PRESUPUESTO BASE

OBRA: CONTRUCCION DE MURO PERIMETRICO EN EL BARRIO 5A


PROPIETARIO: CRUZ BACILIO JERRY A.

ITEM DESCRIPCION UND. CANT. P.UNITARIO P. PARCIAL


1.00 ALBAÑILERIA
1.1 MURO LONGITUDINAL LADRILLO K.K. SOGA M2. 367.69 87.04 32,003.74
(.09x.13x.24m) MEZCLA 1:5, e=1.5 cm.
2.00 TARRAJEO
2.1 REVOQUES Y REVESTIMIENTOS M2. 920.45 70.07 64,495.93
3.00 PINTURA
3.1 PINTURA LATEX BLANCA Y AZUL M2. 920.45 8.79 8090.7555
OTRAS PARTIDAS 104,590.42
COSTO DIRECTO: S/.
GASTOS GENERALES 12.28%: S/.
SUBTOTAL
COSTO TOTAL DE OBRA: S/.
P. TOTAL
32,003.74

64,495.93

8,090.76

104,590.42
209,180.85
29,285.32
238,466.17
238,466.17
ANALISIS DE COSTOS UNITARIOS

OBRA: MURO PERIMETRICO EN EL BARRIO 5 "A" ALTO TRUJILLO


PROPIETARIO: CRUZ BACILIO JERRY

Partida: 3.01.01 MURO LONGITUDINAL LADRILLO K.K. SOGA (.09x.13x.24m) MEZCLA 1:5, e=1.5 cm.

RENDIMIENTO: M2/Dia 25 COSTO UNITARIO: S/. 87.04

CODIGO DESCRIPCION INSUMO UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL


MANO DE OBRA
470102 OPERARIO HH 1.00 0.32 24.20 7.74 8
470103 OFICIAL HH 1.00 0.32 20.50 6.56
470104 PEON HH 1.00 0.32 17.80 5.70
20.00
MATERIALES
50104 ARENA GRUESA M3 0.40 39.14 15.66
170003 LADRILLO K.K. DE 9X13X24 CM. UND 48.00 0.86 41.28
210000 CEMENTO PORTLAND TIPO I BL 0.40 21.21 8.48
AGUA M3 0.02 0.40 0.01
65.43
EQUIPO
370101 HERRAMIENTAS MANUALES (% MO) 5.00 35.99 1.00
ANDAMIO METALICO DIA 0.25 0.02 30.00 0.62
1.62

Partida: 03.02.00 REVOQUES Y REVESTIMIENTOS

RENDIMIENTO: 12 M2/Dia COSTO UNITARIO: S/. 70.07

CODIGO DESCRIPCION INSUMO UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL


MANO DE OBRA
470102 OPERARIO HH 1.00 0.66 21.6 14.26
470103 OFICIAL HH 1.00 0.66 19.3 12.74
470104 PEON HH 0.50 0.33 16.8 5.54
32.54
MATERIALES
40000 ARENA FINA M3 0.40 50.00 20.00
210000 CEMENTO PORTLAND TIPO I BL 0.70 22.50 15.75
440016 AGUA M3 0.05 0.40 0.02
35.77
EQUIPO
370101 HERRAMIENTAS MANUALES (5% MO) 0.62
ANDAMIO DE MADERA P2 0.30 3.80 1.14
1.76

Partida: 03.04.00 PINTURA

RENDIMIENTO: 34 M2/Dia COSTO UNITARIO: S/. 8.79

CODIGO DESCRIPCION INSUMO UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL


MANO DE OBRA
470102 OPERARIO HH 1.00 0.23 12.35 2.84
470104 PEON HH 0.50 0.11 9.95 1.10
3.94
MATERIALES
540327 PINTURA LATEX AZUL GL 0.05 44.90 2.25
820101 BASE BLANCA GL 0.05 25.50 1.28
3.52
EQUIPO
370101 HERRAMIENTAS MANUALES ( 5% MO ) 0.20
435501 ANDAMIO DE MADERA P2 0.30 3.80 1.14
1.34