Beruflich Dokumente
Kultur Dokumente
Introduction
Project Characteristics
Defined goal or objective stated by the owner and accomplished by
the project team
Specific tasks to be performed
Defined beginning and end
Resources being consumed. The 4 Ms (Manpower, Machinery,
Materials, and Money,)
As the project progresses, the project team learns more about the
project
Information Time
1
Introduction
Project Life Cycle
Introduction
Project Life Cycle (Project stages)
As the construction
progresses, the
cost increases while
the influence
decreases
2
Introduction
Types of Contracts
Contracts are classified according to the method of
payment to the contractor
Contracts
Introduction
Type of Contracts
What is the difference between cost & price?
Price
Margin Cost
Profit
Indirect cost Direct cost
Risk allowance
Site overhead Labor
Financial charge Office overhead Material
Equipment
Subcontractors
19/02/2016 Emad Elbeltagi 6
3
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Unit price or Admeasurement contract
Work items are given in detail (BOQ; Bill of Quantities)
The contractor set a price for each item; the owner doesn’t know the
details of each item pricing
Changes are allowed with 25% only
When new items are added, the price of these items should be studied.
Claims might arises between owner and contractor.
4
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Unit price contract
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Unit price contract
Advantages:
Owner aware of the project details
5
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Lump Sum ()ﻋﻘﺪ اﻟﻤﻘﻄﻮﻋﯿﺔ
A single tendered price is given for the completion of specified
work
Payment may be staged at intervals on the completion
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Cost-Plus ()ﻋﻘﺪاﻟﺘﻜﻠﻔﺔ ﻣﻊ اﺳﺘﺮداد ﻧﺴﺒﺔ ﻣﻦ اﻟﻤﺼﺮوﻓﺎت أو اﻟﺘﻜﻠﻔﺔ واﻻﺿﺎﻓﺔ
The contractor is reimbursed for actual cost plus a special fee
6
Introduction
Type of Contracts
1. Unit Price 3. Cost Plus
2. Lump Sum 4. Target Cost
Target Cost ()ﻋﻘﺪاﻟﺘﻜﻠﻔﺔ اﻟﻤﺴﺘﮭﺪﻓﺔ
Same as previous type (cost-plus)
Introduction
Cost Estimating
Cost Estimating may be defined as:
Estimating is the compilation of all the costs of the elements of
a project within an agreed upon project scope
it is the production of a statement of the approximate quantity
of materials, time and costs to perform construction decisions
The basic challenges the construction contractor faces are to
estimate the cost of constructing a project
The objective of cost estimate is to produce an accurate, cost
effective prediction of what a project will most likely cost and it
needs to be done in different manners at different stages
7
Introduction
Cost Estimating
Required data:
Detailed plans, specifications, available site data, available
resource data (labor, material, & equipment), contract
documents, resource cost information, pertinent
government regulations, applicable owner requirements an
agreed upon project scope
Introduction
Cost Estimating is a Probabilistic Activity
An estimate involves calculating the costs of work on the basis of
probabilities:
Two activities are involved when carrying out an estimate:
Measurements: all measurements are approximate
Pricing: the degree of approximation is even greater
because of the difficulty in predicting all the probabilities of
items such as labor productivity and site conditions
8
Introduction
Estimating Purpose
The purpose of estimating is to forecast the cost required
to complete a project in accordance with the contract plans
and specifications
There are two distinct tasks in estimating:
To determine the probable real cost of the project
To determine the probable real time to build the project
Because construction estimates are prepared before a
project is constructed, an estimate is, at best, a close
approximation of the actual costs
Introduction
Estimating Purpose
The true value of the project will not be known until the
project has been completed and all costs have been
recorded
Therefore, the estimator does not establish the cost of a
project; he simply establishes the amount which the
contractor will receive for constructing the project.
9
Introduction
Estimator (Quantity Surveyor)
the person who prepares estimates in the planning, design,
and perhaps construction stages
Understanding of the principles and methods of engineering
economics
Estimator decisions are very crucial for his/her company
An estimator must not spend so much time and effort to
analyze unnecessary details in determining the costs of
insignificant items as the estimating will take time and be
expensive
Introduction
Estimator Role
The estimator’s job is to prepare estimates of project costs
The success of a contractor’s business depends on the
accuracy of these estimates.
The estimator’s success will be based on his previous
experience and knowledge of the construction industry
A contractor or estimator lacking this experience may over-, or
under-estimates project costs
All cost data is acquired from experience. If an estimator does
not have cost data from his/her own experience, he/she must
use cost data from price books and handbooks
10
Introduction
Estimator Role
The more valid data the estimator has available, the better he
will be able to estimate the probabilities of costs\
The following factors affect the accuracy of cost estimates:
Site, location and accessibility
Subsurface and soil conditions
Time and season
Climatic conditions
Wage agreements
Market prices of basic materials
The demand for construction
Introduction
What Estimator Must Know?
Estimator should has a thorough knowledge of building trades
This includes types of construction and methods of
construction
Be able to read building plans and notes, and understand the
specifications
If there is any discrepancies between the plans and
specifications, he/she will bring them to the attention of the
architect or owner for solution
When all the questions are answered and problems are
solved, an estimate can be prepared and finished
11
Introduction
What Estimator Must Know?
Thorough understanding of the building codes in the area the
building project is to be constructed
Thorough understanding of construction materials
Be able to substitute equal quality materials when specified
material are not available
Be able to project labor cost changes
Must realize that labor costs may vary in different
geographical areas of the country
Must also realize and project in his estimates future
increases in labor costs because of upcoming events
Introduction
Construction Project Costs
The principal components of a contractor's costs result from
the use of labors, materials, equipment, and subcontractors
The costs that spent on a specific activity or project can be
classified as:
Fixed cost
Time-related cost
Quantity-proportional cost
Project direct costs
Project indirect costs
12
Introduction
Cost Estimating: Indirect cost
Indirect costs comprises project (site); and General (head-office)
overheads
Project overheads
The cost of items that cannot be directly charged to a specific
work element
It includes site utilities, supervisors, parking, offices,
workshops, stores, first aid facility, et.
A detailed analysis of site-related costs is required to arrive at
an accurate estimate of these costs
Companies use their own forms and checklists for estimating
these costs. Site overhead costs are estimated to be between
5% - 15% of project total direct cost
Introduction
Cost Estimating: Indirect cost
General overheads
The costs that cannot be directly attributed to a specific project
They represent the cost of the head-office expenses, mangers,
directors, design engineers, schedulers, etc.
Continuous observations of the company expenses help
estimating reasonable values for the general overhead
For a given project, it can be estimated between 2% - 5% of
13
Introduction
Possible Sources of Estimate Errors
Mistakes in material take-offs
Errors in carrying forward material from quantity sheets to
summary sheets and from there to direct cost sheets
Mistakes in estimating labor time required for certain work
Errors in estimating hourly wages of labor
Failure to allow for rising costs of materials
Failure to allow for delays due to breakdown of machines and
other unforeseeable reasons
Making no provisions to have estimates checked
Insufficient allowance for overhead or Omission of profit
19/02/2016 Emad Elbeltagi 27
Introduction
Types of cost estimate
When beginning to prepare an estimate, it is important to
understand its intended use
An estimate can be prepared at any point through the project life
Depending on the information available and the time spent
preparing the estimate, the accuracy it provides will vary
here are four different stages at which estimates take place:
Conceptual phase
Schematic phase
Design development phase
Procurement phase
19/02/2016 Emad Elbeltagi 28
14
Introduction
Types of cost estimate: Conceptual estimate
The owner needs cost information very early on in a project so that
decisions as to the location and scope can be made before money
is spent on design or property purchase
Prepared with very little information, relying on historical data
This type of estimate is called a Conceptual , Rough Order
of Magnitude, top-down or parametric estimate and is generally
prepared long before the construction starts
Sketch or a brief written description of the project
Introduction
Types of cost estimate: Conceptual estimate
Project size is generally known in terms of capacity: number of
beds for a hospital or number of students for a school
The time needed to prepare this type of estimate is short, generally
in the range of a half day or less
The presentation of the conceptual phase estimate is generally
used for the purpose of a providing a target budget
Conceptual phase estimates are often prepared for many different
options so that best alternative(s) can be selected
15
Introduction
Types of cost estimate: Schematic Design Phase
As the project moves into the schematic stage, the designer and
possibly the construction manager have become involved in the
design and estimating of the project
The project team may be incorporating different design alternatives
into the basic design
A schematic estimate will be based on a design that is
approximately 30% designed and include the following information:
Floor plans, elevations, and sections
Outline specification for most trade sections
Drawings for mechanical and electrical systems
19/02/2016 Emad Elbeltagi 31
Introduction
Types of cost estimate: Schematic Design Phase
This estimate include some area take-off, for major project elements
At this stage, some of the key sub-contractors might be asked for
input for complicated systems
At the end of this stage, the presentation of the design to the owner
is accompanied by an estimate of the cost of the project
Any design alternatives will also be accompanied by an estimate of
the cost of the project
Before the project team moves on to the next phase of design, the
owner will decide on basic design parameters and on project budget
Any cost reduction ideas are presented and priced
19/02/2016 Emad Elbeltagi 32
16
Introduction
Types of cost estimate: Design Phase
In this phase, much more defined information
Because of this, the time taken to prepare this type of estimates is
longer, but the accuracy is greater
The estimate in this stage will be based on a design that is 60%
complete
Most of the major project items will be quantifiable, and the more
important unit prices should be known at this point
With the presentation of this estimate, the costs of the materials and
methods will be known and should be compared to past similar
projects
19/02/2016 Emad Elbeltagi 33
Introduction
Types of cost estimate: Design Phase
Network scheduling will begin, allowing a better understanding of
the overall duration of the project as well as when each of the major
project elements is to be constructed
Major assumptions should be noted and compared to what was
assumed at the schematic design stage
The estimate at this stage is a tool used to verify that the design is
within the owner’s budget, and to identify any good cost saving
ideas
17
Introduction
Cost Estimating: detailed (Procurement) estimate
It is also known as a bottom-up, fair-cost, or bid estimate
Prepared once the design has been completed and all
construction documents prepared
the estimator must make a complete and thorough job analysis
For a detailed estimate, a thorough knowledge of labor,
material, equipment, crews, and methods of construction
should be collected
Introduction
Cost Estimating: detailed estimate
Efficiency
Project
Rates Formation
Task 1
Labors Method (s)
Crew
Quantity
Equip.
Resources Constraints
Cost
……
Duration ……
Material
Subs
Task i
18
Introduction
Types of cost estimate
Conceptual cost estimates; incomplete project documentation
Semi-detailed estimates are prepared when parts of the project
have been completed
Detailed cost estimates are prepared based on fully developed
construction drawings and specifications
Expected
Type of Estimate Construction Document Development
Percent Error*
Schematic Design
Conceptual (Parametric) ± 10-25 %
0-30% Construction Documents
Design Development
Semi-Detailed ± 5-15 %
30-90% Construction Documents
Introduction
Types of cost estimate: estimate accuracy
high
Accuracy
low Information
less more
19
Introduction
Types of cost estimate: estimate accuracy
Introduction
Cost Estimating: Steps of detailed estimate
Review the scope of project. Consider the effect of location, security,
1
traffic, available storage space, underground utilities, etc. on costs.
Determine quantities. Perform a material quantity takeoff for all work
2
items.
3 Obtain suppliers’ bids.
4 Price material. Material cost = quantity x unit price.
5 Price labor based on their probable production rate.
6 Price equipment based on their probable production rates.
7 Obtain specialty contractors’ bids.
8 Calculate taxes, bonds, insurance and overhead.
9 Contingency and markup. Add costs for potential unforeseen work.
10 Profit. Add costs for compensation for performing the work.
20
Introduction
Cost Estimating: detailed estimate
Example : The daily production rate of a crew is 175 units/day and
the total crew cost per day is $1,800. The material needed for daily
work is 4.5 units of $100/unit:
Calculate the time and cost it takes the crew to finish 1,400 units.
Calculate the total unit cost. Consider an eight hour work day
Solution
Duration = Quantity / Production per unit of time = 1400 / 175 = 8
days.
Crew Cost = Duration x Cost per unit = 8 days x $1800/day =
$14,400.
Total Cost = Crew cost + Material cost = $14,400 + 4.5 units x 8 days
x $100/unit = $18,000
Unit cost = Total cost / quantity = $18,000/1400 = $12.86 / unit.
Introduction
Quantity Take-off
A quantity takeoff is necessary to perform a cost estimate
The quantity of material in a project can be accurately
determined from the drawing
the estimator must make a complete and thorough job analysis
The unit cost of different materials should be obtained from
material suppliers
Cost of delivery and wastage should be included
The material quantity takeoff is extremely important for cost
estimating
21
Introduction
Production Rates
To determine the time required to perform a given quantity of
work, it is necessary to estimate the production rates of the
equipment or labor
A production rate is the number of units of work produced by a
unit of equipment or a person in a specified unit of time
These rates are subject to considerable variation, depending on
the difficulty of the work, skill of the labor, management
conditions and the condition of the equipment prepared
Introduction
Production Rates: Example
A backhoe with 1 m3 bucket capable of handling 3 bucket-
loads per minute. The average volume per bucket is 0.8 m3
and the backhoe is operating for 45 min/hr. The average output
can be calculated as follows:
22