FOOTING EXCAVATION
OUTLINE
SUBSEQUENTLY, THE FOOTING EXCAVATION SHOULD FOLLOW AFTER THE FOOTING LAYOUT. IF
HARD SOIL, THE CONCRETE BREAKER CAN BE UTILIZED. IF SOFT, THIS CAN BE MANUALLY DONE
UTILIZING THE HOE AND SHOVEL.
BOOK 1 – PAGE
10
WIDTH OF
FOOTING
SHORING OR
RETAINING BOARD
DEEP OF FOOTING
EXCAVATION
RETAINING BOARD IS REQUIRED IF SOFT SOIL EXCAVATION. USUALLY, THE FOOTING FORM ITSELF
CAN BE UTILIZED FOR THE RETAINING BOARD.
P-1
BOOK 1 – PAGE
WIDTH OF
10
FOOTING
TRIM
SHORING OR
RETAINING BOARD
DEEP OF FOOTING
EXCAVATION
THE TOP PORTION OF THE RETAINING BOARD SHOULD BE TRIMMED TO EASILY REMOVE THE
BOARD AFTER CONCRETING OF FOOTING.
FOOTING 11
FOOTING
TIE-BEAM
AFTER POURING OF LEAN CONCRETE OR LAYING OF GRAVEL ON FOOTING BED, THE RSB FOR
COLUMN-FOOTING SHOULD FOLLOW THEN THE RSB FOR FOOTING TIE-BEAM.
P-2
BOOK 1 – PAGE
3 A
18
CONCRETED
COLUMN-FOOTINGS
AFTER CONCRETING OF COLUMN-FOOTING, THE RSB FOR FOOTING-TIE-BEAM SHOULD FOLLOW THEN
ITS SIDE-FORMING. AT THIS POINT, INSTALL THE STARTER BARS FOR WALL.
BOOK 1 – PAGE
18
3 A
B
2
P-3
3 A BOOK 1 – PAGE
18
STARTER BARS
B
2
FOOTING TIE-BEAM
CORNER FOOTING
FOOTING -COLUMN
AFTER CONCRETING OF FOOTING TIE-BEAM, REMOVAL OF ITS FORM SHOULD FOLLOW. THEN,
COMPLETE THE RSB FOR WALL-FOOTING
3 A
STARTER BARS
B
2
HORIZONTAL BARS
WOODEN SIDE-FORM
P-4
CONCRETED FOOTING TIE-BEAM & COLUMN
A B C D
WF-1
3
A BOOK 1 – PAGE
30
2 B
STARTER BARS
FOOTING TIE-BEAM
WALL FOOTING
AFTER CONCRETING OF WALL-FOOTING, REMOVE THE SIDE-FORMS & CLEAN THE INSIDE PORTION OF
FOOTING & SLAB FOUNDATION. THIS IS IN PREPARATION FOR BACKFILLING.
P-5
BOOK 1 – PAGE
BACKFILLED SOIL
A 30
3
2 B
BACKFILLED GRAVEL
1
CONSTRUCTION JOINT
AFTER CONCRETING OF WALL-FOOTING, THE BACKFILLING WORK CAN ALREADY START. THE
BACKFILLING CAN BE DONE IN LAYER-BY-LAYER AT 0.20 M. THICK THOROUGHLY COMPACTED.
BOOK 1 – PAGE
30
FLOOR SLAB
UNDERGROUND CABLE
FINISH PVC DRAINAGE PIPE LINE
P-6
BOOK 1 – PAGE
CONCRETED SLAB
A 30
3
B
2
BACKFILLED SOIL
AFTER FINAL COMPLETION OF BACKFILLING & COMPACTION, UNDER- GROUND UTILITIES, GRAVEL
BEDDING & INSTALLATION OF RSB, CONCRETING OF SLAB SHOULD FINALLY DONE.
3 A 28
2 B
STEELSTEEL
PLATFORM
PLATFORM
1
WOODEN BRACES
WOODEN BRACES&
SUPPORTS
& LATERAL
SUPPORTS
AFTER THE CONCRETING OF GROUND SLAB, INSTALLATION OF RSB & SIDE-FORMING FOR COLUMN
SHOULD FOLLOW. THE VERTICAL ALIGNMENT OF COLUMNS IS VERY IMPORTANT.
P-7
ASSEMBLY DETAIL OF BOTTOM SUPPORT BOOK 1 – PAGE
33
CHANNEL
ADJUSTABLE U-SUPPORT
STEEL POST
CONNECTING PIN
ADJUSTABLE KEY
H-FRAME
BASE JACK
STL. CHANNEL
X-BRACE
TUBULAR &
TUB. CLAMP
H-FRAME
TUBULAR &
TUB. CLAMP
TIMBER PLANK
BASE JACK
THE TOP & BOTTOM DRAWINGS SHOW THE TYPICAL ASSEMBLY OF BOTTOM SUPPORT & FORM FOR
THE SECOND FLOOR CONSTRUCTION UTILIZING H-FRAMES, STEEL POSTS & OTHER STEEL FORM’S
ACCESSORIES.
P-8
BEAM & SLAB UNDER SUPPORT ASSEMBLY BOOK 1 – PAGE
35
H-FRAMES
H-FRAMES STEEL GIRT
STEEL
STEEL BOTTOM
PLATFORM
FORM
3
WOODEN
WOODENPLANK (BASE)
PLANK -
A
2 BASE
STEEL
STEEL POSTS
POSTS
B
1
ISOMETRIC DIAGRAM SHOWING THE UNDER-SUPPORT & BOTTOM FORM OF BEAM UTILIZING THE
STEEL POST & STEEL FORM RESPECTIVELY. ALSO, SHOWS THE H-FRAMES FOR SLAB.
8 39 9
4 5
6 5
ELEVATION SHOWING UNDER-SUPPORT & BOTTOM FORM OF BEAM & SLAB UTILIZING STEEL POST
& H-FRAMES RESPECTIVELY.
P-9
BEAM & SLAB UNDER
BEAM UNDER-SUPPORT & SUPPORT ASSEMBLY
BOTTOM FORM ASSEMBLY
BOOK 1 – PAGE
39 STEEL
ELEVATION SHOWING UNDER-SUPPORT & BOTTOM FORM & SIDE-FORM OF BEAM UTILIZING
POST & STEEL-FORM RESPECTIVELY.
TRANSVERSE
CHANNEL
LONGITUDINAL
CHANNEL
2
"SEROJO" STEEL FORMS
A B C
SECTION ALONG
GL-C
AFTER COMPLETION OF BEAM’S ENTIRE UNDER-SUPPORT & BOTTOM FORM, THE SLAB-FRAMING &
FLOORING SHOULD FOLLOW
P-10
PLAN SHOWING COMPLETE FLOORING BOOK 1 – PAGE
39
1
A B C
SECTION ALONG
GL-C
AFTER COMPLETION OF BEAM’S ENTIRE UNDER-SUPPORT & BOTTOM FORM, THE
SLAB-FRAMING & FLOORING SHOULD FOLLOW
SIDE FORM
BOTTOM FORM
STEEL CHANNEL
ADJUSTABLE U-SUPPORT
H-FRAME
STEEL POST
P-11
SECTION OF EXTERIOR BEAM SHOWING FORMING DETAIL
SIDE FORM
BOTTOM FORM
TUBULAR CLAMP
TUBULAR PIPE
STEEL CHANNEL
ADJUSTABLE U-SUPPORT
H-FRAME
STEEL POST
BAR HANGER
STIRRUP
P-12
Procedure No.
Procedure 2: Tie
No. 2: partial
Installofthe
stirrups and installalong
bar hangers the entire
thebars
beamandline
arrange/tie
and the
assemble the bars.
entire stirrups.
Procedure No. 3: After tying the stirrups with the horizontal bars,
Procedure No. 3: release
After tying
thethe stirrups withbars
assembled the horizontal
from thebars, release the
hangers
assembledandbars fix into
from thethe beam’s
hangers form.
and fix into the beam’s form.
BAR HANGER
BAR
HANGER
BOOK 1 – PAGE
1st1stStep:
47 Bar
Step: Installation
Bar Installation
BAR-3
HANGER
STIRRUPS
Prepare 3 pieces of Bar-3 and the entire bar stirrups. Arrange the 3 pieces Bar-3 on hangers
Prepare
Prepare 33 pieces
pieces ofof Bar-3
Bar-3 and
and all
all the
the bar
bar stirrups.
stirrups. Align
Align the
the 33 pieces
pieces Bar-3
Bar-3 on
hangers
on hangerswith
with the thestirrups
entire
with entire
the stirrups
at
entirerequiredatspacing.
stirrups required spacing.
Finally,
at required tie theFinally,
spacing.stirrups tie the
with
Finally, stirrups
thethe
tie Bar-3
with thewith
stirrups Bar-3.
the Bar-3.
P-13
2ndStep:
2nd BarInstallation
Step: Bar Installation BAR-5
BAR-4
BAR-3
HANGER
STIRRUPS
Prepare 2 pieces of Bar-4 and 2 pieces Bar-5. Install these top bars as shown.
Prepare
Prepare 22pieces
piecesofofBar-4
Bar-4and
and22pieces
piecesBar-5.
Bar-5.Install
Installthese
thesetop
topbars
barsasasshown.
shown
3rdStep:
3rd Step:Bar
Bar Installation
Installation BAR-5
BAR-6
BAR-2
Prepare 3 pieces of Bar-2 and 2 pieces Bar-6. Arrange and tie these bars with the
Prepare 3 pieces of Bar-2 and 2 pieces Bar-6. Install these bottom bars as
shown. stirrups.
P-14
4th Step:
4th Step:Bar
Bar Installation
Installation
BOOK 1 – PAGE
47
ReleaseRelease
the RSBthefrom
RSB from
thethe hangersand
hangers andinstall
install into
intothe
theform.
form.
ELEVATION
ELEVATION SHOWING INSTALLED
SHOWING INSTALLEDRSBRSB
- BEAM
- BEAM
P-15
SLAB FORM
3 A
“SEROJO”
2
B
CONTINUOUS RSB – 3 A
UPPER COLUMNS
SLAB FORM
2 B
After completion of RSB for beam, the slab form and side-forming of beams should follow. (Refer to the
Section Detail of Exterior & Interior Beam for reference).
P-16
W/4 W/2 W/4 W/4 W/2 W/4
L/4
L/2
L/4
A TRANSVERSE BOTTOM C
B
BARS 1
2
TRANSVERSE BOTTOM BARS
2nd Step: Bar Installation 2nd Step: Bar Installation – Slab BOOK 1 – PAGE
<>Install the entire bottom bars along the transverse way. 53
<>Install the entire bottom bars along the transverse way.
P-17
BOOK 1 – PAGE
A 53
1
B
2
C
TRANSVERSE BOTTOM
TRANSVERSE BOTTOM BARS
BARS
2
LONGITUDINAL BOTTOM BARS
3rd Step: Bar Installation 3rd Step: Bar Installation – Slab BOOK 1 – PAGE
<>Install the entire bottom
<>Install barsbottom
the entire alongbars
thealong
longitudinal way. way.
the longitudinal 53
AT THIS STAGE, THE BOTTOM BARS FOR THE TWO PANEL SLAB IS ALREADY INSTALLED & COMPLETED.
ALONG GRIDLINE- 2 & C ARE ADJACENT SLAB, THUS, THE RSB ARE CONTINUOUS.
P-18
TRANSVERSE SHORT BARS
COMPLETE
ISOMETRIC DIAGRAM SHOWING BOTTOM
COMPLETED BARS
BOTTOM BARS OF TWO SLAB PANELS.
A B C
1
2
LONGITUDINAL TOP BARS
AFTER COMPLETION OF BOTTOM BARS, THE LONGITUDINAL TOP BARS SHOULD FOLLOW. THE
LONGITUDINAL BARS SHOULD BE CONTINUOUS TO THE ADJACENT SLAB.
P-19
BOOK 1 – PAGE
TRANSVERSE TOP BARS ON TOP OF LONGITUDINAL TRANSVERSE TOP BARS ON TOP OF LONGITUDINAL
A TOP BARS B TOP BARS
C
1
2
TRANSVERSE TOP BARS
5th Step: Bar Installation 5th Step: Bar Installation – Slab BOOK 1 – PAGE
<>Install the entire<>Install
top bars thealong
entirethe transverse
top bars along theway.
transverse way. 54
AFTER COMPLETION OF LONGITUDINAL TOP BARS, THE TRANSVERSE TOP BARS SHOULD FOLLOW. THE
TRANSVERSE BARS SHOULD BE CONTINUOUS TO THE ADJACENT SLAB.
P-20
BOOK 1 – PAGE
3 A 53
L/4 L1/4
L1
L1/2
L
L/2
L1/4
B
2 L/4
L/4
L/4
A BOOK 1 – PAGE
3
54
L/4 L1/4
L1
L L1/2
L/2
L1/4 A1
2 L1/4
L/4
P-21
EMBEDDED PVC DOWNSPOUT
112
113
STARTER BARS FOR WALL
P-22
114
3 A
2 B
L/4
115
STEEL CHANNEL
ADJUSTABLE U-SUPPORT
H-FRAME
SECTION OFOF
SECTION BEAM SHOWING
BEAM SHOWING RSB
ASSEMBLY WITH SLAB
RSB ASSEMBLY WITH SLAB STEEL POST
P-23
116
TUBULAR PIPE
SUPPORT
TUBULAR CLAMP
TUBULAR PIPE
STEEL CHANNEL
ADJUSTABLE U-SUPPORT
H-FRAME
SECTION OF BEAM SHOWING RSB
SECTION SHOWING RSB
ASSEMBLY AT END STEEL POST
ASSEMBLY AT EXTERIOR BEAM
120
CONSTRUCTION JOINT
P-24
BOOK 1 – PAGE
121
62
JUNCTION BOX
WATER CLOSET INLET FLOOR DRAIN
HANGER
PVC P-TRAP
CLEAN-OUT PVC PIPE
BOOK 1 – PAGE
125
PLATFORM BOTTOM ELEVATION OF BEAM
65
AT THIS STAGE, THE MASONRY WORK AT GROUND FLOOR COULD FOLLOW. THE INSTALLATION
OF CHB WALL COULD START ON BOTH EXTERIOR & INTERIOR WALLS
P-25
BOOK 1 – PAGE
133
67
A 2
STEEL POSTS
H-FRAMES
B
1
ISOMETRIC DWG. SHOWING INSTALLED RSB & SIDE FORMS – ROOF BEAM
BOOK 1 – PAGE
134
BASE PLATES 67
3
A
2
B
1
P-26
BOOK 1 – PAGE
136
70
STEEL PURLINS
0.70 m. on center
T-2 T-2
T-3 T-3
DOWNSPOUT
T-2 T-2
AFTER COMPLETION OF ROOF BEAM, INSTALLATION OF ROOF TRUSSES & PURLINS SHOULD
FOLLOW
BOOK 1 –137
PAGE
FABRICATION PROCEDURES
69
P-27
FABRICATION PROCEDURES BOOK 1 –138
PAGE
69
A
G E C
4) With lines AB, BC, AC, CD, DE, EF and FG, you can already
determine the lengths of the individual web members.
5) Cut the individual members with the correspond angle bar
sizes.
A
G E C
P-28
FABRICATION PROCEDURES BOOK 1 – 140
PAGE
69
B
WELDED
GUSSET PLATE
F
A
G E C
BOOK 1 – PAGE
TRUSS INSTALLATION
72 PROCEDURES
A. LAYOUT THE LOCATION OF TRUSSES ALONG WITH THE CENTERLINES OF THE BASE PLATES. 142
A B C D
ROPEMAN - A
T1 T1 T1 T1 T1
T2
T4
T1
T3 2
T4
T2
CRANE
ROPEMAN - B
THIS SHOWS THE POSITIONING OF THE CRANE ON THE PROPER LOCATION DURING
INSTALLATION OF TRUSSES. WHILE, ROPEMAN A & B ARE IN POSITION WITH THE TRUSS
P-29
BOOK 1 – PAGE
143
CRANE’S CABLE 72
ROPEMAN - B
ROPEMAN - A
C. PLACE THE PICK-UP POINT AT THE CENTER OF TRUSS WITH CONTROLLING ROPES AT
BOTH ENDS.
1. BEGIN THE INSTALLATION STARTING TRUSS-1 (T-1) THEN TRUSS-3 (T-3). CHECK THE
VERTICAL & HORIZONTAL ALIGNMENT OF T-1 & T-3.
2. SPOT WELD AT TOP AND BOTTOM JOINTS OF T-1 & T-3.
SPOT WELD
T-1
T-3
144
BOOK 1 – PAGE
72
P-30
3. INSTALL THE SECOND TRUSS-1 (T-1) THEN ATTACH THE CROSS BRACING. CHECK THE
VERTICAL & HORIZONTAL ALIGNMENT OF T-1 THEN SPOT WELD TO CROSS BRACES.
T-1
CROSS BRACE
145
BOOK 1 – PAGE
72
4. INSTALL THE NEXT TRUSS-1 (T-1) THEN ATTACH THE CROSS BRACINGS. CHECK THE
VERTICAL & HORIZONTAL ALIGNMENT OF ENTIRE T-1 THEN SPOT WELD TO CROSS
BRACES.
T-1
CROSS BRACES
146
BOOK 1 – PAGE
72
P-31
5. INSTALL THE NEXT TRUSS-2 (T-2) & TRUSS-3 (T-3). CHECK THE VERTICAL &
HORIZONTAL ALIGNMENT OF ENTIRE TRUSSES THEN FINAL WELD THE JOINTS.
T-2
T-2 T-3
T-3
147
BOOK 1 – PAGE
72
148
BOOK 1 – PAGE
72
3 A
2 B
C
1
T-2
D
CROSS BRACES
T- 4
T-1
T-3
T-2
6. INSTALL THE NEXT TRUSS-2 (T-2) ; TRUSS-3 (T-3) & (T-4). CHECK THE VERTICAL &
HORIZONTAL ALIGNMENT OF ENTIRE TRUSSES THEN FINAL WELD THE JOINTS.
P-32
7. INSTALL THE ENTIRE C-PURLINS AT 0.70 M. ON CENTER BOTHWAYS. WELD TO
TRUSSES WITH THE STEEL CLEATS.
149
BOOK 1 – PAGE
76
150
BOOK 1 – PAGE
76
P-33
8. INSTALL THE FACIA BOARD AROUND THE ROOF.
133
PLAIN GI GUTTER
134
P-34
9. INSTALL THE DOWNSPOUTS.
GI STRAP
PLAIN GI GUTTER
STRAINER
STEEL HANGER
PVC DOWNSPOUT
135
COLOROOF
PLAIN GI GUTTER
136
BOOK 1 – PAGE
77
P-35
STEEL SCAFFOLDING WITH STEEL LADDERS & LANDINGS
ADJUSTABLE U-HEAD