Step 2 (Short-line method).

PCI JOURNAL/July-August 1982 75


iGET

11141 1\VIII I\ 1

BASE
ELEVATION

LEVEL
MARKER BOLT
Fig. 5. Alignment control (Setup).

the ground in a perfect geometric pat- geometry control is achieved. This se-
tern to that desired on the piers cannot quence is predicated on the use of the
be erected in cantilever without several short-line method. Figs. 2, 3, and 4 de-
corrections to compensate for dead load pict the various steps in the case of the
deflection, prestressing cambers, creep, short-line method of production.
and shrinkage. Fig. 1 indicates the need F'ig. 5 shows the setup required in
for these corrections. Each segment is the casting area. Especially note the in-
intentionally deformed during produc- strument on a permanent base and a
tion to achieve the desired results. permanent target (Fig. 6). It is very im-
From this follows the importance of portant that neither instrument nor
geometry control in production, target be disturbed throughout the
production. In case of a disturbance,
Production Control control must be reestablished so ade-
quate bench marks must be provided.
Let us now follow through the casting Note that in Fig. 5 a new segment has
procedure to indicate how the required been match cast against an old segment.

76
The form is always plumb, level and
square so the geometry control is es-
tablished by properly setting the old
segment.
But to begin, the first segment must
be cast. This might be a pier segment,
but it could be any other element that
the contractor's scheduling indicates
should be first, Since there is no old
segment, a second bulkhead is required
and the segment is cast plumb, level,
and square. As the top slab is being
finished, the four elevation bolts, A, B,
C and D, as well as the centerline
marker are inserted. The following
morning the levels on the bolts are re-
corded and the centerline is scribed
onto the centerline markers. Now the
temporary second bulkhead can he re-
moved and the segment rolled forward
for match casting (see Figs. 7, 8, and 9a,
9b).
Here it is desirable to interject the
idea of permanent record keeping. The
instrument person should be on the job Fig. 6. Instrument set up (Zilwaukee
daily, have the complete confidence of Bridge, Michigan).

Fig. 7. Match-cast segment showing elevation bolt.

PCI JOURNAUJuIy-Augusd 1982 77


'^
fflr t ^^s t¢

G MroE2w

wR } !±
.r,

Fig. 8, Match-cast segment showing centerline marker.

the superintendent, and keep accurate, shown in Fig. 9a. Likewise, vertical
daily records. curvature is handled as shown in Fig.
When the first segment is rolled for- 9b. But in addition to the vertical cur-
ward, it is reset to the information on vature adjustment, if any, it is necessary
the shop drawings. The centerline will to adjust for the segment deformations
be identical as to what it was the previ- as mentioned before and illustrated in
ous day, unless the bridge is curved Fig. 1.
and then an offset angle is used as These deformations will be on the

HORIZONTAL CURVATURE

OLD SEGMENT

y i SEGMENT
ROTATED

_CENTERLINE ON

FORM ALWAYS
PLUMB,LEVELSAOUE
D AMOUNT OF
ROTATION
DETERMINES
HORIZONTAL
CURVATURE.
PLA
N

Fig. 9a. Match-casting operation showing horizontal curvature of segment.

78
shop drawings, and can be taken di-
rectly from the plans unless changes
were made to these. In that case, the
contractor, or his designer, must re-
compute them. After this first (the old)
segment is properly reset and the setup
for the second segment is complete, in-
cluding reinforcing bar cage, tendons,
anchors, embedded items and the posi-
tion of the inner mandrel, the second
segment can be cast. This second seg-
ment is called the new segment in Figs.
5 and 10.
The following morning it is necessary
to mark the centerline and record the
bolt elevations of segment number two.
Also, before segment number one (the
old segment) is moved, it is imperative
to recheck the elevations of its bolts
and its centerline position to determine
if its position has changed since it was
set so carefully the previous day. It is
often noted that position changes occur
due to settlement of the soffit rails by
the segment weight, or due to vibrating
of fresh concrete against it, or clue to Fig. 10. Positioning the old segment
temperature changes. (Zilwaukee Bridge, Michigan).
There is no need to be concerned
about these small changes as long as
these are known and recorded every or accumulated errors that the geometry
day. From these, daily compensations becomes jeopardized. As compensation
can he made. It is only from neglected is made daily, the bridge superstructure

AMOUNT OF
TILT DETERMINES
VERTICAL
VERTICAL CURVATURE URVATURE.
BOLTS A

ELEVATION

Fig. 9b. Match- casting operation showing vertical curvature of segment.

PCI JOURNALJJulyAugust 1982 79


HORIZONTAL ALIGNMENT

5-0 + 19 8`-0" 4-0


- I 1 4 I

VERTICAL ALIGNMENT
Fig. 11. Graphical production chart showing horizontal and vertical alignment.

deviates both vertically and horizon- cured during casting. If segment one
tally from the theoretical alignment by had moved '/s in. (3.2 mm) to the left,
very small amounts. However, if these segment two will now he adjusted 4 in.
small deviations are left uncorrected, to the right. The same procedure holds
they will soon magnify and create an for any vertical adjustment. This shows
unsatisfactory condition. the importance of constant surveillance.
The instrument person should main-
tain a graph of these corrections from
the records as shown in Fig. 11. Superelevation Control
After the alignment of the "old seg- Another geometric problem is han-
ment" is recorded, it can be removed dling superelevation for horizontal cur-
from the soffit and moved to proper vature. If the superelevation is constant
storage. Many times segments are kept within a span, no transverse tilting of
one more day in the manufacturing area the old segment is required in setting it
to complete transverse post-tensioning for match casting. Rather, the superele-
and clean -tip. vation is achieved by setting the pier
The setup to cast segment three, and segment on the proper tilt as shown in
all other segments, is similar to that of Fig. 12. However, as indicated in the
casting segment two with one excep- bottom portion of Fig, 12, the tilting of
tion. When segment two is rolled for- the pier segment does create an unde-
ward, it is set to the proper position as sirahle deflection which must be cor-
per the drawings, but this time it must rected by introducing counteracting
also have a small compensation for a vertical curvature. Likewise, if the
position change of segment one that oc- structure is on a strong vertical curve,

80
SUPERELEVATION (CONSTANT)

1J PER

FORM ALWAYS
PLUMB, LEVEL Ak SQUARE

//CHANGE REFERENCE PLANE FOR^^


\\GEOMETRY CALCULATIONS SURE RELEVATION
ACHIEVED BY TILT

eo^re. e. rna.0 11T

Fig. 12. Superelevation (constant).

an undesirable horizontal curve will be to the tilted position of the old segment.
treated, which must be corrected by While this is usually a very small twist
introducing a compensating horizontal in any one segment, it is a problem for
curvature. the form manufacturer to design a form
More complicated is handling a which can accomplish the twist and
superelevation transition that occurs remain structurally rigid for the con-
when the superelevation is increasing crete casting and still maintain a mortar
or decreasing in a span. Now the old tight seal at the point of joining the old
segment needs to be tilted with respect segment. The practical point of rotation
to the new segment as shown in Fig. is the centerline of the bottom slab.
13. While the permanent bulkhead re- A consequence of transverse tilting of
mains plumb, level and square, the rest the old segment with respect to the
of the form must assume the transition new segment is that the centerline of

51
PCI JOURNAUJuIy-August 1982
'OLD" SEGMENT TILTS 'A^^
IN RESPECT OF "NEW"

"B"

BULKHEAD OF FORM I "


REMAINS
PLUMB, LEVEL a SQUARE FORMWORK IS
FORCED TO ASSUME
TILTED SHAPE OF
OLD SEGMENT
FORM—^i

WN

PREDETEF

Fig. 13. Superelevation Transition I during casting.

the top and bottom slabs are no longer centerline remains constant during
in a vertical plane. It is ideal if the in- production. Fig. 14 indicates the rota-
strument is in a position to establish tion from no superelevation to full
both the bottom slab centerline and the superelevation. According to the pic-
top slab centerline. Since the centerline ture in the middle of Fig. 14, the seg-
of the top slab is offset a predetermined ments in the transition area will have
amount, it is essential that this be mea- some small irregularities which are
sured in the setup. caused by warping of the form.
Fig. 13 shows that the bottom slab In order to line up top slab center-

82
6
a
W
J
Ir
LU
D
V7.
J \\

z
0 DEC
ROTATED
I-

z
zQ _ BOTTO

BOTTOM

z ROT,
a

IN CASE SUPERELEVATION TRANSITION EXTENDS OVER SEVERAL


SPANS: DETERMINATION OF CORRECTIONS LEADS EASILY
TO ERRORS BECAUSE OF REVERSAL OF PIER SEGMENT.
CONCLUSION: MAKE PROPER DRAWINGS OF r. BOTTOM AND
TOP SLAB IN THESE AREAS.

Fig, 14. Superelevation Transition II during erection.

lines instead of bottom slab centerlines, complexity increases because the pro-
segments at the beginning and end of duction often calls for a reversal of the
the superelevation transitions need to pier segment after completion of half a
be rotated. cantilever. In order to avoid errors,
This subject can be more complicated therefore, it is mandatory that proper
than shown in Figs. 13 and 14 because shop drawings be made clearly showing
usually the transition will start within a bottom and top slab centerlines.
span and continue over several piers. It follows from the above that align-
This is complicating in itself, but the ment control is a matter of combining

83
PCI JOURNALJJuIy-August 1982
Fig. 75. Temporary support of pier segment group (Zilwaukee Bridge, Michigan).

the calculated deformations with the provide information regarding the ele-
structure geometry on the shop draw- vation of each segment after erection of
ings and: that segment. If this information is pro-
L Implementing these at the casting vided, the actual position of the seg-
site. ment can be checked against the
2. Recording each morning the cor- theoretical. Readings should be taken
rections achieved. as the segments are erected in order to
3. Comparing the corrections with notice discrepancies, if any, However,
the requirements. the only true readings that can be ob-
4. Correcting the corrections. tained are those taken early in the
morning before the sun's heat has had
Erection Control time to affect the girder.
This effect is very pronounced, and is
It is necessary to consider alignment caused by the fact that the top slab of
control during erection of segments. the box girder heats rapidly while the
First, an erection table, chart, or graph bottom remains cool. This condition
must be prepared after the segments will cause substantial deflection of the
are produced. This provides the girder. Each morning after accurate
theoretical position of each segment readings are taken, a determination
based on actual production mea- must be made whether any corrections
surements, The same leveling bolts are are necessary in erecting the next seg-
used and offsets from an established ment.
centerline provide horizontal control. Usually only two segments are placed
Transverse or horizontal tilt or rotation at each end of the cantilevers in a work
is also on the theoretical chart. day. Hence, there is an accurate read-
The designer of the structure should ing after every two segments. From this

84
Fig. 16. Vertical sag (Turkey Run Bridge, Indiana).

it can he decided whether any field cor- onto permanent bearings. It is very im-
rections are required. portant that the pier group of segments
If small erection corrections are de- be precisely set because an error made
sirable, shimming is recommended in this will be multiplied upon com-
with stainless steel screen wire mesh pletion of the cantilever (Fig. 15).
about'/ in. (1.6 mm) thick, This allows Other items affecting geometry dur-
the epoxy to flow through and prevents ing erection are provisional post-
stress concentration points, yet it will tensioning, post-tensioning of perma-
effectively turn the next segment tip, nent tendons, and midspan splices.
down or laterally. It is recommended Both provisional and permanent ten-
that shimming not be started too soon. dons are a design function, and the use
Only after a number of segments have of correct number and correct placing
been erected in a cantilever, and after are a production responsibility. How-
the temporary bearing assemblies are ever, the sequence of tensioning can be
checked for any discrepancy, can a important and should be established in
judgment of the alignment be made. the work check list for the erecting
And if measurements indicate that the crew. Before the splices are cast, the
erected structure will be out of toler- cantilevers must he aligned. Structural.
ance, careful use of shims will regulate hardware should he provided to hold
the problem. the cantilevers in line during midspan
It is advisable to start erection of the splice casting and continuity post-
pier segment or group of segments on tensioning (Figs. 16 and 17).
temporary bearings. These temporary Further information on the subject of
bearings are designed to allow the can- geometry control in segmental con-
tilevers to be adjusted after the seg- struction can be obtained from Refer-
ments are erected and then let down ences 1 through 6.

PCI JOURNALJJuIy-August 1982 85


Fig. 17. Horizontal curve (Zilwaukee Bridge, Michigan).

CONCLUSIONS
From the preceding discussion the control be started as each phase starts
following conclusions can be stated: and does not cease until that phase
I. Geometry control is most defi- ends.
nitely needed for a satisfactory seg- 4. Cooperation must exist between
mental bridge. groups responsible for various tasks. No
2. Control is essential in all stages of one group has more or less responsibil-
the work from design through casting ity than another. Teamwork is essential.
the final midspan splice. 5. Careful, complete control will in-
3. Control functions are relatively sure that the bridge will meet the seg-
simple, but it is more important that ment criteria.

REFERENCES
I. Precast Segmental Box Girder Manual, Walker, Homer M., "The Kentucky River
published jointly by the Prestressed Con- Bridge," PCI JOURNAL, V. 26, No. 4,
crete Institute and the Post-Tensioning July-August 1981, pp. 60-85.
Institute, 1978, pp. 66-68. 5. Bender, Brice F.,"Economics and Use for
2. Lovell, J. A. B., "The Islington Avenue Lightweight Concrete in Prestressed
Bridge," PCI JOURNAL, V. 25, No, 3, Structures," PCI JOURNAL, V. 25, No, 6,
May-June 1980, pp. 32-66. November-December 1980, pp. 62-67.
3. Bridges, Conrad P., and Coulter, Clifford 6. Joint PCI-PTI Committee on Segmental
S., "Geometry Control for Intercity Construction, "Recommended Practice
Bridge," PCI JOURNAL, V. 25, No. 3, for Precast Post-Tensioned Segmental
May-June 1979, pp. 122-125. Construction," PCI JOURNAL, V. 27, No.
4. Kelly, John B„ Janssen, H. Hubert, and 1, January-February 1982, pp. 14-61.

86

Das könnte Ihnen auch gefallen