Beruflich Dokumente
Kultur Dokumente
1
AR519B Outline by Ar.MCPSoriano
wash and polish glazing, marble and tile work
8. Certificate of completion – an attestation by the AOR that work have been substantially
completed and has satisfactorily passed final test of materials prescribed in the contract;
Substantial completion – value of work completed is not less than 98% of the CA and the
remaining unfinished work is of minor nature only;
9. Notice to proceed – instruction to the contractor to commence work;
10. Contract time – the total project duration to complete the works stipulated in the contract
expressed in calendar days, and starts on the 7th day from the receipt of the NTP;
11. Schedule of completion – the planned date(s) for performing work or activities and the
planned dates for meeting milestones the schedule must be presented in a schematic
display of the logical relationships among the project activities, always drawn from left to
right to reflect project work chronology [PMBOK Guide, 2004]; to include the following data:
Starting and completion dates of each item of work
Equipment to be used
Number of men to be employed
Budget
Progress rate
12. Extension of time – an increase in the length of contract time, allowed on the following
conditions:
Owner’s default
Strikes
Force majeure
Pending arbitration
13. Liquidated damages – payment to the Owner for every of delay of the completion of work
by the contractor (failure to complete work within the contract time);
14. Breakdown of work & corresponding value – document showing the value assigned to
each part of the work including allowance for profit and overhead and will be used as basis
for all requests for payment;
15. Request for payment – amount computed from the work completed on all items in the
BWCV, less 10% retention and previous payments, that a contractor may submit to the
Owner periodically;
2
AR519B Outline by Ar.MCPSoriano
16. Progress billing – request for payment equal to the completed items of work; computation
and progress photographs as supporting documents;
17. Contractor’s obligations – contractor will pay punctually all workmen employed by him for
the project at rates provided by lay; to pay all taxes, materials and equipment (evidences:
signed payroll, receipts, etc...);
18. Correction of work – to replace and re-execute work that failed to conform to the contract;
Retention period – 6 months to one year;
19. Acceptance – the act of formally receiving or acknowledging a building (or portions thereof)
and regarding it as being true, sound, suitable or complete in conformance to contract
specifications[PMBOK Guide, 2004];
20. Retention fee – a portion of a contract payment that is withheld until contract completion
to ensure full performance of the contract terms;
21. Indemnity – a security against damage which exempts the Owner from all losses and all
claims, demands, payments, suits, actions, recoveries, and judgment of every nature and
description brought or recovered against him, by reason of any act or omission of said
Contractor, his agents or employees, in the execution of the work or the guarding of it;
22. Liability – a pecuniary obligation including contingencies or action plan to fulfil this
obligation in accordance with the contract; debts or obligations owed to others;
23. Lien – a charge upon a property or item of work that had been satisfactorily complied
according to contract; claim;
24. Dispute – to call into question an item of work which was deemed as not conforming to
specification; argument between Owner and contractor;
25. Arbitration - the hearing and determination of a case in controversy, i.e. dispute;
B. Enumeration:
3. Owner’s responsibilities:
a. Protection of employees and professionals performing services for the Owner
b. Optional insurance
4. Contractor’s responsibilities;
a. Safety measures
b. Insurance: Liability and Fire
c. Performance and Payment Bonds
d. Guaranty-Warranty
4
AR519B Outline by Ar.MCPSoriano