Sie sind auf Seite 1von 6

GHALEMDI KHOLA HYDROPOWER PROJECT

Myagdi, Nepal

Site Visit Report


FOR
LOT-2Hydraulic Steel Structure
Prepared By:
CE Hydro Mechanical Work Pvt.Ltd.
Kathmandu, Nepal
November 2017
Site Visit Report. Ghalemdi Khola Hydorpower Project (5 MW)

 Present:
Ghalemdi Hydro Ltd.(Client)
1.Mr.Bishow Vijaya Shrestha

CE Hydro Mechanical Work Pvt.Ltd.(HM Contractor)


1.Mr. Khageshor Upadhaya
2 Mr. Kishan Sharma subedi
3 Mr. Krishna Hari Sapkota

World Wide Construction Pvt.Ltd (Civil Contractor)


1Mr.Kailash Neupane.

AS Per the meeting of client & contractors on 25th October 2074.three Representatives
made site visit on 30th October 2017.& Agenda ,Discussion & Decision made by three
Representatives are flowing attach photos .then HM Contractor prepared work schedule
on the base on three Representatives Decision.
We kindly Request to all client , Consultant & Civil Contractor work are progress on the
basis of Decision made by three Representatives

2|
Site Visit Report. Ghalemdi Khola Hydorpower Project (5 MW)

3|
Site Visit Report. Ghalemdi Khola Hydorpower Project (5 MW)

 Conclusion & Recommendation:


1: Civil Contractor Shall Maintain Work Progress on the basis of site visit
Decision.

2: Clint Shall Arrange Effective storage for gates Embedded Parts.


3.Clint ,Consultant & Civil Contractor should be flow working time properly.
Because HM Contractor arrange manpower ,Transportation vehicle & prepared

4|
Site Visit Report. Ghalemdi Khola Hydorpower Project (5 MW)

Work schedule on the basis of Decision make by three Representative Site Visit
Meeting.

 HM Work Schedule:
On the basis of Three Representative Site Visit Meeting Decision . we Prepared
HM Work Schedule.

HM Work Schedule
5-Jul 24-Aug 13-Oct 2-Dec 21-Jan 12-Mar 1-May 20-Jun

Penstock Fabrication/Testing/Painting/Transportation
Tower Preparation
Winch Machine Installation
Penstock /Bend Erection
Pipe Welding
Penstock Testing
Penstock Painting

Penstock
Penstock /Bend Winch Machine Tower Fabrication/Testi
Penstock Painting Penstock Testing Pipe Welding
Erection Installation Preparation ng/Painting/Trans
portation
Start Date 15-Jan 5-Jan 29-Dec 21-Dec 10-Dec 10-Nov 5-Jul
Day to complete 135 125 125 120 10 30 180