Sie sind auf Seite 1von 22

Introduction

Introduction
Project Characteristics
 Defined goal or objective stated by the owner and accomplished by
the project team
 Specific tasks to be performed
 Defined beginning and end
 Resources being consumed. The 4 Ms (Manpower, Machinery,
Materials, and Money,)
 As the project progresses, the project team learns more about the
project

Information Time

19/02/2016 Emad Elbeltagi 2

1
Introduction
Project Life Cycle

The project life cycle may


be viewed as a process
through which a project is
implemented from
beginning to end

 From the owner’s Perspective

19/02/2016 Emad Elbeltagi 3

Introduction
Project Life Cycle (Project stages)

As the construction
progresses, the
cost increases while
the influence
decreases

19/02/2016 Emad Elbeltagi 4

2
Introduction
Types of Contracts
Contracts are classified according to the method of
payment to the contractor

Contracts

Cost based Price based

Cost plus Target Cost Unit price Lump sum

19/02/2016 Emad Elbeltagi 5

Introduction
Type of Contracts
What is the difference between cost & price?

Price

Margin Cost
Profit
Indirect cost Direct cost
Risk allowance
Site overhead Labor
Financial charge Office overhead Material
Equipment
Subcontractors
19/02/2016 Emad Elbeltagi 6

3
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost

Factors favoring the use of a specific contract

 Providing incentive for efficient performance

 Introducing changes during construction

 Allocation of risk between owner & contractor

19/02/2016 Emad Elbeltagi 7

Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Unit price or Admeasurement contract
 Work items are given in detail (BOQ; Bill of Quantities)

 The contractor set a price for each item; the owner doesn’t know the
details of each item pricing
 Changes are allowed with 25% only
 When new items are added, the price of these items should be studied.
 Claims might arises between owner and contractor.

19/02/2016 Emad Elbeltagi 8

4
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Unit price contract

Used for typical projects and civil engineering projects where


changes are limited

19/02/2016 Emad Elbeltagi 9

Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Unit price contract
Advantages:
 Owner aware of the project details

 Widely used; about 80% of projects

 Project period is defined


Disadvantages
 All attention are given to the prices only

 Allows limited design changes

 Errors of quantities leads to disputes

 Disputes may arises when new items of work are added

19/02/2016 Emad Elbeltagi 10

5
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Lump Sum (‫)ﻋﻘﺪ اﻟﻤﻘﻄﻮﻋﯿﺔ‬
 A single tendered price is given for the completion of specified

work
 Payment may be staged at intervals on the completion

 very limited flexibility for design changes

 Contract final price is known at tender

 This contract may be used for a turnkey construction

 It is appropriate when work is defined in detail

19/02/2016 Emad Elbeltagi 11

Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Cost-Plus (‫)ﻋﻘﺪاﻟﺘﻜﻠﻔﺔ ﻣﻊ اﺳﺘﺮداد ﻧﺴﺒﺔ ﻣﻦ اﻟﻤﺼﺮوﻓﺎت أو اﻟﺘﻜﻠﻔﺔ واﻻﺿﺎﻓﺔ‬
 The contractor is reimbursed for actual cost plus a special fee

for head office overheads and profit


 high level of flexibility for design changes

 Final price depends on changes and risks

 High level of owner involvement

 The fee may be a fixed amount or a percentage of actual costs

 It may be used when it is desirable for design to proceed

concurrently with construction


 the client wishes to be involved in contract management
19/02/2016 Emad Elbeltagi 12

6
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Target Cost (‫)ﻋﻘﺪاﻟﺘﻜﻠﻔﺔ اﻟﻤﺴﺘﮭﺪﻓﺔ‬
 Same as previous type (cost-plus)

 owner and contractor agree on a target cost for the project

 contractor will be paid a share for any saving

 When work is added or removed, target cost is adjusted

 The contractor has an incentive to reduce the cost


19/02/2016 Emad Elbeltagi 13

Introduction
Cost Estimating
Cost Estimating may be defined as:
 Estimating is the compilation of all the costs of the elements of
a project within an agreed upon project scope
 it is the production of a statement of the approximate quantity
of materials, time and costs to perform construction decisions
 The basic challenges the construction contractor faces are to
estimate the cost of constructing a project
 The objective of cost estimate is to produce an accurate, cost
effective prediction of what a project will most likely cost and it
needs to be done in different manners at different stages

19/02/2016 Emad Elbeltagi 14

7
Introduction
Cost Estimating
Required data:
 Detailed plans, specifications, available site data, available
resource data (labor, material, & equipment), contract
documents, resource cost information, pertinent
government regulations, applicable owner requirements an
agreed upon project scope

19/02/2016 Emad Elbeltagi 15

Introduction
Cost Estimating is a Probabilistic Activity
An estimate involves calculating the costs of work on the basis of
probabilities:
 Two activities are involved when carrying out an estimate:
 Measurements: all measurements are approximate
 Pricing: the degree of approximation is even greater
because of the difficulty in predicting all the probabilities of
items such as labor productivity and site conditions

19/02/2016 Emad Elbeltagi 16

8
Introduction
Estimating Purpose
 The purpose of estimating is to forecast the cost required
to complete a project in accordance with the contract plans
and specifications
 There are two distinct tasks in estimating:
 To determine the probable real cost of the project
 To determine the probable real time to build the project
 Because construction estimates are prepared before a
project is constructed, an estimate is, at best, a close
approximation of the actual costs

19/02/2016 Emad Elbeltagi 17

Introduction
Estimating Purpose
 The true value of the project will not be known until the
project has been completed and all costs have been
recorded
 Therefore, the estimator does not establish the cost of a
project; he simply establishes the amount which the
contractor will receive for constructing the project.

19/02/2016 Emad Elbeltagi 18

9
Introduction
Estimator (Quantity Surveyor)
 the person who prepares estimates in the planning, design,
and perhaps construction stages
 Understanding of the principles and methods of engineering
economics
 Estimator decisions are very crucial for his/her company
 An estimator must not spend so much time and effort to
analyze unnecessary details in determining the costs of
insignificant items as the estimating will take time and be
expensive

19/02/2016 Emad Elbeltagi 19

Introduction
Estimator Role
 The estimator’s job is to prepare estimates of project costs
 The success of a contractor’s business depends on the
accuracy of these estimates.
 The estimator’s success will be based on his previous
experience and knowledge of the construction industry
 A contractor or estimator lacking this experience may over-, or
under-estimates project costs
 All cost data is acquired from experience. If an estimator does
not have cost data from his/her own experience, he/she must
use cost data from price books and handbooks

19/02/2016 Emad Elbeltagi 20

10
Introduction
Estimator Role
 The more valid data the estimator has available, the better he
will be able to estimate the probabilities of costs\
 The following factors affect the accuracy of cost estimates:
 Site, location and accessibility
 Subsurface and soil conditions
 Time and season
 Climatic conditions
 Wage agreements
 Market prices of basic materials
 The demand for construction

19/02/2016 Emad Elbeltagi 21

Introduction
What Estimator Must Know?
 Estimator should has a thorough knowledge of building trades
 This includes types of construction and methods of
construction
 Be able to read building plans and notes, and understand the
specifications
 If there is any discrepancies between the plans and
specifications, he/she will bring them to the attention of the
architect or owner for solution
 When all the questions are answered and problems are
solved, an estimate can be prepared and finished

19/02/2016 Emad Elbeltagi 22

11
Introduction
What Estimator Must Know?
 Thorough understanding of the building codes in the area the
building project is to be constructed
 Thorough understanding of construction materials
 Be able to substitute equal quality materials when specified
material are not available
 Be able to project labor cost changes
 Must realize that labor costs may vary in different
geographical areas of the country
 Must also realize and project in his estimates future
increases in labor costs because of upcoming events

19/02/2016 Emad Elbeltagi 23

Introduction
Construction Project Costs
 The principal components of a contractor's costs result from
the use of labors, materials, equipment, and subcontractors
 The costs that spent on a specific activity or project can be
classified as:
 Fixed cost
 Time-related cost
 Quantity-proportional cost
 Project direct costs
 Project indirect costs

19/02/2016 Emad Elbeltagi 24

12
Introduction
Cost Estimating: Indirect cost
Indirect costs comprises project (site); and General (head-office)
overheads

Project overheads
 The cost of items that cannot be directly charged to a specific
work element
 It includes site utilities, supervisors, parking, offices,
workshops, stores, first aid facility, et.
 A detailed analysis of site-related costs is required to arrive at
an accurate estimate of these costs
 Companies use their own forms and checklists for estimating
these costs. Site overhead costs are estimated to be between
5% - 15% of project total direct cost

19/02/2016 Emad Elbeltagi 25

Introduction
Cost Estimating: Indirect cost
General overheads
 The costs that cannot be directly attributed to a specific project
 They represent the cost of the head-office expenses, mangers,
directors, design engineers, schedulers, etc.
 Continuous observations of the company expenses help
estimating reasonable values for the general overhead
 For a given project, it can be estimated between 2% - 5% of

the contract direct cost

19/02/2016 Emad Elbeltagi 26

13
Introduction
Possible Sources of Estimate Errors
 Mistakes in material take-offs
 Errors in carrying forward material from quantity sheets to
summary sheets and from there to direct cost sheets
 Mistakes in estimating labor time required for certain work
 Errors in estimating hourly wages of labor
 Failure to allow for rising costs of materials
 Failure to allow for delays due to breakdown of machines and
other unforeseeable reasons
 Making no provisions to have estimates checked
 Insufficient allowance for overhead or Omission of profit
19/02/2016 Emad Elbeltagi 27

Introduction
Types of cost estimate
 When beginning to prepare an estimate, it is important to
understand its intended use
 An estimate can be prepared at any point through the project life
 Depending on the information available and the time spent
preparing the estimate, the accuracy it provides will vary
 here are four different stages at which estimates take place:
 Conceptual phase
 Schematic phase
 Design development phase
 Procurement phase
19/02/2016 Emad Elbeltagi 28

14
Introduction
Types of cost estimate: Conceptual estimate
 The owner needs cost information very early on in a project so that
decisions as to the location and scope can be made before money
is spent on design or property purchase
 Prepared with very little information, relying on historical data
 This type of estimate is called a Conceptual , Rough Order
 of Magnitude, top-down or parametric estimate and is generally
prepared long before the construction starts
 Sketch or a brief written description of the project

19/02/2016 Emad Elbeltagi 29

Introduction
Types of cost estimate: Conceptual estimate
 Project size is generally known in terms of capacity: number of
beds for a hospital or number of students for a school
 The time needed to prepare this type of estimate is short, generally
in the range of a half day or less
 The presentation of the conceptual phase estimate is generally
used for the purpose of a providing a target budget
 Conceptual phase estimates are often prepared for many different
options so that best alternative(s) can be selected

19/02/2016 Emad Elbeltagi 30

15
Introduction
Types of cost estimate: Schematic Design Phase
 As the project moves into the schematic stage, the designer and
possibly the construction manager have become involved in the
design and estimating of the project
 The project team may be incorporating different design alternatives
into the basic design
 A schematic estimate will be based on a design that is
approximately 30% designed and include the following information:
 Floor plans, elevations, and sections
 Outline specification for most trade sections
 Drawings for mechanical and electrical systems
19/02/2016 Emad Elbeltagi 31

Introduction
Types of cost estimate: Schematic Design Phase
 This estimate include some area take-off, for major project elements
 At this stage, some of the key sub-contractors might be asked for
input for complicated systems
 At the end of this stage, the presentation of the design to the owner
is accompanied by an estimate of the cost of the project
 Any design alternatives will also be accompanied by an estimate of
the cost of the project
 Before the project team moves on to the next phase of design, the
owner will decide on basic design parameters and on project budget
 Any cost reduction ideas are presented and priced
19/02/2016 Emad Elbeltagi 32

16
Introduction
Types of cost estimate: Design Phase
 In this phase, much more defined information
 Because of this, the time taken to prepare this type of estimates is
longer, but the accuracy is greater
 The estimate in this stage will be based on a design that is 60%
complete
 Most of the major project items will be quantifiable, and the more
important unit prices should be known at this point
 With the presentation of this estimate, the costs of the materials and
methods will be known and should be compared to past similar
projects
19/02/2016 Emad Elbeltagi 33

Introduction
Types of cost estimate: Design Phase
 Network scheduling will begin, allowing a better understanding of
the overall duration of the project as well as when each of the major
project elements is to be constructed
 Major assumptions should be noted and compared to what was
assumed at the schematic design stage
 The estimate at this stage is a tool used to verify that the design is
within the owner’s budget, and to identify any good cost saving
ideas

19/02/2016 Emad Elbeltagi 34

17
Introduction
Cost Estimating: detailed (Procurement) estimate
 It is also known as a bottom-up, fair-cost, or bid estimate
 Prepared once the design has been completed and all
construction documents prepared
 the estimator must make a complete and thorough job analysis
 For a detailed estimate, a thorough knowledge of labor,
material, equipment, crews, and methods of construction
should be collected

19/02/2016 Emad Elbeltagi 35

Introduction
Cost Estimating: detailed estimate
Efficiency
Project
Rates Formation
Task 1
Labors Method (s)
Crew
Quantity

Equip.
Resources Constraints
Cost
……
Duration ……
Material

Subs
Task i

19/02/2016 Emad Elbeltagi 36

18
Introduction
Types of cost estimate
 Conceptual cost estimates; incomplete project documentation
 Semi-detailed estimates are prepared when parts of the project
have been completed
 Detailed cost estimates are prepared based on fully developed
construction drawings and specifications

Expected
Type of Estimate Construction Document Development
Percent Error*
Schematic Design
Conceptual (Parametric) ± 10-25 %
0-30% Construction Documents

Design Development
Semi-Detailed ± 5-15 %
30-90% Construction Documents

Detailed 90-100% Plans and Specifications ± 2-5%


* Percent error means the expected variation between cost estimate and actual cost
19/02/2016 Emad Elbeltagi 37

Introduction
Types of cost estimate: estimate accuracy

high
Accuracy

low Information
less more

Concept Design Construction O&M

19/02/2016 Emad Elbeltagi 38

19
Introduction
Types of cost estimate: estimate accuracy

19/02/2016 Emad Elbeltagi 39

Introduction
Cost Estimating: Steps of detailed estimate
Review the scope of project. Consider the effect of location, security,
1
traffic, available storage space, underground utilities, etc. on costs.
Determine quantities. Perform a material quantity takeoff for all work
2
items.
3 Obtain suppliers’ bids.
4 Price material. Material cost = quantity x unit price.
5 Price labor based on their probable production rate.
6 Price equipment based on their probable production rates.
7 Obtain specialty contractors’ bids.
8 Calculate taxes, bonds, insurance and overhead.
9 Contingency and markup. Add costs for potential unforeseen work.
10 Profit. Add costs for compensation for performing the work.

19/02/2016 Emad Elbeltagi 40

20
Introduction
Cost Estimating: detailed estimate
Example : The daily production rate of a crew is 175 units/day and
the total crew cost per day is $1,800. The material needed for daily
work is 4.5 units of $100/unit:
Calculate the time and cost it takes the crew to finish 1,400 units.
Calculate the total unit cost. Consider an eight hour work day

Solution
Duration = Quantity / Production per unit of time = 1400 / 175 = 8
days.
Crew Cost = Duration x Cost per unit = 8 days x $1800/day =
$14,400.
Total Cost = Crew cost + Material cost = $14,400 + 4.5 units x 8 days
x $100/unit = $18,000
Unit cost = Total cost / quantity = $18,000/1400 = $12.86 / unit.

19/02/2016 Emad Elbeltagi 41

Introduction
Quantity Take-off
 A quantity takeoff is necessary to perform a cost estimate
 The quantity of material in a project can be accurately
determined from the drawing
 the estimator must make a complete and thorough job analysis
 The unit cost of different materials should be obtained from
material suppliers
 Cost of delivery and wastage should be included
 The material quantity takeoff is extremely important for cost
estimating

19/02/2016 Emad Elbeltagi 42

21
Introduction
Production Rates
 To determine the time required to perform a given quantity of
work, it is necessary to estimate the production rates of the
equipment or labor
 A production rate is the number of units of work produced by a
unit of equipment or a person in a specified unit of time
 These rates are subject to considerable variation, depending on
the difficulty of the work, skill of the labor, management
conditions and the condition of the equipment prepared

19/02/2016 Emad Elbeltagi 43

Introduction
Production Rates: Example
 A backhoe with 1 m3 bucket capable of handling 3 bucket-
loads per minute. The average volume per bucket is 0.8 m3
and the backhoe is operating for 45 min/hr. The average output
can be calculated as follows:

The ideal output: 3 m3/min x 60 min/hr = 180 m3/hr


The bucket factor = 0.8
The efficiency factor = 45/60 = 0.75
The combined operating factor = 0.8 x 0.75 = 0.6
The average output = 0.6 x 180 = 108 m3/hr

19/02/2016 Emad Elbeltagi 44

22

Das könnte Ihnen auch gefallen